Bert Bielefeld, Roland Schneider - Basics Budgeting-Birkhäuser (2014)
Bert Bielefeld, Roland Schneider - Basics Budgeting-Birkhäuser (2014)
Bert Bielefeld, Roland Schneider - Basics Budgeting-Birkhäuser (2014)
BUDGETING
Bert Bielefeld, Roland Schneider
practical basis.
DESIGN
PROFESSIONAL PRACTICE
FUNDAMENTALS OF PRESENTATION
CONSTRUCTION
PROFESSIONAL PRACTICE
BUILDING PHYSICS AND BUILDING SERVICES
BUILDING MATERIALS
LANDSCAPE ARCHITECTURE
URBANISM
THEORY
BASICS
www.birkhauser.com
Bert Bielefeld – Roland Schneider
Budgeting
Bert
Bert Bielefeld
Bielefeld –- Sebastian
Roland Schneider
El Khouli
Entwurfsidee
Budgeting
Birkhäuser
BIRKHÄUSER
Basel
BASEL
Contents
Foreword _7
Introduction _8
In conclusion _65
Appendix _66
Literature _66
The authors _66
Foreword
The key part of an architect’s job, alongside design and planning work,
lies in managing matters relating to the project and the client. This
includes organizational, technical and financial aspects: from planning
the sequence of events, tendering, deadline planning and costing via site
management to handing over to the client. Here efficient and successful
building project management relies essentially on the confident handling
of building costs and deadline planning.
It is the planner’s duty to deploy the client’s money for the building
work as the client intended. As a ruler the planner has a pre-arranged
budget that he has to distribute between all the costs generated in the
course of the work undertaken. Keeping to the prescribed budget is usu-
ally crucial to the success of the project as a whole.
7
Introduction
The relevance of Estimated and actual costs are a key topic for client and architect in
construction costs many building projects. This is not least because the client has to invest
a considerable sum in a building project, a sum that in many cases is far
larger than other expenditure. It is therefore essential for the client that
contractors work within budgets. This applies particularly when money
is being invested in properties to provide a return on investment, where
subsequent income (such as rents or sales) is set against the necessary
expenditure (building costs, financing costs, depreciation, maintenance
costs). The yield or profit (income minus expenditure) from property
investments is a key criterion in deciding in favour of the project, and in
its success. Even slight building price rises during the construction phase
can drag the project into loss – with consequences that can last for many
decades.
Life cycle costs Even if this time span can entail considerable financial fluctuation, it
is very short if measured against the life cycle of a building, but will still
make a substantial impact. Financial decisions, e.g. about options for
construction or domestic services, have an effect throughout the entire
use or life cycle of the building, and lead to differing running costs. If the
costs generated (heating, water and power supplies, repairs, mainte-
nance etc.) while the building is being used are added up, they will be
substantially greater than the initial investment. But investment in a build-
ing project has to be raised within a very short period of a very few
months or years, while running costs extend continuously over decades.
Higher initial investment in technical equipment, such as more efficient
heating systems, for example, can achieve significant savings within the
lifetime of the building. > Fig. 2
8
project development
n
litio
mo p
de
ro
t|
jec
en
t re
pm
alis
velo
atio
rede
n
hase
use p
use p
has
e
s
ta
t
en nd
ing
ishm em
rb pty
refu
maintenance |
ts
cos
ding
Life cycle
uil
ed b
imis
Min
g costs
d runnin
Minimise
Aim of investment:
Aim of investment:
long-term use
rapid progress
9
Useful life
Shell
Screed, plaster
Technical fittings
Surfaces
Renovation
Refurbishment
In-depth refurbishment
Fig. 3: Life cycle of building sections
Investments Alongside the investment costs while a new building is under con-
during use struction and the on-going maintenance costs, new investment is needed
at various intervals (maintenance and replacement costs) in the life cycle
of buildings in order to raise the structure to a more up-to-date technical
standard or to repair significant damage. Here a distinction is made
according to the part of the building concerned between various cycles
that may well turn out differently from project to project. The shell of the
building is generally the longest lasting section, and the end of its useful
life usually coincides with demolition and rebuilding. Sections with a ro-
bust finish such as the outer shell, plaster and screed are also pretty du-
rable and have to be replaced only after some decades. Technical fittings
(e.g. ventilation plants, plumbing, electrical installations, data systems
technology) and surfaces subject to wear and tear (e.g. paintwork, floor
coverings) last for a considerably shorter time and some of these are sub-
ject to very short investment cycles according to their function, construc-
tion method and maintenance level. > Fig. 3
10
investment would be significantly more costly than would be the case
if reversible and accessibly installed installations in a shaft were used,
for example.
Generally speaking, clients will keep a careful eye on holding con- Clients’ expectations
struction costs in check and – in the case of a longer-term interest in the
use of the building – on their impact on the use phase as well. So archi-
tects and planners must accept that an interest in information and suc-
cess are a central planning outcome and build the necessary working
steps into the process. Keeping to budget and to the planned completion
date are among the few physical known quantities that clients can and
will use to judge the quality and professionalism of the architects and
planners involved.
11
Basic budgeting principles
Some basic principles have to be set down at the outset if budgeting
is to be understood. As well as defining the technical terms involved, it
is above all necessary to ensure that the areas of influence and fluctua-
tion range of building costs are grasped, as this is the basic essential for
assessing the validity of costing. Handling imponderables and cost risks
transparently is a key feature of responsible care for the client during the
planning and construction process.
Fixing the budget A budget is fixed for almost all projects when the decision to put
them in train is taken, regardless of whether it is a new building or an
existing project, or whether a private or a public client is involved. The
budget is not the same as the sum of money that provides the planning
base for the work of architects and specialist planners. As a rule the
budget contains additional cost factors for the client, e.g. plot acquisi-
tion, financing costs, additional internal costs, legal advice and solicitors’
costs etc. Project related cost factors are relevant to the planning team
◯ as a costing specification.
12
WLC, whole life costs
Under the minimum principle, it is assumed that the client has fixed Minimum/maximum
quality requirements and that these are to be realised at the lowest pos- principle
sible building costs. This applies, for example, when there are already
fixed rental contracts in place, including building descriptions relating to
later users, or if a hotel chain is building another hotel following a tried
and tested, financially optimised scheme.
Budgeting is the generic term for all activities carried out during the Budgeting
planning and building process. Generally this includes listing costings,
13
Minimum principle Maximum principle
Building cost
Building cost
Quality Quality
monitoring and checking results and events within the process, and also
controlling activities such as feeding price increases into the budget.
Cost classification Another key factor is the way in which costs are presented and struc-
tured. Here a distinction is made between two fundamental ways of look-
ing at things:
14
Structural Building components Contract
component bases award bases
– plaster rendering
Dry wall construction and rendering
– wall tiles
plasterboard walls
plaster rendering
Ceiling costs
Tiles and ashlar
– reinforced concrete ceiling
wall tiles
– floating screed
floor tiles
– carpeting
– floor tiles Floor covering work
– plaster rendering carpeting
Costing parameters
Building costs are calculated mainly by following a scheme of multi-
plying volumes/quantities within a costing parameter and then adding
in individually identified costing parameters where appropriate. Here a
distinction has to be made between various cost parameter types.
—— Cubic capacity/plot area-related costing parameters
—— Cost parameters for building components/raw elements (ceiling,
roof, wall)
—— Cost parameters for building components/light elements (ceiling
rendering, reinforced concrete ceiling, screed, floor covering)
—— Unit prices/tender prices (request for tenders or previously con-
cluded projects)
—— Construction estimate from contractors (personnel costs, material
costs, site overheads)
15
Fig. 7: Specimen structural component based costing following German DIN 276
16
700 Additional construction costs 710 Client requirements
720 Preparation for property planning
730 Architects’ and engineers’ fees
740 Expert reports and consultation
750 Artistic work
760 Financing costs
770 General additional construction costs
790 Other additional construction costs
order to do this, the allotted overall sum required for a building and cor-
responding values such as
—— gross cubic capacity (GCC) as the building volume
—— gross floor area (GFA) as the sum of all the storey areas including
construction areas or
—— usable area (UA)
has to be established. Dividing these into each other gives rough val-
ues per square or cubic metre for future projects. Values of this kind often
come in very useful in the early stages of a project, when no precise data,
plans or quality requirements are available.
One major problem when using volume- or area-related parameters Cost generators
arises because these do not relate to the actual cost factors. > Fig. 8 ◯
17
component part
demolition
Lack of coherence when using gross area Costs according to cost generators
18
Specification level
Building element dry wall including
with quality requirement additional components
Fig. 9: Connection between building elements and unit prices (UP) in a tender
But building elements also include the whole range of typical addi- Inclusive price
tional components. So when setting a price per m² for floor coverings it
must include skirting boards, connecting bars, penetrations etc., and a
dry wall structure must include doorways, wall ends, connections etc. in
the price per m². > Fig. 9
Unit costs are the accounting prices offered by the contractor for Unit cost
each individual item in a tender. The unit cost in agreed contracts after
precise calculation (not all-in contracts) forms the contractual basis
between client and contractor. It is also possible to work out costs based
on unit prices before the contract is awarded. This approach will be pre-
ceded by tenders backed up by statistically determined unit prices.
Costs that can be allocated directly are known as single partial ser- Individual partial
vice costs. These include wages, the cost of materials, equipment and service costs
machine costs and where applicable outside service costs that can be
allotted to a service and are offered as an item for tender.
19
specification items
Wages Materials Equipment Outside services
Manufacturing costs
Costs for
The relevant wage elements within a unit costing are calculated from
the average wage and the amount of time needed to produce one square
metre of tiling, for example. The average wage includes social and addi-
tional wage costs, as well as the actual wage paid to employees. To cal-
culate this, all the costs generated in a year for an employee are divided
by the number of effective working hours per year (minus annual leave,
sickness, training, public holidays etc.).
The relevant material costs within a unit costing include the purchase
price for materials such as tiles, tile adhesive, and grouting cement for
tiling, and also additional costs for breakages, waste etc. Auxiliary build-
ing materials (e.g. shuttering, supports) and fuel (e.g. fuel for a digger,
power for a screed machine) are included in the calculation.
20
Once all the above-mentioned costs that can be directly itemised Overheads and
have been calculated, they are added to individual costs within the rel business expenses
evant section of the work. All items are additionally increased by supple-
ments for further costs that may arise. These include building site over-
heads, general business costs and supplements for risk/profit.
Building site overheads (BSO) include all costs that cannot be allo-
cated directly to the building work but that are nevertheless generated
within the building operation. This includes items such as accommoda-
tion expenses, site insurance, expenses on the contractors’ management
side etc.
Finally, risk and profit (R+P) represent the commercial result that the
building project would like to achieve, over and above the previous prime
costs.
21
fixing budget prediction
cost
estimation
point
planning realisation
actual costs
—— Carry out the best possible risk investigations. > Chapter on assessing
cost risks
—— Do not see costing as static but update it throughout the whole
process and keep adjusting it to current developments. > Chapter on
updating the budget
General influences that may well make the project in question dif-
ferent from your own have to be taken into account, particularly in the
case of parameters that are not directly linked to cost factors. > Fig. 12
Scale and context The scale of a project is highly relevant to the costs per square
etre, as small projects are often associated proportionately with higher
m
expenditure.
If very difficult sites are involved such as an inner city area that has
to be developed in its entirety, then it will be extremely difficult and
expensive to organise the building site, as it may be that external areas
22
plot
function
quality
installation level
costs
time
organisation
size
form
will have to be rented and streets closed, which will cost money. If the
site is not accessible by a developed road (e.g. a research observatory
in a high mountain range), then considerable expenses may well be gen-
erated in getting to the building site. ●
It is goes without saying that different buildings such as dwellings, Function and
offices, warehouses or laboratories cannot be compared in terms of vol- complexity
If the project for which estimates are to be prepared is within the Projects in existing
e xisting building stock and is to be converted or refurbished, consider building stock
ably greater costs will be involved than for a new building. In the sphere
23
of monument preservation, individual finishing and adjustment work is
often necessary, with large numbers of personnel involved. Many build-
ing contractors work on the basis of higher expenditure simply because
the project in question deals with existing building stock. They know from
experience that wide-ranging problems and special features will mean
that it will not be possible to work as efficiently as for a new building.
Building period The building period required for a project can also be very important
if building has to be carried out very quickly or will be subject to a large
number of interruptions. If the contractor can use employees only for
short periods – for example because breaks have to be taken in the
course of work on projects in existing building stock that continue to be
in use – s/he will also have to factor in wage costs for the unproductive
intermediate periods. If realisation times are very short, additional costs
for personnel and machines will have to be built in. The provision of build-
ing site facilities can also be a key factor in terms of overall costs, espe-
cially if these costs are not reflected in the physical end result – the fabric
of the building.
Quality The quality of both architecture and the materials is significant in the
same way. Products made mechanically in large production runs offer
considerable savings over components made by hand. Material prices
can rise exponentially in the luxury sector, for example for kitchens, bath-
room furniture, tiles, facades etc. In the case of individually designed and
produced components such as special facade structures or windows it
may be necessary to take further expenses into account, such as individ-
ual permits and technical experts, as well as individual manufacturing
costs.
Wages and Generally speaking, the question arises of the extent to which pro-
material costs ducing a construction element is very labour-intensive and thus domi-
nated by wage costs, or whether its key features are rapid installation
and possibly high material costs. In countries with high wage levels it is
preferable to opt for industrial prefabrication and simple delivery/instal-
lation instead of craft work and raw materials processed on site.
24
But regional and local market fluctuations have to be taken into Market prices/
a ccount, as well as world trade and international raw material prices. If economic
developments
the building trade is doing well in the economic cycle and building con-
tractors have full order books, prices will be much higher than in times
of underemployment when every contractor is desperate for orders.
Sometimes prices can fluctuate by 20–30 % between recession and
growth phases.
Risks in the broader sense are fundamentally assessed on the basis Damaging effects
of the incidence rate and the damaging effect in each case. In particular, and the incidence
rate
the risks that are very damaging with disastrous consequences and are
very likely to occur have to be limited in advance. The rigour of the exam-
ination and the limits to due diligence are fixed for individual projects.
It can be helpful to limit risk to a tolerable and above all financially via-
ble level by using the ALARP method (As Low As Reasonably Practicable).
> Fig. 14
Cost risks can be allotted in terms of their origin in various risk areas. Market and
As has already been explained, market risks such as fluctuations in the commercial risks
25
Costs
Expense
Subsoil risks Subsoil risks also have to be taken into account. For example, high
groundwater levels can require elaborate reinforcement in the cellar and
temporary lowering of groundwater levels in the building phase. If the
subsoil turns out during the building phase to be non-loadbearing, com-
pensatory measures (pile foundations, soil improvement, anchoring, load
distribution slabs etc.), which are usually elaborate and very cost inten-
sive, have to be undertaken.
Risk in existing Particular risks in existing building stock have to be taken into
building stock a ccount for projects in existing stock. These can include:
—— contamination (asbestos, PCB, PAH, AMF, timber protection agents
etc.)
—— static stability can no longer be guaranteed (non-existent
documentation, corrosion, inappropriate interventions etc.)
—— data unavailable (missing plans/planning permission for the
project, unapproved modifications, building geometry etc.)
—— damage to parts of building (damp penetration, mould formation,
cracks etc.)
26
catastrophic
Extent of damage
critical
noticeable
minor
trivial
incidence rate
to be excluded in
no measures to be taken ALARP area advance
This is why is it necessary to assess the building land and any exist-
ing building where appropriate carefully at the beginning of the project,
in order to minimise the greatest of these risks.
Major uncertainties in terms of keeping within the costs as fixed fre- Costing risks
quently arise as a result of setting the project budget early and on the
basis of insufficient data. Fluctuation in the area- or volume-related
parameters arise because no reference has been made to cost factors
as described above, and in addition to this qualities are often described
imprecisely in the early stages, e.g. “average quality”, which leaves con-
siderable scope for interpretation.
27
Fig. 15: Example of a risk assessment
Risk assessment The first key basis for assessing cost risks involves addressing pos-
methods sible risk areas. While it is possible to reduce uncertainty through early
analysis and expert reports, risks cannot be definitely ruled out until
completion and the final invoice. So possible risks areas have to be
recorded from the outset, assessed in terms of damage caused and
the incidence rate, and then observed throughout the process and the
assessment updated in order to guarantee complete risk management.
As this involves considerable effort and expense, risk must be assessed
in direct relation to the project and an agreement reached about the level
of detail and assessment to be taken as a basis.
Now usually only a few potential dangers actually emerge during the
planning and building process, so it is not very helpful just to add up the
possible risk costs. So the risk budget can be assessed using various
mathematical processes, but this depends to a very large extent on the
client’s risk awareness. One possibility is to present the risks using the
following formula:
Risk buffer One typical approach in dealing with costs risks is to build in a risk
buffer. This can be placed in the costing as a cost item or planning in
optionally as a possibly quality reduction. > Fig. 16
28
Ascertained construction costs
Minimum investment
Construction costs
– statical measures – room sizes and types
– sound insulation requirements – function groups and access
– minimum energy standards – escape and emergency routes
– foundations – workplace requirements
– etc. e.g. air conditioning and lighting
– technical requirements
In this way, modules are identified that can be used for buffering
should a risk occur. These are usually based on finishing requirements
for the later stages of the project such as floor coverings, external facil-
ities etc. Essential basic requirements for this method are:
—— the client’s agreement
—— the cost relevance of the selected construction elements
(for example, the quality of the toilet walls offers only a very small
buffer in a EUR 20 million project)
—— that the contract has not yet been awarded (if parts of an agreed
building contract are cancelled, further payments still have to be
made to the building contractor)
29
Fig. 17: Example of modular risk buffering
Project
Money
development
Planning
Building begins
Shell
Completion
Outer walls complete
Fitting
and finishing
Risk
Possible buffers
Time
Risks and their financial implications, and their savings potential, can
be compared directly in this way, and related to a timescale. This also
shows up corresponding gaps in cover provision. > Fig. 18
30
Costing methods
There are various ways of drawing up costings. The choice of method
depends on the project phase concerned or the depth of planning
achieved. The fundamental principle is that costing figures are always
multiplied by a unit of quantity in order to be able to make a statement
about the costs to be expected. > Chapter on costings For example, the more
detailed the available information about the quality of wall and floor sur-
faces or technical domestic equipment standards, the more precisely
this can be taken into account when costings are being drawn up. There
is usually not much available in terms of detailed information at the be-
ginning of a project, as this has still to be established in agreement with
the client or the various specialist planners in the course of the planning
process. But the amount and type of space needed is usually fixed from
the outset, as this is clear from the intended use or from the prescribed
spatial programme, which means that appropriate cubic capacity and
floor areas can be worked out and costs calculated. The more details
about the planned building are fixed, the more possible it should be to
produce detailed costings. The various costing methods and their appli-
cation potential for various project phases are described below.
Cubic capacity is derived from the area of the building and its height
from the foundation of the floor slab to the top edge of the roof covering.
In Germany, cubic capacity parameters are defined precisely in DIN 277,
which calculates them as gross cubic capacity (GCC). Costing figures can
be obtained from national building cost information services ( > Literature
chapter), who record and evaluate these statistically by project type, fin-
ishing standard and use. > Fig. 20 It is also possible for individuals to de-
vise or set up their own costing systems, provided that a large number of
projects of the same type, similar size and finishing standard have been
planned, built and budgeted for. In such cases the building costs are
finally worked out at the end of the project and then calculated back to
the cubic capacity of the building as a rough reference unit. It is essen-
tial to ensure that uniform references are made to cost values and quan-
tities. Construction costs calculated from the cubature of the building
always remain imprecise, as it is necessary to rely on very rough assump-
tions about construction quality and to an extent about quantities as well,
and it may well be that no definitive building design is available. Direct
31
h
b
a
links with cost factors are also not available. > Chapter on costings So work-
ing out the expected building costs based on gross cubic capacity is sim-
ply a planning instrument for defining building targets in terms of quan-
tity and quality.
If the gross cubic capacity needed for a building project has already
been fixed, it is then possible to check the essential feasibility or financial
viability of a construction project by using product-specific cost figures.
Following the minimum principle > Chapter on concepts and structures, the quan-
tities here are provided by the gross cubic capacity and the qualities by
the choice of the project-specific cost figure. But by the client can follow
the maximum principle and name a certain sum for construction ex-
penses as the target cost specification, which will then make it possible
to aim for the maximum building size that can be achieved and/or the
best possible qualities and finish characteristics within the costs as fixed.
Example 1: An investor wants to erect a new office building. The gross cubic
Specifying the gross c apacity is laid down by the maximum size of building allowed on the
cubic capacity
plots, which is 3000 m³. The investor provides the architect with rough
information about the desired standard of finish and the material quality
of the building. But as no definite plans have yet been made for the office
building, the architect can draw up a costing only on the basis of the
information provided by the investor. The architect has no costings of his
or her own derived from similar buildings, and so turns to a information
service to find a comparable property that is closest to the design ideas
and the requirements for the new building. > Fig. 20
32
Fig. 20: Costings for average standard office and HQ buildings
It is usual to give certain price ranges (from ... to ...) for the cost
arameters. If no further clear and detailed information about the build-
p
ing is available it is advisable to use the average cost figures at first and
make the client aware of the fluctuation ranges by means of additions
and deductions.
The given cost figures actually lie between EUR 3000/m³ and
EUR 475/m³. So the fluctuation is moves between EUR 225,000 down-
wards and EUR 200,000 upwards.
An investor lays down a fixed investment sum of EUR 800,000 for a Example 2:
new office building. As he wants to let the building later, he wants the Specifying the
construction costs
architect to provide some information about the maximum built area he
can aim to achieve. Costings can be researched via standards fixed as in
example 1, and this means that details about the gross cubic capacity
that can be realised can also be obtained. The following calculation does
not represent an actual costing, but is an important planning instrument
in the early project phase.
The GCC that can be realised for the office building is estimated as
follows:
33
◯ Note: Once the gross cubic capacity that can be real-
ised is established it is possible, by using conversion
factors for the storey heights (incl. structures on floors
and ceilings), to calculate the gross area and build it
into the preliminary design for the building as a plan-
ning requirement. A further calculation based on the
net floor area of the building and deductions for neces-
sary additional areas can also lead to a statement
about the rentable space that can be realised without a
definite preliminary design for the building
the fluctuation range for the estimated possible gross cubic capacity is
between approx. 2,666 m³ and 1,684 m³.
Example 3: It is not unusual for the client to prescribe both the desired cubic
Specifying the gross c apacity and also a fixed budget for the building costs to the architect. If
cubic capacity and
the building costs this is the case, a costing can be calculated by dividing the target costs
by the desired cubic capacity, and this will give some insight into the qual-
◯ ity that can be achieved or whether the project can be realised at all.
The client would like to erect an office building with a gross cubic
c apacity of 3,500 m³ for EUR 800,000. The following equation makes it
possible to calculate a project-specific costing.
Now the architect has to set the calculated cost against the other
properties available for comparison in order to check whether the client’s
ideas can be realised at all. The lowest cost for comparable office build-
ings is EUR 300/m³ of gross cubic capacity. > Fig. 20 If the calculated cost
falls within the price fluctuations for the comparable properties, the build-
ing project can definitely be realised in the form desired. If, as in the sam-
ple quotation, the calculated cost falls clearly below that of the compa-
rable properties, then the architect’s targets are questionable. In this
case the architect and the client can decide whether to concentrate on
keeping to the target costs or to the desired gross cubic capacity, as it
seems that the project cannot be realised within the target costs. If the
desired gross cubic capacity still has to be achieved, the target costs will
have to be corrected upwards. If the client is prepared to scale the proj
ect down, the architect can follow example 1 and use a realistic costing
◯ to calculate the gross cubic capacity that can be realised.
34
Calculating construction costs by using the cubic capacity of a build- Advantages and
ing, as shown in the examples, is a very flexible planning instrument for disadvantages of
costing based on
early project phases without a definitive building design. But the results gross cubic capacity
must always be treated critically, and system-related fluctuations should
definitely be pointed out.
On the other hand, increasing the gross cubic capacity does not have
to go hand in hand with a catastrophic increase in costs.
that becomes larger, but this cannot be seen as increasing the cost.
◯ Note: The costings for gross cubic capacity should that he or she feels most closely resembles his/her
not be calculated from an average value for a typical own. Information about individual properties for com-
building typology alone. If an office building is being parison can be taken from the property details. Given
planned, for example, information from building cost inadequate links with the actual cost factors at the
information services will usually list several properties building elements level, the correct choice of property
for reference, differing in size and design. Here the for comparison is the only way of keeping any state-
architect should use the costs for the building project ment about costs as realistic as possible.
35
h + 1m
h
b b
a
a
Fig. 21: Factory halls with the same area and different gross cubic capacity
Costing based on Determining the expected construction costs based on the gross
gross floor area floor area uses similarly simple calculation methods to those used pre-
viously for gross cubic capacity.
36
b
a
2. The client sets a prescribed target cost. The gross floor area
that can be realised within the cost framework is calculated by
dividing the target costs by an appropriate cost figure (taking
the desired qualities into account).
An investor intends to put up an office building with a gross floor area Example 1:
of 3000 m². He asks the architect to estimate the building costs entailed Specifying the gross
floor area
so that he can raise the finance. The architect researches costings for
comparable properties intended for the same use and of the same size
(obtaining this information from construction cost enquiry services or
from his own experience of such costing), and is thus able to prepare a
first rough statement about the building costs. An average price of
37
EUR 1,500/m² GFA is to provide the basis for the calculation, and sub-
sequent fluctuations with additions and deductions are to be considered
when estimating the costs. > Fig. 20
The result of the calculation comes out at EUR 4,500,000 and can
deviate up or down by up to EUR 750,000 in each case on the basis of
the costings referenced.
But if the client specifies terms based on target costs or the gross
floor area and the target costs, simple calculation methods as in exam-
ples 2 and 3 can be used based on the gross cubic capacity.
Calculation based The calculation of construction costs based on the gross floor area
on the usable area of a building, as described above, is very easy for the architect to use,
and also readily comprehensible. But most clients are not property
◼ experts, and so can make relatively little of planning costs calculated in
this way. In the case of private housing construction and rented office
property the areas that can be actually used or let are placed in the fore-
ground, as it is based on these that later use or later income and profit
can be determined. A cost estimate relating to the usable area (UA) will
be more accessible to the client as he is familiar with his actual use-
specific area requirements from his own experience, and can thus eval-
uate a project better in terms of economic viability in this way. The client
can give the architect specifications for the usable area relatively easily
by referring to previous area requirements and any increase that is nec-
essary for the future. But it is not unusual for much more abstract spec-
ifications to be given, based for example on the necessary number of
employees laid down by a company (e.g. at least 1500 employees in sin-
gle offices), the number of beds required in a hotel, or on a particular
number of single or double rooms in hospitals.
38
If, as mentioned above, the client gives the architect much more
a bstract specifications, then the architect must establish the area needed
in each case and the usable area required for this, as this is the para
meter that is relevant for his construction planning. Construction costs
calculated by reference to area or cubic capacity can then be recalcu-
lated retrospectively to relate to project-specific abstract reference fac-
tors, so that the client can always keep an eye on this in the contexts of
financial viability checks. Area requirements and conversion calculations
made in relation to particular reference points should always be worked
out in close agreement with the client.
A client intends to erect an office building for 600 employees. As well Example 1:
as individual offices for the employees, the client says that, exactly as in Specifying the
number of employees
his present office building, approx. 400 m² of additional area is required
for toilets, corridors, foyer, kitchens, storage etc., and a further four con-
ference rooms each of 60 m². The architect works on the basis of simple
cubicle offices, each with an area of 14 m². Given the same economical
use of space as in the present building and the additional conference
rooms required in the new building, the following calculation for the us-
able area emerges:
Costing based on the gross floor area of a building is as quick and Advantages and
easy to use as calculation based on gross cubic capacity, but it is equally disadvantages of
costing based on floor
imprecise. If the usable area required is specified by the client or worked area and usable area
out by the architect, corresponding cost figures can be taken as a basis.
But then a decision has to be made when selecting the cost figures about
whether similarly economical use of space is possible for this particular
project. If the ground plan arrangement and access facilities were to
differ significantly, this would create problems in relation to the building
costs as calculated. This is why it is particularly important to select
39
c omparable properties correctly. It is also necessary to decide to what
extent additional floor space can or may be calculated into the usable
area, or the area that can be let out subsequently. Failure to take account
of the height of the building when using this method can lead to further
imprecision in the case of non-standard storey heights. As almost every
building client finds usable area a comprehensible and familiar para
meter, it offers the best way of checking specifications and requests, and
makes costs readily intelligible. Calculating the building costs to be ex-
pected by reference to the usable area can make the result noticeably
more precise if applied correctly, as the costing parameters take further
information about the financial viability of the space into account. But
this concealed information about the financial viability of the space can
also bring great imprecision in its wake if no reference objects with
appropriately realistic cost parameters are available for concrete com-
parison, or the depth of planning achieved for the project so far does not
◯ make it possible to say anything on this.
But these rough calculation methods are too imprecise for the later
planning stages, which means that a more detailed calculation method
is needed. One option here is to calculate the building costs in terms of
component elements. But a definitive building design is essential for this,
as quantities have to be calculated for the individual structural building
components (component elements) needed for the planned building. A
uniform procedure must be followed when establishing quantities for the
individual component elements. A component element applies to individ-
ual parts of the building such as an exterior wall, for example, a ceiling or
a roof, and it can be further broken down into construction elements.
◯ Note: Basically, the ratio of the usable area to the ◼ Tip: It is rare for a building to use the same compo-
gross floor area expresses the financial viability of the nent elements all the time. This is why it is necessary
space. The fewer the construction and traffic areas to distinguish between possible ceiling, wall and roof
needed for the same gross floor area, the more eco- structures clearly at an early stage when working out
nomical the building will be. the building costs, as this considerably increases the
accuracy of the costing, while only relatively unreliable
costing statements can be made without reliable infor-
mation about the composition of the individual
component parts.
40
outside wall
ceiling
1. tiles, d = 15 mm + adhesive
2. floating cement screed 6.0 cm
3. thermal insulation, footfall sound insulation 5.0 cm
4. reinforced concrete ceiling 25 cm
5. ceiling plaster rendering 1.5 cm
6. paint
41
Fig. 24: Example of a simple costing using component elements allocated to cost groups according to German
standard DIN 276.
Advantages and Costing based on component elements makes it possible to work out
isadvantages of
d the costs by reference to the cost factors, and is thus considerably more
costing based on
component elements precise than calculation methods using building volumes or areas. But it
is difficult to reduce the component elements to a single structural item
in each case. The calculation will take a lot more time if the component
elements are described and recorded in a sophisticated way, taking all
the different structural elements into account. But as has already been
pointed out, surface finishes, which affect the cost of a component ele-
ment significantly, are not specified until much later. Precise building
costs can be worked out very quickly and in a very uncomplicated way
for very simple buildings with few different structural features. But if a
building is planned in a way that is highly individual, technical and archi-
tecturally ambitious, calculation by component elements can result in a
high potential for imprecision. Like the above-mentioned costing meth-
ods, building projects in existing stock are very difficult to illustrate or
cost using component elements. A further problem lies in the fact that
different specialist areas or craftsmen doing the work are mixed up to-
gether when costing for a component element.
The list below shows which skilled workers are already involved in
the above-mentioned example of the ceiling:
42
The following skilled work can be needed for an outside wall as a
component element:
43
◯ Note: This means that a construction element ◯ Note: In the case of a dry construction wall, for
c annot be subdivided further according to its function e xample, it is important to have information about
in the building (e.g. a “wall, non-loadbearing or load- the thickness of the wall, details about the materials
bearing, including doors” can be subdivided into required for insulation, and also the materials and
non-loadbearing walls, loadbearing walls, and doors). the thickness required for the planking layers, as this
There are no construction elements that can be will imply certain fire- and sound-insulation require-
assigned to several work areas or tender units – for ments that make a crucial impact on the costs. If a wall
example, “ceiling plaster with emulsion paint” can consists of two separately constructed partition walls,
be subdivided as construction element one “ceiling this also affects costs considerably, as it increases the
plaster, rendering work” and construction element amount of time needed for the work, and thus the
two “emulsion paint, painting and decorating”. wages to be paid for doing it.
Allocation by rooms It makes complete sense to identify rooms in the construction ele-
ment catalogue. This is particularly helpful to the client in understanding
the planned qualities of the building. Rooms can be identified in groups
or by the numbers required. For example, if all the floor coverings in
the conference rooms in an office building are identical, floor coverings
in other rooms can be unambiguously defined using this description
44
exterior m² tiles
rendering
m²
floating
screed
masonry outside wall ceiling
m² reinforced
concrete ceiling
interior
rendering
m² ceiling
rendering
Fig. 25: Outside wall and ceiling as component elements broken down into construction elements
(e.g. “parquet floor, oak as in the conference rooms”). If the rooms are
identified meticulously and fully, the building description will also work
as a room schedule, as all the construction elements featuring in a
room or group of rooms can be presented clearly. But a table in a con-
struction element catalogue is considerably easier to work with than a
room schedule.
If the appropriate cost figures are now added to the construction ele Allocating cost
ment catalogue, it is possible to proceed with determining the costs. The figures
The chief advantage of costing based on construction element clearly Advantages and
lies in the additional use that can be made of the calculated costs by disadvantages
of costing based
re-allocating them in budgets for tendering units for individual craft skills. on construction
The building description with construction elements makes it possible to elements
define and adapt the qualities of the building as described more precisely
even when the project is under way. Ultimately it forms the basis for draw-
45
Fig. 26: Construction elements catalogue (with cost groups allocated according to German standard DIN 276)
46
Fig. 27: Construction element catalogue incl. allocation by room and quantity determination.
areas (trades). An example of this is shown in figure 29 for a tile and par-
quet floor and a loadbearing exterior wall. ◯
A specification for laying parquet, for example, would list all the items Example:
necessary for preparing the completed floor, including ancillary items (all costing based on
specifications
materials, protective measures, preparing the base, applying adhesive to
the parquet, smoothing and oiling the parquet, fitting footboards etc.) for
47
Fig. 28: Construction element catalogue incl. room allocation, quantity determination and cost figure allocation
Cost Construction Work type Room groups Quantity Inclusive Total price
group element price
the entire project on all floors. When the specification is complete, the
architect can insert average unit prices for the individual items; multiply-
ing them by the quantities determined will then give the total sum required
for the parquet work. Once all the specifications for the different work
needed to complete the building have been drawn up, the unit prices for
the individual services can be added in as well. The individual specifica-
tion totals then represent one tendering unit at the planning stage before
the project is realised. Adding together all the specification totals with
their unit prices gives a very realistic view of the total costs to be expected
48
exterior wall
masonry m² tiles
Item 1 Prepare floor
Item 2 Floor tiles
Item 3 Skirting tiles
...
m² parquet
Item 1 Prepare site Item 1 Prepare floor
Item 2 Calcareous sandstone Item 2 Parquet laying
Exterior masonry Item 3 Baseboard
...
Item 3 Cover apertures
with lintel
...
Fig. 29: Construction elements broken down into individual service items
for the project as a whole. The specifications can then also be drawn up
in a simplified form, with all the items defined by short titles only.
Account must also be taken of the fact that drawing up all the nec- Advantages and
essary specifications takes a comparatively long time, so the architect disadvantages of
costing based on
has to look at each project phase and decide whether the construction specifications
element or component element method might not be the right tool for
determining the costs in this case. But if the planning is at a very ad-
vanced stage, no additional time will really be needed. On the contrary,
costing based on specifications in fact anticipates planning work that the
architect has to do anyway as part of putting building work out to tender.
The work can be cut down to some extent by using simplified specifica-
tions, but the individual work items have to be expanded and adapted
subsequently so that they can be used as a basis for seeking tenders
from contractors.
49
Fig. 30: Costing for parquet work using a specification
of work for which wide-ranging information and thus certainty about plan-
ning are available can be described and priced sufficiently precisely
based on specifications, whereas cost determination based on construc-
◯ tion methods can make sense in other areas.
50
Continuing the budgeting process
There are no circumstances in which a building cost calculation that
is set too low from the outset can produce a satisfactory outcome, as it
will not be possible either to deliver the desired quality or to complete
the full number of rooms required. This is why it is essential to conduct
cost planning continuously and in stages in order to work within the proj
ect budget and thus keep the client satisfied. The foundation stone for
this is laid when the project budget is first fixed. The following describes
the project phases into which cost planning can be divided meaningfully
and how the insights or results provided should be updated in the next
project phase.
Costs must be fully presented at the point of each key decision by Costing stages
the commissioning client as the project proceeds and handed over as a
basis for decisions along with the actual project documents such as plans,
for example. The usual decision levels are:
51
It is essential to check at this stage whether the specified cost and
the desired usable area are statistically realistic, by reference to sample
projects for which budgets have been calculated.
At this stage, costs are compiled with reference to the design using
cost figures based on construction components/elements backed by
quantity surveying. This compilation is more detailed than at the last
stage, as considerably more information about the project and the shape
it is taking is available as a basis for costing.
52
t endering and awarding procedure. Planning precision is enhanced by
the degree of detail provided by the quality requirements in the tender’s
global description sections, and then by drawing on the detailed specifi-
cations, and this can lead to marked changes in the costs. After the doc-
uments have been submitted there is very little scope for making rel
evant changes, particularly in the case of public commissions. Thus fixing
the “agreed construction work” is crucial within the tender process.
53
Fig. 31: Example of a price comparison
Tender 1 Tender 2
Item Work involved Quantity Unit price Total price Unit price Total price ...
01.001 Site preparation Flat rate EUR 200.00 EUR 200.00 EUR 450.00 EUR 450.00
01.002 Ceiling rendering 60 m² EUR 19.00 EUR 1140.00 EUR 22.00 EUR 1320.00
01.003 Interior wall rendering 40 m² EUR 25.00 EUR 1000.00 EUR 20.00 EUR 800.00
01.003 Exterior wall rendering 40 m² EUR 42.00 EUR 1680.00 EUR 46.00 EUR 1840.00
Cost control Every cost determination stage is bound to deviate from its pre
decessor because new information has come to light, changes have been
made or matters have become more concrete. So it is necessary to rec-
oncile the current cost determination stage with the one before it and
with the costs as originally specified. Here detailed reasons have to be
supplied for any changes to the overall costs and how they can be picked
up again if necessary. One way of presenting this via the planning and
construction process is to produce a decision list and a list of changes,
in which the main events after commissioning relevant to costs are listed
chronologically. > Fig. 32
Sometimes the client or the project managers will insist that every
decision or request for change by the client that is relevant to costs must
be assessed and shown to the client. This makes for precise documen-
tation of the cost-relevant processes.
54
Wall structure
Facade paint, white
Lime cement plaster, 3.0 cm
Porous concrete, 36.5 cm
Interior wall rendering, gypsum 1.0 cm
Emulsion paint, white
Ceiling structure
Stoneware tile, 1.5 cm + adhesive
Cement screed, 6.0 cm
Footfall sound insulation, 5.0 cm
Reinforced concrete ceiling, 25.0 cm
Ceiling rendering, gypsum, 1.5 cm
Emulsion paint, white
The aim is to put the client in a position to think over his or her deci- Controlling
sions, and where appropriate to compensate for them by taking other interventions
measures. For example, this could entail reducing the quality of finish
elsewhere, reducing the usable area or providing additional financial
resources. It is essential here that the client be informed immediately or
at a time close to the decision about which past arrangements have led
to which consequences, and not simply be given a summary in a later
project revision. So this work is not restricted to particular cost determi-
nation stages, but must accompany the process and be carried out
continuously.
precise qualities and surface finishes. This is because materials and sur-
face qualities tend to be decided on successively in the course of the
planning process. So in the first place costs are worked out by working
on general assumptions about quality. > Figs. 33 and 34
55
Fig. 34: Simple costing based on construction elements for figure 33
Clients will often have said nothing at all about individual materials
or quality, so that the architect has to set a first general quality standard.
The client will then see from these listings what standard the architect is
working from, and what general quality standards the architect has used
when determining the construction costs.
Continuing the Decisions are made and details are regularly clarified throughout the
planning process planning process, in meetings with the client, for example, so that these
can then be incorporated into the current costing. > Fig. 35 Cost changes
can then be identified directly and passed on to the client by matching
● the qualities laid down in the list to the relevant costing figures.
56
Fig. 35: Concrete detail for cost determination based on construction elements
57
Fig. 36: Costing based on contract award
58
Fig. 37: Matching up budgets and contract award sums
pared directly when submitting and assessing the offers. This listing
forms the basis for keeping an eye on costs throughout the building phase.
59
Realisation planning Tenders invited for Building work
Work on shell work on shell carried out on shell
Dependencies/Re-planning
Realisation planning
for …
Time sequence
Fig. 38: Typical sequence for planning and contract award during the building phase
Structuring The following cost control sequence is triggered by each award unit:
cost control 1. Fixing the budget
2. Invitation to tender and submission of offers
3. Assessment and checking of the contract award sum with the
budget specification
4. Cost predictions and cost control during the building process
5. Following up changes in the scope or content of work
6. Cost statement after checking the final invoice
> Chapter on working with trade-referenced cost determination in the contract award phase
Sequence of events If contracts for the building work are awarded to several firms, this
with single tenders scheme makes it possible to check on each individual contractor in terms
of costs. This is because the contractors are all appointed at different
times. So it can come about in the course of the building process that in-
dividual items of work (e.g. earthworks, shell construction) have been
paid off, but later items have not yet even gone out to tender and been
awarded. Other jobs may still be in progress. If a current cost estimate
60
Shell Final invoice total
Fig. 39: Working out the current financial position during the building phase
Checking contractors’ invoices can reveal that the bills of quantities Information gained
as originally accepted clearly differ from the quantities invoiced. Any from checking the
invoice
quantity deviations for items affecting costs should feature in the table
of costs. ●
◯ Note: In the case of a unit price contract, payment ● Example: Quite often the ground to be built on is
is made according to the amount of work done. Con checked only by random test drillings prior to the work.
solidating payment into a lump sum shifts the risk The resultant assumptions about quantities can turn
in relation to quantities to the contractor. This depends out to be wrong once soil starts to be excavated. If this
on the degree of detail provided in the description of occurs, the costs should be adjusted correspondingly
the agreed construction work. in the case of unit price contracts.
61
Fig. 40: Structure of a costs table during the building phase
Incorporating It is not unusual for work to be listed that is not included in the
additional sums “agreed construction work”, perhaps because it was forgotten when the
work went out to tender, was not open to identification, came to light only
in the building phase, or was ordered by the client at a later stage. Sums
that deviate from the “agreed construction work” (also know as additional
payments), can be generated as modifications to work required or delays
during the building period, as well as by the above-mentioned quantity
deviations. Changes to work required include all changes ordered by the
client, plus necessary work, exclusions/partial terminations etc. Costs
generated by delays during the building period mean all the additional
costs resulting from obstacles to the building process, extending or
speeding up the building period.
Cost predictions But it is not only additional costs that make the building process more
expensive. Often the site manager will notice things that have not yet
been addressed but will or could generate additional costs as the build-
ing process moves on. For example, if items were omitted from the invi-
tation to tender, then the costs generated should be built into the cost
predictions as soon as they are identified – even if the contractor con-
cerned has not yet made an additional charge.
62
Fig. 41: Established costs for the client based on contracts as awarded
The costing that documents the actual project costs (> Chapter on the Total of all final
is made up of the sum of all the
basic approach to updating and serving cost planning) invoices
costs incurred and thus represents a survey of all the costs already gen-
erated, and represents the final cost determination stage. Usually a list
of all the costs in the final invoices is drawn up here and presented as
a total sum, and this is usually sufficient information in terms of the
client’s interest.
If the table structure for the planning and construction process had Re-organisation based
been updated systematically, the contract-based totals can be re-allo- on structural
components
cated to the original construction elements without a great deal of effort.
This has distinct advantages for the architect, as it means that he or she
can assess the project as a whole and thus draw conclusions and deter-
mine costs for future projects.
To do this, the sums actually invoiced, including all changes, addi- Compiling
tional charges etc. are divided by quantities invoiced. When compiling cost f igures
cost figures based on construction elements, care must be taken that all
63
Fig. 42: Determining costing figures
Job/contract Heading Sum due under Quantity invoiced Inclusive price cost
award unit heading figure
Dry construction
Dry-built walls EUR 24,154.50 517.56 m² approx. EUR 47.00/m²
Firewalls EUR 3468.36 46.50 m² approx. EUR 75.00/m²
Suspended ceilings EUR 11,210.42 214.67 m² approx. EUR 52.00/m²
... ...
the additional constituent elements are added in again. This can be done
most successfully if all the essential building components including
relevant secondary items are listed under their own headings in the invi-
tations to tender. In this way the specific value can be derived from the
invoiced sum under this heading and the total quantity under the main
◯ item. > Fig. 42
◯ Note: It is important for planning practices to set up ◼ Tip: Costings should always be entered in a personal
their own costing databases. Costs derived from database without value added tax, in case this is
their own projects define costs according to the indi- altered by law. It also makes sense to name the con-
vidual quality requirements, constructions and degrees struction year as well, so that cost values can still be
of detail customary for the practice, and are therefore used by allowing for inflation and statistical adjust-
significantly more precise than average statistical val- ments. Statistics offices in almost all countries keep
ues that are generally accessible. records of significant price fluctuations in the build-
ing sector.
64
In conclusion
Construction costs are a key element for the client in almost all
a rchitectural projects, and determine their success or failure. The aes-
thetic quality of a building is very important, but it is governed by subjec-
tive evaluation criteria – as a layperson, the client can judge a building
technically only to a limited extent. But apart from the user-friendliness
of a building, keeping to costs and where necessary to deadlines are fixed
factors that are extremely important for the client, who can also assess
them very readily. Keeping within the planned building costs can always
be checked in terms of concrete figures. High creative ambitions and
good architectural concepts can be realised and implemented attrac-
tively only if they are based on professional budgeting. This ensures that
the desired quality will be delivered, but also guarantees that the project
as whole is financially viable, and no architecture can be realised if this
does not happen. So it is essential for architects to see the subject of
costs as an essential planning element, to tie the emerging designs and
projects together in a structured way, and to cost them carefully.
65
Appendix
Literature
Bert Bielefeld, Lars-Philip Rusch: Building projects in China, Birkhäuser
Verlag, Basel 2006
Bert Bielefeld, Falk Würfele: Building projects in the European Union,
Birkhäuser Verlag, Basel 2005
Chartered Institute of Building (ed.): Planning and Programming in
Construction, Chartered Institute of Building, London 1991
CIRIA: The Environmental Handbooks for Building and Civil Engineering:
Vol 1. Design and Specification, Thomas Telford Ltd, 1994
Sandra Christensen Weber: Scheduling Construction Projects.
Principles and Practices, Pearson Prentice Hall, Upper Saddle
River, NJ, 2005
Institution of Civil Engineers, Association of Consulting Engineers and
Civil Engineering Contractors Association: Tendering for Civil
Engineering Contracts, Thomas Telford Ltd, 2000
Richard H. Neale, David E. Neale: Construction Planning, Telford,
London 1989
Jay S. Newitt: Construction Scheduling. Principles and Practices,
Pearson Prentice Hall, Upper Saddle River, NJ, 2009
The authors
Bert Bielefeld, Prof. Dr.-Ing. Architect, architect teaches construction
economics and construction management at Siegen University and
is managing partner of the bertbielefeld&partner architecture
practice in Dortmund.
Roland Schneider, Dipl.-Ing. M.Sc. Architect, is academic assistant in
the construction economics and construction management
department at Siegen University and managing director of the
art-schneider architecture practice in Cologne.
Thanks go to Ann Christin Hecker and Benjamin Voss for their support
in creating the graphics.
66
Also available from Basics Modelbuilding Basics Project Planning
Birkhäuser: Alexander Schilling Hartmut Klein
ISBN 978-3-0346-1331-6 ISBN 978-3-7643-8469-2
Design
Basics Design and Living Basics Technical Drawing Basics Site Management
Jan Krebs Bert Bielefeld, Isabella Skiba Lars-Phillip Rusch
ISBN 978-3-7643-7647-5 ISBN 978-3-0346-1326-2 ISBN 978-3-7643-8104-2
www.birkhauser.com
Series editor: Bert Bielefeld aterial is concerned, specifically the rights of
m
Conception: Bert Bielefeld, Annette Gref translation, reprinting, re-use of illustrations,
Translation from German into English: recitation, broadcasting, reproduction on
Michael Robinson microfilms or in other ways, and storage in
English copy editing: Monica Buckland databases. For any kind of use, permission
Layout print edition: Andreas Hidber of the copyright owner must be obtained.
EPUB production: Kösel Media, Krugzell
This publication is also available as a softcover
Library of Congress Cataloging-in-Publication (ISBN 978-3-03821-532-5) and in a German lan-
data guage edition (ISBN PDF 978-3-0356-1260-8;
A CIP catalog record for this book has been ap- ISBN EPUB 978-3-0356-1180-9).
plied for at the Library of Congress.
© 2014 Birkhäuser Verlag GmbH, Basel
Bibliographic information published by the P.O. Box 44, 4009 Basel, Switzerland
German National Library Part of Walter de Gruyter GmbH, Berlin/Boston
The German National Library lists this publica-
tion in the Deutsche Nationalbibliografie; ISBN 978-3-0356-1292-9 PDF
detailed bibliographic data are available on the ISBN 978-3-0356-1311-7 EPUB
Internet at http://dnb.dnb.de.