HP Bypass

Download as pdf or txt
Download as pdf or txt
You are on page 1of 15

4/30/22, 12:48 PM Technical Feedback

COMMISSIONING CHECK LIST

FOR HP BYPASS SYSTEM

1.0.0 MECHANICAL

1.1.0 Preliminary checks

1.1.1 Check that all the valves, piping, oil supply units, etc. are erected as per the layout.

1.1.2.0 Ensure that the following are serviced, if necessary, according to the condition of equipments and fitted
back properly.

1.1.2.1 Bypass control valve (BP) actuators.

1.1.2.2 Spray water control valve (BPE) actuators.

1.1.2.3 Accumulators.

1.1.3 Ensure all joints are properly tightened and the pipelines are clamped with proper supports.

1.1.4 Ensure cleanliness of oil tank in oil supply units.

1.2.0 Acid cleaning of pipelines

1.2.1 The oil pipe line system (fig. 1) has to be subjected to chemical cleaning in order to avert
plugging of servo valves, filters, etc. Visual inspection of pipes before erection reveals the condition. If rusted
heavily and pitted, the pipes are to be chemically cleaned, preferably before erection. If the piping erection is
completed, suitable arrangements for filling, draining and venting, are to be made at appropriate levels. Soaking
method is recommended if circulation method is not practicable.

https://www.bhelpswr.co.in/Technical/C&I/Commissioning/Hp Bypass/Commissioning Checklist.htm 1/15


4/30/22, 12:48 PM Technical Feedback

1.2.2 Alkaline water wash

The oil pipelines are to be flushed with water to remove loose debris before subjecting it to acid
cleaning. Fill the pipeline with 1% solution containing sodium carbonate and trisodium phosphate. (5 gms of
sodium carbonate and 5 gms. Of Trisodium phosphate per litre of water). Soak the lines in alkaline solution for
four to six hours. Drain and rinse the pipelines with clear filtered water or demineralised water to free them
from any remnant alkali.

1.2.3 Acid cleaning

Fill the oil pipelines, with 6% hydrochloric acid mixed with 0.2% Rodine 213 special inhibitor for 6 hrs.
(200 CC of HCL and 2 CC of Rodine per lit. of water). Drain the pipeline, flush it with clear filtered water or
demineralised water to ward off remnant acidity. Test it with litmus paper. If the litmus paper does not turn red
no acidity.

1.2.4 Neutralisation and passivation

Fill the pipelines with solution containing 0.5% sodium hydroxide of PH 13 and 0.5% sodium nitrite for
6 to 8 hrs. (10 gms. Of sodium hydroxide of PH 13 and 10 gms. Of sodium nitrite per lit. of water). Drain and
flush the lines with clear filtered water or demineralised water. Dry the pipelines by blowing hot air. Preserve the
pipe lines by filling with recommended oil and cover the ends.

1.3.0 Precommissioning

1.3.1 Filling the oil tank with Hydraulic fluid.

Ensure that the entire system is clean and also connections are tight.

Fill the tank upto the level �Max� (on the dip stick) with recommended Grade of oil (Fig. 2). Presently
Servo prime 311 of IOC used or as per the recommendation given by the manufacturer to the project.

1.3.2 Check the gas pressure in Accumulator

https://www.bhelpswr.co.in/Technical/C&I/Commissioning/Hp Bypass/Commissioning Checklist.htm 2/15


4/30/22, 12:48 PM Technical Feedback

Keep the ball � valve of pressure line (P) in closed condition and pressurise the accumulator appx. 20
bar above the stamped gas filling pressure. Switch off the pump motor. Reduce the pressure from the
accumulator via the drain screw in the supply manifold. (Fig. 3) The oil pressure drop to zero as soon as the gas
pressure reached.

1.3.3 Charging the accumulator with Nitrogen

Fix the special charging device (Fig. 4) and verify the gas pressure in the Accumulator bladder. If the
pressure is less than the recommended value, i.e. 80 Kg/sq.cm., recharge the bladder using commercial quality
Nitrogen storage bottle at high pressure.

https://www.bhelpswr.co.in/Technical/C&I/Commissioning/Hp Bypass/Commissioning Checklist.htm 3/15


4/30/22, 12:48 PM Technical Feedback

1.3.4 Check the tripping pressure of safety relief valve

https://www.bhelpswr.co.in/Technical/C&I/Commissioning/Hp Bypass/Commissioning Checklist.htm 4/15


4/30/22, 12:48 PM Technical Feedback

The tripping pressure of the safety relief valve is set at higher pressure than that of �Switch off
presssure� for oil pump and also the �Pressure too high� alarm. The set pressure can be rechecked as follows
:

- Close the ball valve in pressure line (P) in OSU.

- Check the oil level in tank and lower the level to 20 cm below the
maintenance opening in the tank

- Remove the cover

- Bridge the micro switch for �Pump motor off� (switch no.1).

- Start the oil pump and switch off as soon as relief valve trips. Note
the tripping pressure. Reset the tripping pressure if necessary by adjusting the set screw
on the valve.

- Repeat the checking until the tripping pressure is correct. The


tripping pressure of safety relief valve should be set at 180 kg/sq.cm.

1.3.5 Check the accumulator operating pressure

The accumulator operating pressure is set with four pressure switches provided in one box. (Fig. 5). The
pressure at any instant can be read from the manometer which is provided between accumulator and supply
manifold. The set pressure of the individual micro switches should be checked and resetting is to be done if
necessary by adjusting the set screws. Turning the set screw in clockwise results in a lower value. The purpose
of each micro switch setting is as follows :

Switch No. 1 : - �Pump motor off�. The max. operating pressure in accumulator at which the pump
motor is switched off (i.e.) 160 kg/sq.cm.

Switch No. 2 : - �Pump motor on�. The min. operating pressure in accumulator at which the pump
motor is switched on. (i.e.) 110 Kg/sq.cm.

Switch No. 3 : - �Pressure too low� alarm. The oil pressure is below the min. operating pressure
(i.e.) 70 Kg/sq.cm.

Switch No. 4 :- �Pressure too high� alarm. The oil pressure is higher than the operating pressure
(i.e.) 170 Kg/sq.cm.

After the setting, the individual settings must be rechecked for its correctness.

1.3.6 Oil Flushing

The oil flushing operation is to be carried out to clean the complete system of pipe work. For the normal
operating system, the flushing is to be done in two stages. First stage includes the pressure line (P) and the
return line (T) and second stage includes pressure line (P) and the leakage line (L)

1.3.7 Stage I Flushing

- Connect the pressure line (P) and the return line (T) with high pressure hose at actuator (Fig. 6) for
all valves.

- The filtering elements for suction strainer in OSU, air filter and the pressure filter must remain in
place.
https://www.bhelpswr.co.in/Technical/C&I/Commissioning/Hp Bypass/Commissioning Checklist.htm 5/15
4/30/22, 12:48 PM Technical Feedback

- The 3 micron filter elements in the pressure line (P) filters before the actuator must be removed.

- Instal the flushing filter in the return line between supply manifold and ball cock (Fig. 7).

- Instal 25 micron filter element into the flushing filter.

- Keep open all ball cocks in �P� and �T� lines near the actuators and �T� line near OSU.

- Close ball valve in pressure line (P) near OSU.

- Start the oil pump. When the pressure in accumulator reached the �Pump motor off� limit the ball
valve is opened (While charging the line for the first time the valve is to be opened slowly and
watched for any oil leakage) and then closed when the pressure reduced to �Pump motor on�
limit.

This processes of flushing is to be continued for not less than 30 minutes per loop. During the flushing
operation, the fluid temp. has to reach minimum of 40 deg.C. and also the maximum temp. should not exceed
70 deg. C or as specified in O & M manual.

- If more than one OSU feed the same system, we can install flushing filter in the return line of each
unit. This will enable us to use the OSU alternately for flushing purpose. If number of flushing
filter are not available, then the leakage lines must be closed off on all the OSU which is not used
for the flushing purpose.

- Remove the 25 micron filter element and install 3 micron filter element in flushing filter. Continue the
flushing operation as described above for minimum 30 minutes per loop.

1.3.8 Stage II Flushing

- Connect the pressure line (P) and leakage line (L) with high pressure hose at the actuator for all the
valves (Fig.8)

- The flexible hose in return line (T) at OSU is to be changed to leakage line (L)

- Flushing operation as described in 1.3.7 is to be followed for flushing of leakage line (L). The flushing
is to be done for 30 mts. With 25 micron filter and then for 30 mts. With 3 micron filter for each
loop.

1.3.9 Restoration

- Remove the flushing filter unit from the oil supply unit (OSU).

- Restore all piping connections in the original condition.

- Install 3 micron filter elements.

https://www.bhelpswr.co.in/Technical/C&I/Commissioning/Hp Bypass/Commissioning Checklist.htm 6/15


4/30/22, 12:48 PM Technical Feedback

https://www.bhelpswr.co.in/Technical/C&I/Commissioning/Hp Bypass/Commissioning Checklist.htm 7/15


4/30/22, 12:48 PM Technical Feedback

1.3.10 Oil flushing for lines of quick opening device (SSB Unit)

- Close the isolating ball valves in the pressure and return line near OSU.

- Additional accumulator connection block (SAB) should be isolated from the flushing circuit.

- Remove the filter elements fitted in pressure line before the additional accumulators.

- Install the flushing device in oil return line of SSB Unit near OSU.

https://www.bhelpswr.co.in/Technical/C&I/Commissioning/Hp Bypass/Commissioning Checklist.htm 8/15


4/30/22, 12:48 PM Technical Feedback

- Connect the supply line and return line as shown in Fig. 9, using suitable fittings, hoses, etc.

- Carry out the flushing operation as described in 1.3.7 The isolating valve in pressure line to
additional accumulator near OSU is to be used to carry out flushing operation.

- After completing the flushing, connect the oil line as shown in Fig. 10 for flushing the additional
accumulator drain line to tank. Carry out the flushing as per the procedure in 1.3.7.

- Remove the flushing device and restore the oil pipe line connections after declaring the completion of
flushing operation.

2.0.0 ELECTRICAL

2.1.0 Preliminary checks

2.1.1 Ensure completion of erection of all components like control panel (CP), pressure transmitter, Temp.
transmitter, etc. as per the bill of material.

2.1.2 Ensure cabling for various points like MCC to OSU-motor, Incomer cable CP, CP to field equipments, CP
to UCB insert and termination of the same.

2.1.3 Identify the cables and ensure proper termination

2.1.4 Ensure proper fixing of fabricated cable from CP to UCB console insert.

2.1.5 Ensure proper earthing of CP (i.e.) CP earthing should be connected to the common earth bar.

2.2.0 Pre-commissioning

2.2.1 Check the IR value using 500V megger for power cables and for motor of OSU. Ensure the healthiness
and record the value.

2.2.2 Extend power supply to both incomers of the control panel up to the breakers and check the
correctness. Check the voltage in the respective TB and also ensure proper polarity.

2.2.3 Extend supply to CP by switching �ON� the incomer breakers. Energise the CP by switching ON the
power supply modules (NER 30) one by one and check the correctness.

2.2.4 Isolate all the out going leads and charge each rack by pressing the respective breakers and check all
the out going voltages are as per the requirement.

2.2.5 Ensure availability of all cards and placed in respective position.

2.2.6 Using test kit, calibrate the cards and set the valves as per the recommendation wherever possible
(Annex. B)

2.2.7 Isolate the power supply to OSU-Motors. Energise the Module for control and monitoring of OSU (SOL
10) and check power contractor picking and also drops when local stop PB pressed.

2.2.8 Ensure the readiness of OSU, switch on the motor and check whether the oil pressure is developed as
per the requirement by keeping the cock valve of �P� line closed.

2.2.9 Set the accumulator operating pressure as described in 1.3.5.

2.2.10 Charge the oil lines and keep OSUs on auto operation. Check the auto operation of OSU-motors to
maintain the operating pressure as per the requirement (1.3.5).

https://www.bhelpswr.co.in/Technical/C&I/Commissioning/Hp Bypass/Commissioning Checklist.htm 9/15


4/30/22, 12:48 PM Technical Feedback

3.0.0 Commissioning

3.1.0 Check the operation of bypass valves (BP), Temperature control valves (BPE) and the Isolation valve
(BD) from control desk (UCB). Adjust the stroke locally for full open/close (4 to 20 mA).

3.2.0 Calibrate the position feed back transmitters for (BP) bypass valves as well as (BPE) temperature
control valves (5-15 mA).

3.3.0 Set for valve opening time of BP & BPE valves at 8 to 10 seconds for full open by adjusting the throttle
valve located in �P� line near the actuator of each valve.

3.4.0 Charge the oil in fast opening system. Check the operation of BP valves from UCB-Control desk �Fast
open� push button.

3.5.0 Check the timing for full open when the �Fast open� PB actuated. Set 3 seconds for full open by
adjusting the throttle valve in �P� line of fast opening system.

3.6.0 Ensure calibration of pressure and temperature transmitters. Extend supply and adjust for zero of the
span of each one (4 mA)

3.7.0 Check for the availability and proper termination of cable for fast opening criteria like (i) GCB open (ii)
Turbine load shedding relay operated (iii) Turbine trip (iv) Pressure deviation too high etc. and also for closing
criteria like condenser vacuum low, etc.

3.8.0 Check the over rides and interlocks for the following important functions.

3.8.1 For BP valves

- BP closing over ride

- BD closing over ride

- BD opening interlock

- BPE auto interlock

- Fast opening

- Protection over ride

3.8.2 For BPE valves

- Auto interlock

- Opening signal

- Closing interlock

3.9.0 Keep the HP bypass system on Auto operation when the unit is in service and check adjust the
autoloops for (i) pressure master controller (ii) temperature controller and (iii) fast opening system.

4.0.0 General

4.1.0 The respective O & M manual should be made available before start to commissioning activities.

4.2.0 A format on �Check list for commissioning of HP bypass system� prepared taking into account of all
commissioning aspects enclosed as Annex. A. This format will be very much useful for commissioning engineers
to carry out the commissioning activities systematically.

4.3.0 A typical set values for 210 MW HP bypass system used in various cards and also in OSU is enclosed as
annex B for information. However, the set values as specified in the respective O & M manual of a particular
https://www.bhelpswr.co.in/Technical/C&I/Commissioning/Hp Bypass/Commissioning Checklist.htm 10/15
4/30/22, 12:48 PM Technical Feedback

project/unit capacity should be considered while commissioning the HP bypass system.

ANNEX A

BHARAT HEAVY ELECTRICALS LIMITED

PS SR < TECHNICAL SERVICES

CHECK LIST FOR COMMISSIONING

OF HP BYPASS SYSTEM

PROJECT UNIT NO. CAP : MW

Checks Remarks

01. Completion of erection

a) Mech. System :
b) Electrical :

02. All components as per bill of


material installed

a) Mechanical :
b) Electrical :

03. Acid cleaning of oil pipelines :

04. Ensure tightness of all joints :


and proper supprot

05. Cleanliness of oil tank :

06. Filling the hydraulic fluid in :


oil tank.

07. Serving of valve actuators, :


accumulator, etc.

08. Cable identification and proper :


termination.

09. IR value using 500V megger in (Mm)

- Motor of OSU :

- Cable :

- Control panel :

10. Extend both power supply to :


CP (Incomers) upto breakers and
check for its correctness
(Polarity and voltage)

https://www.bhelpswr.co.in/Technical/C&I/Commissioning/Hp Bypass/Commissioning Checklist.htm 11/15


4/30/22, 12:48 PM Technical Feedback

11. Energise CP by switching ON the :


breaker in power supply module
(NER � 30) and ensure healthiness

12. Energise CP and check all outputs :


and inputs are as per the
requirement

13. Ensure availability of all cards :


and also fixed in proper locations

14. Ensure isolation of power to motor


of OSU and energise the modules
SOL-10 (Control & Monitoring module)
Check the following

- Power contactors picking :

- Dropping of power contractors when


local stop P.B. pressed.

15. Close the Ball valve in �P� line :


of supply manifold. Switch on
the motors and check whether the
pressure is developed to the
required value.

16. Check the operating pressures and :


reset if required.

17. Ensure no oil leakage :

18. Carry out oil flushing

- Normal operating system :

- Fast opening system :

19. Calibration of cards using : (Values are set


test kit. As per Annex A1)

20. Operate all valves (BP, BPE & BD) :


from UCB control desk and carry
out the stroke adjustment for full
close/open for all valves (4-20 mA)

21. Calibrate the position feed back


transmitter for BP & BPE valves
(5 � 15 mA)

22. Check/Set the opening time for BP & :


BPE valves (8-10 seconds)

23. Check fast opening of BP valves :


when fast opening P.B. actuated from
control desk.

24. Set the opening time 3 seconds for :


full open when fast opening P.B.
actuated

https://www.bhelpswr.co.in/Technical/C&I/Commissioning/Hp Bypass/Commissioning Checklist.htm 12/15


4/30/22, 12:48 PM Technical Feedback

25. Put pressure & temp. transmitters :


in service and set for zero span
(4 mA)

26. Check over rides and interlock for :


BP, BPE and BD valves and correct
if necessary.

27. Check auto operation of control


loops for

- Pressure master controller :

- Temperature controller :

- Fast opening system :

28. Remarks :

ANNEX A1

HP BYPASS SYSTEM

(Enclosure to Annex A)

Project :

Unit No. :

CAP :

I Using test kit, the following cards were tested and values are set as noted against each :

Sl. No. Card location Card Setting Set


type on value

II The following settings were made on OSU

Sl. No. Description Unit Set Value

1. Switch No.1 Pump off Pa (1) Kg/sq.cm

2. Switch No. 2 Pump on Pe (2) Kg/sq.cm.


3. Switch No. 3 Pr. too low Dt (3) Kg/sq.cm.
4. Switch No. 4 Pr. too high Ph (4) Kg/sq.cm.
5. Accumulator bladder pr. Kg/sq.cm.
6. System oil pressure Kg/sq.cm.
7. Standby Accumulator bladder pr. Kg/sq.cm.

https://www.bhelpswr.co.in/Technical/C&I/Commissioning/Hp Bypass/Commissioning Checklist.htm 13/15


4/30/22, 12:48 PM Technical Feedback

ANNEX B

Typical setting values of 210 MW HP Bypass system

(For guidance only)

I For cards

Sl. Location Card Setting on Set Value


No.

01 B/021 RPV-10 U 0.25 V


02 B/055 RPV-10 U 0.25 V
03 B/071 RUM-20 U1 0.2 V
04 B/087 RUM-20 U1 0.5 V
05 B/095 RUM-20 U1 0.5 V
U2 1.0 V
06 B/119 RUM-20 U2 0.25 V
07 C/021 RUM-20 U1 0.2 V
08 C/029 RUM-20 U1 9.8 V
U2 0.2 V
09 C/037 RUM-20 U1 1.0 V
10 D/021 RUM-20 U1 0.2 V
U2 0.2 V
11 D/029 RUM-20 U1 9.8 V
U2 0.2 V
12 D/037 RUM-20 U1 1.0 V
13 E/021 RUM-20 U1 8.0 V
U2 8.6 V
14 F/021 RUM-20 U1 8.0 V
U2 8.6 V

II For Oil supply unit

Sl. Description Operating value Set value


No. (kg/sq.cm) (kg/sq.cm)

01 Pump off pa (1) (Switch no.1) - 160


02 Pump off Pe (2) (Switch no.2) - 110
03 Pressure too low dt (e) (Switch no.3) - 70
04 Pressure too high Ph (4) (Switch no.4) - 170
05 Accumulator bladder pressure 80 -
06 System oil pressure - 100
07 Standby accumulator bladder pressure 80 80
08 Blow off pressure of relief valve - 18

https://www.bhelpswr.co.in/Technical/C&I/Commissioning/Hp Bypass/Commissioning Checklist.htm 14/15


4/30/22, 12:48 PM Technical Feedback

Back to Technical Services

https://www.bhelpswr.co.in/Technical/C&I/Commissioning/Hp Bypass/Commissioning Checklist.htm 15/15

You might also like