1. Field daily activity report from PT Saloi Pusaka Halmahera for the road construction project at Gunung Hamiding for client PT Sarku Enjinering Utama. 2. Today's activities included excavation work using excavators from Hyundai and Hitachi between stations 13.600 to 13.640 and manpower of 3 direct staff and 1 indirect staff. 3. The plan for tomorrow is to continue slope excavation and embankment work between stations 13.590 to 13.640.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
36 views2 pages

Add Progress 22 8

1. Field daily activity report from PT Saloi Pusaka Halmahera for the road construction project at Gunung Hamiding for client PT Sarku Enjinering Utama. 2. Today's activities included excavation work using excavators from Hyundai and Hitachi between stations 13.600 to 13.640 and manpower of 3 direct staff and 1 indirect staff. 3. The plan for tomorrow is to continue slope excavation and embankment work between stations 13.590 to 13.640.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

FIELD DAILY ACTIVITY REPORT

CLIENT : PT Sarku Enjinering Utama


SUB-CONTRACTOR : PT Saloi Pusaka Halmahera
CONTRACT : SEU-005-SCA-2103-0001
PROJECT : Pelaksanaan Pekerjaan Jasa Pembangunan Jalan - 2103 Project
Location : Gunung Hamiding
Report No : Rain Recapitulation Table
Date/Day : 22 Augustus 2023 07.00-08.00 08.00-09.00 09.00-10.00 10.00-11.00 11.00-12.00 12.00-13.00 13.00-14.00 14.00-15.00 15.00-16.00 16.00-17.00
Working Hours : 07.00 - 17.00 C : Clear
Work Category : Construction CL : Cloudy C C C C C C C CL CL CL
TR : Tiny Rain
Location : Gn. Hamiding HR : Heavy Rain
Manpower Volume Qty Progress Summary Activities
No. Today Activities / Achievement UNIT Qty Previous Today SUM % No. Tomorrow Activities Plan

1 Pekerjaan Sloop Exca Hyundai. STA. 13.600- STA 13.640 (Refly) 09.00 - 14.00 Continue Pekerjaan Sloop & Galian Katingan STA 13.590-STA 13.640
Pekerjaan Galian Exca Hyundai STA13.600-sta 13.611(Refly) (exca hyundai breakdown gantiM3 115,500
Exca Hitachi. 14.00-17.00

Man Power
No No. Tools Unit Qty
DIRECT QTY INDIRECT Qty
1 Operator 1 1
2 SHE Officer Admin HSE 2
3 Helper 1 HRD Manager 3
4 Flagman PR Manager 4
5 Driver General Admin 1 5
6 Supervisor 1 Project Manager 6
7
8
9
10
TOTAL DIRECT 3 TOTAL INDIRECT 1 TOTAL TOOLS 0
TOTAL MANHOURS 27 9
TOTAL MANHOURS PREVIOUS 0
TOTAL MANHOURS CUMULATIVE 36

No. Equipment Qty No. Material Unit Previous Today Total


1 LV (Double Cabin 4X4) 1 1.
2 Excavator HYUNDAI 1 2.
3 Excavator Hitachi 1 3.
4 Dump Truck 4.
TOTAL EQUIPMENT 3
DAILY PROGRESS REPORT

CLIENT PT Sarku Enjinering Utama


CONTRACTOR PT Saloi Pusaka Halmahera
CONTRACT SEU-005-SCA-2103-0001
PROJECT Pelaksanaan Pekerjaan Jasa Pembangunan Jalan - 2103 Project