Process Flow Chart - Method Statement

The document outlines the process flow for reviewing method statement submissions. The document controller receives submissions and logs them, then provides them to the project manager. The project manager assigns a quality assurance person to review the submission. The quality assurance person checks that the submission complies with shop drawings and contract specifications, and either approves it or returns it to the contractor if issues are found. The planning engineer and coordinator work with the contractor if there are any delays.
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
844 views1 page

Process Flow Chart - Method Statement

The document outlines the process flow for reviewing method statement submissions. The document controller receives submissions and logs them, then provides them to the project manager. The project manager assigns a quality assurance person to review the submission. The quality assurance person checks that the submission complies with shop drawings and contract specifications, and either approves it or returns it to the contractor if issues are found. The planning engineer and coordinator work with the contractor if there are any delays.
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 1

Method Statement Process Flow Diagram * Approve, Approve as noted.

# DC to ensure one copy for the team, one copy for the record DC Document Controller SD Shop drawings MS Material Submittal
Y ES Check submissio n as per planned date. Input NO Y ES Check if complying with SD & contract specification NO DC to Return to Contrac Approve * DC to forward to the concerne

MS submitted by the Contractor.

DC will log in & give to PM. PM will assign QA to review.

Checks SD/MS are approve

Planning Engineer & coordinator to interact with the Contractor for the delays in