Trenching-Backfilling and Compaction of Utilities1

Download as pdf or txt
Download as pdf or txt
You are on page 1of 46

Div 02275 - Trenching, Backfilling and Compaction of Utilities Page 02275-1

02275 - TRENCHING, BACKFILLING AND COMPACTION OF UTILITIES


(Last revised 7/24/06)

SELECTED LINKS TO SECTIONS WITHIN THIS SPECIFICATION

Part 1- General Common Trench Backfill


Part 2 – Products Compaction – Min Require’ts Minimum Pipe Cover
Part 3 – Execution Def-Common Trench Backfill Pavement Repair
Backfilling Def-Select Earth Backfill River & Creek Crossings
Bedding Definitions Dewatering Rock Excavation
Bedding for Pipe Erosion Control, NPDES Seeding & Groundcover
Blasting Flowable Fill Concrete Select Earth Backfill
Cleanup & Restoration Foundation Preparation Trench Backfilling
Clearing and Grubbing Highway Crossings Unclassified Trench Excavation

PART 1 – GENERAL
1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and


Supplementary Conditions apply to this specification.

B. Division 02530 – SANITARY SEWER

C. Division 02510 – WATER DISTRIBUTION

D. Division 02630 – STORM DRAINAGE

E. Division 02920 – SEEDING, SODDING, AND GROUNDCOVER

1.2 SUMMARY

A. This section includes:

1) Excavating and backfilling trenches for buried water, sewer, storm drainage,
buried utility structures, and appurtenances.

2) Preparing subgrade for buried water, sewer, storm drainage, buried utility
structures, and appurtenances.

B. Construction and materials related to this section but covered elsewhere:

1) Erosion Control: North Carolina Sediment Control Law and the City of
Jacksonville’s erosion control ordinance.

1.3 DEFINITIONS

A. For the purposes of this specification, the following definitions refer to sanitary
sewer, water distribution, and storm drainage systems that come under the
authority of the City of Jacksonville as specified within this section and other
sections of this manual.

City of Jacksonville, NC - Manual of Specifications, Standards & Design June 2006


Div 02275 - Trenching, Backfilling and Compaction of Utilities Page 02275-2

B. Backfill: Soil materials used to fill an excavated trench:

1) Initial Backfill (Carefully Compacted Select Earth Backfill): Backfill placed


beside and over the top 12-inches of the pipe in a trench, including haunches
to support sides of pipe.

2) Final Backfill (Common Trench Backfill): Backfill placed over the initial
backfill to fill a trench.

C. Bedding Course: Layer of clean coarse stone placed over the excavated
subgrade in a trench to bring the trench bottom up to grade before laying pipe.
When natural materials encountered in trenches are of fine grains and migration
of material into the bedding is possible, use well graded bedding material without
voids.

D. Haunching: Layer of clean coarse stone placed and compacted up to the


springline of the pipe. Where voids may cause migration of native or backfill
material, use well graded material without voids.

E. Foundation Stone: Clean well-graded stone, authorized by the Public Services


Director, used to strengthen and/or provide support to an otherwise weak
subgrade. Foundation stone is placed, and the subgrade improved before
bedding stone is placed. Where voids may cause migration of native or backfill
material, use well graded material without voids.

F. Rock Excavation: Removal and satisfactory disposal of all unsuitable materials,


which, in the opinion of the Public Services Director, cannot be excavated except
by drilling, blasting, wedging, jack hammering or hoe ramming. It shall consist of
undecomposed stone, hard enough to ring under hammer. All boulders
containing a volume of more than ½ cubic yard and/or solid ledges, bedded
deposits, unstratified masses and conglomerations of material so firmly
cemented as to possess the characteristics of solid rock that cannot be removed
without systematic drilling and blasting, will be classified as rock.

G. Structures: Buildings, footings, foundations, retaining walls, slabs, tanks, curbs,


mechanical and electrical appurtenances, or other man-made stationary features
constructed above or below the ground surface.

H. Subgrade: Surface or elevation remaining after completing the trench


excavation or, the top surface of a backfill (stone or soil) immediately below the
pipe conduit or pipe bedding, as applicable.

I. Topsoil: See Division 02920 – Seeding, Sodding, and Groundcover.

J. Select Fill: Select fill shall consist of approved material imported from off-site for
use as fill or backfill required to be placed in trenches either as initial carefully
controlled select earth backfill or as final common trench backfill. Select fill shall
not be used until all suitable trench excavation material has been placed in the
trench, unless authorized by the Public Services Director. Unless otherwise
designated on the plans and in the contract documents, the Contractor shall
make his own arrangements for obtaining borrow and pay all costs involved.

City of Jacksonville, NC - Manual of Specifications, Standards & Design June 2006


Div 02275 - Trenching, Backfilling and Compaction of Utilities Page 02275-3

K. Unclassified Excavation: Removal and disposal of any and all material above
subgrade elevation, except solid rock and classified excavation, located within
the limits of construction.

L. Classified Excavation: Classified excavation shall consist of the removal and


satisfactory disposal of all unsuitable material located below subgrade elevation.
Where excavation to the finished grade section results in a subgrade or slopes
of muck, peat, matted roots, etc., the Contractor shall remove such material
below the grade shown on the plans or as directed; and areas so excavated
shall be backfilled with approved select fill or stone as ordered by the Public
Services Director.

M. Competent Person: Competent Person means one who is capable of


identifying existing and predictable hazards in the surroundings or working
conditions which are unsanitary, hazardous, or dangerous to employees, and
who has authorization to take prompt corrective measures to eliminate them.

N. The following are industry abbreviation for various pipe materials:

1) AC: Asbestos Cement Pipe

2) CAP: Corrugated Aluminum Pipe

3) CI: Cast Iron Pipe

4) DIP: Ductile Iron Pipe

5) HDPE: High Density Polyethylene Pipe

6) PCP: Plain Concrete Pipe

7) PVC: Polyvinyl Chloride Plastic Pipe

8) RCP: Reinforced Concrete Pipe.

1.4 SUBMITTALS

A. Submit product data and a sample of drainage fabric or separation fabric and
fully document each with specific location or stationing information, date, and
other pertinent information.

B. Material Test Reports: Provided from a qualified testing agency which either
indicate or interpret test results for compliance of the following requirements
indicated:

1) Classification according ASTM D2487 of each on-site or borrow soil


proposed for backfill, unless otherwise directed by the Public Services
Director.

2) Laboratory compaction curve according to ASTM D698 for each on-site or


borrow soil material proposed for backfill.

City of Jacksonville, NC - Manual of Specifications, Standards & Design June 2006


Div 02275 - Trenching, Backfilling and Compaction of Utilities Page 02275-4

C. Blasting:

1) Insurance Certificate naming the City of Jacksonville as “additional Insured.”


See paragraph 3.8 – Blasting for other blasting insurance requirements.

2) Qualifications, proposed procedures, and schedule shall be submitted at


least 2 weeks prior to commencing any blasting operations.

3) Permits from City and local Fire Department and City officials.

4) Blasters shall, at all times, have their license and blasting permits on the job
site, and shall allow examination of same by any official that may have
jurisdiction.

5) If required by the Public Services Director, seismic survey agency report, for
record purposes.

6) Bury Depth Computations: Computations justifying pipe bury when bury


depth exceeds the allowable depth shown in this specification. Provide
method, applicable charts/graphs, printouts, assumptions, etc. used in
justifying the adequacy of the pipe to withstand the loads imposed by the
excessive depth.

7) Product Data:

a. Each type of plastic warning tape

b. Stabilization/Separation fabric

c. Drainage Fabric

1.5 QUALITY ASSURANCE

A. Geotechnical Testing Agency Qualifications: An independent testing agency


qualified according to ASTM E 329 to conduct soil materials and rock-definition
testing as documented according to ASTM D 3740 and ASTM E 548.

B. Comply with all codes, laws, ordinances, and regulations of governmental


authorities having jurisdiction over this part of the work.

C. The Contractor shall comply with North Carolina Department of Environment and
Natural Resources, “Erosion and Sedimentation Control Handbook,” latest
revision and the City of Jacksonville erosion control ordinance, which ever is
more stringent.

D. Comply with applicable requirements of NFPA 495, “Explosive Materials Code.”

E. “Gravity Sanitary Sewer Design and Construction,” ASCE Manuals and Reports
on Engineering Practice – NO. 60, WPCF Manual of Practice NO. FD-5.

F. Comply with Uni-Bell PVC Pipe Association “Handbook of PVC Pipe: Design and
Construction,” 3rd ed. Dallas: UNI, 1991 for the installation of PVC piping.

City of Jacksonville, NC - Manual of Specifications, Standards & Design June 2006


Div 02275 - Trenching, Backfilling and Compaction of Utilities Page 02275-5

1.6 QUALITY STANDARDS

A. Materials and operations shall comply with the latest revision of the Codes and
Standards listed below:

American Society for Testing and Materials

ASTM C33 Concrete Aggregates

ASTM D 698 Test Method for Laboratory Compaction Characteristics of


3
Soil Using Standard Effort (12,400 ft-lbf/ft ) (Standard
Proctor).

ASTM D1556 Standard Method of Test for Density of Soil in Place by the
Sand-Cone Method

ASTM D1557 Test Method for Laboratory Compaction Characteristics of


3
Soil Using Modified Effort (56,000 ft-lbf/ft ) (Modified
Proctor).

ASTM D 2049 Standard Method of Test for Relative Density of


Cohesionless Soils

ASTM D2167 Standard Method of Test for Density of Soil in Place by the
Rubber-Balloon Method

ASTM D 2487 Standard Classification of Soils for Engineering Purposes


(Unified Soil Classification System).

ASTM D2922 Test Methods for Density of Soil and Soil-Aggregate in


Place by Nuclear Methods (Shallow Depth).

ASTM D2937 Standard Test Method for Density of Soil in Place by the
Drive-Cylinder Method

ASTM D4253 Standard Test Methods for Maximum Index Density and
Unit Weight of Soils Using a Vibratory Table.

ASTM D4254 Test Method for Minimum Index Density and Unit Weight
of Soils and Calculation of Relative Density.

ASTM D4318 Test Method for Liquid Limit, Plastic Limit, and Plasticity
Index of Soils.

American Association of State Highway & Transportation Officials

AASHTO T99 The Moisture-Density Relations of Soils using a


5.5-pound Rammer and a 12-inch drop.

AASHTO T180 The Moisture Density Relations of Soils using a


10-pound Rammer and an 18-inch drop.

AASHTO M145 The Classification of Soils and Soil-Aggregate Mixtures


for Highway Construction Purposes.

City of Jacksonville, NC - Manual of Specifications, Standards & Design June 2006


Div 02275 - Trenching, Backfilling and Compaction of Utilities Page 02275-6

American Water Works Association

AWWA C600 Installation of Ductile Iron Water Mains and Their


Appurtenances.

Other

ANSI American National Standards Institute

AREA American Railway Engineers Association

DWQ Division of Water Quality

MSDS Material Safety Data Sheets

NCDENR NC Department of Environment and Natural Resources

NCDOT North Carolina Department of Transportation

NPDES National Pollutant Discharge Elimination System

OSHA Occupational Safety and Health Administration

1.7 TESTING SERVICES

A. The Testing Laboratory shall be (selected by the Contractor) approved by the


Public Services Director and will be responsible for conducting and interpreting
tests. The Testing Laboratory shall state in each report whether or not the test
specimens conform to all requirements of the Contract Documents and
specifically note any deviation there from.

B. Specific test and inspection requirements shall be as specified herein.

1.8 PROJECT CONDITIONS

A. Demolition: Demolish and completely remove from the site existing


underground utilities indicated on the plans to be removed.

B. Environmental - Wetlands: Before crossing or entering into any jurisdictional


wetlands, Contractor shall verify whether or not a wetlands permit has been
obtained for the encroachment and whether special restrictions have been
imposed. Care shall be taken to prevent draining or otherwise destroying non-
permitted wetlands. Restore as stated on either the project drawings, the
contract documents, and/or as noted in the permit. All crossings, disturbances,
and encroachments into wetlands shall be subject to US COE and NCDENR
Division of Water Quality approval and permitting requirements and conditions.

C. Environmental - Buffer Crossing Requirements: Before crossing streams or


ditches or working within 50 feet of ponds, lakes, rivers, or Class SA water, the
Contractor shall verify whether the utility line is exempt or if a permit has been
obtained to encroach into such buffers or other such regulated waters, and to
what extent work is permitted to occur. Unless otherwise permitted, shown on
the contract drawings, or exempted by NCDENR or other proper authority, water

City of Jacksonville, NC - Manual of Specifications, Standards & Design June 2006


Div 02275 - Trenching, Backfilling and Compaction of Utilities Page 02275-7

and sewer crossing streams, rivers, ponds, or lake buffers are to be as near
perpendicular as possible (the crossing is considered to be perpendicular if it
intersects the stream or surface water between an angle of 75 and 105
degrees). Do not disturb more than 40 linear feet (longitudinal) of riparian buffer.
When permitted to encroach into zone one of a buffer (the lower 30 feet beside
the stream or water), adhere to all of the following Best Management Practices
during construction.

1) Woody vegetation is cleared by hand. No grading allowed.


2) Stumps to remain except in trench where trees are cut. Minimize disturbance
to roots in buffer zone.
3) Set aside topsoil and replace to existing grade immediately after backfill.
4) Backfill trench with the excavated soil immediately following installation.
5) Do not use fertilizer except for the one-time application to reestablish
vegetation.
6) Minimize removal of woody vegetation, the amount of disturbed area, and the
time the disturbed area remains disturbed.
7) Take measures to ensure diffuse flow of water through the buffer after
construction.
8) In wetland areas, use mats to minimize soil disturbance.
9) Remove the existing topsoil to a depth of 6 inches or to the depth
encountered from all areas in which excavation will occur. The topsoil shall
either be stored in stockpiles separate from the excavated trench material if
the topsoil is to be respread or otherwise disposed of off-site. Topsoil
stockpiles shall be graded to freely drain surface water, and shall have a silt
fence placed around the base of the stockpile.

D. Safety

The Contractor shall keep the surface over and along the trenches and other
excavation in a safe and satisfactory condition during the progress of the work.

1.9 LOCATING SERVICES

Contact the City of Jacksonville Public Services Department to coordinate interruption of


service, operation of valves, line cut-ins, or placement of a tapping sleeve and valve. If
interruption is necessary, the interruption shall be arranged to occur at such a time to
cause the least disruption and minimize loss of service. At the direction of the Public
Services Director, temporary service may be required to be provided. Provide a
minimum of 2 day’s written notice to the citizens affected of the proposed utility
interruption or necessary operation of valves.

1.10 COORDINATION

A. Coordinate tie-in to municipal water mains with the Public Services Director.
Except as needed for fire suppression purposes, the City will be the sole
operator of all valves and hydrants on the City of Jacksonville water distribution
system. Do not interrupt existing utilities or shut off valves of active lines unless
approved by the Public Services Director. If interruption is necessary, the
interruption shall be arranged to occur at such a time to cause the least
disruption and minimize loss of service.

City of Jacksonville, NC - Manual of Specifications, Standards & Design June 2006


Div 02275 - Trenching, Backfilling and Compaction of Utilities Page 02275-8

B. Coordinate tie-in to municipal sewer mains and manholes with the Public
Services Director.

C. At the direction of the Public Services Director, temporary pumping/bypass of


sewerage flow may be required to be provided. See Division 02530 - Sanitary
Sewer, Bypass Pumping for bypass pumping requirements and procedure.

D. When traffic signals, loops, or their appurtenances are likely to be damaged or


interfered as a result of the construction, coordinate temporary operation with the
applicable agency having jurisdiction of the signals. Provide a minimum of 48
hours notice prior to anticipated disturbance or interruption. At the discretion of
the Public Services Director, newspaper publication of the notice may be
required.

E. Repair of pavement markings: When cuts are made through any paved
surface and the cuts extend through the pavement markings, the replaced
pavement shall be marked to match the existing.

F. Water Service Shut-off

The City of Jacksonville requires adherence to the following procedures prior to


shutting off water service on any existing City line:

1) The Contractor must receive approval for shut-off from the Public Services
Department. Generally, shut-offs must occur from 9:00 AM to 11:00 AM and
2:00 PM to 4:00 PM on weekdays.

2) After receiving approval, Contractor shall notify affected residents in writing


24 hours in advance of beginning operation.

G. Contact “NC One Call” 1-800-632.4949 before digging. Call the City of
Jacksonville Public Services Department at 910-938-5249 for water/sewer
location services.

1.11 PUBLIC CONVENIENCE

The Contractor shall at all times so conduct his work as to insure the least possible
inconvenience to the general public and the residents in the vicinity of the work. Fire
hydrants on or adjacent to, the work shall be kept accessible to fire fighting equipment
at all times. Temporary provisions shall be made by the Contractor to insure the proper
functioning of all gutters, sewer inlets, drainage ditches, and irrigation ditches, which
shall not be obstructed except as approved by the Public Services Director.

Fire hydrants that either are abandoned or are not in service shall be bagged by the City
with plain yellow bags.

1.12 TRAFFIC CONTROL

A. When working within any NCDOT System road or highway, conform to the
Manual on Uniform Traffic Control Devices, latest revision (MUTCD) as well as
the NCDOT Standard Specifications for Roads and Structures, latest revision.

City of Jacksonville, NC - Manual of Specifications, Standards & Design June 2006


Div 02275 - Trenching, Backfilling and Compaction of Utilities Page 02275-9

B. Traffic Maintenance shall comply with the latest revision of the NCDOT Standard
Specifications for Roads and Structures, Division 9 – Signing and Division 11 –
Work Zone Traffic Control, as well as other applicable sections.

C. A traffic control plan shall be submitted to the City of Jacksonville Police


Department and NCDOT (if applicable) for approval.

D. NCDOT is to be notified prior to any work being performed within ½ mile of any
traffic signal. When traffic signals or their appurtenances are likely to be
damaged or interfered as a result of the construction, coordinate temporary
operation with the NCDOT and the City’s Police Department. Provide 48 hours
notice prior to anticipated disturbance or interruption.

E. Whenever it becomes necessary to leave a section of trench open after


completion of the days work, the Contractor shall provide barricades and lights to
protect the public. Operate warning lights during hours from dusk to dawn each
day and as otherwise required for inclement weather and visibility.

1.13 EROSION AND SEDIMENTATION CONTROL AND NPDES MONITORING,


CONTROLS, AND LIMITATIONS FOR PERMITTED DISCHARGES

The Contractor shall follow all local and state requirements regarding sedimentation and
erosion control. Construction methods shall minimize sedimentation and erosion.

It is the Contractor’s responsibility to periodically monitor the Stormwater Discharge


Outfall points at the specified frequency and maintain reports as outlined in these
specifications.

A. Final Limitations and Controls for Stormwater Discharges

During the period beginning on the effective date of the permit and lasting until
expiration, the Owner (Permittee) is allowed and authorized to discharge
stormwater associated with construction activity. Such discharges shall be
controlled, limited, and monitored as specified below.

1) The Contractor shall implement the Erosion & Sedimentation Control plan,
which has been approved by the approval authority. The approved plan is
considered a requirement or condition of the general NPDES permit.
Deviation from the approved plan, or approved amendment to the plan, shall
constitute a violation of the terms and conditions of this general permit except
that deviation from the approved plan will be allowed:

a. To correct an emergency situation where sediments are being discharged


off the site, or

b. When minor modifications have been made for the purpose of improving
the performance of the erosion and sedimentation control measures and
notification of the minor modification has been made to the Division of
Land Resources (or approved local program).

City of Jacksonville, NC - Manual of Specifications, Standards & Design June 2006


Div 02275 - Trenching, Backfilling and Compaction of Utilities Page 02275-10

Such a deviation from the approved plan shall be noted on the approved
plan maintained at the job site. During active construction, a copy of the
approved plan shall be maintained on the site.

2) Equipment utilized during the construction activity on a site must be operated


and maintained in such a manner as to prevent the potential or actual
pollution of the surface or ground waters of the state. Fuels, lubricants,
coolants, and hydraulic fluids, or any other petroleum products, shall not be
discharged onto the ground or into surface waters. Spent fluids shall be
disposed of in a manner so as not to enter the waters, surface, or ground, of
the state and in accordance with applicable state and federal disposal
regulations. Any spilled fluids shall be cleaned up to the extent practicable
and disposed of in a manner so as not to allow their entry into the waters,
surface or ground, of the state.

3) Herbicide, pesticide, and fertilizer usage during the construction activity shall
be consistent with the Federal Insecticide, Fungicide, and Rodenticide Act
and shall be in accordance with label restrictions.

4) All wastes composed of building materials shall be disposed of in accordance


with North Carolina General Statutes, Chapter 130A, Article 9 – Solid Waste
Management, and rules governing the disposal of solid waste (North Carolina
Administrative Code Section 15A NCAC 13B).

5) The Contractor, for the Permittee, shall control the management and
disposal of litter and sanitary waste from the site such that no adverse
impacts to water quality occur.

B. Minimum Monitoring and Reporting Requirements

Minimum monitoring and reporting requirements are as follows unless otherwise


approved in writing by the Director of the Division of Water Quality.

1) All erosion and sedimentation control facilities shall be inspected by or under


the direction of the permittee (the Owner). Inspections shall be made:

a. At least once every seven calendar days (at least twice every seven days
for those facilities discharging to waters of the State listed on the latest
EPA approved 303(d) list 1 for construction related indicators of
impairment such as turbidity or sedimentation),

b. And within 24 hours after any storm event of greater than 0.5 inches of
rain per 24-hour period.

A rain gauge shall be maintained on the site by the Contractor and a


record of the rainfall amounts and dates shall be kept by the Contractor.

1 The latest approved list may be obtained from the Division of Water Quality, or from the
following website location: http://h2o.enr.state.nc.us/su/construction303d.

City of Jacksonville, NC - Manual of Specifications, Standards & Design June 2006


Div 02275 - Trenching, Backfilling and Compaction of Utilities Page 02275-11

2) Once land disturbance has begun on the site, stormwater runoff discharges
shall be inspected by observation for stormwater discharge characteristics as
defined below at the frequency stated above to evaluate the effectiveness of
the pollution control facilities or practices. If any visible sedimentation is
leaving the disturbed limits of the site, corrective action shall be taken
immediately to control the discharge of sediments outside the disturbed
limits.

Stormwater Discharge Monitoring Monitoring Location2


Characteristics Type1
Clarity By observation SDO
Floating Solids By observation SDO
Suspended Solids By observation SDO
Oil Sheen By observation SDO
Other obvious indicators By observation
of stormwater pollution SDO
Footnotes:
1
Monitoring Type: The monitoring requires a qualitative observation of
each stormwater outfall. No analytical testing or sampling is required.
2
Sample (observation) location: SDO= Stormwater Discharge Outfall

3) The operator (Contractor) shall keep a record of inspections and forward


copies of these reports to the Public Services Director. Visible sedimentation
found outside of the disturbed limits shall be recorded and a brief explanation
kept with the records as to the measures taken to control future releases.
Any measures taken to clean up the sediment that has left the disturbed
limits shall also be recorded. These records shall also be made available to
DWQ or an authorized agent upon request. If the Public Services Director
discovers sedimentation outside the limits of disturbance, the Contractor will
be notified in writing and requested to remediate the situation.

4) All records of monitoring shall be turned over to the City along with the “red
lined” record water and/or sewer drawings.

C. Schedule of Compliance

1) The Contractor shall comply with Final Limitations and Controls specified for
stormwater discharges once disturbance has begun on the site and until
completion of construction or development and the establishment of a
permanent ground cover.

2) During construction and until the completion of construction or development


and the establishment of a permanent ground cover, the Contractor shall
provide the operation and maintenance necessary to operate the stormwater
controls at optimum efficiency.

City of Jacksonville, NC - Manual of Specifications, Standards & Design June 2006


Div 02275 - Trenching, Backfilling and Compaction of Utilities Page 02275-12

PART 2 – PRODUCTS
2.1 SOIL, BEDDING AND BACKFILL

2.1.1 MATERIAL CLASSIFICATION

A. Bedding Material: #57 or #67 stone.

B. Excavation: All excavation material shall be classified as either Rock or


Unclassified Earth Excavation. Prices bid for the various sizes of pipe shall
include excavation and backfilling.

C. Flowable Fill Concrete Backfill (Controlled Low Strength Material): Concrete


strength shall be liquid enough to flow, be self-leveling, excavatable, and have a
minimum 28-day compressive strength of 30 psi but not more than 100 psi.
Non-excavatable flowable fill concrete shall have a minimum 28-day
compressive strength of 125 psi but no more than 200 psi (to be excavatable by
machine equipment). Materials shall comply with the recommendations within
chapter 3 of ACI 229, latest revision, which include cement, aggregates, fly ash,
water, admixtures, slag and other non-standard materials).

Excavatable is an application where it may be necessary to remove the flowable


fill at a later date. Non-excavatable is an application where it is not necessary to
remove or otherwise excavate the flowable fill at a later date.

D. Foundation Stone: Foundation/Trench Stabilization Material: #5, #357 or #57


stone.

E. Select Initial Earth Backfill: Select earth backfill shall be free of debris, roots,
frozen materials, organic matter, rock, or gravel larger than 1 inch in any
dimension, or other harmful matter and shall generally meet NCDOT Standard
Specifications for Roads and Structures, Section 1016 – Select Material for
properties and gradation.

F. Common Earth (Trench) Backfill:

1) Satisfactory Soils: ASTM D2487 soil classification group (Unified Soil


Classification System) GW, GP, GM, SW, SM, SC, ML, and CL (Classes IA,
IB, II, III and IVA soils; see standard detail 511.01) or a combination of
these group symbols; free of rock or gravel larger than 3 inches in any
dimension, debris, waste frozen materials, vegetation, and other deleterious
matter.

2) Unsatisfactory soils: ASTM D 2487 soil classification group CH, MH, OH,
OL and PT (Classes IVA & V soils; see standard detail 511.01); soils which
contain rock or gravel larger than 3 inches in any dimension, debris, waste
frozen materials, vegetation, clumps of clay larger than 3 inches in any
dimension, and other deleterious matter. Unsatisfactory soils also include
satisfactory soils not maintained within +/- 3% of optimum moisture content
at time of compaction, unless otherwise approved by the Public Services
Director.

City of Jacksonville, NC - Manual of Specifications, Standards & Design June 2006


Div 02275 - Trenching, Backfilling and Compaction of Utilities Page 02275-13

G. Structures, Backfill around: Backfill shall be approved by the Public Services


Director and shall be free from large or frozen lumps, wood, or rocks more than
3 inches in their greatest dimension or other extraneous material. Porous
backfill shall be #67, #57, or #357 clean stone.

H. Topsoil: See Division 02920 – Seeding, Sodding, and Groundcover.

2.1.2 PIPE BEDDING DEFINITIONS

A. Pipe Bedding Definitions

1) Class D Bedding is that condition existing when the ditch is excavated


slightly above grade by excavation equipment and cut to finish grade by
hand. Bell holes are dug, to prevent point loading the pipe bells, so that pipe
bears uniformly upon the trench bottom. Existing soil should be shovel sliced
or otherwise compacted under the hunching of the sewer pipe to provide
some uniform support. Soil is tamped to 90% of the maximum Standard
Proctor dry density around the pipe to a point one foot above the pipe. The
remainder of the soil to the ground surface is to be compacted to the density
specified in Table 2275.3. In poor soils, granular bedding material is
generally a more practical, cost effective installation. The bedding factor for
class D bedding is 1.1.

2) Class C Bedding is that condition where the sewer pipe is bedded in


compacted granular material. The granular bedding has a minimum
thickness of one-eighth the outside sewer pipe diameter, but not less than 4
inches or more than 6 inches, and shall extend up the sides of the sewer
pipe one-sixth of the pipe outside diameter. The remainder of the sidefills, to
a minimum depth of 6 inches over the top (exterior crown) of the pipe,
consists of lightly compacted backfill. The remainder of the soil to ground
surface is to be compacted to the density specified in Table 2275.3. The
bedding factor for class D bedding is 1.5.

3) Class B Bedding is that condition where the sewer pipe is bedded in


carefully compacted granular material. The granular bedding has a minimum
thickness of one-eighth the outside sewer pipe diameter, but not less than 4
inches or more than 6 inches, between the barrel and the trench bottom, and
covering the full width of the trench.

The haunch area of the sewer pipe must be fully supported; therefore, the
granular material should be shovel sliced or otherwise compacted under the
pipe haunch to the springline of the pipe. Both granular haunching (to the
springline) and initial backfill to a minimum depth of 12 inches over the top of
the sewer pipe should be placed and compacted. The initial backfill material,
to a depth of 12 inches over the top of the pipe, should be compacted to no
less than 90% of the maximum Standard Proctor dry density. The remainder
of the soil to the ground surface is to be compacted to the density specified
in Table 2275.3. The bedding factor for class B bedding is 1.9.

4) Class B-1 Bedding (PVC pipe applications) is the same as Class B Bedding
except that granular backfill is placed to the top of the pipe rather than to
the springline of the pipe. The remainder of the soil to the ground surface is
to be compacted to the density specified in Table 2275.3.

City of Jacksonville, NC - Manual of Specifications, Standards & Design June 2006


Div 02275 - Trenching, Backfilling and Compaction of Utilities Page 02275-14

5) Class A Bedding is that condition when the sewer pipe is bedded in a cast-
in-place cradle of either plain or reinforced concrete having a thickness equal
to one-fourth the inside pipe diameter, with a minimum of 4 inches and a
maximum of 15 inches under the pipe barrel and extending up the sides for a
height equal to one-fourth the outside pipe diameter. The cradle width shall
have a width at least equal to the outside diameter of the sewer pipe barrel
plus 8 inches. The bedding factor for class B bedding is 2.2.

The haunching and initial backfill material above the concrete cradle should
be crushed stone or a well graded granular material and carefully compacted
to 12 inches above the crown of the sewer pipe. The remainder of the soil to
the ground surface is to be compacted to the density specified in Table
2275.3.

2.2 MISCELLANEOUS

2.2.1 GEOTEXTILE FABRIC

Geotextile fabric shall be protected from mud, dirt, dust, sunlight, and debris
during transport and storage. Material shall be inert to commonly encountered
chemicals; resistant to mildew, rot, insects, and rodents; and biologically and
thermally stable. Geotextile fabric for subsurface installation shall not be
exposed to direct sunlight for more than 24 hours before or during installation.

A. Filter Fabric for Rip Rap: Filter Fabric for Rip Rap and Rip Rap Beddings shall
conform to Section 1056 – Engineering Fabrics of the NCDOT Standard
Specifications for Roadways and Structures, latest revision for Type 2
engineering fabric.

B. Soil Stabilization Fabric: Generally, soil stabilization fabric shall conform to the
requirements of Section 1056 – Engineering Fabrics of the NCDOT Standard
Specifications for Roadways and Structures, latest revision for Type 4
engineering fabric. However, provide fabric meeting Geotechnical Engineers
recommendations for the application and use intended.

C. Fabric for Subsurface Drains: Non-woven needle-punched fabric shall


conform to Section 1056 – Engineering Fabrics of the NCDOT Standard
Specifications for Roadways and Structures, latest revision for Type 1
engineering fabric.

D. Silt Fence Fabric: Silt fence fabric shall conform to Section 1056 – Engineering
Fabrics of the NCDOT Standard Specifications for Roadways and Structures,
latest revision for Type 3 engineering fabric, Class A or B as specified or shown
on the plans.

2.2.2 WARNING TAPE

Non-metallic underground warning tape: Non-metallic underground warning


tape shall be lead free virgin grade rot resistant polyethylene manufactured in
accordance with ESI 12-23. Minimum elongation shall be 350% in the machine
direction and 300% in the transverse direction. Soil tolerance range to be pH 2.5
to pH 11.0. Minimum tape thickness shall be 0.1mm. The text shall include
either the wording “WATER” or “SEWER,” as applicable and across the top, the

City of Jacksonville, NC - Manual of Specifications, Standards & Design June 2006


Div 02275 - Trenching, Backfilling and Compaction of Utilities Page 02275-15

word “CAUTION” repeated along the length of the tape. Standard color code for
tape:

Blue: Water Systems


Green: Sewer systems

2.2.3 DEFORMED REINFORCING STEEL

Reinforcing Steel bars shall meet ASTM A615, grade 60, latest revision.

2.2.4 WELDED WIRE FABRIC

Welded wire fabric shall meet ASTM A185, latest revision.

PART 3 – EXECUTION
3.1 PREPARATION

3.1.1 GENERAL REQUIREMENTS APPLYING TO ALL AREAS

A. Contractor shall plan construction to minimize disturbance to properties adjacent


to the water, sewer and storm drainage lines.

B. The Public Services Director reserves the right to limit the width of land to be
disturbed and to designate on the drawings or in the field certain areas or items
within this width to be protected from damage.

C. Access and/or Haul Roads: Any grading or excavation required for equipment
travel during the course of construction as well as erosion control, access or haul
road removal, restoration, seeding and ground cover shall be provided by the
Contractor.

D. The Contractor shall be responsible for damage to areas or items designated by


the Public Services Director to be protected. Repairs to, replacement of, or
reparations for areas or items damaged shall be made to the satisfaction of the
Public Services Director and affected property owners before acceptance of the
completed project.

E. The Contractor shall protect all buildings or structures located along the utility
line. Hand trenching, shoring, or other methods may be required.

F. Any fences disturbed by the Contractor shall be repaired with materials to a


condition equal to or better than their original condition or to the satisfaction of
the Public Services Director.

G. Contractor shall limit width of disturbed area through garden areas to a width
absolutely necessary for construction of utility line.

H. Contractor shall obtain written permission from property owners for use of any
access other than ones located within public rights-of-way or easements.
Written permission shall contain conditions for use and restoration agreements
between property owner and Contractor.

City of Jacksonville, NC - Manual of Specifications, Standards & Design June 2006


Div 02275 - Trenching, Backfilling and Compaction of Utilities Page 02275-16

I. All areas disturbed shall be restored to a condition equal to or better than their
original condition and shall be graded to drain.

J. The Contractor shall replace or repair all damaged or destroyed hedgerows and
property corners using the services of a licensed Professional Surveyor.

3.1.2 CONSTRUCTION LIMITS

A. Contractor shall not disturb any areas outside the limits contained in this section
without express written permission from the Public Services Director.

B. Except as indicated on the plans, no “clear cutting” of timber shall be permitted


within the construction limits. Contractor shall make select cutting of trees,
taking smallest trees first, that are mandatory for the construction of the utility
line. The decision of the Public Services Director shall be final on the
determination of which trees are to be cut.

C. The widths measured from the centerline of the water or sewer lines shall be as
shown on the contract drawings. The Contractor shall protect all areas outside
these construction limits unless written variations are granted by the Public
Services Director.

D. Specific requirements applying to developed subdivision/lots

1) All trees located beyond 15 feet of the centerline of water, sewer or storm
drainage lines shall be protected by the Contractor. The Public Services
Director reserves the right to designate other trees located closer to the
centerline for protection where possible.

2) All shrubs, hedges, or other ornamental plantings located along the line shall
be protected or removed and replanted by the Contractor, and survival
guaranteed through the project’s warrantee period. If the plantings fail to
survive, they shall be replaced with specimens of like size whenever
available.

3) The Contractor shall protect septic systems or springs located beyond 15


feet from the centerline of the line. Any septic system damaged by the
Contractor will be maintained and pumped by the Contractor until it is
repaired to the satisfaction of the Onslow County Department of
Environmental Health or the property is connected to the sanitary sewer.

4) Contractor shall grub only brush, roots, and stumps of removed trees.
Damage to lawns shall be kept to an absolute minimum necessary for
construction.

5) Excavated or blasted rock shall be removed from the site unless otherwise
ordered by the Public Services Director.

6) Restoration and fine grading shall follow within 15 calendar days from the
time an area is disturbed or within 1000 feet from the immediate work site,
which ever occurs first. Seeding shall follow as ordered by the Public
Services Director.

City of Jacksonville, NC - Manual of Specifications, Standards & Design June 2006


Div 02275 - Trenching, Backfilling and Compaction of Utilities Page 02275-17

E. Specific requirements applying to undeveloped areas

1) In wooded areas, the clearing shall be 15 feet on each side of pipe, unless
indicated differently on the City of Jacksonville approved construction
drawings, in which case, the work shall be confined to the limits defined on
the plans. All permanent easements shall be fully cleared. On City funded
projects, anll trees 12 inches in diameter or larger located beyond 15 feet of
the centerline of the water or sewer line shall be protected unless Contractor
obtains written authorization from the Public Services Director to remove
them. The Public Services Director reserves the right to designate select
trees located closer to the centerline for protection where possible.

2) In areas where livestock and pets are kept, the Contractor shall notify
property owner prior to commencing work and keep owner advised of
progress of work. Fences shall be kept secure at all times and livestock and
pets protected from open ditches, machinery, blasting, and other hazards.

3) Restoration, fine grading, and permanent seeding shall follow within 15


working days or 30 calendar days, whichever is shorter, from the time an
area is disturbed. Trench disturbance shall not exceed more than 1000 feet
from the immediate work site without the approval/consent of the Public
Services Director. See paragraph 3.16 – Seeding, Sodding and
Groundcover.

3.1.3 PROTECTION OF EXISTING UTILITIES AND STRUCTURES

A. Subsurface obstructions

1) Subsurface obstructions: Take necessary precautions to protect existing


utilities from damage due to any construction activity. The Contractor shall
locate existing utilities, culverts, and structures (above or below ground),
before any excavation starts and coordinate work with utility companies. The
Contractor shall be responsible for notifying utility companies when working
within the vicinity of the existing utilities. Omission from or inclusion of
located utility items on plans do not constitute non-existent or definite
location. Even though for convenience, the utility may be shown on the
plans, the Contractor is responsible for and shall call for utility location a
minimum of 48 hours prior to excavations. Contact underground damage
protection services NC One Call at 1.800.632.4949. Secure and examine
local utility surveyor records for available location data including building
service lines.

2) Unless shown to be removed, protect active utility lines shown on the


drawings or otherwise made known to the Contractor prior to trenching. In
excavating, care must be taken not to remove or injure any subsurface
structure. All existing gas pipes, water pipes, steam pipes, telephone lines,
cable TV lines, electrical conduits, sewers, drains, fire hydrants, and other
structures which, in the opinion of the utility company, do not require
relocation shall be carefully supported, shored up, the flow maintained, if
applicable, and the line/main protected from damage by the Contractor. If
damaged, the Contractor shall give immediate notice to the proper
authorities. The utility shall be restored, at the Contractor’s expense, by the
appropriate utility to original or better condition. Where pipes, conduits, or
sewers are removed from the trench leaving dead ends in the ground, such

City of Jacksonville, NC - Manual of Specifications, Standards & Design June 2006


Div 02275 - Trenching, Backfilling and Compaction of Utilities Page 02275-18

ends shall be carefully plugged or bulk headed by the Contractor at the


Contractor’s expense. The Contractor shall be responsible for any damage
to persons or property caused by such breaks.

3) The Contractor shall be responsible for anticipating and locating underground


utilities and obstructions. When construction appears to be in close proximity
to existing utilities, the trench(es) shall be opened a sufficient distance ahead
of the work or test pits made to verify the exact locations and inverts of the
utility to allow for changes in line and grade.

4) If active utility lines are encountered, and are not shown on the Drawings or
otherwise made known to the Contractor, promptly take necessary steps to
assure that service is not interrupted.

5) Should it become necessary to move the position of any underground


structure, when approved by the Public Services Director, the Contractor may
be required to do such work and shall be paid on a force account basis or on
an extra work basis.

6) If existing utilities are found to interfere with the permanent facilities being
constructed under this Section, immediately notify the Public Services
Director and secure his instructions.

7) Do not proceed with permanent relocation of utilities until written instructions


are received from the Public Services Director.

B. Protection of Surface Features

1) Whenever the utility line is to be placed in or near a paved street, the


Contractor shall provide pads or take necessary precautions to protect the
pavement from damage by the construction equipment. Pavement damaged
by cleated or tracked equipment, or by any other means, shall be repaired by
the Contractor at his expense.

2) Where a utility line is in an existing paved area, the Contractor shall use care
to cut in sharp, neat lines ahead of the excavating/ditching equipment and
parallel to the pipe on each side as may be applicable. If the existing road to
be cut is located within another jurisdiction other than the City of Jacksonville
or within NCDOT rights of way, the Contractor is responsible for contacting
the local representative or NCDOT, respectively about pavement
repair/replacement.

3) Avoid overloading or surcharge a sufficient distance back from edge of


excavation to prevent slides or caving. Maintain and trim excavated
materials in such manner to be as little inconvenience as possible to public
and adjoining property.

4) Provide full access to public and private premises, to fire hydrants, at street
crossings, sidewalks and other points as designated by the Public Services
Director to prevent serious interruption of travel.

5) Protect and maintain benchmarks, monuments, or other established points


and reference points and if disturbed or destroyed, replace items to full
satisfaction of the Public Services Director and the jurisdictional agency.

City of Jacksonville, NC - Manual of Specifications, Standards & Design June 2006


Div 02275 - Trenching, Backfilling and Compaction of Utilities Page 02275-19

C. Procedures for repairing damaged utility services

1) If a located service is interrupted as a result of work under this Section,


immediately restore service by repairing the damaged utility at no additional
cost to the City.

2) House services: If a service pipe supplying water or gas to an adjoining


house is broken, the Contractor shall repair it at once and at his expense.
The City may, at the Contractor’s expense, repair any such service without
prior notice to the Contractor.

3.1.4 PROTECTION OF PERSONS AND PROPERTY

A. Barricade open holes and depressions occurring as part of the work, and post
warning lights on property adjacent to or part of public access.

B. Protect structures, utilities, sidewalks, pavements, and other facilities from


damage caused by settlement, lateral movement, washout, and other hazards
created by operations under this or other related sections.

C. Protection and Restoration of Property: The contactor shall not enter upon
private property for any purpose without first obtaining permission. He shall use
every precaution necessary to prevent damage or injury to any public or private
property, trees, fences, monuments, and underground structures, etc., on and
adjacent to the site of the work. He shall protect carefully from disturbance or
damage all land monuments and property markers until an authorized agent has
witnessed or otherwise referenced their locations, and shall not remove them
until directed.

The Contractor shall be responsible for all damage or injury to property of any
character resulting from any act, omission, neglect, or misconduct in his manner
or method or executing said work, from his nonexecution of work, or from
defective work or materials, and he shall not be released from said responsibility
until the work shall have been completed and accepted.

When or where any direct or indirect damage or injury is done to public or private
property by or on account of any act, omission, neglect, or misconduct in the
execution of the work, he shall restore such property, at his own expense, to a
condition equal to or better than that existing before such damage or injury was
done, by repairing, rebuilding, or otherwise restoring, and may be directed or he
may make good such damage or injury in an acceptable manner.

The Contractor shall, at his own expense, sustain in their places and protect
from direct or indirect injury all pipes, poles, conduits, walls, roadways, buildings,
and other structures, utilities and property in the vicinity of his work. Such
sustaining and supporting shall be carefully done by the Contractor and as
required by the Company or party owning the structures or Agency controlling it.
The Contractor shall take all risks attending the presence or proximity of pipes,
poles, conduits, walls, thereof and any costs associated will be deducted from
any monies due the Contractor. Failure of the Public Services Director or his/her

City of Jacksonville, NC - Manual of Specifications, Standards & Design June 2006


Div 02275 - Trenching, Backfilling and Compaction of Utilities Page 02275-20

authorized representative to direct the correction of unsafe conditions or


practices shall not relieve the Contractor of his responsibility hereunder.

3.1.5 CLEARING AND GRUBBING

A. Description: This work shall consist of clearing, grubbing, removing, and


disposing of all vegetation and debris within the limits of construction, as
designated on the plans or as required by the Public Services Director. The
work shall also include the preservation from injury or defacement of all
vegetation or objects designated to remain. Clearing shall consist of cutting,
removal, and satisfactory disposal of all trees, down timber, brush, rocks,
projected roots, stumps, rubbish, laps, and other material within easement.

B. A preconstruction meeting shall be held with appropriate forestry personnel and


the City prior to any clearing, if required. The Public Services Director may
require tree protection fencing in sensitive areas, where specifically identified
trees are desired to be protected, and when required by landscape ordinances.

C. The Contractor shall provide barricades, fences, coverings, or other types of


protection necessary to prevent damage to existing improvements, not indicated
to be removed, and improvements on adjoining property. All improvements
damaged by this work shall be restored to their original condition and to a
condition acceptable to the owner or other parties or authorities having
jurisdiction. Trees and shrubs that are to remain within the construction limits
will be indicated on the drawings or conspicuously marked on site. Unless
otherwise noted, trees within the construction limits shall become the property of
the Contractor and shall be removed from the site.

D. Contractor shall protect existing tress and other vegetation indicated by the
Public Services Director to remain in place against limb, bark or root damage
such as cutting, breaking, or skinning of roots, skinning and bruising of bark,
smothering of trees by stockpiling construction materials or excavated materials
within drip line, excess foot or vehicular traffic, or parking of vehicles within drip
line. When such damage does occur, all rough edges of scarred areas shall be
removed in accordance with accepted horticultural practices.

E. Carefully and cleanly, cut roots and branches of trees indicated to remain where
the roots and branches obstruct construction of the utility line. If directed by the
Public Services Director, the Contractor shall provide protection for roots and
branches over 1 ½ inches diameter that are cut during construction operations.
Coat the cut faces with emulsified asphalt, or other coating especially formulated
for horticultural use on cut or damaged plant tissues. Temporarily cover all
exposed roots with wet burlap to prevent roots from drying out. Provide earth
cover as soon as possible.

F. Trees and vegetation designated to remain shall be repaired or replaced at


Contractor’s expense in a manner acceptable to the Public Services Director if
they are damaged by construction operations. Repair tree damage as directed
by a qualified tree surgeon.

G. Debris from the site shall be removed in such a manner as to prevent spillage.
Keep pavement and area adjacent to site clean and free from mud, dirt, dust,
and debris at all times.

City of Jacksonville, NC - Manual of Specifications, Standards & Design June 2006


Div 02275 - Trenching, Backfilling and Compaction of Utilities Page 02275-21

H. The method of stripping, clearing, and grubbing the site shall be at the discretion
of the Contractor. However, all stumps, roots and other debris protruding
through the ground surface or in excavated areas shall be completely removed
and disposed of off the site by the Contractor.

I. Stripping of Topsoil: Remove the existing topsoil to a minimum depth of 6


inches or to the depth encountered from all areas in which excavation will occur.
The topsoil shall either be stored in stockpiles separate from the excavated
trench material if the topsoil is to be respread or otherwise disposed of off-site.
Topsoil stockpiles shall be graded to freely drain surface water, and shall have a
silt fence placed around the base of the stockpile.

J. Disposal: All brush, treetops, stumps, and debris shall be hauled away from
site or otherwise disposed of in a manner acceptable to the Public Services
Director. The Contactor shall clean up debris resulting from clearing operations
continuously with the progress of the work and remove promptly all salvageable
material that becomes his property and is not to be reused in construction. Sale
of material on the site is prohibited.

Disposal of cleared material shall be in accordance with all local and state laws.
Trees cut down on the construction site will be hauled away from the site for
proper disposal unless instructed otherwise by the City. Stumps of trees cut
down outside of the excavation area will be removed. Perishable material shall
not be disposed of at the construction site. Brush, laps, roots, and stumps from
trees shall be disposed of in a NCDENR approved and permitted land clearing
and inert debris type landfill. The Contractor will be responsible for obtaining all
applicable permits and paying all fees for the disposal of excess material.

3.1.6 DEWATERING

A. Water in trenches: When ground water is encountered, the Contractor shall


remove the water that accumulates in the trenches or pits, which would affect the
construction of the lines or their appurtenances, by pumping, bailing, well-
pointing, or other approved dewatering method and shall perform all work
necessary to keep the trenches or pits entirely clear from water while bedding is
being placed, the pipe is being laid, masonry units are being placed, and
structures are either being set or constructed. All water removed from the trench
shall be conveyed in a proper manner to a suitable point of discharge and shall
comply with applicable erosion and sediment control laws. Pipe laying and pipe
jointing shall be made in the “dry.”

B. No pipe shall be constructed in water and water shall not be allowed to drain
through the pipe. The open end of the pipe shall be kept closed with a tight
fitting plug to prevent washing of any foreign matter into the line.

C. No structure shall be constructed in water and water shall not be allowed to flow
over or rise upon any concrete masonry structure until the work has been
accepted.

D. The Contractor shall dispose of water from the trenches in such a manner to
cause no injury to public health, public or private property, work completed or in
progress, street surfaces, or which may cause any interference with the use of
the streets. Water, if odorless and stable, may be discharged into an existing

City of Jacksonville, NC - Manual of Specifications, Standards & Design June 2006


Div 02275 - Trenching, Backfilling and Compaction of Utilities Page 02275-22

storm drain, channel, or street gutter in a manner approved by the Public


Services Director. When required by the Public Services Director, a means shall
be provided for desilting (filtering) the water before discharge. Under no
circumstances shall water be discharged to the sanitary sewer.

E. Prevent surface water from ponding on prepared subgrades and from flooding
project site and the surrounding area. Reroute surface water runoff away from
or around excavated areas.

F. Do not allow water to accumulate in excavations. Do not use excavated


trenches as temporary drainage ditches.

G. Install a dewatering system to keep subgrades dry and convey ground water
away from excavations. The cost of shoring, sheeting, well pointing, gravel
bedding and other dewatering devices shall be included in the unit price of each
respective item bid. Maintain until dewatering is no longer required.

H. Protect subgrades from softening, undermining, washout, and damage by rain or


water accumulation. Include cost of de-watering in proposal for water, sewer, or
storm drainage lines. No additional remuneration for this item is permitted.

I. Where underground streams or springs are encountered, provide temporary


drainage, well pointing, or bailing. Notify the Public Services Director of such
conditions.

J. Backfilling shall not take place when the trench contains water in an amount to
create soupy conditions.

3.2 TRENCH EXCAVATION

3.2.1 GENERAL

A. Classification of Excavated Material: All excavated material shall be classified


as either earth or rock. Prices bid for the various sizes of pipe shall include
excavation and backfilling; such excavation shall be classified as earth. Rock
excavation shall be paid for as a separate item.

B. Remove all material of whatever nature, including but not limited to clay, silt, and
gravel. Provided the material meets the requirements of paragraph 2.1.1
Material Classification, subparagraph F, Common Trench Backfill, material of a
compactable nature that can be re-used as trench backfill shall be replaced and
re-compacted to the requirements set forth in these specifications.

C. Unsuitable Material and Wasting: When directed by the Owner’s Engineer or


the Public Services Director, unsuitable material in the trench shall be removed
to an appropriate depth and width. At the Contractor’s expense, dispose of all
unsuitable material, of whatever nature, to a site that legally can accept such
material as fill. Adhere to all applicable laws and ordnances regarding permitting
of waste site, erosion control, zoning, etc. as may be applicable.

D. Excavation shall be performed in accordance with OSHA Standard 29 CFR Part


1926, OSHA Subpart P “Excavation and Trenching.”

City of Jacksonville, NC - Manual of Specifications, Standards & Design June 2006


Div 02275 - Trenching, Backfilling and Compaction of Utilities Page 02275-23

E. Sanitary and Storm Sewer Alignment and Grade: Offset stakes set at each
manhole, catch basin, or curb inlet shall indicate the line and grade of the sewer.
Alignment and grade of the pipe by the Contractor shall be established by laser
beam. The Contractor shall employ personnel experienced in the use of laser
beams. The alignment and grade of the sewer shall be constructed as indicated
on the approved plans. Prior to making changes in the field, the Public Services
Director shall approve any change in grade or alignment that deviates from the
approved plans. Refer to Water and Sewer Design, paragraph 1.3.3 H regarding
acceptance and compensation for lines deviating from minimum grade.

F. Concrete collars shall be installed on lines with slopes 10% or greater.

3.2.2 PIPE COVER

A. General: Where lines traverse public property or are subject to other


governmental or utility company jurisdiction, provide depth, bedding, cover, and
other requirements as set forth by legally constituted authority having jurisdiction,
but in no case less than the depth shown in the Contract Documents.

B. Minimum Cover: Unless shown otherwise on the construction documents,


provide minimum trench depth indicated below to maintain a minimum cover over
the top of the installed item. Minimum cover on pipe is measured perpendicular
from top of pipe or fittings to original ground or proposed finished grade as
applicable and shall be per Table 2275.1, below. Where the minimum cover is
not provided, either use Ductile Iron Pipe or encase the pipe(s) in concrete as
indicated. Provide concrete with a minimum 28-day compressive strength of
3000 psi.

City of Jacksonville, NC - Manual of Specifications, Standards & Design June 2006


Div 02275 - Trenching, Backfilling and Compaction of Utilities Page 02275-24

Table 2275.1
Minimum Cover above top of Main Pipe Lines
Condition
Utility Subject to NOT subject to With Concrete
vehicular traffic vehicular traffic Encasement
Sanitary Sewer 36b inches 24b inches As Designed
(use DIP if < 36 (use DIP if < 36
inches of cover) inches of cover)
Sewer Services At depth shown At depth shown As Designed
on plans but no on plans but no
b b
less than 36 less than 12
inches inches
Water 36a inches 36a inches 18 inches
Distribution (see paragraph
C, regarding
encasement)
Water services 30a inches 30a inches As Designed
Storm Drainage As designed but As designed As Designed
c
no less than 12
inches for
reinforced
concrete pipe
a
Minimum/Maximum Cover for Water Pipe: The Public Services Director must
approve all installations of water mains with less than 36 inches of cover or greater
than 60 inches of cover.
b
Minimum/Maximum Cover for Sewer Pipe: The Public Services Director must
approve all installations of sewer lines with 36 inches of cover or less or with greater
than 18 feet of cover. Ductile iron pipe is required where depth of pipe exceeds 12
feet or the line is placed in fill.
c
Minimum/Maximum Cover for Storm Drainage Pipe: The Public Services
Director must approve all installations of storm drainage lines in areas subject to
traffic load with less than 12 inches of cover or with greater than 12 feet of cover. The
pipe class, trench width, and/or the bedding class shall be modified for the depths
exceeding 12 feet of cover to accommodate the extra depth/loads. Pipe subject to
vehicular traffic shall be reinforced concrete pipe. No plain concrete pipe is permitted
in traffic areas.

C. Water lines that have no more than 24 inches of cover below the original flow
line of a ditch or culvert crossing may be required by the Public Services Director
to be encased in concrete for a length of at least 5 feet beyond each side of the
ditch or culvert.

3.2.3 TRENCHING

A. General: The trench for gravity pipe shall be excavated to conform to standard
details 511.01 (water and drainage) and 531.01 (sewer) as applicable. Where it
is necessary to remove existing pavements, prepared road surfaces, sidewalks
and curbs, these structures/surfaces must be replaced by the Contractor. When
making a pavement cut, the Contractor shall use care to saw cut in sharp, neat
lines ahead of the excavating/ditching equipment and parallel to the pipe on each
side as may be applicable. Edges of existing pavement shall be re-cut and

City of Jacksonville, NC - Manual of Specifications, Standards & Design June 2006


Div 02275 - Trenching, Backfilling and Compaction of Utilities Page 02275-25

trimmed to square, straight edges after the pipe system has been installed and
prior to placement of the new base and pavement.

All trenching shall be open-cut from the surface. No tunneling or boring will be
allowed without the consent of the Public Services Director. All trenches shall be
excavated to the lines and grades as shown on the plans. Where utility lines are
in an existing paved area, the edges of the pavement for the utility line shall be
cut in a straight line, parallel to the pipe.

Trenches shall be excavated in straight lines, in general, following the contour of


the ground, and shall be accurately graded in order to establish a true elevation
of the invert of the pipe. Trenches for water lines may be curved within the limits
of curvature of the pipe as allowed by AWWA C600. In no case shall the trench
alignment exceed the allowable vertical or horizontal pipe deflection of offset
recommended by the pipe manufacturer.

1) Trench Width: The sides of trench shall be uniform and vertical. The width
of the trench at the top of the pipe shall be a width that will permit the proper
construction of joints and compaction of backfill around the pipe and shall be
equal to the largest outside diameter of the pipe plus 12 inches on each side
of the pipe, measured at the top of the pipe. The sides of the trenches shall
be vertical unless otherwise approved by the Public Services Director.
Vertical walls should project at least 2 feet above the top of the pipeline laid
to existing construction grade unless the finished grade fill depth is less than
2 feet. Lowering trench wall height may necessitate a change in either pipe
or bury classification. Notwithstanding, this section is subject to OSHA
guidelines and regulations regarding trench protection and shoring.

Every effort shall be made to maintain the width of the pipe plus 24 inches
but trench width must also be wide enough to provide adequate space for
laying and connecting pipe and appurtenances. Sufficient space shall be
allowed at the joints for the free use of wrenches for tightening of bolts.

The minimum trench width should generally be no less than 36 inches in


order to accommodate a “Rammax” type tamp.

In excavating for the trench, it is essential that the trench bottom be uniform
in grade and remains static during backfilling and under all subsequent
trench conditions. To insure a uniform depth of stone, the grade of the
bottom of the trench shall be graded to within 0.04 foot (1/2-inch) of the plan
specified grade. The stone shall be graded to the same tolerance.

2) Trench Depth:

a. General: All trenches shall be excavated to accommodate the bedding


as shown in standard details 511.01 (water and drainage) and 531.01
(sewer) as applicable. No extra compensation will be made for stone
bedding used to bring the trench up to grade other than that required in
standard detail C01.02 where yielding or wet subgrade is encountered.

b. Water: Trench depth shall generally conform to that shown on the plans
and in conformity to the requirements of Table 2275.1, Minimum Cover
above top of Main Pipe Lines.

City of Jacksonville, NC - Manual of Specifications, Standards & Design June 2006


Div 02275 - Trenching, Backfilling and Compaction of Utilities Page 02275-26

c. Gravity sewer: Excavate to the depth and grades shown on the plans.
Trench depth shall generally conform to the requirements of Table
2275.1, Minimum Cover above top of Main Pipe Lines.

d. Storm drainage: Excavate to the depth and grades shown on the plans.
Trench depth shall generally conform to the requirements of Table
2275.1, Minimum Cover above top of Main Pipe Lines.

3) Open trench exposure: Once trench is opened, proceed immediately and


with dispatch to place specified materials in trench, or to otherwise utilize
trench for intended purpose. Long stretches of open trench ahead of pipe
laying shall be avoided. Excavating, pipe laying, and backfilling must move
forward at approximately equal rates of progress. The Contractor shall only
open as much ditch as he can completely install pipe, backfill, compact, and
cleanup within that working day. The Contractor shall string out the pipe that
can be installed in one day, and no more than 300 feet of trench shall be
open in advance of the completed work in any section. There shall be no
trenches left open without proper supervision during working hours or after
work has been completed for the day. Any exception to this construction
practice must be approved, in writing, by the Public Services Director.
Schedule work and order materials so that trenches are not left open for a
longer period than is reasonably necessary. If the Contractor should fail to
heed the aforementioned requirement, the Public Services Director may
refuse payment until these conditions are complied with.

4) Containment of Sediment (solids and mud): The Contractor shall at all


times so conduct his work to insure that all solids and mud are contained
within the trench. This containment shall be by the employment of a brick or
block weir or a rock check dam at the junction of new construction and the
existing City system in order to trap material for the Contractor’s removal and
City’s inspection prior to acceptance. The installation and removal of this
dam shall be at the Contractor’s expense and shall be removed before the
line is televised.

3.2.4 SHEETING AND BRACING, TRENCH BOXES

A Certified Competent Person designated by the Contractor shall be on-


site at all times excavation or pipe installation is being conducted.

Conditions permitting, trench walls may have vertical sides up to a maximum


depth of 5 feet above subgrade elevation. Above this depth, the entire side must
be laid back or either shoring or a trench box, certified for the depths being used,
must be used. The Contractor shall be required to furnish, put in place, and
maintain such sheeting, bracing, etc. as may be required to support the sides of
the trenches. Brace and sheet trenches in full observation of OSHA
requirements.

Brace trenches running near walls or columns, to prevent any settlement or


other disturbance of walls or columns.

Do not remove sheeting until backfilling has progressed to stage that no damage
to piping, utility service, or conduit will result due to removal. All shoring and
form material shall be removed before backfilling. When sheeting, bracing, or
trench boxes are required, in order to prevent damage to existing facilities or

City of Jacksonville, NC - Manual of Specifications, Standards & Design June 2006


Div 02275 - Trenching, Backfilling and Compaction of Utilities Page 02275-27

structures, or as a matter of safety, or as directed by the Public Services


Director, the costs are to be included in the unit prices as bid for sanitary sewers,
storm drains, water lines or structures as applicable and there shall be no
additional cost for these items.

Sloping trench walls: If trench walls are to be sloped or benched, Contractor is


responsible for determining the proper and applicable slope based on soil type in
order to meet OSHA requirements. Laying back slopes also applies for areas
where the top of the trench box is lower than the top of the bank. Contractor
shall employ the services of a Geotechnical Engineer for direction and guidance
if unstable or difficult soils are encountered. In any event, the Contractor shall
hold the City harmless for injuries and/or damages resulting from failure to
properly adhere to trench protection regulations/requirements in force at the time
of a failure or mishap including, but not limited to, damage to utilities, equipment,
structures, paving, etc.

3.2.5 ROCK:

A. Rock Excavation/Definition: Rock excavation shall consist of the removal and


satisfactory disposal of all materials, which in the opinion of the Public Services
Director, cannot be excavated except by drilling, blasting, “jack hammering, or
hoe ramming” (reasonable production for rock excavation by “jack hammering or
hoe ramming” will be defined as five or more cubic yards per hour). Rock shall
consist of undecomposed stone, hard enough to ring under hammer. All
boulders containing a volume of more than one-half cubic yard will be classified
as rock. When rock is encountered in the trench, the Public Services Director
must be notified before any rock has been blasted or removed. The Public
Services Director will measure the rock, after which, the rock shall be excavated
to a depth 6 inches below the grade of pipe and the bottom of trench brought
back to grade by using an approved fill material. See paragraph 3.8, Blasting for
other requirements regarding rock excavation.

B. Cushioning pipe in rock: Special precautions shall be exercised to prevent any


pipe from resting on rock or any other hard projection that might cause breakage
of pipe. At no time shall the pipe bell or the pipe barrel rest on rock. A minimum
of 6 inches of stone cushioning is required between the barrel of the pipe and
rock. A minimum of 12 inches of clearance is required between the sides of the
pipe and the rock. Thicker cushioning may be required for deeper pipe on a
case-by-case basis.

C. Disposal of Rock: Rock excavated from the trench shall be hauled off the site
at the Contractor’s expense. Borrow required to replace excavated rock shall be
provided by the Contractor and shall be included in the unit price bid for rock
excavation. No rocks or boulders shall be used as backfill in any part of the
trench. Where rock has scattered over adjoining property as a result of blasting,
the Contractor shall remove the rock and restore the area to its original condition
at no cost to the City.

3.2.6 PREPARATION OF FOUNDATION FOR PIPE LAYING

A. Excavation of trenches for all pipelines shall be done to line and grade as
established by the design engineer. The bedding surface shall provide a firm,
stable, and uniform support through the entire length of the pipe. Recesses shall
be excavated to accommodate bells and joints. When bedded firmly on the

City of Jacksonville, NC - Manual of Specifications, Standards & Design June 2006


Div 02275 - Trenching, Backfilling and Compaction of Utilities Page 02275-28

subgrade, the pipe shall be on the exact grade of the completed water, sewer, or
storm drainage line.

In excavating for the trench, it is essential that the trench bottom be uniform in
grade and remains static during backfilling and under all subsequent trench
conditions. To insure a uniform depth of stone, the grade of the bottom of the
trench shall be graded to within 0.04 foot (1/2-inch) of the plan specified grade.
The stone shall be graded to the same tolerance.

Excavation in Class II, III, or IV soils shall be made to grade to provide


undisturbed bedding in accordance with AWWA C600.

B. Unsuitable Trench Subgrade/Foundation Improvement: Excavation in Class


V, wet, yielding, unstable, inadequately supporting, or mucky soils shall be
excavated 6 inches or more below the specified grade (see standard detail
C01.02). The material shall be removed for the full width of the trench and the
excavated area strengthened for foundation purposes. The over excavated
material shall be replaced with thoroughly compacted Class I, II, or III materials
as directed by the Public Services Director. The trench bottom shall provide a
stable and continuous support for the pipe system with bell holes provided to
permit jointing.

Whenever the bottom of the trench is such that it cannot be reasonably


stabilized, the Public Services Director may require the utility to be laid in a
concrete mud mat, concrete encasement, cradles, in cradles supported on piles,
or a combination of these materials. When necessary, the Contractor shall
provide for the temporary diversion of water in order to maintain the pipe
foundation in a dry condition.

Observe the following requirements when unstable trench bottom materials are
encountered:

1) Notify the City when unstable materials are encountered and define by
drawing station locations and limits when encountered.

2) Remove unstable trench bottom materials as directed and replace with


subgrade stabilization material specified.

Over-excavation: Unauthorized over-excavation consists of removal of material


beyond indicated subgrade elevations or side dimensions, without specific
approval of the Public Services Director. Exercise care to avoid excavations
below established grade where firm earth conditions exist. Where unauthorized
excavations have been carried beyond points required, restore these areas to
the elevations and dimensions shown on the drawings with approved fill material
and compact as specified (as noted in the preceding paragraph). In no case
shall the pipe be brought to grade by blocking under the barrel of the pipe. A
uniform support shall be provided for the entire length of the pipe. Unauthorized
excavation shall be replaced at Contractor’s expense.

Care shall be taken not to over excavate the trench. All trenches excavated
below grade (over excavated) shall be refilled to grade with thoroughly
compacted Class I, II, or III materials (see standard detail 511.01 for
classifications) as directed by the Public Services Director. No extra

City of Jacksonville, NC - Manual of Specifications, Standards & Design June 2006


Div 02275 - Trenching, Backfilling and Compaction of Utilities Page 02275-29

compensation shall be allowed for this work unless such excavations are
ordered by the Public Services Director.

3.2.7 TRENCH PREPARATION FOR PIPE

A. Preparation of Trenches for Gravity pipelines

The bottom of the trench for gravity sanitary sewer pipelines shall be excavated
to a minimum over depth as shown on standard detail 531.01 to provide for
improved pipe bedding material for the entire length of the gravity pipeline,
including sewer lateral connections, except in rock where bedding shall be a
minimum of 6 inches deep (see paragraph 3.2.5 B, above). The bedding shall
be shaped so that the bottom half of sanitary sewer pipe rests on the bed. Bell
holes and depressions as required of the joint shall be dug after the bedding has
been graded and shaped, and shall be only of such length, depth, and width as
required for properly making the particular type of joint. The trench for sanitary
sewers and lateral connections shall then be backfilled and compacted as
indicated in Table 2275.3.

B. Preparation of Trenches for Storm Drainage Pipelines

The bottom of the trench for storm drainage pipelines shall be excavated to a
minimum over depth as shown on the construction drawings in accordance with
the applicable laying condition specified (as shown on standard detail 511.01)
to provide for pipe bedding for the entire length of the gravity pipeline, including
lateral connections if any, except in rock where bedding shall be a minimum of 6
inches deep (see paragraph 3.2.5 B, above). The bedding shall be shaped so to
conform to a Type 2 or Type 3 laying condition as may be indicated on the
drawings. Bell holes and depressions as required of the joint shall be dug after
the bedding has been graded and shaped, and shall be only of such length,
depth, and width as required for properly making the particular type of joint. The
trench for storm drainage and lateral connections, if any, shall then be backfilled
and compacted as indicated in Table 2275.3. Rock larger than 3 inches shall be
removed from the trench bottom and any voids filled with Class I, II, or III
material. Rock shall be removed 6 inches below pipe and the void filled with
clean stone.

C. Preparation of trenches for Water Mains and Force Mains

The trenches for water lines and sewage force mains shall be graded to avoid
local high points. Trenches shall be graded either level or on a continuous
upslope to the high points designated on the drawings. Trenches shall be of
such depth as to provide a minimum cover over the top of the pipe as noted in
Table 2275.1. The trenches shall have 4 inches of loose soil in the bottom
before pipe is placed, so pipe is firmly and continuous in contact with the soil.
Pipe shall not bridge any areas. Rock larger than 3 inches shall be removed
from the trench bottom and any voids filled with soil or clean stone. Bell holes
shall be provided at each joint to permit proper joint assembly and proper pipe
support. Rock shall be removed 6 inches below pipe and the void filled with
clean stone.

D. Surface or Ground Water in Trenches/Pipe

City of Jacksonville, NC - Manual of Specifications, Standards & Design June 2006


Div 02275 - Trenching, Backfilling and Compaction of Utilities Page 02275-30

When ground water is encountered, the Contractor shall pump, or otherwise


remove any water that accumulates in the trenches and shall perform all work
necessary to keep the trenches clear from water while pipe is being laid. No
pipe shall be laid in water and the pipe shall not be used as a means of draining
ground water from the trench. All water removed from the trench shall be
conveyed in a proper manner to a suitable point of discharge and shall comply
with the applicable erosion and sedimentation laws. See paragraph 3.1.6 –
Dewatering, of this specification.

The open end of water or sewer pipe shall be kept closed with a watertight plug
to prevent washing of any foreign matter into the line. At the conclusion of the
workday, or at any other time when pipe laying is not in progress, a watertight
plug shall be placed in the bell of the last joint of pipe laid.

Storm drainage pipe shall either be plugged or an appropriate sediment trap


placed at the upstream end to prevent siltation.

3.2.8 TRENCHING IN FILLS

In areas where trenching for pipes will be in fills, the fills shall be brought to an
elevation of at least 12 inches above the top of the pipe, and then the trench
excavated in the compacted fill, as herein specified for trench excavation.

3.2.9 SUBSURFACE DRAINAGE

Installation of subsurface drainage systems shall conform to the requirements of


Section 815 – Subsurface Drainage of the NCDOT Standard Specifications for
Roadways and Structures, latest revision using non-woven needle-punched
fabric.

3.2.10 EXCAVATION FOR STRUCTURES

A. Excavate to provide a minimum of 3 feet of horizontal clearance between outer


surface of structure and trench wall.

B. Where rock is encountered so that a built-in-place manhole, precast structure


(such as a manhole or vault), or other structure will bear over rock, remove the
rock to a minimum of 8 inches below the foundation or footing of the structure
and place an 8 inch cushion of clean #57 stone over the rock.

3.2.11 WATER MAIN BEND BLOCKING INSTALLATION

A. Excavate area to receive poured in place concrete blocking to exact dimensions


shown in standard detail 512.01. Blocking is to be placed in undisturbed
residual soils. If blocking is to be placed in areas where boulders or stumps
have been removed or in areas of loosely compacted fills, such as in landscaped
areas (outside of pavements or parking lots), contact the Public Services
Director for directions.

B. Concrete shall be plain concrete with a minimum compressive strength of 3000


psi at 28 days.

C. Wrap bolts in plastic or provide other acceptable means of protection, approved


by the Public Services Director before pouring concrete blocking.

City of Jacksonville, NC - Manual of Specifications, Standards & Design June 2006


Div 02275 - Trenching, Backfilling and Compaction of Utilities Page 02275-31

3.2.12 DEPOSITION OF EXCAVATED MATERIAL

A. All excavated material shall be placed on one side of the trench (a minimum of 2’
from the edge of excavation as required by OSHA regulations) away from the
roadway unless permission is given by the City’s representative to place it on
both sides. Excavated materials shall be so placed as not to endanger the work
and so that free access may be had at all times to all parts of the trench and to
all fire alarm boxes, fire hydrants and gate valves on water pipes, which are
located in the vicinity. Excavated material shall be placed to inconvenience the
public as little as possible. All fences and walls shall be protected and, if
damaged, shall be repaired or replaced in as good or better condition as before it
was disturbed. Protect shade trees from stockpiling of material.

B. Exercise care when stockpiling excavated material on the bank in order to


prevent surcharging the bank of the trench and potentially rendering the
excavation unstable.

C. Wasting of Unsuitable Material: Material of an uncompactable nature, material


unsatisfactory for backfill, trash and excess material shall be removed from
project site and disposed at the Contractor’s expense. Where removal of
unsatisfactory material is due to negligence on the part of the Contractor (i.e.
resulting from inadequate shoring or bracing, failure to dewater, improper
material storage exposing it to rain or flooding, or other failure to meet specified
requirements), work shall be performed at no additional cost to the City. If
additional material is required, the Contractor shall supply it from an approved
borrow pit at no additional cost to the City. Rock excavated from the trench shall
be hauled off the site at the Contactor’s expense.

3.3 BEDDING

3.3.1 BEDDING DEFINITIONS: see paragraph 2.1.2, Pipe Bedding Definitions.

3.3.2 MINIMUM BEDDING REQUIREMENTS by type of pipe:

A. Sewer Pipe Bedding: Provide granular trench bedding material. In no case,


unless specifically exempted in writing by the Public Services Director, shall the
stone bedding be less than the minimum bedding shown in standard detail
531.01. Unsuitable subgrade shall be improved as directed by the Public
Services Director and as shown on standard detail C01.02.

B. Bedding Water Pipe, Water Service Pipe, and Sewage Force Mains: Unless
otherwise directed by the Public Services Director, do not bed water pipe, water
service pipe, and sewage force mains in stone except as indicated for rock
areas (see standard detail 511.01). Where rock is encountered bed in
accordance with paragraph 3.2.5 B Cushioning pipe in rock.

C. Storm Drainage Bedding: Provide granular trench bedding material. In no


case, unless specifically exempted in writing by the Public Services Director,
shall the stone bedding be less than the minimum bedding shown in standard
detail 631.01. Unsuitable subgrade shall be improved as directed by the Public
Services Director and as shown on standard detail C01.02.

City of Jacksonville, NC - Manual of Specifications, Standards & Design June 2006


Div 02275 - Trenching, Backfilling and Compaction of Utilities Page 02275-32

D. Bedding for Structures: The bottom of manhole bases and other precast
structures and appurtenances shall be excavated to minimum over depth of 6 or
8 inches, as indicated in the applicable standard details, below the bottom of the
structure. The structures shall be placed on clean stone bedding that has been
firmly consolidated. Bedding material shall be shaped, graded, and compacted
so that the entire bottom of the structure rests level on the material for its entire
area.

3.3.3 BEDDING MATERIAL PLACEMENT

A. Unless otherwise specified, the bottom of the pipe trench for sanitary sewer, and
where indicated by the Public Services Director, storm drainage pipe shall be
excavated to below the bottom of the pipe, to provide for the compacted
bedding materials, expect as specified in rock. Bedding material shall be
placed, shaped, and compacted so that at least the bottom of the pipe rests
uniformly upon the material for the entire length of the pipe. Bell holes and
depressions required for the jointing of pipe shall be dug after the compacted
bedding material has been graded and shaped and shall be only of the length,
depth, and width required to make the joint properly. Care shall be taken to
make sure bedding fills the voids beneath the pipe haunches, by poking with a
shovel or tamper. See standard details 511.01 and 531.01, as applicable.

3.4 BACKFILLING (MATERIALS AND METHODS)

3.4.1 BACKFILLING

A. GENERAL:

1) Materials: See paragraph 2.1.1 - Material Classification for Select Earth


Backfill and Common Trench Backfill classification. In areas of extensive
rock excavation, where there is a shortage of suitable backfill, the Contractor
shall, at his own expense, haul suitable material in to be placed over the
pipe.

2) Pipe and fittings shall be inspected before backfilling.

3) Except as otherwise specified or directed for special conditions, backfill


trenches to the ground surface with Common Trench Backfill material
approved by the Public Services Director. After the pipe has been brought to
grade on a proper foundation, earth fill shall be placed carefully about the
pipe and tamped properly to hold the pipe in position. Exercise extreme care
in backfilling operations to avoid displacing joints and appurtenances or
causing any horizontal or vertical misalignment, separation, or distortion.
Repair damages, distortions, or misalignments to full satisfaction of the
Public Services Director. Pipe shall be removed if broken or damaged during
installation. Backfill shall closely follow the pipe installation. Unless
otherwise directed or permitted by the Public Services Director, all pipe laid
shall be backfilled during the same day, and prior to the completion of the
day’s work, to provide a firm continuous support and covering for the pipe.

4) Reopen trenches that have been improperly backfilled, to a depth as required


for proper compaction. Refill and compact as specified or otherwise correct
to the approval of the Public Services Director.

City of Jacksonville, NC - Manual of Specifications, Standards & Design June 2006


Div 02275 - Trenching, Backfilling and Compaction of Utilities Page 02275-33

5) Do not allow or cause any of the work performed or installed to be covered


up or enclosed by work prior to required inspections, tests, and approvals.
Should any of the work be so enclosed or covered up before it has been
approved, uncover all such work and, after approvals have been made, refill
and compact as specified, all at no additional cost to the City.

6) Observe specific pipe manufacturer's recommendations regarding methods


of backfilling and compaction.

7) Insure compaction of each lift to requirements stated in these specifications.

8) All pipe areas shall be graded and maintained in such a condition that
erosion or saturation will not damage the pipe bed or backfill.

9) Heavy equipment shall not be operated over any pipe until it has been
properly backfilled and compacted with a vibratory compaction device (i.e.
Rammax or jumping jack, NO PLATE TAMP) and has a minimum cover as
required by the plans. Pipe that is misaligned, shows excessive settlement,
or has been otherwise damaged by the Contractor’s operations, shall be
removed and replaced at no cost to the City.

10) Installation of Warning Tape: All water mains and sewer force mains shall
have a non-metallic underground warning tape shall be installed directly over
the pipe approximately 8 inches to 12 inches below finished (final design)
grade.

11) Installation of Tracer Wire: All non-metallic pipes shall have a bare 10
gauge copper tracer wire attached to the pipe. On water mains, copper wire
shall be from valve to valve with copper wire protruding up in valve box. On
force mains, copper wire will be from lift station to the manhole tie-ins. It
shall be continuous and uninterrupted with valve boxes placed at major
bends or at 1000 feet maximum intervals. A sufficient excess length of wire
shall be left in each box to provide at least a 2-foot length of wire above
finished grade.

Clamps used to bond wire to conductor to metal (in instances where both
PVC and DIP are used in the same run of pipe) shall be heavy-duty stainless
steel approved by the Public Services Director.

B. METHODS:

Provide backfill and compaction methods of following types:

1) Carefully Compacted SELECT INITIAL EARTH BACKFILL: Furnish


carefully compacted select earth backfill where indicated on drawings or
where determined necessary by the Public Services Director and specified
for compacted backfill conditions up to 12 inches above top of pipe. See
paragraph 2.1 Soil, Bedding, and Backfill for definition of Select Initial Earth
Backfill. Comply with the following:

Care shall be taken to prevent any disturbance to the pipe or damage to


newly made joints. The filling of the trench shall be carried on
simultaneously on both sides of the pipe in such a manner that injurious side

City of Jacksonville, NC - Manual of Specifications, Standards & Design June 2006


Div 02275 - Trenching, Backfilling and Compaction of Utilities Page 02275-34

pressures do not occur such that the pipe could be displaced or dislodged.
Do not backfill on muddy or frozen soil.

Sheeting and shoring generally should be removed only when the trench
below it has become substantially filled, and every precaution shall be taken
to prevent any slides of material from the sides of the trench onto or against
the pipe.

a. Unless otherwise approved by the Public Services Director, place backfill


in lifts not exceeding six inches (loose thickness).

b. Hand place, shovel slice, and hand tamp carefully compacted backfill
solidly around pipe. Only hand tamping shall be used to compact earth
around the pipeline. When the backfill has been brought to 12 inches
above the top of the barrel, vibratory compaction devices (i.e. Rammax or
jumping jacks, NOT PLATE TAMPS) shall be used to compact the
remainder of the soil.

2) COMMON EARTH (FINAL) BACKFILL. Perform remaining backfill in


accordance with drawings or as directed by the Public Services Director.
See paragraph 2.1 Soil, Bedding, and Backfill for definition of Common Earth
Backfill. Comply with the following:

a. Unless otherwise specified or approved by the Public Services Director,


backfill the remainder of the trench, from 12 inches above the pipe to
grade, with clean earth fill free of stones larger than 3 inches in diameter.
Material shall be free from all perishable and objectionable materials
(organic). Before placing any backfill, all rubbish, forms, blocks, wires, or
other unsuitable material shall be removed from excavation. The
backfilling shall be placed in layers not over 6 inches thick in the street
right of way and 12-inch layers outside of the street right of way. See
Table 2275.4. Final backfill shall be tamped with a vibratory compaction
device (i.e. Rammax or jumping jack, NOT A PLATE TAMP). See Table
2275.3 below, for specific density requirements.

b. All areas within the limits designated on the drawings, including adjacent
transition areas, shall be uniformly graded. The Contractor shall finish
surfaces within the specified tolerances with uniform levels or slopes
between points where elevations or existing grades are shown.

i) Finish subgrade areas that are to receive topsoil. Bring such areas to
within 0.10 foot of required subgrade elevations.

ii) Shape subgrade under sidewalks to line, grade, and cross-section.


Subgrade is to be brought to within 0.10 foot of required subgrade
elevations.

iii) Shape subgrade under pavement to line, grade, and cross-section.


Bring to within ½ inch of required subgrade elevations.

c. Surface Protection – Traffic: The Contractor shall protect newly graded


areas from traffic and erosion, repair, and re-establish grade in settled,
eroded, or rutted areas. Where compacted areas are disturbed by
subsequent construction or adverse weather, the Contractor shall scarify

City of Jacksonville, NC - Manual of Specifications, Standards & Design June 2006


Div 02275 - Trenching, Backfilling and Compaction of Utilities Page 02275-35

the surface, reshape, and re-compact to the required density. If the


Contractor shall fail to maintain any trench within 2 days after receipt of
written notice from the Public Services Director, the City may refill said
depressions and the cost of such work may be retained from monies due
the Contractor. In case of emergency, the Public Services Director may
refill any dangerous depressions without prior notice to the Contractor.

3) Structure Backfill: Backfill placed within 2 feet of manholes and other


special structures shall be of the same quality as that specified for backfill
around water, sewer or storm drainage lines. Take care to prevent wedging
action of the backfill against structure by carrying the material uniformly
around the structure so approximately the same elevation is maintained in
each lift. Material shall be solidly tamped with a mechanical or pneumatic
tamper in such a way as to avoid damaging the structures or producing
unequal pressures. The Contractor shall refill all excavations as rapidly as
practical after completion of the structural work therein, or after the
excavations have served their purpose.

3.5 COMPACTION/DENSITY

Soil shall be compacted using equipment suitable for the material and the work area
location. Power driven hand tampers shall be used for compacting materials adjacent to
structures. Use hand tamper for recompaction over underground utilities.

A. Testing

Testing of backfill shall be performed by an independent laboratory approved by


the City and the Contractor. The Contractor shall be responsible for excavation
for testing.

Quality Assurance vs. Quality Control:

Quality Assurance (QA) testing, and the associated cost, is the responsibility of
the City. Quality Assurance testing by the City is used to confirm that the
Contractor is generally performing his/her work in compliance with these
specifications.

Quality Control (QC) testing is the necessary and required testing that is to be
performed by the Contractor to assure that he/she is meeting and complying with
the requirements of these specifications. The associated cost for QC testing is
the Contractor’s responsibility. The Contractor is also responsible for “re-testing”
costs incurred by the City when the City test results (tests for Quality Assurance)
results in a “failure.”

B. Quality Assurance (QA):

In the course of backfilling trenches for utility installations, the Public Services
Director may require “Field Density Determinations” or compaction tests. When
compaction tests are called for, the Public Services Director will determine the
location of the tests and the City shall engage a qualified testing firm to perform
the test. Field density determinations shall be performed in accordance with
AASHTO T191, T205, and T214, modified to include material sizes used in the
laboratory determination of density with nuclear field density testing device or by

City of Jacksonville, NC - Manual of Specifications, Standards & Design June 2006


Div 02275 - Trenching, Backfilling and Compaction of Utilities Page 02275-36

other approved methods. A representative of the City will observe tests and a
copy of the test results and inspection report will be submitted by the testing firm
directly to the Public Services Director. When the average of 3 test results, with
no one test failing by more than 3 percentage points, indicate that the density is
less than the percent specified, the Contractor shall excavate and re-compact
the areas that have failed at no expense to the City. Payment for failed
compaction test shall be made by the Contractor by deducting the cost from the
forthcoming retainage or billed directly to the Contractor.

C. Quality Control (QC):

For City funded projects, the cost of Quality Control testing shall be included in
the bid prices for water and/or sewer installation. Where backfill compaction is
suspect and questionable, the material shall be removed as directed by the
Public Services Director and the area tested. If a suspect area fails to meet the
prescribed minimum moisture density test requirements, the soil shall be
removed, replaced, compacted, and re-tested, as directed by the Public Services
Director, until the backfill meets or exceeds the minimum density requirements.
The Contractor shall pay for all costs associated with re-testing.
Table 2275.2
Testing Frequency
Location Frequency
Trench areas in road 1 per road crossing, and/or
crossings
Trench areas 1 per 200 linear feet per two feet of fill thickness

Exception:
D. SWhere additional tests are required to determine the extent of unacceptable
i compaction (having been determined by the initial QA/QC test). In this case,
t the costs for these additional tests are the responsibility of the Contractor.
e
access for testing: Ensure City, at all times, has immediate access to the site
for the testing of all soils related work. Ensure excavations are in a safe
condition for testing personnel.

E. Compaction Requirements: Unless noted otherwise on drawings or more


stringently by other sections of these specifications, place and ensure backfill
and fill materials achieve an equal or "higher" degree of compaction than
undisturbed materials adjacent to the work; however, in no case shall degree of
compaction fall below the following percentages of the maximum density at
optimum moisture content. Tolerance is to be within +/- 3 percentage points of
the optimum moisture content.

City of Jacksonville, NC - Manual of Specifications, Standards & Design June 2006


Div 02275 - Trenching, Backfilling and Compaction of Utilities Page 02275-37

Table 2275.3
Minimum Compaction Limits
(Cohesive Soils)
Location Density
Areas under Top 12 inches 100% of the maximum dry density
roadway by ASTM D698 (Standard
pavement Proctor), AASHTO T99.
surfaces, curb Up to within 100% of the maximum dry density
and gutter, and 12 inches by ASTM D698 (Standard
sidewalks Proctor), AASHTO T99.
Roadway 95% of the maximum dry density by ASTM D698
shoulders (Standard Proctor), AASHTO T99.
Under turf, 90% of the maximum dry density by ASTM D698
sodded, planted, (Standard Proctor), AASHTO T99.
or seeded non-
traffic areas
Beneath and 100% of the maximum dry density by ASTM D698
within 5 feet of (Standard Proctor), AASHTO T99.
buildings

F. Compaction Lifts:

Table 2275.4
Compaction Lift Thickness of Common Earth Backfill
Lift Thickness (inches) Location
6 Inside street rights-of-way
12 Outside street rights-of-way

G. In-place testing of soils shall be tested based on the following:

Table 2275.5
In-Place Density Tests
Soil Type/Classification Reference Standard
Crushed Rock ASTM D 2049 by percentage of relative density
ASTM D 1557 or D 698 (standard Proctor)
GW, GP, SW and SP ASTM D 2049 by percentage of relative density
ASTM D 1557 or D 698 (standard Proctor)
GM, GC, SM, SC, ML, CL ASTM D 2167, D1556, D2922, or D2937 by
percentage of Standard Proctor Density according
to ASTM D 698 or AASHTO T99

3.6 SERVICE CUTS, DIRECTIONAL BORED OR PUNCHED SERVICES

A. Open trenches: Sewer lateral and water service connections that cross-paved
streets shall be installed by saw cutting the pavement and opening the trench.
The open trench width shall be no wider than 36 inches.

Lateral connection trenches in non-paved areas shall be buried as specified for


gravity sewers and for water lines, as applicable. See Table 2275.1.

Do not bed water service pipe, except when rock is encountered.

City of Jacksonville, NC - Manual of Specifications, Standards & Design June 2006


Div 02275 - Trenching, Backfilling and Compaction of Utilities Page 02275-38

B. Directional Boring or Punching: With approval of the Public Services Director,


service pipes may be required to be “punched” or “directional bored” beneath the
pavement.

3.7 PAVEMENT REPAIR AND REPLACEMENT

A. General: This work shall consist of replacing subbase stone, and bituminous
material in the street in areas where it becomes necessary to remove the original
pavement for sewer, water main, and storm drainage trenches. Pavement repair
shall be as shown on the drawings, or as determined by the Public Services
Director. The pavement patch shall provide a uniform and smooth driving
surface free of humps or depressions.

B. Construction in Public Rights of Way: Water, sewer, and storm drainage


lines installed in or across NCDOT roads shall be installed in accordance with, if
applicable, the requirements stipulated in the approved encroachment permit
and the latest requirements of both the NCDOT Standard Specifications for
Roads and Structures and the Roadway Standard Drawings. All water, sewer
and storm drainage lines installed in or across City streets shall be in accordance
with these specifications and the applicable standard details.

When it is necessary to remove the existing pavements, prepared road surfaces,


sidewalks, or curbing, it shall be the responsibility of the Contractor to replace
these surfaces to original or better condition. The Contractor shall be
responsible for contacting the City or the NCDOT, as applicable. NCDOT is to
be notified prior to work in any right-of-way within ½ mile of any traffic signal.
Unless specified more stringently by the owner of the right of way, the backfill
shall be compacted in accordance with Table 2275.3.

Contractor shall replace pavement base with a minimum of 8 inches of ABC


compacted to 95% of the Standard Proctor (ASTM D698) maximum dry density
prior to pavement overlay.

C. When water, sewer and/or storm drainage lines are installed in or across
roadways that have been macadamized or graveled, the Contractor shall save
the gravel or stone, refill the upper 12 inches of the trench with the material, and
supply sufficient new stone or gravel to return the roadway to the original grade.
It shall be the Contractor’s responsibility to maintain the original grade by adding
gravel or ABC until the ditch is stable and the pipeline accepted by the City.
Maintain area as outlined in paragraph 3.4.1 B - Surface Protection - Traffic.

D. Cutting Pavement: See also paragraph 3.1.4 B – Protection of Surface


Features. Perform cutting operations prior to installation of line to avoid
excessive removal of asphalt.

E. Protection of Pavement: See paragraph 3.1.4 B – Protection of Surface


Features.

3.8 BLASTING

3.8.1 GENERAL

City of Jacksonville, NC - Manual of Specifications, Standards & Design June 2006


Div 02275 - Trenching, Backfilling and Compaction of Utilities Page 02275-39

A. Blasting procedures shall conform to all applicable local, state, and federal laws
and ordinances and shall be performed in accordance with OSHA Standard 29
CFR part 1910.109, NCDOT Rules for Transporting Explosives, and local Fire
Department Regulations. Prior to any blasting, a blasting permit shall be
obtained. The approval of the Public Services Director shall be obtained before
any blasting takes place and the Public Services Director may fix the hours of
blasting if he/she deems it necessary. The use of explosives shall be in
accordance with approved methods that safeguard lives and property.
Explosives shall only be handled, placed, and detonated by persons licensed in
this work. It is the responsibility of the Contractor to provide proper notification to
appropriate parties.

B. Rock Excavation: See paragraph 3.2.5, - Rock for the definition of rock.

C. The minimum insurance coverage for blasting shall be as specified by the Public
Services Director. The coverage shall include explosion and collapse. If blasting
occurs within 200 feet of any underground structure or utility, underground
coverage will be required. The owner and the property owners shall be named
as “additional insured.”

D. Storage: Store explosives in accordance with the Occupational Safety and


Health Act and with other Federal, State and Local ordinances and regulations.
The Contractor shall keep explosive materials that are on the job site in special
constructed boxes provided with locks. These boxes shall be plainly identified as
to their contents. Failure to comply with this specification shall be grounds for
suspension of blasting operations until full compliance is made. No blasting shall
be allowed unless a galvanometer is employed to check cap circuits.

E. The City may prohibit blasting when the method of detonation or the means of
protection provided is inadequate. Blasting conducted with or without direct
supervision of the City will not relieve the Contractor of the responsibilities
stipulated herein.

F. Blasters shall not explode or attempt to explode blasting powder or high


explosives unless it is performed with a suitable electric blasting machine.
Electric current from batteries, telephone, or power lines shall not be used for
detonation.

G. A minimum of 3 minutes prior to the detonation, the blaster shall inform


competent flagmen, equipped with red flags, stationed at reasonable distances
from the blast area at every avenue of approach, to warn all persons.

H. Immediately after the loading and tamping of the drill hole and before fixing the
blast, the material to be blasted shall be covered on all exposed sides with
blasting mats, or other approved protective material. After the protection has
been applied, the blast shall be fired without unnecessary delay.

3.8.2 BLASTING PROCEDURE

A. The Contractor shall provide a blast warning signal system. The blast warning
signal system shall consist of one or more air horns located at the blast site. The
air horn(s) shall be audible a minimum of 1 mile from the blast site. The signals
shall be one long horn five minutes prior to the blast, one short horn 1 minute
prior to the blast, and one long horn after the blast to signal all clear. The

City of Jacksonville, NC - Manual of Specifications, Standards & Design June 2006


Div 02275 - Trenching, Backfilling and Compaction of Utilities Page 02275-40

Contractor shall erect two clear and legible blast warning signal signs at
locations determined by the Public Services Director. The signs shall list the
blast warning signal system, the Contractor Superintendent’s name and
telephone number, and the City representative’s name and telephone number.

B. The Contractor shall establish test pits at up to two representative locations


along the alignment and up to three locations adjacent to the site proposed to be
blasted to determine if the rock is “rippable” with a track backhoe caterpillar 225
or equivalent and the feasibility of rock excavation by “hoe ramming.” If these
procedures do not offer reasonable production for rock excavation, then blasting
will be allowed unless otherwise indicated.

C. The Contractor shall notify in writing all property Owners within 250 feet of the
proposed blast at least 1 week prior to the proposed blast and verbally on the
day of the scheduled blast.

D. Blasting shall be limited to mid-morning hours on days of clear-to-partly cloudy


skies with increasing surface temperature and light wind. The Contractor shall
provide monitoring equipment to monitor all blasting. A copy of monitor record
shall be given to the City daily.

E. The use of unconfined explosives shall be prohibited.

F. Unless otherwise stipulated in Title 13 of the NC Administrative Code, chapter 7,


the maximum allowable peak particle velocity shall be 1.25 inches per second for
all structures located 0 to 300 feet from the blasting site. The maximum
allowable peak particle velocity shall be 1.00 inch per second for all structures
located 301 to 5,000 feet from the blasting site. The maximum allowable peak
particle velocity shall be 0.75 inch per second for all structures located 5,001 feet
and beyond from the blasting site.

G. To minimize vibration, minimum-scaled distance (SD) of 50 shall be used to


determine maximum explosive weight per delay. A test blast shall be conducted
to verify the scaled distance. The maximum explosive weight per delay shall not
exceed the distance from the blast to the nearest structure divided by 50
squared. Maximum explosive weight per delay may be revised pending outcome
of test blast. The recommendations indicated for blasting criteria in no way
relieves the Contractor of his liability.

H. The peak overpressure of air blast shall not exceed 0.015 pound per square inch
or 138 decibels.

I. Preblast meetings may be scheduled with the Public Services Director to


document hole depths and spacing, charge weight per delay, shot scheduling,
and weather conditions. The Contractor shall obtain accurate measured
distances from structures to center of blast area prior to determining the safe
maximum charge-weight per delay and loading blast holes.

J. Preblast and post blast surveys will be performed by the Contractor. The
Contractor may review this data and supplement it as he sees fit or conduct
separate survey after written permission is obtained from the property Owners.
In this event, the written permission shall be submitted to the Public Services
Director prior to entering upon private property. The preblast and post blast
surveys will include all occupied buildings within 250 feet of blasting areas. The

City of Jacksonville, NC - Manual of Specifications, Standards & Design June 2006


Div 02275 - Trenching, Backfilling and Compaction of Utilities Page 02275-41

Contractor is strongly encouraged to have a representative present during these


surveys. The preblast and post blast surveys performed by the City or the
property owner in no way relieve the Contractor of his liability.

K. The City reserves the right to monitor production blasting. In this event, the
Contractor shall provide the Public Services Director ample notice of scheduled
blasts to allow set-up of monitoring equipment.

3.9 HIGHWAY CROSSING

A. Pipeline crossings shall be installed in a steel casing pipe installed by the “dry
bore and jacking” method. Length of steel pipe shall be welded to the preceding
length installed. The carrier pipe shall be protected by spiders constructed as
shown on standard detail C07.01. The ductile iron carrier pipe shall be as
specified for sewer and water pipe and shall be slip joint ductile iron pipe. If, in
the opinion of the Contractor, boring and jacking of the highway crossing is not
possible due to rock, he shall test drill, in the presence of the Public Services
Director at the proposed crossing locations, at least 3 evenly spaced points in
the placement along the crossing alignment. Upon verifying the presence of
rock at a depth that would conflict with the boring and jacking operation, the
Contractor shall make application to the applicable City or the NCDOT, as
applicable, to allow open cutting of the crossing. The Contractor shall be
responsible for providing all data and shall pay any fees required for this
application. If the trench is allowed to be open cut, casing pipe shall be
provided and the trench shall be backfilled entirely with flowable fill concrete to
the bottom of the pavement base course and the pavement restored within one
day of placing the pipe. Non-woven fabric separation fabric is to be provided
between the stone and the pavement.

B. The steel casing pipe shall be of the thickness as specified in standard detail
C07.01. Refer to specification Division 02530 - Sanitary Sewer and Division
02510 - Water Distribution for casing pipe specifications.

C. Installation shall be in accordance with AREA.

D. The jacking operation shall be carried on in such a manner that settlement of


the ground or the highway above the pipeline will not occur. The use of water or
other fluids in connection with the boring and jacking operation shall not be
allowed. Excavation shall be made by auger or manual methods, at the
Contractor’s option, to suit the conditions encountered. The Contractor shall
repair or replace, as directed by the Public Services Director, at his own
expense, casing pipe damaged during the jacking operation.

E. After installation of the casing pipe, the carrier pipe, if required, shall be
installed. The ends of the casing shall be plugged in accordance with standard
detail C07.01.

F. All operations of the Contractor shall be subordinate to the free and


unobstructed use of the highway right of way for passage of traffic without delay
or danger to life, equipment, or property. The Contractor shall provide all
necessary bracing, bulkheads, and shields to ensure complete safety to all
traffic at all times.

City of Jacksonville, NC - Manual of Specifications, Standards & Design June 2006


Div 02275 - Trenching, Backfilling and Compaction of Utilities Page 02275-42

3.10 RAILROAD CROSSING/TRACKS

Crossing of railroad tracks with water, sewer or storm drainage lines shall be by the
method shown on the contract drawings and approved by the applicable Railroad
Company. It is the responsibility of the Project Engineer and Contractor to contact the
Railroad Company and to comply with all Railroad Company requirements for
specifications, drawings, permits, etc. All water, sewer, and storm drainage lines
installed beneath railroad tracks shall be in accordance with the Railroad Company’s
policies, procedures, and permits requirements. The railroad right of way and track
structure shall be fully restored to its original pre-existing condition and to the full
satisfaction of the Railroad Company. The work shall not interrupt the use of the
railroad tracks or in any way endanger the traffic on them.

3.11 UNDERGROUND RIVER OR CREEK CROSSINGS

In accordance with the contract drawings, underground river or creek crossings shall be
made either by horizontal directional drilling (HDD) with HDPE pipe or constructed in the
dry by providing a temporary cofferdam or bulkhead. River or creek crossings shall be
in accordance with the requirements of the Public Services Director, NCDENR, The US
Army Corps of Engineers, and all other agencies having jurisdiction. Unless horizontal
directional drilling is specified in the contract documents, river or creek crossings shall
be made by providing a temporary cofferdam or bulkhead using ductile iron pipe for the
crossing.

River or creek crossings shall be as near to perpendicular as possible to the stream.

A. Cofferdam Method: The Contractor shall construct the river crossing in the
“dry” by providing a temporary cofferdam or bulkhead of non-erodible material.
The cofferdam shall not obstruct more than one-half of the water surface at any
time and shall not extend more than 3 feet above the normal water surface. The
Contractor shall not be allowed to operate construction equipment on the native
steam bottom, except during removal of the cofferdam. The Contractor shall be
advised that the level in the river can fluctuate rapidly.

1) Non-erodible material shall be defined as heavy coarse aggregate as


specified on the plans. An earth core for the cofferdam may be constructed
over the propose excavations; however, the non-erodible materials shall be in
place prior to the placement of the earth, so that the erodible earth does not
come in contact with the flowing water.

2) A bulkhead may be constructed in lieu of the cofferdam. The bulkhead shall


be made of wood, steel or some like material suitable to withstand the
hydraulic forces to permit construction in a dry trench.

3) Construct the crossings as indicated. The Contractor shall then remove the
cofferdam, bulkhead, or whatever equipment or material that was used to
construct the crossing. The bottom of the river in the construction area shall
be restored to its original cross section. All disturbed areas on the banks of
the river shall be seeded and mulched in accordance with paragraph 3.16 –
Seeding, Sodding, and Groundcover.

4) Comply with all terms and conditions of all permits issued by the US Army
Corps of Engineers, CAMA, and/or NCDENR for this work.

City of Jacksonville, NC - Manual of Specifications, Standards & Design June 2006


Div 02275 - Trenching, Backfilling and Compaction of Utilities Page 02275-43

5) The pipe and joints of water or sewer main entering or crossing streams shall
be tested in place and shall exhibit zero infiltration. This testing shall be done
prior to encasing in concrete.

B. Horizontal Directional Drilling (HDD) Method: HDPE pipe shall be installed by


horizontal directional drilling using a surface mounted rig, first to drill a guided
hole along a bore path consisting of a shallow arc and then to pull a string of
pipe into the hole. Pull back is facilitated by a back-reamer, which enlarges the
hole to approximately one and a half times the pipe diameter. Drilling fluids are
injected into the bore hole to stabilize the hole and lubricate the pipe and drilling
string. Tracking equipment is used to guide and direct the drilling. See Division
02510 - Water Distribution for installation, testing and other requirements for
horizontal directional drilling.

3.12 SURFACE WATER CROSSINGS

Surface water crossings, with pipe above the water, shall be adequately supported by
pipe support piers or beams. Surface water crossings with pipe under streambed shall
have the pipe encased in concrete when the cover is less than 3 feet.

3.13 CONCRETE COLLARS ON SEWER MAINS

Concrete collars shall be used on sewer lines with slopes 10% or greater. At least one
concrete collar shall be placed before the bell of each joint of pipe. Additional collars
may be required by the City.

3.14 PLACEMENT OF RIP RAP AND RIP RAP BEDDING

Placement of Rip Rap and fabric shall conform to Section 876 – Rip Rap of the NCDOT
Standard Specifications for Roadways and Structures, latest revision.

3.15 CLEANUP AND RESTORATION OF SITE

A. During the progress of the work, the Contractor shall keep the premises and the
vicinity of the work clear from unsightly and disorderly piles of debris. Suitable
locations shall be specified for the various construction materials and for debris.
The materials shall be kept in their storage locations, except as needed for the
work and debris shall be promptly and regularly collected and deposited in the
specified location.

B. Upon completion of section of pipeline and appurtenances, the Contractor shall


fine grade the ground adjacent thereto, removing all surplus excavated material,
leaving the area free from surface irregularities. He shall dispose of all surplus
material, dirt, and rubbish from the site; and shall keep the site free of mud and
dust to the satisfaction of the Public Services Director. The Contractor may be
required to flush or sprinkle the street to prevent dust nuisance.

C. When working on the shoulders of paved roads, the Contractor shall keep the
pavement clean of all loose earth, dust, mud, grave, etc., and shall restore road
surfaces, shoulders, and ditches as required by either the NCDOT or the right-
of-way owner.

D. Grading Easements: Easements shall be graded to have cross slopes of 4% or


less. The ground surfaces of easements shall be graded and cleared in such a

City of Jacksonville, NC - Manual of Specifications, Standards & Design June 2006


Div 02275 - Trenching, Backfilling and Compaction of Utilities Page 02275-44

way to promote proper drainage and allow mowing by vehicular equipment


without damage to equipment from rocks and other debris.

E. After all work is completed, the Contractor shall remove all tools and other
equipment, leaving the site free, clean, and in good condition.

F. The Contractor shall keep the surface over and along the trenches and other
excavation in a safe and satisfactory condition during the progress of the work
and for a period of one year after the work has been completed. He shall be
held responsible for any accidents that may occur on the account of the
defective condition of such surface.

3.16 SEEDING, SODDING, AND GROUNDCOVER

3.16.1 GENERAL

A. Seeding, Sodding, and Groundcover shall comply with the applicable provisions
and requirements of Division 02920 - Seeding, Sodding and Groundcover.

B. Seeding and groundcover includes seedbed preparation, liming, fertilizing,


seeding, and mulching of all disturbed areas. Areas inside or outside the limits
of construction that are disturbed by the Contractor’s operation and activity shall
be seeded and mulched.

Unless called for otherwise on the Erosion and Sedimentation Control Plan, in
areas where natural sod or vegetation has been disturbed, the area shall be
seeded in accordance with standard detail 350.01.

If the line is installed through a landscaped lawn, sod of the same type shall be
placed to restore ground cover to the existing lawn.

C. Seeding shall be carried out as soon as practical after the construction in any
one area, and shall be maintained against erosion through the completion of the
project. Seeding shall be accomplished as work progresses and shall be in
accordance with Sediment and Erosion Control regulations.

The Contractor shall be responsible for proper care of the seeded area during
the period that vegetation is being established. In the event of an erosive rain
before an adequate stand of vegetation has been established, damaged areas
shall be repaired, fertilized, seeded, and mulched at the Contractor’s expense.

Seeding on rights of way of NCDOT maintained roads shall be in accordance


with NCDOT specifications and the requirements of the approved encroachment
permit.

D. Temporary Seeding: Denuded areas to be graded during the construction


phases that are not to be brought to final grade within 30 days shall receive
temporary seeding within 15 days of completing initial earthwork. Note that the
time for establishment of permanent ground cover is 15 working days or 30
calendar days whichever is shorter. Temporary seeding shall also be used to
stabilize finished grade areas if the time of year is outside the specified
permanent seeding periods.

City of Jacksonville, NC - Manual of Specifications, Standards & Design June 2006


Div 02275 - Trenching, Backfilling and Compaction of Utilities Page 02275-45

E. Stockpile Area: The Contractor is responsible for securing a material lay down
and stockpile storage area for the contract. As such, the Contractor is
responsible for the necessary erosion control measures, including but not
necessarily limited to, a construction entrance, silt fence, protection of
streams/buffers, clean up and restoration of site to the satisfaction of the City
and the NCDENR, Department of Water Quality, Land Quality Section. Stockpile
and/or waste areas must be maintained within the limits of the areas protected
by the proposed measures and otherwise temporarily seeded if to be left
stockpiled over 30 calendar days.

3.17 MISCELLANEOUS

3.17.1 DUST CONTROL

The Contractor shall be required to sprinkle with water or to apply dust-allaying


materials in the vicinity of dwellings, schools, churches, stores, or other places,
where in the opinion of the Public Services Director, it is necessary to ensure
that dust is held to an absolute minimum. Dust control is considered incidental
and shall be carried out at the Contractor’s expense.

3.17.2 IDENTIFICATION OF NEW WATER OR SEWER LINES –


Underground Warning Tape

Placement of underground warning tape during backfill operations shall be


required on all newly installed water mains, sewer force mains and sewer mains
installed outside of a street right-of-way. Underground warning tape is to be
placed 8 to 12 inches below the finished grade directly above the line. The non-
metallic locating tape shall be per paragraph 2.2.2, Warning Tape of this
specification. No separate payment will be made for locating tape as it is
considered incidental to the cost of construction of the line being installed.

3.17.3 FLOWABLE FILL CONCRETE BACKFILL

When directed by the Public Services Director, the Contractor shall backfill
trenches or undercut areas with flowable fill concrete plant mix. To allow for
future re-excavation of filled area, concrete strength shall be liquid enough to
flow, be self-leveling, and have an ultimate minimum strength 225 psi (this
product is a combination of sand and Portland cement). Except for structural
applications, traffic can be placed on mixture within an hour or two after
placement. Final surfacing of pavements; however, should be delayed if
possible at least 24 hours to allow for shrinkage and hydration of concrete.
Settlement of 2" to 3" is to be expected.

The option to use flowable fill is open to the Contractor to reduce delay and
inconvenience to traffic. However, payment for flowable fill backfill is considered
incidental to the cost of construction unless a pay item has been provided in the
proposal, a change order has been approved, or the Contractor is ordered by the
Public Services Director to place flowable fill concrete as an emergency
measure.

3.17.4 SALVAGE OF USEABLE MATERIALS

All materials such as paving blocks, brick, castings, and pipe etc., removed
during excavation that is useable on this project shall be used after approval of

City of Jacksonville, NC - Manual of Specifications, Standards & Design June 2006


Div 02275 - Trenching, Backfilling and Compaction of Utilities Page 02275-46

its use by the Public Services Director or the applicable owner of the street right-
of-way. Such material shall be stockpiled on site. Unnecessary abuse and
damage to these items shall be the Contractors responsibility and the cost of
replacement may be deducted from the retainage.

End of Division 02275

Back to Top

bj.North Carolina.Jacksonville.Specs.COJv02275UtilTrench.doc

City of Jacksonville, NC - Manual of Specifications, Standards & Design June 2006

You might also like