Add Progress 21 8
Add Progress 21 8
Add Progress 21 8
1 Pekerjaan Galian Katingan Exca Hyundai STA13.605-sta 13.620, 09.00-16.00 M3 390,000 Continue Pekerjaan Sloop & Galian Katingan STA 13.590-STA 13.640
Man Power
No No. Tools Unit Qty
DIRECT QTY INDIRECT Qty
1 Operator 1 1
2 SHE Officer Admin HSE 2
3 Helper 1 HRD Manager 3
4 Flagman PR Manager 4
5 Driver General Admin 1 5
6 Supervisor Project Manager 6
7
8
9
10
TOTAL DIRECT 2 TOTAL INDIRECT 1 TOTAL TOOLS 0
TOTAL MANHOURS 18 9
TOTAL MANHOURS PREVIOUS 0
TOTAL MANHOURS CUMULATIVE 27