TABLE OF CONTENTS
Section A – General Quality Standards for Purchased Material
SQM-1.0 Purpose 3
SQM-2.0 Scope 3
SQM-3.0 Supply Chain ___________________________________________ 3
SQM-4.0 Supplier Contact Information 3
SQM-5.0 Quality Systems 3
SQM-6.0 Right of Access 4
SQM-7.0 Confidentiality Agreement____________________________________________ 4
SQM-8.0 Raw Material Suppliers ___ 5
SQM-9.0 Special Processes Suppliers 5
SQM-10.0 Sub-Tier Suppliers__________________________________________ 5
SQM-11.0 Distributors ___________________________________________ 5
SQM-12.0 First Article Production Approval 6
SQM-13.0 Purchased Part Control 6
SQM-14.0 Process Control for Key Characteristics 6
SQM-15.0 Material Identification 6
SQM-16.0 Sampling 6
SQM-17.0 Drawing and Change Control 6
SQM-18.0 Records 7
SQM-19.0 Change in Manufacturing Process Control 7
SQM-20.0 Foreign Object Debris/Damage (FOD) Prevention Program 7
SQM-21.0 Nonconforming Material 7
SQM-22.0 Notification of Escapes 8
SQM-23.0 Certification of Conformance 8
SQM-24.0 DFARS 8
SQM-25.0 ITAR Sensitive 8
SQM-26.0 Shipment and Packaging Requirements __________________________ 8
Section B – Supplier Approval
SQM-27.0 Introduction 9
SQM-28.0 PMP Register of Approved Suppliers: Requirements ______ 9
SQM-29.0 Supplier Performance Requirements 9
Section C – Purchase Order Terms and Conditions
SQM-30.0 Formation: Offer, Acceptance; Exclusive Terms 10
SQM-31.0 Quality 10
SQM-32.0 Delivery 11
SQM-33.0 Changes 11
SQM-34.0 Applicable Laws 12
SQM-35.0 Liability 12
SQM-36.0 Conflict Minerals ___________________________________________________ 12
SQM-1.0 Purpose
The purpose of this Supplier Quality Requirements Manual (“Manual”) is to define the supplier quality
requirements for Precision Machined Products, LLC. (“PMP”) to ensure that purchased product
conforms to specified purchasing requirements.
PMP reserves the right to amend/update/revise this Manual at any time.
SQM-2.0 Scope
This Manual applies to suppliers who directly provide material (raw materials, production services,
component parts and assemblies) to PMP, unless otherwise exempted by Contract, Purchase Order,
or noted in this Manual. Facility (building) MRO items and general services are excluded from this
process, except for the purchase order terms and conditions.
In the event that the Purchase Order or Contract conflicts with the requirements of this document, the
Purchase Order or Contract requirements will supersede.
SQM-5.2 A supplier must have an environmental, health and safety (EHS) program
that meets all statutory and regulatory requirements appropriate to their
business.
SQM-5.3 A supplier not meeting the above quality system requirements may be
assessed at any time for reasons not limited to performance, and may be
liable for actual costs of such assessments.
The Supplier shall provide PMP, its customer(s), and/or a specified third party (statutory/regulatory
agency) right of access to the facility and all records related to product ordered by PMP or its
customers. PMP, its customer(s) representative(s), and/or a specified third party reserves the right to
perform an audit or inspection at the supplier’s facility to verify that supplied product conforms to
specified requirements. This verification does not absolve the supplier of the responsibility to provide
acceptable product and does not preclude subsequent rejection by PMP or its customer.
• Customer-supplied documentation/records;
• Customer-supplied product/property;
• Customer furnished data used for design, production, and/or inspection;
• Intellectual property.
SQM-7.1 NO USE – Supplier agrees not to use Confidential Information in any way, or
to manufacture, test, and/or distribute any product embodying Confidential
Information, except for the purpose set forth in the Purchase Order.
SQM-7.2 NO DISCLOSURE – Supplier agrees to use its best efforts to prevent and
protect the Confidential Information, or any part thereof, from disclosure to
any person other than supplier's employees having a need for disclosure in
connection with supplier's authorized use of the Confidential Information and
production/process activities.
prevent the Confidential Information from falling into the public domain or into
the possession of unauthorized persons.
and manufacture, parts that do not contain proper external or internal materials or components
required by the OEM and are not constructed in accordance with OEM design, parts that have been
re-worked, re-marked, re-labeled, repaired, refurbished but are represented as OEM authentic or as
new or parts that have not successfully passed all OEM required testing, verification, screening, and
quality control processes.
Distributors of aerospace commodity items must employ a documented quality system that is
compliant to (AS/EN/JISQ) 9120 Aerospace Requirements for Stockist Distributors or (AS/EN/JISQ)
9100 Quality Management Systems – Aerospace – Requirements. Copies of the AS standards can be
purchased from SAE International at www.sae.org.
A Manufacturer Certificate of Conformance is required for each item delivered to ensure that the
product provided is as specified in the PMP procurement document.
SQM-16.0 Sampling
Supplier may use sampling plans when historical records indicate that a reduction in inspection can
be achieved without jeopardizing the level of quality. Supplier may employ sampling inspection in
accordance with nationally accepted or customer required standards. Sampling may not be used to
justify the existence of known defectives or discrepancies in a lot. Supplier shall maintain quality
Revision 1 / 29 August 2016 Page 6
SUPPLIER QUALITY REQUIREMENTS MANUAL
records in sufficient detail to establish evidence that any sampling was representative, the required
tests and verifications were properly performed, and only material meeting specified requirements has
been accepted for production and delivery to PMP. These records shall be available for review by
PMP or a PMP authorized representative, as required and copies of individual records shall be
furnished to PMP upon request.
Supplier must coordinate and document all changes with PMP’s Order Processing personnel. This
may involve customers and/or regulatory authorities in accordance with contract or regulatory
requirements.
In the event that supplier discontinues business operations, supplier shall agree to transmit to PMP
those records maintained in support of PMP’s contract agreements.
Nonconforming products identified:(1) at a supplier’s facility;(2) returned from PMP’s facility; or (3)
through performance testing, and/or field failures must be systematically analyzed to determine the
root cause(s) of the nonconformance. Failure to respond to a Corrective Action Request may result in
punitive action up to and including removal and/or suspension from the PMP’s Approved Supplier
List/Register.
Each shipment shall include a Certification of Conformance unless otherwise specified by Purchase
Order. The Certificate of Conformance must contain a statement that all inspections, processing, and
tests have been performed as required by the drawing requirements and/or Purchase Order.
Products controlled by heat numbers, certification numbers, batch numbers, or cure dates must be
linked to the Certificate of Conformance by the controlling number, and show physical and chemical
values when applicable.
When required by Purchase Order, materials shall comply with all U.S. Government, Defense Federal
Acquisition Regulation Supplement (DFARS) 252.225-7008 and 252.225-7009 requirements,
including Country of Origin.
Supplier shall comply with all requirements for shipping, packaging, and labeling. In the absence of
specific requirements, suitable protection from corrosion, contamination, and handling damage during
transit is required (see SQM-33.3).
SQM-27.0 Introduction
The approval process is an ongoing, comprehensive supplier-monitoring and feedback procedure that
optimizes total cost and quality and minimizes process variation. It requires performance
measurements and reporting and communicating with the supply base and features a method of
recognizing high-performance suppliers. Suppliers that are currently on an approved suppliers list of
a PMP customer may automatically be added to PMP’s Approved Suppliers List/Register.
these limits may be placed on conditional status. Conditional status requires the supplier to submit a
Corrective Action Plan acceptable to PMP. Once accepted, supplier must show significant
improvement toward meeting the required measurable within a reasonable period of time as defined
by PMP. A supplier that fails to show improvement may be removed from PMP’s Approved Supplier
List/Register.
TOTAL
SCORING RATING STATUS
SCORE
2 Barely Meets
SQM-30.2 A contract is formed when supplier accepts the Purchase Order and the
terms and conditions of PMP by shipment of goods, performance of
services, and commencement of work on goods, written
acknowledgement, or any other conduct by supplier that recognizes the
existence of a contract.
SQM-31.0 Quality
SQM-31.1 Supplier shall meet all quality requirements of PMP and its customers,
including, but not limited to, the applicable quality management system
requirements (ISO 9001, AS9100, etc.) and any other customer specific
requirements.
SQM-31.3 Supplier may be held responsible for any and all costs associated with
nonconforming product or services provided by supplier, including, but not
limited to, PMP’s raw material cost, added value cost, quality issue
investigation, administrative costs, containment, and remedial actions
(including third party activities identified by PMP or its customers).
SQM-31.4 PMP or its customers may reject and return, at the supplier’s risk and
expense, or retain and rework goods received that fail to conform to the
requirements of the Purchase Order or any other specifications within that
Order. Supplier shall replace any nonconforming goods with conforming
goods unless otherwise notified, in writing, by PMP’s Purchasing
personnel.
SQM-32.0 Delivery
SQM-32.1 Deliveries shall be made both in quantities and at the times specified on
the Purchase Order. Supplier shall adhere to all shipping directions from
the Purchasing personnel and/or directions on the Purchase Order.
SQM-32.3 Supplier agrees to properly pack, mark, and ship goods in accordance with
the Purchase Order requirements and/or the requirements of PMP or its
customers. The marks on each package and identification of the goods on
the packing slips, bill of lading, and invoices shall be sufficient to easily
identify the goods purchased.
SQM-33.0 Changes
SQM-33.1 Without prior approval from PMP, supplier shall not make any changes to
any PMP Purchase Order, including goods and/or services covered by
Contract and/or Purchase Order, such as, but not limited to:
Any third party supplier to the supplier of services, raw materials, or goods used by
supplier;
The nature, type, or quality of any goods or services, raw materials, or goods used
by the supplier or its sub-tier suppliers;
SQM-35.0 LIABILITY
Supplier shall indemnify and hold PMP and its officers, agents, servants and employees, or any of
them, harmless from any loss, damage, liability or expense, including attorney’s fees, for: (1) any
breach of any representation, warranty, covenant, or agreement herein, in the Order, or in any related
agreement, and (2) on account of damage to or loss of property or injuries, including death, to all
persons, including employees of supplier and its subcontractors and all other persons performing any
part of the work which may arise in the performance of any of its obligations or otherwise under the
Order. Supplier shall defend, at its own expense, any suits or other proceedings brought against PMP
and its officers, agents, servants or employees, or any of them, on account thereof and will pay all
expenses and satisfy all judgments which may be incurred by or rendered against any of them in
connection therewith. PMP shall have the reasonable right of approval with respect to any legal
counsel selected to defend a claim. Supplier shall be excused from liability for failure to deliver, and
PMP from failure to accept deliveries hereunder when such failure is due to the acts of God or the
elements, fire, war, the public enemy, strikes, civil commotion, transportation or other embargoes,
acts of civil or military authority, governmental priority, or other similar causes beyond their control.
In the Democratic Republic of Congo and neighboring countries, conflict materials may serve as
funding sources from mines that finance militia groups committing human rights abuses. PMP is
committed to meeting all legislative and regulatory requirements that seek to eliminate conflict
minerals from the supply chain. PMP’s policy is not to purchase conflict minerals, materials or
products using metals made from conflict minerals. PMP expects its suppliers and their suppliers to
acquire minerals only from responsible sources.