8006 Project Procedure Manual Guidelines
8006 Project Procedure Manual Guidelines
8006 Project Procedure Manual Guidelines
: 8006
Director of
09-09-2013 0 Ray Manes R. Manes
Projects
Director of
07-18-2014 1 Ray Manes R. Manes
Projects
PROJECT PROCEDURE MANUAL PM-100 PROCEDURE NO.: 8006
1.0 PURPOSE
The Purpose of this document is to provide explanation and directions for preparing a
Project Procedure Manual PM-100. This procedure is to be used on all Samuel Engineering
Project Procedure manuals (PPM).
2.0 SCOPE
This procedure is for use on all of Samuel Engineering, small, medium and large size
projects. The format is adaptable to all industries that SE provides services for. Use of the
procedure to develop the PPM will ensure that the project scope, client expectation, Level
of Effort and execution plan is clearly understood and provided to all project Stakeholders.
It will also provide a base document from which the project changes and scope additions,
deletions or adjustments can be managed.
3.0 UPDATING
This procedure will be updated or revised as required. All contributions or suggestions in
this respect will be considered and incorporated.
4.0 RESPONSIBILITIES
The Manager of Projects is responsible for the content, administration and maintenance of
this procedure.
The PPM should be completed and will be the basis of the SE internal project kickoff
meeting.
The PPM will be updated as required as the project evolves. All revisions will be noted and
hi-lighted.
6.0 APPENDICES
Appendix A
PM-100
FOR
Rev. No. By Revisions Approval Date Commented [E4]: Track changes between issues by changing
the date in this column.
A Issue for Client Review MO/DAY/YEAR
B Issue for Project Kickoff Commented [E5]: All revisions are to be “letter” revisions. This
document will not become a construction document.
C Working
Samuel Engineering
Project Number: XXXXX-XX Commented [E11]: SE Project Number
Prepared by:
Samuel Engineering, Inc.
8450 East Crescent Parkway, Suite 200
Greenwood Village, Colorado 80111
303.714.4840 – Telephone
303.714.4800 - Fax
www.samuelengineering.com
PROJECT NAME Match the Project Name that is used on
the cover page for all pages.
LEGAL CLIENT NAME Commented [E12]: Use Legal Name of Client for the Master
Service Agreement of the Contract
PROJECT NAME
This Project Procedure Manual (PPM) is not a contractual document and is subject to change and
revision at any time. Information stated herein shall not in any way affect the interpretation of the
contract between LEGAL CLIENT NAME (the “CLIENT”) with its principal office located at CLIENT
ADDRESS and Samuel Engineering (SE).
This Procedure Manual defines the procedures to be used for the PROJECT NAME.
INSERT A BRIEF SUMMARY OF PROJECT DETAILS. Commented [E13]: Include a brief reference to the level of
involvement for departments or disciplines. Examples: Detailed
Engineering, Procurement, Logistics, Construction, Construction
Management, Startup and Commissioning, Testing, Scoping Study,
Pre-feasibility, Bankable Study, Process Design, Architectural, Civil,
Structural, Mechanical, Plant Design, Piping, Electrical,
Instrumentation, Automation, Project Controls, Scheduling, Cost
Estimating, Information Technologies, Project Management.
X 1 Project Manager SE John Doe Commented [E15]: PPM Sent Electronically Only
Commented [E16]: Position #, see organization chart and
Engineering Manager Project Document List
Project Engineer Commented [E17]: Name of Lead for the respective Discipline
Project Sponsor
Project Coordinator
Automation Lead Engineer N/A Commented [E18]: Position not required on project to be
denoted by N/A
Instrumentation Lead Engineer
Piping Lead
Procurement Lead
IT Manager
Construction Manager
Startup/Commissioning Manager
1.0 GENERAL
Commented [E24]: In the General Section, it is important that
the information from the RFP and the proposal are recorded. The
Project Procedure Manual, once complete, will be submitted to the
client for review and will serve as a base document and record for
future scope changes.
Formation Capital Corporation, U.S. (FCC) is a wholly owned subsidiary of Formation Capital
Corporation. The Idaho Cobalt Project (ICP) is the company’s flagship property. FCC owns
100 percent of the ICP, which is a high-grade, primary cobalt deposit that is capable of
producing super-alloy-grade cobalt metal and cobalt chemicals. Commented [E25]: This information can usually be obtained
from the original Request for Proposal (RFP). It can also be
obtained from the Clients web page
1.2 PROJECT BACKGROUND
(EXAMPLE ONLY: DELETE & REPLACE)
In 1892, copper mineralization was first discovered along Blackbird Creek. Since then, the
area was intermittently developed by a number of companies. The area was first mined for
cobalt during World War I. From then until 1941 limited quantities of cobalt ore were
produced by two operators. Between 1943 and 1959, the Blackbird Mine was developed
and operated under a contract to supply cobalt to the U.S. government. From 1963 to 1966,
the last significant production from the area occurred under new ownership. Since that
time the property changed hands several times, and the new owners carried out extensive
exploration, mine rehabilitation and metallurgical testing. However, no commercial
production was carried out. The total historical production of cobalt ore from the district is
approximately 2.1 million tons.
In 1994, the then-current owner allowed perimeter claims to lapse, and FCC re-staked much
of that ground. From 1995 to the present, FCC completed surface geochemical sampling
and drilled 113 diamond drill holes on the property. FCC has carried out metallurgical
testing and various studies of the geology as well as completing resource estimates, water
treatment plant designs, mining plans, and other studies related to bringing the property
into commercial production. SE has completed a bankable feasibility study which was
completed in July 2007. Commented [E26]: This information can usually be obtained
from the original Request for Proposal (RFP)
The present processing plan assumes a mill throughput of 30,000 tonnes per day. The plant
will initially utilize conventional flotation. This study will determine if a year 7 cyanide leach
circuit, to treat lower grade oxide ore will be feasible. The plant will operate on a 24 hour
per day, 365 day per year basis. The flotation plant design consists of a lead-silver flotation
circuit followed by zinc flotation and bulk concentrate scavenger circuits.
• Primary Crusher
• Primary Grinding
• Flash flotation of the primary grind cyclone underflow
• Lead-Silver rougher flotation followed by regrind and cleaner flotation
• Zinc rougher flotation followed by regrind and cleaner flotation
• Bulk scavenger flotation of lead-silver and zinc flotation tailings to recover additional metal
values
• Regrinding of the concentrates
• Cyanide leaching will be employed for the treatment of the western ores from Minas and Main.
For this study it has been assumed that 25% of the total ore will be treated by leaching
• Cyanide leaching of the cleaner flotation tailings may be included to improve overall recovery in
the flotation plant on selected tailings streams. Initial process and infrastructure capital costs
are estimated at $281M (U.S.) with an additional $71.8M (U.S.) if a leach plant circuit is added.
The current plan includes trucking bulk concentrate approximately 75 kilometers to an
existing railhead. The concentrate will then be transported by rail to the port of Maturani.
The port has existing concentrate handling facilities that will load concentrate on to ships for
export.
Infrastructure for the project will include installation of a new power line from the city of
Macusani and road improvements and road additions from Macusani. Macusani is located
approximately 30 kilometers east of Corani. Water to operate the facility is expected to be
obtained by collecting surface run-off water in the tailings facility. Well water sources have
also been identified within 5 kilometers of Corani and a river water source has been
identified within 5 kilometers. Figure 1.1 shows the location of the project site, major roads
and rail lines in Peru. Commented [E27]: This information can usually be obtained
from the original Request for Proposal (RFP).
Commented [E28]: This information can usually be obtained
from the Original Request for Proposal (RFP)
1.5 PROJECT CONTACT INFORMATION Commented [E30]: Edit this page as required. Do not include
any non-business personal information i.e. home or personal cell
numbers or personal e-mail accounts
Samuel Engineering Client
1.6 TRAVEL POLICY Commented [E31]: Review and edit Travel Policy as required.
What is shown here is SE’s travel policy and changes to this policy
must match the project proposal and contract. Any other changes
The Samuel Engineering Travel Policy (Obtain from HR Department) must be approved by SE Management
1.6.1 Transportation
• All trips and means of travel shall be approved by the Project Manager prior to the trip
using the Travel Request Form (see Appendix A).
• While working in on site, transportation will be provided via car rental. Fuel for a rental
car is 100% reimbursable.
• Use of personal vehicle from the SE office to and from the airport can be expensed at
the 2016 rate of $0.54 per mile. Use of shuttle bus, RTD, or taxi is 100% reimbursable.
• Airport parking in long term parking areas is 100% reimbursable for a one week period.
Parking in short term parking areas will be reimbursed at the long term parking rate if
the parking period exceeds three (3) days.
• Air travel to and from Denver to site will be arranged by SE.
1.6.2 Subsistence
• While traveling to and from the site, the reasonable cost of meals will be reimbursed
with submittal of expense report.
• Any other miscellaneous expenses may be reimbursable at the Project Manager’s
discretion.
1.6.3 Accommodations
• Employees are required to furnish their own passports and assure they are up to date
and valid for travel. Any visa requirements and expenses will be handled through SE and
are 100% reimbursable.
• All hours worked will be paid at the employee’s base rate, unless otherwise stated in a
personnel site assignment letter.
• Travel from the SE office to and from the site, will be paid at the employee’s base rate
for up to 12 hours maximum per day. Employees are expected to attend work at the
Denver office (before or after travel) on partial travel days. Of course, travel schedules
involving late return and early departures are excluded.
• No more than 12 hours of combined travel and actual work may be charged in any one
day, unless otherwise approved by the Project Manager.
• Only hours worked shall be charged. No more than 12 hours (subject to PM approval)
may be charged in any one day of onsite work.
• Employees are expected to work the hours as required by project demand or scheduled
activities.
1.6.7 Conduct
• The Client and his representatives shall be treated with a high level of respect at all
times in keeping with SE’s core values – “Without clients SE does not exist”!
• At all times, all site personnel shall represent SE at the highest level of professionalism
expected of a consulting firm of SE’s standing. All actions and communication to client
personnel and contractors shall be done respectfully and with discretion. When in
doubt, defer to someone at a higher level within SE.
• All site safety regulations, drug, alcohol and company policies set forth by the SE and
CLIENT safety and drug and alcohol policies, must be adhered to. For Client/site-specific
requirements, please refer to the Field Safety Instructions (PM-114).
• Employees are to be at the jobsite on time as required by the project demands. These
hours may be extended or curtailed based on the request of the Client and/or SE’s
Project Manager or site lead personnel.
• Employees will abide by all local, regional and federal laws pertaining to the job site.
1.6.8 Relocation of Residence Commented [E33]: If a new section needs to be added, add it
to the end. Do not insert it in between existing sections
SCOPE OF WORK
Commented [E34]: The Scope of Work Section should be a
2.0 thorough description of all the work performed. The proposal
should be used to obtain the detailed information. The estimate
section of the proposal will give you line item details of what
deliverables and activities are to be included in the project. In
addition to the Scope of Services details, this section must also
include any clarification, assumptions and exclusions. Also refer to
the final project contract or MSA to verify the details of the scope.
The PROJECT NAME is based on the approved Scope of Work as presented in the Master Commented [E35]: Edit to match the information from the
Services Agreement for Engineering, Procurement and Construction Management cover sheet.
Consulting Services Contract between CLIENT LEGAL NAME and SE. Specifics to the work
Commented [E36]: To match information from the cover page
agreement are outlined in this section.
Commented [E37]: The Scope of Services Description will
include details defining the level of effort for each Division of SE.
2.1 SCOPE OF SERVICES Discipline detail descriptions will be summarized in detail in section
3.0 Execution Plan.
The scope of services for which SE is responsible is described below.
(EDIT AS REQUIRED)
The assigned Project Manager, Name, will manage all aspects of SE’s activities in
cooperation with Client’s personnel. SE’s project manager will interface with Client’s project
manager and ensure that the Client is notified of important decision dates required to
maintain the project schedule.
The lead discipline engineers will lead, coordinate and develop the requisite drawings,
specifications and quantity take-offs, etc. as required for the project.
2.1.2 Engineering
(EDIT AS REQUIRED)
SE will assume full responsibility for the engineering, including preparation of all required
drawings, specifications and associated documents. SE will ensure that the engineering and
design for all systems are in accordance with industry, country and Clients standards and
that the engineering and design services meet the production and performance
requirements set forth by the project’s design criteria.
SE will prepare drawings, specifications, and other technical documents necessary for
construction work and other types of work or services to be performed to the accuracy
described herein. Engineering services will be performed in accordance with:
• Accepted sound engineering practices, Commented [E40]: Use bullets rather than numbers or letters.
This allows for easy revision by removing or adding lines at any
• Standard practices for industrial hygiene and safety, incorporating the principles of location
Inherent Safety analyses,
• The design criteria, standards, specifications and procedures of the Project,
• Relevant statutory authorities, applicable laws, codes, guidelines, regulations and
standards acceptable within the industry,
• Industry best practices as applicable,
• SE will be responsible for administrative control and cataloguing of all technical
documents prepared by SE. This includes maintenance of a filing system and records.
• International Building Codes (IBC)
(EDIT AS REQUIRED)
The principal objective of the Project Controls group is to assist the Project Manager in
completing the project within the target budget and agreed upon completion date.
• Change Management Commented [E42]: Delete bullet items not required on project.
• Cost Control
• Document Control
• Estimating
• Planning and Scheduling
The core objective is to prevent cost and schedule overruns while maintaining quality, safety
and design integrity. Emphasis will be placed on identifying schedule and cost variances
early so mitigating action can be implemented to ensure all aspects of the scope are
completed on time and within budget.
(EDIT AS REQUIRED)
SE will be responsible for the design and procurement for equipment, materials, and
services required under contract.
• Bid selection
• Required documentation
• Field inspections
• The bid and award of the General Construction Contract for the Project will be managed
by SE,
• Construction Management will be performed through the final completion and start-up
of the project.
• The field work will be performed by the SE Construction Management team, consisting
of team members from SE’s Denver office providing senior management on site and a
few selected regional construction professionals to complete the full site staffing
requirements.
• Battery Limits for the Tailings Handling Facility are detailed below. The Facility will
interface with an existing operation. SE is required to interface utilities, piping, process
equipment and controls from within the existing facility.
• Design for the installation of new medium voltage switchgear from the existing
substation, including a power line to the Filter Plant area transformers,
• Design for a new tailings discharge manifold and pipe line from the existing
detoxification mix tanks to the feedwell of the Outotec 24 m Dia. Paste Thickener,
• Design, or coordination of design, for the conveyor system including Filter Press
Discharge Conveyors, Filter Press Collection Conveyors, Portable Grasshopper
Conveyors and the Fixed Radial Stacking Conveyor,
• An independent geotechnical engineering firm will be engaged to perform design work
for the Dry Stack Tailings Facility,
• The batch distribution system and the Paste Backfill Plant are to be considered as a
portion of the flowsheet development. The design will only be developed to the extent
of delivering thickened or filtered tailings to the underground mine portal area.
Plant startup will be initiated with the preparation of an overall plan for acceptance testing,
safety, lock-out tag-out, compilation of instruction manuals, and supply of reagents, spare
parts, and supplies. Process control system checkout will also be included.
Training of operational personnel will include onsite instruction, training at similar existing
facilities, training at vendor facilities, and in-plant training when the facilities are completed.
Maintenance personnel will obtain similar training and will participate in the commissioning
of the plant.
2.2 ASSUMPTIONS, CLARIFICATIONS AND EXCLUSIONS Commented [E43]: The information for Assumptions,
Clarifications and Exclusions should be obtained from the Proposal
and the Master Service Agreement (MSA) or the Contract. In
2.2.1 Project Management general, the design team will not have access to these documents
as they are considered confidential/business sensitive so it is
important to include this information in the PMM so the team has a
(EXAMPLE ONLY – DELETE AND REPLACE) full understanding of the expectations.
• All meetings will be held at SE’s office.
• PHA will be 2 days at site
2.2.2 Engineering
ARCHITECTURAL
• All buildings will be modular.
CIVIL
• Site survey will be provided to SE.
• Access roads by others.
ELECTRICAL
• Overhead power to site by others.
INSTRUMENTATION
• Client will provide recommended suppliers.
CIVIL
• Site survey will be provided to SE.
• Access roads by others.
MECHANICAL
• Client will provide compressor specs.
• Client will provide all conveyor systems.
PIPING
• Pipe spool drawing not required.
• All piping 2” and smaller will be field routed.
PROCESS
• Flow sheets will be provided by client.
• Design Basis will be by client.
N/A
N/A
EXECUTION PLAN
Commented [E45]: The execution plan section should contain
3.0 all the information required to provide each discipline with a clear
understanding of SE and Client expectation s and level of effort
required to meet the scope, budget and schedule. Consult with the
discipline lead and the project discipline lead to develop each
section of the execution plan. This section serves as a guideline for
development of the design basis.
CAUTION
Keep the information in this section focused on how the work will
be executed and order of execution. DO NOT include design details
or level of effort in design. These will be addressed in Sections 6.0
and 7.0 of the PPM.
(EDIT AS REQUIRED)
To meet project requirements, the following disciplines will participate in executing the
work outlined below.
• Project Management
• Plant Layout
• Civil
• Electrical
• Mechanical
• Structural
• Instrumentation and Control
• Piping
• Process
• Project Controls
• Procurement
• Construction Management
• Start-up and Commissioning
• Scope of Work
• Review of technical reports and studies to date, design criteria, available existing project
data
• Project Procedures Manual
• Schedule and agreement on milestones
• Project controls - reports, timesheet codes, accountability
• Reporting procedures
• Client Expectations
• Project Manager
• Project Engineer
• Piping Lead
• Lead Electrical Engineer Commented [E46]: These Site Visit attendees must match the
proposed team as submitted in the proposal. Refer to the travel
3.3 PROJECT REPORTING section in the estimate.
SE believes in frequent and open reporting of project activities to provide the status of the
work to all parties.
There will be weekly coordination meetings with the project team to review the project
status, information needs, problem areas, and forecasted activities for the next week. There
will also be a monthly SE project review meeting. Commented [E47]: After the initial issue of the PPM for any
subsequent issues, all revisions will be identified with a revision
triangle with the corresponding revision letter. The revised
SE will provide a formal progress report to the Client’s Project Manager monthly. information will be hi-lighted. If information is deleted, it will be
stricken through.
All Correspondence between Samuel Engineering and the Client will be through CLIENT’S
PROJECT MANAGER, NAME.
• Project Background
• Project description
• Project Map
• Project Contact Information
• Travel Policy
• Scope of Work
• Scope of Services
• Assumptions, Clarifications and Exclusions
• Execution Plan
• Internal Kick-Off Meeting
• Site Visit
• Project Reporting
• Preparation of Project Procedures
• Project Roles
• Project Document List
• Drawing Formats
• Communications
• Project Design Criteria
• Design Requirements
• Engineering Procedures
• Engineering Control
• Reports
• Organizational Charts
• Schedule
• Manhour Budget
• Appendices
The document will be dynamic and can be modified as required.
(EDIT AS REQUIRED)
Name will serve as the Project Manager, and is directly responsible to the Client for all
aspects of the work. He/she is SE’s primary contact for the project. Name will plan, direct,
coordinate, and control every phase of project execution.
Name will serve as the Project Sponsor, and will communicate with the Client and the SE
team as required to independently ensure that the Project proceeds successfully.
Name will serve as the Engineering Manager, and will ensure the quality of the engineering
effort.
Name will serve as Project Coordinator/Engineer, and is responsible for the directions of all
project engineering matters related and is the key contact in the absence of the Project
Manager.
Name will serve as the Construction Manager, and is responsible for the directions of all
project construction management in the field.
The project management team will insure a highest level of quality and accuracy for all
project deliverables. Below are all key areas of project development and completion
described:
• Project management
• Engineering management
• Procurement
• Logistics and transportation
• Construction
• Start-up and commissioning
• Quality assurance
• Health and safety
• Communications
• Project controls
• Project schedule
• Project closeout
The management team will provide critical project execution guidance and oversight to
ensure timely project completion. Key activities include:
• Conduct risk review meetings with key project and management personnel, and develop
and implement action items
• Oversee the development of an integrated activity schedule that will plan and prioritize
all the major activities
• Establish an execution technology implementation plan with regard to automation
tools, software, work processes, procedures, and design execution centers
• Ensure the project is appropriately staffed with competent personnel
• Ensure the Client’s Project Manager has the most current information regarding design
schedule and budget.
3.5.2 Process
The process engineer is responsible for preparing the mass balance and process philosophy
as required to determine retention times and initial equipment sizes. The engineer will
review test work and provide any recommendations for guidelines as to equipment
selection or additional testing or studies that may be deemed necessary. The engineer will
develop to project flow sheet design. All PHA and PSM meetings will be attended by the
process engineer.
(EDIT AS REQUIRED)
Plant Layout will commence upon the availability of process and equipment information.
The facilities will be modeled in 3D and the general arrangements will be generated and
updated on an as required basis. The models will be maintained and updated constantly
throughout the project. Models will form the basis for design and plant layout. SE will
design for the structural support requirements for vendor supplied package systems. All
equipment will be designated with SE’s standard equipment numbers and shown on the
flow-sheets, equipment list and design drawings. The layout group is responsible for all
General Arrangement drawings, plans & sections, conveyor profiles, and Mechanical
drawings.
material transfer work points. The drawings will be used to maintain dimensional control
for all design disciplines.
3.5.4 Architectural
3.5.5 Civil
(EDIT AS REQUIRED)
The extent of SE’s civil effort will include creation of the earthwork design for the plant
areas, required roads and benches. During the preliminary design phase, the civil engineer
will evaluate cut and fill quantities and take-offs suitable for supporting plant site selection.
During the detailed design phase, civil engineering will develop construction specifications
and necessary drawings suitable for construction.
(EDIT AS REQUIRED)
The structural engineer will be responsible for delivering construction specifications,
material specifications, and drawings suitable for construction.
Based on General Arrangements and vendor information, SE will prepare drawings showing
the layout, elevations and information necessary to define the size and details of the
concrete elements.
Structural concrete, complete with reinforcing steel requirements, list of embeds, and
anchor bolt requirements.
(EDIT AS REQUIRED)
The structural engineer is responsible for delivering construction specifications, material
specifications, and drawings suitable for construction.
Based on General Arrangements and vendor information, SE will prepare drawings showing
the layout, elevations and information necessary to define the size and details of the
structural elements.
SE will review and approve contractor’s rebar and structural steel fabrication drawings.
(EDIT AS REQUIRED)
Ventilation, heating and freeze protection design for all buildings will be specified and
incorporated into pre-engineered building specifications.
3.5.9 Mechanical
(EDIT AS REQUIRED)
Mechanical engineering is responsible for providing input for P&ID development, creating
and maintaining an equipment list and evaluating mechanical equipment requirements to
ensure proper equipment selection. Mechanical specifications will be created for all
mechanical equipment. The engineer is responsible for producing necessary construction
specifications. The mechanical engineer is responsible for equipment and pipeline sizing,
HVAC design, and fire protection that is considered necessary.
Mechanical engineers will be responsible for sourcing and bidding and final review of bids
for all mechanical equipment.
• P&IDs
• Issue for approval drawings
• Issue for bid drawings as required
• Issue for construction drawings
• Line sizing calculations
• Pipe Stress Analysis
• Mechanical Equipment list
• Equipment data sheets and specifications
• Suggested equipment suppliers list for Client review and approval
• Equipment sizing, RFQs and filled out PO forms, material & document tracking
• Perform layout and design of equipment, piping, controls, buildings and other site
facilities
• Issue engineered equipment and building specs and data sheets, RFQs, perform
technical bid evaluations, and create Client POs
• Vessel outline drawings (data sheets)
Supporting tasks include development of requisition packages for process equipment bid
solicitation, technical evaluations, making recommendations for purchase, and provide post-
award vendor drawing and data reviews to support process equipment fabrication.
3.5.10 Piping
(EDIT AS REQUIRED)
The piping designer is responsible for drafting and creating P&IDs. The designer is
responsible for plant layout drawings generating review of Clients construction
specifications and material specifications for valves and piping. Bulk piping quantity MTO’s
will be produced. The designer is also responsible for developing tank data sheets, all piping
drawings (including orthographics), and pipe spools.
3.5.11 Instrumentation/Automation
(EDIT AS REQUIRED)
The engineer will support P&ID development and evaluate instrumentation requirements.
The instrument group will prepare instrument data sheets and the instrument index.
• Control system architecture block diagram, spec, quote and filled out PO forms
• Filled out instrument data sheets on Hunter Ridge data sheet templates, quotes, and
filled out PO forms for tagged instruments, control valves, and relief valve
• Control philosophy narratives and coordination with control system programming
contractor
• Instrument installation details
• Instrument loop drawings
• Safety system plot plan - ESD pushbuttons, fire detection, gas detection, strobes,
beacons, etc.
• Perform control system design including I/O lists, Cause and Effect Diagram and
Instrument Index
• Control panel layout drawings and wiring diagrams
(EDIT AS REQUIRED)
Electrical engineering will perform calculations for such items as a load and power factor
study, a fault analysis and protective relay coordination, voltage regulation, motor starting
voltage dip, lighting, grounding, and power distribution design.
• Perform all electrical engineering calculations, design and construction documents for a
completed and operational facility.
• Full system model and studies including load flow, coordination, short circuit, motor
starting transient analysis and arc flash evaluation.
• Provide electrical input (cable tray and major electrical equipment) into the 3D model.
• Develop design and construction documents for the full scope of the 138kV-13.2kV
substation.
• Specify engineered electrical equipment including 138kV switches/breakers, switchgear
(MV & LV), MCCs (LV & MV), UPS, transformers (MV & LV secondary), motors, MV VFDs,
etc. to be purchased by Client. Provide datasheets and documentation requirements to
Client. Specification should be based off Company’s Specifications & Recommended
Practices (SARP) when available. Project specific specification will be provided when a
SARP is not available.
• Assist Client as needed with building permits
• Generate commodity material take-off (MTO) for cable, tray, and any other long lead
equipment required.
• Provide vendor inspection trips as necessary for electrical equipment (local vendors
assumed).
• Provide an integrated test plan (ITP) for the field acceptance testing for major electrical
equipment, relays and cable systems. Field acceptance testing should be based of NETA
FAT requirements or similar methods preferred by Electrical Engineer and approved by
Company. The ITP shall be able to submit to 3rd party testing companies to execute
during the testing, commissioning and startup phase of the project.
3.5.13 Project Controls
(EDIT AS REQUIRED)
Project cost control covers all costs incurred on the Engineering design portion of the
project and the forecasting of trends and/or deviations from the original budgets. This
control is achieved by monitoring the costs and commitments against the project budget
and reporting on trends as they develop. Cost performance will be monitored, analyzed and
reported to the client on a periodic basis, thru the project manager.
Project Controls and Engineering will assess and validate physical progress against
deliverables in the ‘Engineering Status Report’ and report earned hours, productivity and
Estimate to Complete (ETC) hours on a bi-weekly basis.
SE will develop and maintain a comprehensive project cost reporting system. The cost
reporting system will include a breakdown of the following cost elements.
Change Management
3.5.14 Procurement
(EDIT AS REQUIRED)
SE will provide procurement services for the project for major mechanical and electrical
equipment.
(EDIT AS REQUIRED / show as “N/A” if not in Scope) In the development of a Project Procurement Plan document (PX-
111), refer to procedure #5003 Purchasing Plan.
SE will award the construction of the project to a “General Contractor” as a single contract
from the earthwork to mechanical completion.
The management team will manage the site activities of onsite general contractor and
specialty construction contractors. The General Contractor is responsible to supply all bulk
materials and install all owner-supplied (SE managed) equipment. The contractor is also
responsible for providing turn-key fabrication and erection of the filter building.
Specific timing for all engineering work packages and construction RFP packages will be
included in the project master schedule.
(See Construction Plan (C-114), Appendix H) Commented [E50]: On some Projects, the construction may be
complex enough to require a separate detailed comprehensive
Construction Plan. If it is determined that one is required,
3.5.16 Startup and Commissioning reference the document and appendix numbers.
SE will manage all equipment acceptance and start-up activities and provide signed records
upon completion. Client’s operators will participate in commissioning activities as the SE
Start-up Team will provide the training of the operators during this phase. Training of
operational personnel will include onsite instruction, training at similar existing facilities,
and in-plant training when the facilities are completed. Maintenance personnel will obtain
similar training and will participate in the commissioning of the plant.
(See Startup Commissioning Plan (C-115), Appendix I) Commented [E51]: On some Projects, the startup may be
complex enough to require a separate detailed comprehensive
Startup Plan. If it is determined that one is required, reference the
document and appendix numbers.
CAUTION
At the stage of the project when this PPM is developed, all drawings
and specs may not yet be determined. That level of detail will be
shown on separate lists which will be developed as the project
progresses. EXAMPLE: Drawing list, Specification list, Iso list, etc.
(REVISE AS REQUIRED)
All documents will be identified with a unique document number. The development and
maintenance of each document will be the responsibility of a single team member. The
document assignments are shown on the Project Documents List PM-101 (see Appendix L)
by a number listed under “responsible position.” The responsible position number
corresponds to a specific team member who is identified on the Project Organization Chart
(Section 11.0).
Master cover sheets have been created for the project. All documents identified as a
deliverable will require a cover sheet to track document status. (Exception: Drawings
contain this information in the title block.) For project document quality and consistency, all
documents will follow the Standard Cover Sheets (see Appendix J and K).
COMMUNICATIONS
Commented [E53]: This section will address how
5.0 communication will be controlled and documented both internal
within SE and external to Client, Subconsultants and Vendors. Be
sure all correspondence complies to SE standards.
5.1 GENERAL
(EDIT AS REQUIRED)
The correct forms and format for all correspondence to be used is in accordance with the
guidelines found in Appendix N through S).
All correspondence to the Client will be addressed to the Client’s Project Manager and
signed/approved by SE’s Project Manager, SE Project Coordinator/Engineer or Construction
Manager.
5.2 CORRESPONDENCE
(EDIT AS REQUIRED)
5.2.1 Letters
Letters should be limited to one subject wherever possible. The subject and project number
will be given in the reference line at the heading of the letter. Letters to the Client will be
reviewed by SE’s Project Manager or Project Engineer.
5.2.2 Faxes Commented [E54]: NOTE: The use of fax machines is nearly
obsolete. When SE retires our fax machine, 5.2.2 will be revised.
Faxes to the Client will be reviewed by SE’s Project Manager or Project Engineer before issue
(Appendix N). Commented [E55]: NOTE: If it is determined that a series
number (i.e. 5.2.3) will be “N/A,” be sure to remove the related
appendix.
5.2.3 Telephone Conversations
Meeting Agenda’s and Minutes of Meetings will be created for all meetings pertaining to the
project, will be compiled and circulated to attendees of the meeting. Content of the
Minutes should be brief but shall contain all important facts, decisions, agreements, design
details and most importantly, action items including responsible persons for the action
items. All Meeting Agendas and Meeting Meetings will be reviewed by Project Manager or
the Project Engineer before issue (see Appendix P and Q).
5.2.5 Transmittals
Transmittals will be used to record each transmission of drawings, bills of material, contract
documents and any document/item sent out of SE’s office (Appendix R). A project
transmittal log will be maintained for each project by document control.
5.2.6 E-mail
The purpose of the e-mail filing procedure is to ensure that all project personnel are aware
of where and how e-mails are to be stored. Further, it is to create a simple and consistent
policy for naming e-mails for ease of reference at a later date.
• Newforma
ALL e-mail for the Project will be filed in Newforma which will then automatically file it
in the project e-mails. Newforma is accessible to all SE Team members.
The Newforma system will prevent duplicate e-mail and will make it easier to find an e-
mail when needed for reference. The additional safe-guard is that the emails will be
backed up on the server so that the information will not be accidentally lost.
The only emails that should be copied to the project folder are emails that impact the
project, contain important information, or are necessary for email trail.
• Accessibility
The project e-mails will be accessible to all personnel in the Newforma system, except
those for restricted PM and procurement sections. All project related e-mails will be
filed by the system and can be located by various sorting and searching techniques.
• Link
To create a link in the e-mail: Right click in the e-mail or choose the ‘Insert’ tab, then
‘hyperlink’ and choose the path where the file is located. Press enter and the link will
appear in the e-mail message. If you go back to use the link in an older e-mail and the
link does not take you to the document, check in the ‘linked folder name’ for an archive
directory.
NOTE: The e-mail must be in HTML format to create a ‘link’ in the message. When
selecting the hyperlink command on the insert menu, a pop-up will ask if you want to
switch the e-mail to HTML format (click ‘switch to HTML’). Also, the ‘link’ has to be
inserted into the body of the e-mail. ‘TO’ Address Procedure
• Identifier in the Email Subject Line
Subject line is to contain the project code and a short description of the e-mail content
separated with a “-”. This description is very important for future investigation.
When scanning or .PDF’ing a file, it MUST be renamed with a logical name and the
project number.
Example:1100-CE-001 Rev B
DO NOT save a scanned or PDF’ed document with the long automatic file name from the
scanner.
Ambient Temperatures
Average annual maximum, °C
Average annual minimum, °C
Mean barometric pressure, plant, kPa
Design Loads
Precipitation
Average rainfall, mm/yr
Snow load, kPa
Wind
IBC basic wind speed, km/h
IBC exposure
Wind importance factor
6.4.1 Architectural
(INSERT DATA NOTE “NOT REQUIRED”) Commented [E57]: For a small to mid-size project the design
brief should be inserted into each discipline sub section in the form
of paragraphs and bullet items. For a mid-size to large project, a
6.4.2 Automation / Instrumentation full design basis document should be created and inserted into the
PPM.
(INSERT DATA OR NOTE “NOT REQUIRED”)
6.4.3 Civil
6.4.4 Electrical
6.4.5 Instrumentation
6.4.6 Mechanical
6.4.7 Piping
Piping sizes will be expressed by nominal pipe diameter in inches. Measurements including
lengths and elevations will be given in feet and inches. Flows will be expressed in gallons
per minute (gpm). Pressure will be expressed in pounds per square inch (psi).
Temperatures will be expressed in degrees Fahrenheit (°F). Volumes will be expressed in
United States gallons. Weights will be expressed in pounds. Commented [E58]: Example of a design brief that can be used
in place of a full design basis document.
DOCUMENTS
To be produced by Samuel Engineering (SE) as part of the piping services package to include:
GENERAL
This document will define the minimum requirements to establish the process flow and the
general arrangement and layout of buildings and equipment. The process flow including
wet and dry materials will be recorded on process flowsheets. Flows will be defined and
balanced. All equipment will be identified. Arrangement drawings of buildings and
equipment will be created. The documents described above will be produced in enough
detail to clearly define the scope of the project. These documents will be submitted to the
Client for review and approval. Approved drawings will be used as the basis for detailed
engineering design.
All measurements including, lengths and elevations, will be given in feet (ft) and inches (in.);
weights will be expressed in pounds (lb). Flows will be expressed in gallons per minute
(gpm). Pressure will be expressed in pounds per square inch (psi). Temperatures will be
expressed in degrees Fahrenheit (°F). Volumes will be expressed in United States gallons
(gal).
DOCUMENTS:
The general layout design will be based upon a definitive set of drawings and documents
that will contain information necessary to provide a basis for the detailed design of the
equipment and related facilities. Each design drawing will be done on CAD and will contain
information and detail only to the extent as described in subsequent paragraphs of this
document. All drawings shall conform to current office CAD standards.
General Layout drawings will be produced in MicroStation. Drawings will be in the form of
plans or sections and are intended to be a coordinating tool for all other engineering
disciplines. General Layouts are conceptual and should not be used by contractors for
construction except as a coordinating tool with other discipline detailed design drawings. All
other disciplines should follow the design set forth by the general layouts as close as
possible to prevent unnecessary revisions of previously completed layouts.
General Layout drawings will be produced for the following areas only:
• Fuel storage
Process Flow Diagrams:
Process Flow Diagrams shall contain a graphic representation of material flow from the
Owner’s underground conveyor feed the first stage crushing to surface load out facilities.
Included will be additive treatment and mine dewatering flowsheets. There will be no
flowsheet covering mine utilities. All flowsheets will be complete with equipment names,
numbers, and mass flow balance chart. Graphic symbols will be per Samuel Engineering’s
“Metflow” cell library. The mass flow balance will be calculated and then inserted into the
respective flow diagrams. All other pertinent equipment information shall be contained in
the project Equipment List.
Conveyor Profiles:
Conveyor profiles will be provided with only critical detail being noted.
Workpoint elevations of head and tail end of conveyor will be noted at intersections of belt
line and centerlines of feed and discharge chutes. Workpoints on head and tail pulleys will
be calculated by supplier due to unknowns such as final pulley diameters, belt speed and
material trajectories. Conveyor angles will be noted for reference only.
Support bent locations will be determined by conveyor supplier. All possible interferences
with bent locations such as road crossings, structures, conveyors and other equipment will
be noted on profile drawings.
Tentative locations for take-ups will be shown on profiles with final location being
determined by conveyor supplier with Engineer’s approval.
All points of curve (PC), intersection (PI), tangent (PT) and belt curve radius shall be
tentatively noted when concave or convex curves are required. Final points shall be
determined by conveyor supplier.
6.4.9 Process
DESIGN REQUIREMENTS
Commented [E59]: In the Design Requirements Section, list all
7.0 related non SE codes standards and procedures.
ENGINEERING PROCEDURES
Commented [E61]: The Engineering Procedures Section is SE’s
8.0 standards for executing the work consistent with our proven
methods.
Design units shall be imperial or metric. Process reporting units (flows, pressure,
temperature, etc.) shall be imperial or metric.
8.2 DRAWINGS
(EDIT AS REQUIRED)
Drawings will be issued with title blocks and notes in English. The title block used on the
project will be SE standards as shown in “Standard Drawing Title Block and Drawing
Numbering (see Appendix M).
The SE CAD Standards shall be followed throughout the development process of all
drawings. Intelligent models shall be created for generating equipment lists, line lists, valve
and instrument lists. (See section 8.10 for CAD requirements.)
Consistency in revision issues, names, line weight, drawing titling, numbering, drafting
standards and notes will be maintained between disciplines.
All drawings shall be started, reviewed, revised, approved and issued in accordance with the
Internal Drawing Revision and Issuing Procedure flowchart (see Appendix V).
Drawings will be dimensioned using the imperial or metric system. Document Control will
develop and maintain a drawing list (E-DC-101) showing the exact drawing title and the
current and past revision status of all drawings.
Each discipline may maintain a project stick file ensuring the latest issue of each drawing is
in the file. When a drawing is reissued, the drawing on the stick will be removed and placed
in the project drawing file folder.
Drawing originals will be stored on the SE network which is backed up daily and current
copies kept on the project stick file as working copies.
Print sets of mark-ups, check prints, review copies and client comments will be kept folded
in files for each drawing number. Drawing files will be the responsibility of the document
control department.
Vendor drawings and information reviewed must be signed by the lead discipline engineer
and the reviewing engineers on the circulating copy. The final signature must be that of the
Project Manager or Project Engineer. Document control will be responsible to notify
discipline leads and the Project Engineer upon completion.
Any drawings released “FOR APPROVAL” or “FOR CONSTRUCTION” shall be signed by all
responsible disciplines and approved by the Project Manager.
All drawings which are no longer current to the project shall be voided by Document Control
upon the direction of the originating Discipline Lead. A VOID stamp with the originating lead
discipline engineer’s initials and date shall be placed on the drawing original. One copy of all
voided drawings shall be kept by Document Control in the drawing history file until the end
of the project.
If a drawing to be voided has already been issued, the drawing must be revised to the next
appropriate letter or number and designated “Issued as Void”. The voided drawings shall
then be issued in the same manner as an Issued for Construction drawing.
Each drawing should be reviewed as it becomes available. Drawings will first be reviewed by
the Designer and Discipline Lead prior to making the check print. Although sometimes the
Discipline Lead is also the Designer or the Designer is also the Draftsperson, the Checker
should always be someone other than the Designer of the drawing.
All corrections, modifications, and additions will be made on the check print in RED pencil.
Deleted items will be marked off in GREEN pencil. Information checked and corrected will
be marked off in YELLOW pencil. Comments and notes to the designer will be marked in
BLUE pencil. Initial and date all remarks made.
Document Control will maintain a list of the drawings out for checking and will expedite
them for timely review. The drawing list may be used for this purpose. Marked up check
prints will be kept in a folder by the Designer or Lead Discipline Engineer for filing by
Document Control in the project drawing file.
The Discipline Lead will order a print, stamped CHECK PRINT and dated. All pertinent data
used to generate the drawing is attached and a Checker is assigned by the lead discipline
engineer. Any drawings released prior to having a Discipline Check must be marked and
stamped UNCHECKED on the original prior to reproduction except for drawings released as
PRELIMINARY or FOR INFORMATION which need not be Discipline Checked.
The checker will resolve inadequacies with the Designer or Discipline Lead. The Checker
should not redesign the drawing. If this is required, the Lead Discipline Engineer should be
advised.
The Checker will review the checked drawing with the Discipline Lead and the Designer will
make the necessary changes. Upon revision of the drawing, the Discipline Lead will
proofread the corrections with the mark-ups and sign the original on the first “checked”
line. The Project Engineer or Project Manager will then review the drawing and sign on the
second “checked” line. The drawing will then be issued.
Interdisciplinary Check:
Drawings will be Discipline Checked prior to an Interdisciplinary Check (IDC). The discipline
lead will order prints, with the date stamped on it. Initials of the individuals in each
discipline required to review will be added. A number placed beside the name will indicate
the sequence of circulation. Each drawing will be stamped. All drawings will be routed to
the Project Engineer.
Discipline leads will give top priority to checking IDC prints and should be reviewed within
the day received. A maximum of five working days will be allocated for IDCs. Prints will be
hand carried between individuals. In some cases documents will be placed in a common
area designated for the project where individuals may check the documents. Each Lead
Discipline Engineer will sign and date the print.
Revisions to the equipment list will be made promptly and periodically whenever there are
additions, deletions or changes in description of equipment. All disciplines will review each
issue of the equipment list and mark appropriate corrections and updates. All disciplines
will check and update their drawings and specifications to the revised information on each
issue of the equipment list.
Equipment will be numbered using SE’s standard numbering system, unless otherwise
required by the Client. Commented [E62]: CAUTION: Our Client may require use of
their own numbering systems. Edit this document accordingly.
All specifications will be managed using SE’s Internal Specification Revision and Issuing
Procedure (see Appendix W).
Samuel Engineering will prepare performance specifications for the solicitation of price
quotations for equipment not purchased or provided by the Client. These specifications
should be complete enough to allow for their use as purchase specifications with minimal
change. The specification questionnaire will be complete in design detail (as quoted) unless
the design has not been finalized by the supplier or by SE. In this case, the supplier will
complete the questionnaire after purchase and supply it for final approval by SE.
Performance specifications will be developed using imperial or metric units for process
design data and imperial or metric units for all other design information.
Site criteria for all specifications will be according to the site data.
to the project. Employees at all tiers of SE’s organization are expected to achieve quality
assurance for all work.
Quality must be maintained at all times and on all tasks through SE’s quality assurance
program.
Drawings will be created and dimensioned using the imperial or metric system.
CAD models are not to be issued or sent to Vendors, Subcontractors or the Client without
approval by the Project Manager.
The most current version of Auto CAD or Microstation will be the CAD platform for the
project.
The file naming structure for the project will per SE or Client standards.
All project team members are responsible for identifying and documenting scope changes.
When a change of scope has been identified, the Discipline Lead whose work has been
affected will initiate a Trend / Scope Change Record (PC-110-A). The completed Trend /
Scope Change record will then be submitted to the Project Engineer. The Project Engineer
will log the Trend / Scope Change Record using PC-110 and review. If it is determined by the
Project Engineer that the change affects the project cost, budget or schedule, the Project
Engineer will initiate a Project Scope Change Notice – Advance Authorization form PC-104-A
(see Appendix E).
SE will maintain a Contract Change Log on PC-104 (see Appendix F) and will initiate and
process all owner-directed and engineering change orders. Changes are to be executed in a
timely basis and not accumulated.
When the Project Engineer initiates a Project Change Notice, it will be submitted to the
Project Controls Lead. Project Controls will log it, cost it, and schedule it. The change notice
will then be forwarded to the Project Manager for approval and sent to the Client. Once
approved by the Client, it will be sent back to Project Controls to be logged, and have the
proper adjustments made to the budget and schedule. Project Controls will then send the
notice to the Project Engineer for execution. See Appendix B for the Project Change
Procedure Flow Diagram.
The change order will become a budget and/or schedule adjustment on the baseline and
work plans will be adjusted to reflect the revised scope. This will ensure that progress and
performance are monitored against an accurate baseline.
REPORTS
Commented [E64]: In the Reports Section all methods of
10.0 capturing project progress will be considered. Review each section
and ensure that it agrees with what was proposed in the proposal
and also agrees with the final contract or MSA.
(EDIT AS REQUIRED)
SE believes in frequent and open reporting of project activities to provide the status of the
work to all parties.
The following reports (to Client) will be used to best monitor the project (all reports will
produced in English only):
The following report (internal) will be used to best monitor the project:
• Summary
• Procurement
The Action Item Register will act as the meeting minutes for all weekly project meetings.
The Action Item Register will be maintained by the Project Engineer and/or the Project
Manager.
Project Controls and Engineering will assess and validate physical progress against
deliverables and report the following:
• Earned Hours
• Productivity Index
• Percent Complete
A visual graph displaying spending curves for budgeted, actuals and forecasted hours will be
maintained separately as an internal tool to easily detect deviations from the baseline, this
can be provided to the client upon request.
SE will develop and maintain a comprehensive project cost reporting system (PC-103). The
cost reporting system will include a breakdown of the following cost elements.
• Incurred to Date
• Total Commitment
• Baseline Budget
• Approved Budget
• Variance
10.7 SCHEDULE
(EDIT AS REQUIRED)
SE will develop a Critical Path Method (CPM), Integrated Project Schedule (IPS) for planning
the project. Critical and near-critical path activities will be monitored throughout the
project to avoid any delays in project completion.
For each task, scheduled starting and completion dates will be estimated and listed on the
schedule.
• Procurement activities;
This Project will be tracked using a Level X Schedule. Commented [E65]: To determine the Level of schedule, refer to
SE’s Scheduling Overview Procedure No.: 3210 and select the level.
Also be sure to check and see if a schedule level was stated in the
Development, progressing and maintenance of the IPS are the responsibility of the Project proposal document.
Scheduler with oversight by the Project Manager.
The Scheduler will monitor activities on the critical path, analyze the progress against the
target, identify significant changes in logic and will forecast activities for the coming month
in the monthly report.
Re-baselining of the IPS will not occur unless requested by the client as a result of an
approved change order that significantly impacts the schedule.
ORGANIZATIONAL CHARTS
Commented [E66]: The Organizational Chart Section will
11.0 identify Project Stake Holders and reporting structure.
Reporting Structure for the project is shown on the project organizational chart. The chart
shows the names, titles, positions, and responsibility number for project team members. Commented [E67]: In most cases, a project organizational
chart was submitted with the proposal. Be sure that when you
develop the PPM charts that they meet the commitments made in
the Proposal and the IMSA or Contract.
3
(TBD)
(TBD) Project Engineer or Coordinator
Insert the Names and Titles of Insert the Names and Titles of
the Discipline Lead on top. the discipline support team.
Project Controls Document Control Procurement Mechanical Process Piping Automation/ Electrical Civil/Structural
Instrumentation
16 23 17 12 11 13 8 14 10
(TBD) (TBD) (TBD) (TBD) (TBD) (TBD) (TBD) (TBD) (TBD)
Project Controls Lead Doc. Control Procurement Lead Lead Mechanical Engineer Chief Process Engineer Chief Piping Designer Lead I&C Engineer Lead Electrical Engineer Lead Structural Engineer
Professional
11.2 MANAGEMENT ORGANIZATIONAL CHART Commented [E68]: This Organization chart is to be issued when
the project has interfaces set up with multiple contractors,
consultants, or other project stakeholders that require participation
in the project and what that reporting structure is
1
(TBD)
Project Manager
Process Document Control Procurement Mechanical Project Controls Piping Automation/ Electrical Civil/Structural
Instrumentation
1 23 17 12 16 13 8 14 10
*(TBD), PE *(TBD) *(TBD) *(TBD), PE *(TBD), MBA *(TBD) *(TBD), PE *(TBD), PE (TBD), PE
Chief Process Lead Doc. Control Procurement Lead Lead Mechanical Director of Project Chief Piping Lead I&C Engineer Lead Electrical Lead Structural
Engineer Professional Engineer Controls Designer Engineer Engineer
(TBD) (TBD) (TBD) (TBD) (TBD) (Lead) (TBD) (Lead) (TBD), PE (TBD), PE (TBD), PE (Civil)
11.3 CONSTRUCTION MANAGEMENT ORGANIZATIONAL CHART Commented [E69]: Select relevant Organizational Charts and
delete any that do not apply to the project.
Construction Management
Organizational Chart (C-116) (TBD)
Client Name Project Manager
Project Name
SE Project No. XXXXX-XX QA/ Peer Review Team
(TBD)
(TBD) (TBD)
Construction Manager Project Manager
(TBD)
Construction Engineer
LOCAL HIRE LOCAL PROFESSIONAL (TBD) REGIONAL PROFESSIONAL (TBD) *(TBD), MBA
Secretary/Document Control Project Accounting Mech./Piping Field Engineer Electrical Field Engineer Automation/Start-Up Engineer Director of Project Controls
*(TBD)
Mechanical Engineer
* Indicates Department Head
**Provide Field Management for CM when unavailable
SCHEDULE
Commented [E70]: The Schedule Section will contain the
12.0 project schedule. The Schedule in the PPM should be completed
prior to project kick off. The SE project controls department will
produce the schedule. Check to ensure the milestone dates and
data match those that were stated in the project proposal, the MSA
and/or the contract.
(EDIT AS REQUIRED)
The Project requires a Level I, II, II, IV and V Project Schedule (PC-101). Commented [E71]: Select Schedule Level. Refer to section 10.8
for schedule level determination.
(INSERT SCHEDULE AFTER THIS PAGE)
MANHOUR BUDGET
Commented [E72]: The Manhour Budget Section will show the
13.0 manhour breakdown by Discipline. It is important that each
discipline lead knows what his/her budget is. The lead will manage
his/her budget. The manhours can be obtained from the project
proposal or obtained from the Project Controls Department. DO
NOT include dollar budgets in the PMM. This information is
confidential and should remain in projects contract book only.
14.0 APPENDICES
LIST OF APPENDICES
Approval: Date:
Itinerary Number:
Page 83 of 113
Appendix B – Project Change Procedure-Flow Diagram
Page 84 of 113
Appendix C – Trend/Scope Change Record
Page 85 of 113
Appendix D – Trend/Scope Change Record Log
Page 86 of 113
Appendix E – Scope Change Notice-Advanced
Page 87 of 113
Appendix F – Contract Change Log
Page 88 of 113
Appendix G – Project Procurement Plan (PX-111)
8450 East Crescent Parkway, Suite 200 Phone: 303-714-4840
Greenwood Village, CO 80111 Fax: 303-714-4800
PX-111
FOR
Client Name
Project Name
MO/DAY/YEAR
1.0 PURPOSE
Page 90 of 113
Appendix H – Construction Plan (C-114)
8450 East Crescent Parkway, Suite 200 Phone: 303-714-4840
Greenwood Village, CO 80111 Fax: 303-714-4800
CONSTRUCTION PLAN
C-114
FOR
Client Name
Project Name
MO/DAY/YEAR
1.0 PURPOSE
Page 92 of 113
Appendix I – Start-up and Commissioning Plan (C-115)
8450 East Crescent Parkway, Suite 200 Phone: 303-714-4840
Greenwood Village, CO 80111 Fax: 303-714-4800
C-115
FOR
Client Name
Project Name
MO/DAY/YEAR
1.0 PURPOSE
Page 94 of 113
Appendix J – Standard Cover Sheet
8450 East Crescent Parkway, Suite 200 Phone: 303-714-4840
Greenwood Village, CO 80111 Fax: 303-714-4800
DOCUMENT TITLE
FOR
Client Name
Project Name
DOCUMENT TITLE
FOR
Client Name
Project Name
PM-101
FOR
Client Name
Project Name
MO/DAY/YEAR
Deliverable
Site/Field
Responsible
Internal
Document
Document Title Person/ Notes
Number
Position
Page 98 of 113
Appendix L Project Document List (PM-101)
8450 East Crescent Parkway, Suite 200 Phone: 303-714-4840
Greenwood Village, CO 80111 Fax: 303-714-4800
Construction Management
Deliverable
Site/Field
Responsible
Internal
Document
Document Title Person/ Notes
Number
Position
Engineering
Deliverable
Site/Field
Responsible
Internal
Document
Document Title Person/ Notes
Number
Position
Page 99 of 113
Appendix L Project Document List (PM-101)
8450 East Crescent Parkway, Suite 200 Phone: 303-714-4840
Greenwood Village, CO 80111 Fax: 303-714-4800
Engineering
Deliverable
Site/Field
Responsible
Internal
Document
Document Title Person/ Notes
Number
Position
Engineering
Deliverable
Site/Field
Responsible
Internal
Document
Document Title Person/ Notes
Number
Position
Project Controls
Deliverable
Site/Field
Responsible
Internal
Document
Document Title Person/ Notes
Number
Position
Site/Field
Responsible
Internal
Document
Document Title Person/ Notes
Number
Position
Procurement
Deliverable
Site/Field
Responsible
Internal
Document
Document Title Person/ Notes
Number
Position
To: Date:
Fax No.: Ref.:
Company: Location:
From:
If you have any problems, please call: Insert Name Insert # and Ext.
THIS MESSAGE IS INTENDED ONLY FOR THE USE OF THE ADDRESSEE, AND MAY CONTAIN INFORMATION THAT IS PRIVLEDGED AND
CONFIDENTIAL. If you are NOT the intended recipient, or an employee or agent responsible for delivering the message to the intended recipient,
you are hereby notified that any dissemination, distribution or copying of this communication is strictly prohibited. If you received this
communication in error, please notify us immediately by telephone. Thank you.
Subject: Ref.:
Client: Date:
Insert Text
ACTION
Insert Text