Paper 3 RCM
Paper 3 RCM
a r t i c l e i n f o a b s t r a c t
Article history: Reliability Centered Maintenance Method (RCM) currently used for maintenance optimization based on
Received 6 June 2014 the analysis of modes of dysfunctional system failures (FMEA), and after determining the criticality of the
Received in revised form 29 April 2015 system, an adequate maintenance plan is adopted. Following the succession of several applications of this
Accepted 5 May 2015
method, in several areas, along twenty years of experience, it was proved that the use of this approach
was incomplete for other analysis and evaluation criteria were completely ignored especially in electrical
systems. Our view is to apply this method rationally by introducing a whole dependability study (RAMS).
Keywords:
Ó 2015 Elsevier Ltd. All rights reserved.
Power distribution systems
Rational reliability centered maintenance
RRCM
Analysis of failure modes effects and
criticality
Optimization
Modeling
Costs
Introduction exiting the dreaded condition for each component of the electrical
network based on cost. And parallel with the modeling we will do a
In this work (extracted and summarized from my doctoral thesis) cost analysis of the life cycle to estimate the total cost of ownership
[1], we have applied a maintenance optimization approach based of the electricity networks of each analyzed element. Finally,
on techniques of modeling and simulation by applying the experi- everything is completed and simulated by the Monte Carlo
mental approach RCM that based on the functional and dysfunc- simulation in order to give important recommendations to keep
tional analysis of failure modes of the grid by using the FMEA the electrical system in the best circumstances [1–3].
model, and by using the SADT approach for decomposing hierar-
chically these different functional analysis tasks to classify the
material in order of criticality. Then we have modeled the system Presenting the new approach: Rational RCM
by using static methods (combinatorial, deductive, functional and
qualitative approaches) such as reliability diagram RBD and fault The implementation of a simplified maintenance plan
trees analysis FTA that identify the paths of weakness in the sys- comprises 4 steps. These steps call on many data whose supports
tem and determine these characteristics RAMS, by using data of are relating to production, quality, and maintenance. All
REX feedback that are collected from the old method (scheduled along these steps, involved groups must determine objectives
periodic preventive maintenance SPPM); then we determine the having priority and validate results of each phase in order to
characteristics of dependability and reliability indices (time, rate continue without over diversifying their work [1–4,10,12,13]
and cost) by dynamic methods (analytical, behavioral, quantitative (see Fig. 1).
and stochastic approaches) such as Markov graphs MG and Petri
network PSN, and therefore the determination of residence times,
the execution frequency of the program and the probability of Case studies: Application to the power distribution systems
http://dx.doi.org/10.1016/j.ijepes.2015.05.015
0142-0615/Ó 2015 Elsevier Ltd. All rights reserved.
B. Yssaad, A. Abene / Electrical Power and Energy Systems 73 (2015) 350–360 351
Table 1
Data of reliability.
Determination of site to study 1
Equipment Failure mode MTTF MTTR Estimated
(years) (h) average cost of
repair/year (x
103 AD)
2 Risk assessment 3 History of dependability
and feedback Electrical line EL Clippings 3.5 2.5 345
Analyses of functional Bus bars SB Short-circuit 8 4 210
failures Insulator IS Ageing 4 3 135
Determination of
characteristics and evaluation Priming
of RAMS reliability indicators Transformer Low insulation 5.5 3.5 240
Research of components and (λ, μ …) RBD, FTA, MG, PTR resistance
modes of significant failures PN Triggering power at the
(FMECA, HAZOP … etc.) time of operation
shedding
Noise: the necking
Event and Economic Analysis phenomena in
(maintenance costs) LCCA transformers
Research components and
Breaker CB Long and short 8 5 165
critical failure modes
interruptions
Arresters PL Overvoltage 8 2.5 75
Fuse F Overloads 2 1 75
Sectionalizer – Closing difficult or 7.5 5 30
SW – Opening difficult
Analysis and selection of maintenance tasks
Corrective
Materials and failures
maintenance
Not critical action Table 2
Critical Probability of occurrence (Safety).
Final selection and preparation of preventive maintenance Criteria Frequency (O) Value
Failure by 10 years Very rare failure 0.1
Maintenance optimization 4
Failure by 5 years Rare failure 0.2
Failure by 3 years Possible failure 0.3
Fig. 1. Steps of RCM rational approach. Failure by one year Frequent failure 0.4
Failure by 4–6 months Very common failure 0.5
L1: 60 KV L2 : 60 KV
PL Table 3
G
Severity (Availability).
Coupling
CB Criteria Severity (S) Value
Table 4
CT
Detectability (Maintainability).
VT
Criteria Detectability (D) Value
Time taken to detect the failure Obvious detection 1
PTR Failure early detectable Possible detection 2
Failure is difficult to detect Detection unlikely 3
Failure painfully detectable Detection improbable 4
Failure undetectable Cannot detect 5
Table 5
Partition equipment and action plan.
alternative for the Power Distribution Systems can be schematized
as follows (Fig. 2) [1–3]. Condition Consequence Maintenance action
imposed
Data reliability material according to the method SPPM C<R No problem, nothing to Correctives de maintenance
report
R<C<S Acceptable but! Special surveillance preventive/
These data are collected and calculated in collaboration with predictive maintenance
engineer’s service station maintenance of Subsidiary Power C>S Complete questioning – Systematic preventive maintenance
Distribution System PDS SONELGAZ of RELIZANE [1–3] of the study action
– New ameliorative study.
(see Tables 1–5).
352 B. Yssaad, A. Abene / Electrical Power and Energy Systems 73 (2015) 350–360
Risk assessment of power distribution systems by using the FMECA this step, we projected phases of RCM on the SADT model [1,2]
method (see Fig. 3).
The glossary in (Table 6) is essential in the SADT method
The FMECA (Failure Modes, Effects and Criticality) is a method because this approach is based on symbolization of all effects influ-
of predictive reliability analysis that identified the potential fail- encing its description.
ures whose consequences affect the proper functioning of the sys- The experimental results of the FMECA analysis is summarized
tem being studied, and then estimate the risks related to the in (Table 7) below, and therefore we moved to different simula-
occurrence of these failures to take action to provide maintenance tions and modeling to confirm this practical result and therefore
during the design, implementation or operation of the system [01, to come up with important recommendations to put at the disposal
32, 33]. of the maintenance department, whose purpose is to improve
management of the electrical systems [1–3].
Risk estimation
When FMEA is completed, an analysis of risk assessment is
The determination of optimal parameters failure rate k, repair rate l,
realized for all the previously determined failures. The criticality
RAMS, cost and reliability indicators
C or the risk priority number RPN is given by:
RPN ¼ S O D ð1Þ After realizing the FMECA analysis in the Relizane PDS post, we
could identify and rank the most critical components during the
where
trial period on electrical network (see Fig. 4).
O: Represents the probability or the frequency of occurrence
The FMEA analysis leads to two complementary descriptions of
that causes the failure to display and leads the considered potential
the network:
mode of failure. The rating scale ranges between 0.1 and 0.5.
S: Represents the severity. The rating scale ranges between 0.1
– A description formalized by functional block diagrams RBD and
and 0.5 based on the failure caused by the effects in terms of:
fault tree FTA whose purpose is to present the system architec-
ture and functional links between the different elements of the
– Response time
system and determine the characteristics RAMS.
– Quality power supply
– Safety of people and property
The functional analysis of the RCM approach describes, in visual NODE G1 TITLE The glossary NUMBER 1
and textual form, the role of network and/or the components. In
Optimzation of
the maintenance
by RCM
A0
WF ISO and
Periodicity
OHSAS
OB
Site is Failures are
MDP selected analyzed
Determination
of sites to study
Post
PDS A1
RAMS are
Analyses of determined
RD functional
failures Project is
valited
A2 Post PDS
Setting up is
TMP maintened
Study of the
A4 Optimization
safty
and experince
A3 feedback
A5
SG
Intervention
TV report
and update
MOS MT HD HOM
Electrical distribution station located in the region of RELIZANE Northwest of ALGERIA Date: 20/05/2013
Element Function Failure mode Cause Effect Detection Criticality Maintenance plan adopted: Action to be taken
O S D C The test
Electrical Line EL Electrical – Contact of two Electrodynamics force of the wind – Line break Visual 0.5 0.5 4 1 C>S – Corrective action: If the fault is minor
transport lines – Preventive systematic maintenance action
– A new study, using cables of the same material
(replacement)
Insulator out of glass, or Insulation – Aging – Partial or complete discharge of the arc in – Perforation Visual 0.5 0.5 4 1 C>S – Corrective action: it can be covered with grease or washed
ceramics IS its volume regularly
– Priming – Over voltage (lightning) streamer surface – Preventive systematic maintenance action
by an electric arc
Bus Bars SB Selection of lines Short-circuit – Air pollution (depositing a layer of pollution – A new study, using composite insulator (replacement)
on the surface of the insulator, progressive
353
loss
– To inhale the dust and clean all accessible parts then blow
This is an almost direct representation of the functional vision
system, through a series parallel juxtaposition, or mixed blocks
associated with basic entities of the system. In this representa-
tion, the blocks represent elements (hardware or events) whose
Maintenance plan adopted: Action to be taken
Fig. 5).
This model is regulated by the resulting equation simulation of
the reliability from following Monte Carlo simulation.
– Replacement
Replacement
Y
n Y
p
RðtÞ ¼ ½1 ½1 Rij ðtÞ ð2Þ
1¼1 j¼1
S = 0.999
The test
R<C<S
R<C<S
4
3
event.
Fig. 6, above, shows the shaft events example of the studied sys-
0.3
0.4
Criticality
R = 0.540
– Visual
ity indicators.
– Noise
– Heat
Visual
Blocking
Fusion
Effect
Analysis of failure modes effects and criticality FMECA
– Permutations sources
follows:
Hence, the system of equations state space of the system ele-
PDS of R in A: Power Distribution System of RELIZANE in ALGERIA.
– Reset
Cause
>
Over current
>
– Closing
>
> !
difficult
difficult
>
> þl6 P6 ðtÞ þ l7 P7 ðtÞ
>
>
>
>
:
P1 þ P2 þ P3 þ P4 þ P5 þ P6 þ P7 ¼ 1 P0
– Electrical
– Galvanic
separation
Protection
Function
isolator
of Chapman–Kolmogorov) [1–3]:
Sectionalizers SW
[PDS of R in A]a
(
dPðtÞ
dt
¼ M Pi ðtÞ
P ð4Þ
Element
Fuses F
n
i¼0 P i ¼ 0
a
where
B. Yssaad, A. Abene / Electrical Power and Energy Systems 73 (2015) 350–360 355
ReliaSoftBlockSim7 -
FAILURE CRITICALITY INDEX (FCI) The resolution and the result of this equation are given in the
26,93 AVAILABILI
100
Appendix A.
2154 91
Stochastic Petri nets
83
16,16
5 To represent the operation of the maintenance optimization of
our studied processes system, we used the graphical modeling by
10,77 using SPN and it all depends on the Markov graph Fig. 7.
Markov model characterizing Fig. 7 is given by the following LCCA ¼ LCA þ C V i LCAi ð10Þ
i¼1
equations:
2 dP 0
3
2
6
dt
dP1
7 ðk0 þ k1 þ k2 þ k3 þ k4 þ k5 þ k6 þ k7 Þ l1 l2 l3 l4 l5 l6 l7 32 P0 3
6 7 6 76 P1 7
6 dt 7 6 k1 l1 0 0 0 0 0 0 76 7
6 dP2 7 6 76 7
6 7 6 k 0 l2 0 0 0 0 0 76 P2 7
6 dt 7 6 2
76 7
6 dP3 7 6 76 P 7
6 7 6 k3 0 0 l3 0 0 0 0 76 3 7
6 dt 7¼6 76 7 ð6Þ
6 dP4 7 6 k 0 0 0 l4 0 0 0 76 P4 7
6 dt 7 6 4
76 7
6 7 6 76 P 7
6
6
dP5 7 6
7 6 k5 0 0 0 0 l5 0 0 76 5 7
6 dt
7 4 76 7
6 dP6 7 k6 0 0 0 0 0 l6 0 54 P6 5
4 dt 5
dP7
k7 0 0 0 0 0 0 l7 P7
dt
2 3 2
0 ðk0 þ k1 þ k2 þ k3 þ k4 þ k5 þ k6 þ k7 Þ l1 l2 l3 l4 l5 l6 l7 3 2 P 0 3
607 6 l1 0 0 0 0 0 0 7 6 7
6 7 6 k1 76 P 1 7
6 7 6 76 7
607 6 k2 0 l2 0 0 0 0 0 76 P 2 7
6 7 6 76 7
607 6 0 0 l3 0 0 0 0 7 6 7
6 7 6 k 3 76 P 3 7
6 7¼6 76 7 ð8Þ
607 6 k4 0 0 0 l4 0 0 0 76 P 4 7
6 7 6 76 7
607 6 0 0 0 0 l5 0 0 7 6 7
6 7 6 k5 76 P 5 7
6 7 6 76 7
405 4 k6 0 0 0 0 0 l6 0 54 P 6 5
1 k7 0 0 0 0 0 0 l7 P7
356 B. Yssaad, A. Abene / Electrical Power and Energy Systems 73 (2015) 350–360
PL3
PT3
DS23
CB3 CT3 DS35
1/2.3 2/2.3
CBB DSB VT3
DS13 Node
DS34
S3
Line B DSB VTB
PL2
PT2
PT1
PL1
Failing system
Post VHV
OR
Choice of
power line AND
VT
Line in or / out Line in or / out Line in or / out
servce servce servce
OR OR OR
OR OR
OR OR OR OR OR OR
OR SB/ISA OR SB/ISB
OR VT1 OR VT3
OR VT2
Cost for distribution equipment maintenance before Thus, the expected number of preventive maintenance per year
optimization (following SPPM) in Markov model and simulated by the Monte Carlo simulation is
L
2% shown in the following figure:
11% SB
5% 24% Finally, the graph shows clearly that the optimal intervention
5% IS
strategy is given by the point (CVCT 300,103 AD and
Tr
12% t2 10 years, 3 months). Inducers of different maintenance costs
CB
15% and total costs are shown relative to the optimum value for t2 in
PL
17% 9% F the following Fig. 13.
DS
charges
Fig. 10. Distribution equipment maintenance costs before optimization for a year.
Reliability
The expected annual costs for PM
1.0
SPPM
500 0.8
RCM
0.8
RRCM
400 0.7
Costs of PM
0.6
300
R (t) 0.5
0.4
200
0.3
Not remitted
100 Remitted (PA) 0.2
0.1
0 0.0
0 13 26 39 52 65 78 91 104 117 130
10 15 20 25 30
TIME (Months)
Years (n)
Fig. 14. Reliability curve before and after optimization.
Fig. 11. The expected annual costs for PM.
Unreliability
1.0
The expected number of PM per year
SPPM
0.8
RCM
0,05 0.8
RRCM
0.7
0,04
0.6
F (t) 0.5
0,03
NPM
0.4
0,02 0.3
0.2
0,01 0.1
Markov model
Monte Carlo Simulation 0.0
0,00 0 13 26 39 52 65 78 91 104 117 130
10 15 20 25 30 35 TIME (Months)
Year (n)
Fig. 15. Unreliability curve before and after optimization.
Fig. 12. The expected number of PM.
Failure rate λ
The current value of the total cost 4.0E-3
SPPM
3.6E-3
5000 RCM
3.2E-3
RRCM
CV of Cost * 100AD
4000 2.8E-3
Optimal 2.4E-3
3000
r (t) 2.0E-3
Total costs
2000 Inspection costs 1.6E-3
Costs CM
Costs PM 1.2E-3
1000 8,0E-3
4,0E-3
0
0.0
0 1 2 3 4 5 0 13 26 39 52 65 78 91 104 117 130
Fig. 13. The current value of the total cost. Fig. 16. Failure rate curve before and after optimization.
B. Yssaad, A. Abene / Electrical Power and Energy Systems 73 (2015) 350–360 359
The graphs of reliability The next figure shows the failure rate k of the three approaches.
It confirms that the failure rate starts at an early date from the 25th
Figs. 14 and 15, below, show the curves of the reliability and month and it increases greatly by applying the method SPPM. But
unreliability of the equipment of the three approaches for a trial it is within the standards by the application of RCM model, and it
period of 10 years. So we see clearly that the power system reliabil- remains still be better by adopting RRCM approach (see Fig. 16)
ity decreases below 50% from the 27th month to the SPPM method, From the average availability viewpoint and according to the
but for the RCM model, it decreases from the 49th month and 60th previous figure (Fig. 17), it is quite evident that the electrical sys-
month for the model RRCM. This, in, turn gives a ratio improve- tem will remain available for a very good period by applying our
ment of 1.81 and of 2.22 of the RCM and RRCM compared to the approach.
SPPM. Fig. 18, below, shows the maintenance cost vs time. So we,
clearly, see the big difference in spending between the three
approaches.
Mean Availability
1.0 Through these reliability curves, we can clearly feel the differ-
0.8
SPPM ence between these three approaches, hence, improving reliability
0.8
RCM and availability of an overall report (practice and simulation) of
0.7
RRCM 1.81 of the RCM model and of 2.22 of the RRCM approach com-
pared to the old SPPM method and reduced maintenance cost of
0.6
34.58% for a mission time of four years, see Table 8.
A (t) 0.5
0.4
0.3
Conclusion
0.2
This paper presents the application of the new RRCM model to
0.1
0.0
optimize the maintenance management of electrical power equip-
0 13 26 39 52 65 78 91 104 117 130 ment. From the various results obtained by experimental applica-
TIME (Months) tion and the different simulations of the model, we can conclude
that the effective implementation of the maintenance optimization
Fig. 17. Failure rate curve before and after optimization. by such an approach will therefore improve the reliability and
availability of the electrical system, increase the persons’ safety
and property and the environment and reduce overall operating
and maintenance costs. The main recommendations that we used
Cost over time
35000.00
is the re-integration of this maintenance strategy, including an
31500.00
SPPM optimal and rational implementation of the RCM approach. This
28000.00
RCM work showed the feasibility of conducting an optimization of the
24500.00
RRCM maintenance by using this method in power electrical system.
21000.00 And therefore, it will be necessary to take into account the follow-
Cost (t) 17500.00 ing recommendations: A complete renovation of the system, since
14000.00 most of the equipment is very old and comes from the colonial per-
10500.00 iod, especially the electric lines and transformers, energize the
7000.00 maintenance department, completely change the power lines
3500.00 using the same material, rebuild or replace power transformers
0.0 by other more powerful and robust and finally, change the old
0 13 26 39 52 65 78 91 104 117 130
insulators completely by other composite material to resist mois-
TIME (Months)
ture and salinity of this area. [1–3].
Fig. 18. Cost curve before and after optimization.
Acknowledgments