FIELD DAILY ACTIVITY REPORT

CLIENT : PT Sarku Enjinering Utama


SUB-CONTRACTOR : PT Saloi Pusaka Halmahera
CONTRACT : SEU-005-SCA-2103-0001
PROJECT : Pelaksanaan Pekerjaan Jasa Pembangunan Jalan - 2103 Project
Location : Gunung Hamiding
Report No : Rain Recapitulation Table
Date/Day : 21 Augustus 2023 07.00-08.00 08.00-09.00 09.00-10.00 10.00-11.00 11.00-12.00 12.00-13.00 13.00-14.00 14.00-15.00 15.00-16.00 16.00-17.00
Working Hours : 07.00 - 17.00 C : Clear C C C C C C C C CL
Work Category : Construction CL : Cloudy
TR : Tiny Rain
Location : Gn. Hamiding HR : Heavy Rain
Manpower Volume Qty Progress Summary Activities
No. Today Activities / Achievement UNIT Qty Previous Today SUM % No. Tomorrow Activities Plan

1 Pekerjaan Galian Katingan Exca Hyundai STA13.605-sta 13.620, 09.00-16.00 M3 390,000 Continue Pekerjaan Sloop & Galian Katingan STA 13.590-STA 13.640

Man Power
No No. Tools Unit Qty
DIRECT QTY INDIRECT Qty
1 Operator 1 1
2 SHE Officer Admin HSE 2
3 Helper 1 HRD Manager 3
4 Flagman PR Manager 4
5 Driver General Admin 1 5
6 Supervisor Project Manager 6
7
8
9
10
TOTAL DIRECT 2 TOTAL INDIRECT 1 TOTAL TOOLS 0
TOTAL MANHOURS 18 9
TOTAL MANHOURS PREVIOUS 0
TOTAL MANHOURS CUMULATIVE 27

No. Equipment Qty No. Material Unit Previous Today Total


1 LV (Double Cabin 4X4) 1 1.
2 Excavator HYUNDAI 1 2.
3 Excavator Hitachi 3.
4 Dump Truck 4.
TOTAL EQUIPMENT 2
DAILY PROGRESS REPORT

CLIENT PT Sarku Enjinering Utama


CONTRACTOR PT Saloi Pusaka Halmahera
CONTRACT SEU-005-SCA-2103-0001
PROJECT Pelaksanaan Pekerjaan Jasa Pembangunan Jalan - 2103 Project