SAVELITE ENGINEERING SDN BHD
KUALA LUMPUR WELLNESS CITY PROJECT
METHOD STATEMENT
INSTALLATION OF CABLE CONTAINMENT INCLUD
Reference No. : KLWC-SESB-MST-0003
Revision : 00
Date Issued : 19/10/2023
Prepared by Approved by
Name Muhd Zuraimyzanizam Bin Zamhuri Name
Position Asst. Project Manager Position
SAVELITE ENGINEERING SDN BHD
KLWC/SESB/MST-0003
METHOD STATEMENT
INSTALLATION OF CABLE CONTAINMENT INCLUDING SUPPORT Revision:
BRACKET 00
AMENDMENT HISTORY
REVISION NO. ISSUE DATE DETAILS OF AMENDMENT
00 19/10/2023 First Submission
Table of Contents
1 SCOPE OF WORK 4
SAVELITE ENGINEERING SDN BHD Page 2 of 40
KLWC/SESB/MST/003
METHOD STATEMENT
INSTALLATION OF CABLE CONTAINMENT INCLUDING SUPPORT Revision:
BRACKET 00
1.1 General Description 4
1.2 References 4
1.3 Materials 4
1.4 Plant and Equipment 7
1.5 Manpower 7
1.6 Work Procedure 8
2 SAFETY AND HEALTH 19
2.1 Job Safety & Health Analysis 19
2.2 Information to Personnel 19
2.3 Housekeeping 19
3 QUALITY ASSURANCE & QUALITY CONTROL 19
3.1 Inspection & Testing Error! Bookmark not defined.
SAVELITE ENGINEERING SDN BHD Page 3 of 40
KLWC/SESB/MST/003
METHOD STATEMENT
INSTALLATION OF CABLE CONTAINMENT INCLUDING SUPPORT Revision:
BRACKET 00
1 SCOPE OF WORK
1.1 General Description
This statement is to outline the installation of cable containment including
support bracket. This includes the methodology for the installation of
Cable Tray, and Cable Ladder. To ensure the work is carried out in
controlled and systematic manner, all respective parties shall conform to
the specified requirements, emphasizing on the aspects of meeting
quality standard, safe working environment and compliance of safety
requirements.
1.2 References
No Descriptions Documents Number
1.0 Construction Drawing All related regulation and guideline for
construction
1.3 Materials
No. Materials Purpose
Cable ladders including To support insulated electrical
1.3.1
accessories (HDG/G.I) cables
MS Cable tray including To support insulated electrical
1.3.2
accessories cables
MS Cable trunking including To support insulated electrical
1.3.3
accessories cables
To support data and electrical
1.3.4 Underfloor Trunking
cables
As a terminal box for wire
1.3.5 MS Junction Box
connection
To act as a support bracket for
1.3.6 Angle iron bracket
cable containment
To hang threaded rod for support
1.3.5 C-channel
bracket
To tighten the joint of cable ladder,
1.3.6 Screw, nut & washers
cable tray and cable trunking
To attach objects to
1.3.7 Anchor bolts
structures/concrete
To use for hanging support bracket
1.3.8 Stud rods
of cable containment
1.3.9 Flat bar To attach rod with unistrut
1.3.10 Earthing connectors To bond to earthing system
SAVELITE ENGINEERING SDN BHD Page 4 of 19
KLWC-SESB-MST-0004
METHOD STATEMENT
INSTALLATION OF CABLE CONTAINMENT INCLUDING SUPPORT Revision:
BRACKET 00
1.3.1 Cable Ladder Types as shown in Table 1 & Figure 1.
ITEM TYPE SIZE
1.3.1.1 Cable Ladder HDG/G.I 1000mm (W) x 100mm (H) x 2.0mm (T)
1.3.1.2 Cable Ladder HDG/G.I 1000mm (W) x 150mm (H) x 2.0mm (T)
Table 1: Cable Ladder Types
Figure 1: Cable Ladder
1.3.2 Cable Tray Types as shown in Table 2 & Figure 2.
ITEM TYPE SIZE
1.3.2.1.1 MS Cable Tray 600mm (W) x 100mm (H) x 1.5mm (T)
1.3.2.1.2 MS Cable Tray 1000mm (W) x 100mm (H) x 1.5mm (T)
Table 2: Cable Tray Types
SAVELITE ENGINEERING SDN BHD Page 5 of 19
KLWC-SESB-MST-0004
METHOD STATEMENT
INSTALLATION OF CABLE CONTAINMENT INCLUDING SUPPORT Revision:
BRACKET 00
Figure 2: Cable Tray
1.3.3 Cable Trunking Types as shown in Table 3 & Figure 3.
ITEM TYPE SIZE
1.3.3.1 MS Cable Trunking 50mm (W) x 50mm (H) x 1.2mm (T)
1.3.3.2 MS Cable Trunking 75mm (W) x 50mm (H) x 1.2mm (T)
1.3.3.3 MS Cable Trunking 100mm (W) x 50mm (H) x 1.2mm (T)
1.3.3.4 MS Cable Trunking 100mm (W) x 75mm (H) x 1.2mm (T)
1.3.3.5 MS Cable Trunking 100mm (W) x 100mm (H) x 1.2mm (T)
Table 3: Cable Trunking Type
SAVELITE ENGINEERING SDN BHD Page 6 of 19
KLWC-SESB-MST-0004
METHOD STATEMENT
INSTALLATION OF CABLE CONTAINMENT INCLUDING SUPPORT Revision:
BRACKET 00
Figure 3: Cable Trunking
1.4 Plant and Equipment
Item Description Purposes
1.4.1 Mobile scaffold / Ladder Working at height
1.4.2 Metal cutting saw / Grinder For cutting purposes
1.4.3 Zinc rich galvanising spray To touch up scratches area
1.4.4 Power hand drill with bits Penetrating purposes
1.4.5 Nylon cord or laser To mark level during installation work
1.4.6 Tool box full set Installation Purpose
1.4.7 Bolts, nuts and washers Fix brackets and supports
1.4.8 Lorry Crane To unload materials at site
1.5 Manpower
Item Designation Responsibilities
The Project Manager has overall authority in the
determination of all matters affecting the
1.5.1 Project Manager implementation and operation of the project. He
reports to the Head of Construction (Project
Director)
Monitor and ensure site progress as per schedule.
1.5.8 Site Supervisor To coordinate for daily work inspection with SC and
PDP
Competent Assist in installation, repair and maintain electrical
1.5.9
Electrician circuits, plants and equipment.
1.5.10 Skilled Workers To carry out skilled works.
1.5.11 General Workers Conduct general works at site
SAVELITE ENGINEERING SDN BHD Page 7 of 19
KLWC-SESB-MST-0004
METHOD STATEMENT
INSTALLATION OF CABLE CONTAINMENT INCLUDING SUPPORT Revision:
BRACKET 00
1.6 Work Procedure
1.6.1 Pre Installation
1.6.1.1 Delivery Plan
1.6.1.1.1 Data from the site measurement will be referred for material
delivery in accordance with the need and availability.
1.6.1.1.2 A number of materials will be unloaded at a store yard for
reasonable intervals along the proposed locations installation by
obtaining the approval from local authority.
1.6.1.1.3 The location where materials will be unloaded must be carefully
selected to avoid users around that area
1.6.1.1.4 All the materials shall be approved by Consultant prior delivery to
store yard.
1.6.1.1.5 All the materials at the work areas shall not block any access.
1.6.1.2 Preliminary & Site Inspection
1.6.1.2.1 Get all related working permit before start work.
1.6.1.2.2 All materials must be inspected by consultant/engineer/Clerk-of-
Work to ensure all materials are according to required
specifications and approved MSA. RFI will be raised for material
inspection.
1.6.1.2.3 All works are to be carried out according to the approved MST and
also approved shop drawing.
1.6.1.2.4 A mock up installation will be carried out if needed before work
start.
1.6.1.2.5 Personnel are equipped with PPE & safety harness when working
at height.
1.6.2 Cable Containment Support Bracket Installation
1.6.2.1 Suspended Support Bracket Installation
1.6.2.1.1 The required elevation from the floor to the bottom of the cable
containment is measured according to approved shop drawing to
install the cable containment support.
1.6.2.1.2 A level line is established with laser or nylon string. A string works
well because it can be used to align the threaded rods one side of
the Trapeze and find the top of the support.
1.6.2.1.3 Mark in a way to ensure that the routing of the cable containment is
either parallel or perpendicular to the building line. It can be either
SAVELITE ENGINEERING SDN BHD Page 8 of 19
KLWC-SESB-MST-0004
METHOD STATEMENT
INSTALLATION OF CABLE CONTAINMENT INCLUDING SUPPORT Revision:
BRACKET 00
marked by line on soffit or slab by pulling a string along the cable
containment route.
1.6.2.1.4 Holes are drilled on the marked point to secure stud rod on the slab
or structure by using anchor bolt. The bolt is then tightened with nut
and washer by using spanner.
1.6.2.1.5 Once anchored, a stud rod will be installed at slab. Nuts and
washers are fixed to secure the rod as shown in Figure 4.
Figure 4: Stud Rod installation details (Detail A)
1.6.2.1.6 At bottom of the rods, angle iron bracket will be fixed with the rod at
both end of angle iron bracket to hang cable containments. Spring
nuts, flat bar, nuts and washers are tightened to secure the rod
1.6.2.1.7 The distance between hangers is 1000mm.
1.6.2.2 Wall Mounted Support Bracket Installation
1.6.2.2.1 The required elevation from the floor to the bottom of the cable
containment is measured according to approved shop drawing to
install the cable containment support.
1.6.2.2.2 A level line is established with laser or nylon string. A string works
well because it can be used to align the bracket one side of the
Trapeze.
1.6.2.2.3 Mark in a way to ensure that the routing of the cable containment is
either parallel or perpendicular to the building line. It can be either
mark by line on wall by pulling a string along the cable containment
route.
SAVELITE ENGINEERING SDN BHD Page 9 of 19
KLWC-SESB-MST-0004
METHOD STATEMENT
INSTALLATION OF CABLE CONTAINMENT INCLUDING SUPPORT Revision:
BRACKET 00
1.6.2.2.4 Holes are drilled on the marked point to secure Unistrut on the wall
or structure by using anchor bolt as shown in Figure 6 and 7. The
bolt is then tightened with nut and washer by using spanner
Figure 6: Installation of Wall Mounted Support Bracket
1.6.2.3 Wall Mounted Support Bracket Installation in Riser
1.6.2.3.1 The required position of cable containment in riser is marked
according to approved shop drawing.
1.6.2.3.2 A straight line is established with laser or nylon string. A string
works well because it can be used to align the bracket one side of
the Trapeze.
1.6.2.3.3 Mark in a way to ensure that the routing of the cable containment is
either parallel or perpendicular to the building line. It can be either
mark by line on wall by pulling a string along the cable containment
route.
1.6.2.3.4 Holes are drilled on the marked point to secure C-channel on the
wall or structure by using anchor bolt as shown in Figure 8. The bolt
is then tightened with nut and washer by using spanner.
SAVELITE ENGINEERING SDN BHD Page 10 of 19
KLWC-SESB-MST-0004
METHOD STATEMENT
INSTALLATION OF CABLE CONTAINMENT INCLUDING SUPPORT Revision:
BRACKET 00
Figure 8: C-channel as Support Bracket
1.6.3 Cable Containment Installation
1.6.3.1 Installation Method for Cable Tray
1.6.3.1.1 After the support brackets are installed, cable tray will be placed on
the support brackets according to the designed size in the
approved shop drawings as in Figure 9.
Figure 9: Installation of Cable Tray
SAVELITE ENGINEERING SDN BHD Page 11 of 19
KLWC-SESB-MST-0004
METHOD STATEMENT
INSTALLATION OF CABLE CONTAINMENT INCLUDING SUPPORT Revision:
BRACKET 00
1.6.3.1.2 Hole is drilled on the cable tray to fix the screw into it. Spring nut is
placed in the Unistrut under the cable tray and screw is fixed to lock
the tray with the angle iron bracket as in Figure 10 and 11.
Figure 10: Detail C
Figure 11: Detail D
1.6.3.1.3 Cable trays shall be connected to adjacent lengths, tees, elbows,
reducers and other fittings with approved couplers and securely
fastened. Connection shall be mechanically strong so that there is
no movement between joints.
1.6.3.1.4 At the interconnection of two cable trays or fittings, splice plate is
attached on the centre of the interconnection and tightened by
using bolts, nuts and washers as in Figure 12.
SAVELITE ENGINEERING SDN BHD Page 12 of 19
KLWC-SESB-MST-0004
METHOD STATEMENT
INSTALLATION OF CABLE CONTAINMENT INCLUDING SUPPORT Revision:
BRACKET 00
Figure 12: Splice Plate Installation
1.6.3.1.5 For cable tray earthing, an earth link is fixed at adjoining of splice
plates on the outer side of cable tray.
1.6.3.1.6 In the event of splice plate is required, it shall be placed on the
inside of the cable tray with bolt’s head faces the inside of cable
tray as in Figure 13, unless otherwise specified by manufacturer.
Figure 13: Splice Plate and Fixture
1.6.3.1.7 All sharp edges and corner are filed off to ensure no damage on
cable laid.
SAVELITE ENGINEERING SDN BHD Page 13 of 19
KLWC-SESB-MST-0004
METHOD STATEMENT
INSTALLATION OF CABLE CONTAINMENT INCLUDING SUPPORT Revision:
BRACKET 00
1.6.3.1.8 All cut edges are treated with an anti-corrosion paint, to the same
colour as the adjacent surfaces.
1.6.3.1.9 In the event of divider required, it shall be placed inside the cable
ladder and screw, nut and washer are fixed to hold the divider.
1.6.3.2 Installation Method for Cable Ladder
1.6.3.2.1 After the support brackets are installed, cable ladder will be placed
on the support brackets according to the designed size in the
approved shop drawings as in Figure 14.
1.6.3.2.2 Hold down clamps are installed on side rail of cable ladder and
fixed onto angle iron bracket by using bolts, nuts and washers as
shown in Figure 15.
Figure 14: Installation of Cable Ladder
SAVELITE ENGINEERING SDN BHD Page 14 of 19
KLWC-SESB-MST-0004
METHOD STATEMENT
INSTALLATION OF CABLE CONTAINMENT INCLUDING SUPPORT Revision:
BRACKET 00
Figure 15: Installation of Hold Down Clamp
1.6.3.2.3 Cable ladders shall be connected to adjacent lengths, tees, elbows,
reducers and other fittings with approved couplers and securely
fastened. Connection shall be mechanically strong so that there is
no movement between joints. 25mm2 tinned copper braid earth link
will be installed between the joints along the containment to ensure
the continuity.
1.6.3.2.4 At the interconnection of two cable ladders or fittings, splice plate is
attached on the centre of the interconnection and tightened by
using bolts, nuts and washers as in Figure 16.
Figure 16: Installation of Splice Plate
1.6.3.2.5 In the event of up and down bending are required, vertical
adjustable splice plate shall be placed on the outer side rail of the
cable ladder with bolt’s head faces the inside of cable ladder as in
Figure 17, unless otherwise specified by manufacturer.
SAVELITE ENGINEERING SDN BHD Page 15 of 19
KLWC-SESB-MST-0004
METHOD STATEMENT
INSTALLATION OF CABLE CONTAINMENT INCLUDING SUPPORT Revision:
BRACKET 00
Figure 17: Vertical Adjustable Splice Plate
1.6.3.2.6 For cable ladder earthing, an earth link is fixed at adjoining of splice
plates on the outer side of cable ladder.
1.6.3.2.7 All sharp edges and corner are filed off to ensure no damage on
cable laid.
1.6.3.2.8 All cut edges are treated with an anti-corrosion paint, to the same
colour as the adjacent surfaces.
1.6.3.2.9 In the event of divider required, it shall be placed inside the cable
ladder and screw, nut and washer are fixed to hold the divider as in
Figure 18.
Figure 18: Installation of Divider
1.6.3.3 Installation Method for Cable Trunking
1.6.3.3.1 After the support brackets are installed, cable trunking will be
placed on the support brackets according to the designed size in
the approved shop drawings as in Figure 19.
1.6.3.3.2 Hole is drilled on the cable trunking to fix the screw into it. Spring
nut is placed in the Unistrut under the cable trunking and screw is
fixed to lock the trunking with the Unistrut as in Figure 20.
SAVELITE ENGINEERING SDN BHD Page 16 of 19
KLWC-SESB-MST-0004
METHOD STATEMENT
INSTALLATION OF CABLE CONTAINMENT INCLUDING SUPPORT Revision:
BRACKET 00
Figure 19: Installation of Cable Trunking
Figure 20: Fixing of Screw inside Cable Trunking
1.6.3.3.3 Cable trunkings shall be connected to adjacent lengths, tees,
elbows, reducers and other fittings with approved couplers and
securely fastened. Connection shall be mechanically strong so that
there is no movement between joints.
1.6.3.3.4 At the interconnection of two cable trunkings and fittings, coupler is
attached on the centre of the interconnection and tightened by
using bolts, nuts and washers as in Figure 21.
SAVELITE ENGINEERING SDN BHD Page 17 of 19
KLWC-SESB-MST-0004
METHOD STATEMENT
INSTALLATION OF CABLE CONTAINMENT INCLUDING SUPPORT Revision:
BRACKET 00
Figure 21: Cable Trunking Coupler
1.6.3.3.5 For cable trunking earthing, an earth link is fixed at adjoining of
trunking coupler on the outer side of cable trunking.
1.6.3.3.6 Cable trunking is closed by using trunking cover and locked by the
screw.
1.6.3.3.7 All sharp edges and corner are filed off to ensure no damage on
cable laid.
1.6.3.3.8 All cut edges are treated with an anti-corrosion paint, to the same
colour as the adjacent surfaces
2 SAFETY AND HEALTH
2.1 Job Safety & Health Analysis
2.1.1 Safety and health implementation at work site are to be exercised in
accordance with Safety & Health Policy..
SAVELITE ENGINEERING SDN BHD Page 18 of 19
KLWC-SESB-MST-0004
METHOD STATEMENT
INSTALLATION OF CABLE CONTAINMENT INCLUDING SUPPORT Revision:
BRACKET 00
2.2 Information to Personnel
2.2.1 All workers and site personnel employed in the project site must have
valid CIDB Green Card.
2.2.2 All new workers and staff to attend the Safety Induction before
commencing works at site and attendances shall be recorded in an
induction record.
2.3 Housekeeping
2.3.1 Housekeeping is an essential part of environmental team for the daily routine.
2.3.2 Housekeeping shall include the following terms:
• Store and stack all construction materials in safe and orderly manner.
• Park the machineries in orderly manner.
• No littering around the site
3 QUALITY ASSURANCE & QUALITY CONTROL
3.1 Inspection & Evaluation
RFIs and respective Permit to Work shall be submitted prior execution of
any construction activities.
SAVELITE ENGINEERING SDN BHD Page 19 of 19