Temporary Footingfor Rectangular Tank
Temporary Footingfor Rectangular Tank
Temporary Footingfor Rectangular Tank
CLIENT : DESIGN BY :
Tian Li JOB NO. : DATE : REVIEW BY :
Temporary Tank Footing Design Based on ACI 318-05
ANALYSIS
DESIGN LOADS (ACI 318-05 SEC.9.2.1)
ASD: DL + LL P = 1582 kips
SD: 1.2 DL + 1.6 LL Pu = 2189 kips
M n MIN 5 f 'c S , 0.85 f 'cS = 45.09 ft-kips
0.5L 0.25b10.25c1
2
P u ,max
Mu = 19.95 ft-kips < fMn [Satisfactory]
2L
CHECK FLEXURE SHEAR (ACI 318-05 SEC.22.5.4)
4
V n f 'c BT = 86.58 kips
3
where f = 0.55 (ACI 318-05, Section 9.3.5 )
P u ,ma x
V u 0.5 L 0.25b1 0.25c 1 T = 2.17 kips < fVn [Satisfactory]
L
CHECK PUNCHING SHEAR (ACI 318-05 SEC.22.5.4)
4 8
V n MIN , 2.66 f c c1 c 2 b1 b2 4T T
'
= 976.18 kips
3 3 c
where f = 0.55 (ACI 318-05, Section 9.3.5 )
bc = ratio of long side to short side of concentrated load = 1.99
1 b1 c 1 b c
V u P u ,ma x 1 T 2 2 T = 136.98 ft-kips < fVn [Satisfactory]
BL 2 2