Chapter 7 HW
Chapter 7 HW
1. What is a unique, one-time event that is intended to achieve an objective in a given time
period?
a) a project
b) a job
c) a task
d) an activity
e) an event
4. Which of the following would probably not benefit from the use of critical path scheduling?
a) constructing a new bridge over the Mississippi River
b) moving the company’s credit card center to a new city
c) building a new natural gas pipeline
d) receiving orders for the company’s products by phone
e) developing a new computer system for financial planning
5. Which phase in the project life cycle involves identifying the need for the project?
a) conception
b) feasibility analysis or study
c) planning
d) execution
e) termination
6. Which phase in the project life cycle involves evaluating expected costs, benefits, and risks?
a) conception
b) feasibility analysis or study
c) planning
d) execution
e) termination
1
7. Which phase in the project life cycle involves analyzing the work to be done and developing
time estimates for completing each of the activities?
a) conception
b) feasibility analysis or study
c) planning
d) execution
e) termination
8. Which phase in the project life cycle involves analyzing the project risk?
a) conception
b) feasibility analysis or study
c) planning
d) execution
e) termination
9. Which phase in the project life cycle involves carrying out the activities that make up the
project?
a) conception
b) feasibility analysis or study
c) planning
d) execution
e) termination
10. Which phase in the project life cycle involves ending the project?
a) conception
b) feasibility analysis or study
c) planning
d) execution
e) termination
2
13. Actions that consume resources and/or time are project ______________________.
a) events
b) activities
c) nodes
d) arrows
e) tasks
17. The critical path is the sequential path of interrelated activities which has the
____________________.
a) most activities
b) longest time
c) most nodes
d) most events
e) most arrows
18. If a delay in an activity will delay completion of the whole project, the activity
____________________.
a) is on the critical path
b) has slack
c) is costly
d) is a dummy
e) is represented by a node
3
19. The sum of the activity times on the critical path determines
____________________________________.
a) total slack available
b) total labor time required for the project
c) minimum time to complete the project
d) the number of milestones
e) amounting of crashing that needs to be done
20. When we are unsure about the duration of project activities, we use time
estimates.
a) variable
b) probabilistic
c) estimated
d) deterministic
e) cumulative
24. In making a forward pass through a network, activities L, M, and P are immediate
predecessors for activity T, which has an activity time of 7. The early start times for activities L,
M, and P are 22, 17, and 27, respectively. The early finish times for activities L, M, and P are 29,
27, and 33, respectively. What is the early start time for activity T?
a) 17
b) 24
c) 27
d) 33
e) 40
4
25. In making a backward pass through a network, activity L has an activity time of 4 and
immediately precedes activities M, P, and T. The late start times for activities M, P, and T are 22,
17, and 27, respectively. The late finish times for activities M, P, and T are 29, 27, and 33,
respectively. What is the late start time for activity L?
a) 13
b) 17
c) 22
d) 33
e) 37
27. With probabilistic time estimates, when we calculate the expected time for an activity, we
treat each activity time estimate as a random variable derived from a
probability distribution.
a) normal
b) beta
c) gamma
d) Poisson
e) uniform
5
29. Joe’s radio tower fabrication company has developed the following milestone project
schedule. What is the expected time duration for the project?
ACTIVITY PRECEDENCE P M O
A Complete design None 4 3 2
B Develop BOM A 2 1 1
C Order Materials B 3 2 1
D Site Selection A 7 4 3
E Receive Materials C 6 3 2
F Obtain permits A, D 4 2 1
Begin fabrication facility
G development E, F 6 5 3
a) 9
b) 10
c) 14
d)14.33
e) 17.33
30. Joe’s tower fabrication firm has revised their earlier project time estimates. Based on the new
time estimates what is the critical path standard deviation?
ACTIVITY PRECEDENCE P M O ET
A Complete design None 4 3 2 3
B Develop BOM A 2 1 1 1.17
C Order Materials B 3 2 1 2
D Site Selection A 7 4 3 4.33
E Receive Materials C 6 3 2 3.33
F Obtain permits A, D 5 2 1 2.33
Begin fabrication facility
G development E, F 6 5 3 4.83
a) 0.94
b) 1.0
c) 1.14
d) 1.25
e) 1.3