Risk Based Inspection
Risk Based Inspection
Presented by Eur.Ing. R.T.Canaway, B.Sc., F.I.Chem.E., Managing Director of Suregrove Limited +44-1737-813605 [email protected]
Suregrove Limited
Suregrove Limited
thickness Assess the REMAINING SAFE OPERATING LIFE say 5 years left Retire plant which is deemed not usable Examine failure mode
Suregrove Limited
his/her work without interference Competent Tools Records Able to trend thinning Or tolerances
Suregrove Limited
Focus on Critical Plant to ensure the business is in a safe and profitable state
Suregrove Limited
Inspection Methods
Visual Penetrant Dye Testing finds surface flaws Radiography volumetric Magnetic Particle Flux Field Distorted Ultrasonic Testing planar and volumetric
ACFM/ACPD Ultrasonic TOFD Time of size of flaw Testing - size of Flight Alternating Current Field flaw Diffraction all Measurement or Potential Drop details from 2 probes
ultrasound from upper and lower extremes of flaw
Suregrove Limited
Failure Modes
Corrosion/Erosion, Water, Chloride, High Temperature Sulphidation, V/L Impingement
Creep > 350oC High Temp Damage > 450oC - Cracks grow Embrittlement Stress Corrosion Caustic with T>70oC, Cracking
Ammonia, Chlorides H2 Partial P>5 bar, H2S Partial P>0.05 psia HCN/HF promotes
Suregrove Limited
Suregrove Limited
Objective
The main aim of RBI, if properly carried out, is to manage the Risk of plant failure at an acceptable level. Risk = Likelihood x Consequence
Suregrove Limited
Then we can :
Eliminate unnecessary work? Reduce inspection work load Increase/Decrease Frequency of Inspection Save Time and Money
Suregrove Limited
11
& 2000) has enabled a move towards inspection strategies based on the risk of failure. This legislation allowed a user/owner together with a nominated Competent Person the flexibility to decide a suitable written inspection regime based on system information and good engineering practice.
Suregrove Limited 12
Application:
The evolution to a risk-based approach has
been supported by specific process plant operating experience together with better knowledge of material degradation mechanisms and availability of fitness-forservice assessment procedures. Also, developments in NDT technology have improved inspection ability, performance and consistency.
Suregrove Limited 13
Major Plants
Industry considers there are benefits from
more informed inspection, particularly in refining & petrochemicals where they are now setting inspection priorities on the specific risk of failure. Benefits include: Improved inspection screening for high risk areas; Prioritising inspection based on measured risk;
Suregrove Limited 14
inspection, extending inspection intervals and greater plant availability; Systematic management of risks associated with equipment failures.
Suregrove Limited
15
But!
Inspection is usually only one part of a
sites integrated integrity management strategy which also normally includes routine and preventative maintenance and they are usually linked within a common framework.
Suregrove Limited
16
Suregrove Limited
17
Risk Analysis
Risk Analysis usually contains the following 6 stages: Identification of equipment failure scenarios Identification of potential deterioration mechanisms and modes of failure Assessment of the probability of failure from each mode/mechanism
Suregrove Limited
18
Risk Analysis
Assessment of consequences resulting from
failure Determination of the risks from failure Risk ranking and categorisation.
Suregrove Limited
19
Suregrove Limited
20
Measuring Risk
Qualitative risk analysis is based primarily
on objective engineering judgements made by an RBI team. The Likelihood and Consequences of Failure (LoF & CoF) are expressed in relative terms, as below: Risks are usually expressed within a Risk Matrix.
Suregrove Limited
21
Measuring Risk
L.o.F: Very unlikely Possible Reasonably probable and Probable C.o.F: High Moderate or Low
Suregrove Limited
22
Suregrove Limited
23
Measuring Risk
Semi-Quantitative risk analysis determines
single numerical values for the probability of failure and the consequences from every cause and effect. Analysis of failure is more numerically based and detailed than the Qualitative approach, but may still include a large element of engineering judgement.
Suregrove Limited
24
Suregrove Limited
25
Measuring Risk
For a fully Quantitative risk analysis, the
likelihood and consequences of failure are determined for each scenario using standard reliability analysis methods with the total probability of failure evaluated using methods such as survival statistics. Results are normally presented on logarithmic probability-consequence plots.
Suregrove Limited
26
10-1
Likelihood
Suregrove Limited
27
Measuring Risk
Whilst all these approaches to Risk
Analysis may be valid, the process and the data needs to be transparent and the use of non-validated software may be restricted. The risk analysis & measuring process must be consistent and able to be independently assessed.
Suregrove Limited
28
Definitions
Risk The risk of failure of an item combines the probability or likelihood of failure with a measure of the consequences of that failure:Risk = Probability x Consequence The Consequence of failure through the unintentional release of stored energy and/or hazardous material is the potential for injury, damage, lost production, pollution, reputation etc. These can be measured in a variety of ways fatalities, fines and compensation payments, bankruptcy, higher insurance premiums..
Suregrove Limited 29
Definitions cont.
Inspection in RBI is the planning, implementation and evaluation of examinations to determine the physical and metallurgical condition of equipment or a structure in terms of fitness-for-service. It is usually part of a company, site or facility Integrated Integrity Management Strategy for managing risk of failure which should still include conventional routine and preventive maintenance.
Suregrove Limited 30
logical and structured process of planning and evaluation as shown in the following flow chart for plant integrity management by RBI:-
Suregrove Limited
31
Suregrove Limited
32
Definitions etc
In-service inspection is most valuable where there is uncertainty about the process operating conditions, their effect on materials, particularly where the conditions are such as to promote deterioration. Deterioration is defined as damage, defects or degradation from the design intent or the as-manufactured condition.
Suregrove Limited 33
Organisations for Testing, Inspecting, Certification and Prevention - recognised inspection intervals varied significantly within the EEC and basis is not one of risk and that it would be desirable to inspect on a variable throughout cycle life.
Suregrove Limited
35
Safe Practice proposed two interrelated concepts Grade Allocation and Sampling examination procedures. - allocation of grading depends upon assessment following 1st examination if rapid deterioration item is allocated a low grade (i.e. high failure risk). If reasonable deterioration and predictable then given less severe grade.
Suregrove Limited 36
Suregrove Limited
37
60
72
108
144
24
36
72
~
38
Suregrove Limited
1. 2. 3. 4. 5.
The UK HSE published a Guide to Risk Assessment Requirements in 1996 intended for employers which set down 5 steps:Look for Hazards; Decide who might be harmed and how; Evaluate risks and review precautions; Record findings; Review assessment & revise if necessary.
Suregrove Limited
39
document which described the assessment of risk process adopted by the HSE.
It also introduced the important concept of
Suregrove Limited
40
Qualitative & Quantitative approach including historical and analytical approaches to estimating probability of failure they noted weaknesses of both methods and concluded improvement of both methods should continue and also building of data bases required.
Suregrove Limited
41
Guidelines on RBI
The UK HSE Hazardous Installations
Directorate issued an internal circular in 1999 as guidance for HSE inspectors for auditing plant inspection systems which adopt RBI.
Suregrove Limited
42
Guidelines on RBI
ASME issued an overview of RBI
1. 2. 3. 4.
principles in 1991 recommending a fourpart process:Definition of the System; A Qualitative Risk assessment; A Quantitative Risk Analysis; Development of inspection programme
Suregrove Limited
43
Guidelines on RBI
This ASME document mainly considered the theoretical approach to the problem detailing actual analysis methods i.e. FMECA (Failure Modes Effects Criticality Analysis), Structural Reliability & Risk Assessment (SRRA) and Probabilistic Risk Analysis (PRA).
Suregrove Limited
44
Guidelines on RBI
API 581 designed for the petroleum and
chemical industries was published in draft form in May 2000. It followed the same overall approach as ASME, aiming to:1. Define & measure level of risk; 2. Evaluate safety, environmental and Business Interruption risks; 3. Reduce risk of failure by effective use of inspection resources.
Suregrove Limited 45
Guidelines on RBI
The level of risk is assessed following the same procedure as ASME quantitative analysis applied after initial qualitative analysis. The qualitative analysis assesses each plant item in a 5 x 5 risk matrix. The likelihood of failure is determined from the sum of 6 weighted factors viz:Suregrove Limited 46
Guidelines on RBI
Amount of equipment within item; Damage mechanism; Usefulness of inspection; Current equipment condition; Nature of process; Safety design and mechanisms.
Suregrove Limited
47
Guidelines on RBI
The consequence of failure is divided into only two factors:1. Fire/Explosion; 2. Toxicity
Suregrove Limited
48
Guidelines on RBI
Risk is then calculated as the product of each consequence and likelihood for each damage scenario, the total risk for an item equated as the sum of all the scenario risks:-
Risks = Cs x Fs
where:S = Scenario Cs = Consequence of Scenario Fs = Failure frequency of Scenario
Suregrove Limited 49
Guidelines on RBI
RiskItem = Risks The inspection programme is then developed to reduce that risk. To do that one needs to establish:1. What type of damage to look for; 2. Where to look for damage; 3. How to look for damage; 4. When to look for damage.
Suregrove Limited 50
Guidelines on RBI
What and Where is established from design & process data and equipment history. How to look for damage by reviewing the damage density and variability, sample validity, sample size, detection capability of method and validity of future based on past observations. When to look for damage is related to estimated remaining life of item.
Suregrove Limited
51
Suregrove Limited
52
Suregrove Limited
53
RBI Team
In all but the simplest situations situations, RBI is best undertaken as a team activity similar to Hazop. Technical knowledge and experience should encompass; Risk assessment; Process hazards and failure consequences; Plant safety and integrity management; Mechanical engineering/metallurgy/design; Plant operation, maintenance & inspection history; Inspection methods/NDT effectiveness etc.
Suregrove Limited 54
RBI Team
Where there are significant Health & Safety
implications arising from equipment failure, the qualifications and competence of team members needs to be to a recognised professional standing. Where not available in-house duty holders will need to take advice from appropriate external experts and consultants.
Suregrove Limited
55
RBI Team
Ideally, the Team Leader should be independent
from the direct pressures of the site production function and should have appropriate seniority and authority. Good records need to be kept on how qualitative judgements and decisions were kept. In many cases the information required for a quantitative risk assessment either does not exist, or is not sufficiently accurate.
Suregrove Limited
56
information? What are the reasons/drivers for the risk-based approach? Is the availability and accuracy of information sufficient? Does the approach reflect the plant complexity and potential catastrophes? How do Integrity Management & Inspection link to plant operations? How is the documentation managed & controlled?
Suregrove Limited 57
audited and reviewed? Who carries out the audit and review? What aspects of the Management Process are covered; Is documentary evidence available to support each aspect? How has the Integrity Management process changed?
Suregrove Limited 58
Suregrove Limited
59
Failures caused by Wrong selection of presence of unforeseen materials or PMI failure presence of contaminants or pollution (perhaps intermittent occurrence)
Suregrove Limited 60
Suregrove Limited
61
RBI is useful:
In work prioritisation to focus on areas where business outage could be significant As a tool to help the company focus its resources Feedback in industry to highlight failure modes and educate other plants before failure To assess the risk to the business (in terms of loss of production)
Suregrove Limited
62