House Construction Scheduling Example

This document outlines a schedule for a construction project with key milestones including: - Pre-construction tasks from April-October 2023 including discussions with the client, budgeting, floor planning and permitting. - Site work from October-November 2023 including preparation, surveying and material stocking. - Substructure work from November 2023-January 2024 including foundation excavation, reinforcement and concrete work. - Superstructure work from January 2024-October 2024 including columns, brick walls, lintels, beams, slabs, plastering, painting and interior work.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
311 views8 pages

House Construction Scheduling Example

This document outlines a schedule for a construction project with key milestones including: - Pre-construction tasks from April-October 2023 including discussions with the client, budgeting, floor planning and permitting. - Site work from October-November 2023 including preparation, surveying and material stocking. - Substructure work from November 2023-January 2024 including foundation excavation, reinforcement and concrete work. - Superstructure work from January 2024-October 2024 including columns, brick walls, lintels, beams, slabs, plastering, painting and interior work.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 8

ID Task WBS Task Name Duration Start Finish Qtr 3, 2023 Qtr 4, 2023

Mode Aug Sep Oct


1 1 Pre-Construction 36 days Mon 04-09-23 Mon 23-10-23
2 1.1 Discussion with Client 1 day Mon 04-09-23 Mon 04-09-23
3 1.2 Budgeting Process 1 day Tue 05-09-23 Tue 05-09-23
4 1.3 Floor Plan 3 days Wed 06-09-23 Fri 08-09-23
5 1.4 Soil Testing 20 days Tue 05-09-23 Mon 02-10-23
6 1.5 Structural Plan 3 days Mon 11-09-23 Wed 13-09-23
7 1.6 Permits and approvals 15 days Tue 03-10-23 Mon 23-10-23
8 2 Site Inception 7 days Tue 24-10-23 Wed 01-11-23
9 2.1 Site Preparation 5 days Tue 24-10-23 Mon 30-10-23
10 2.2 Temporary Shed 1 day Tue 31-10-23 Tue 31-10-23
11 2.3 Surveying & Column Marking 1 day Wed 01-11-23 Wed 01-11-23
12 2.4 Material Stocking 1 day Wed 01-11-23 Wed 01-11-23
13 3 Sub-Structure 51 days Thu 02-11-23 Thu 11-01-24
14 3.1 Coumpound wall Excavation 3 days Thu 02-11-23 Mon 06-11-23
15 3.2 Foundation Excavation 4 days Thu 02-11-23 Tue 07-11-23
16 3.3 Sump & Septic Tank 4 days Thu 02-11-23 Tue 07-11-23
17 3.4 Shuttering 4 days Wed 08-11-23 Mon 13-11-23
18 3.5 Reinforcement 5 days Tue 14-11-23 Mon 20-11-23
19 3.6 Concreting 1 day Tue 21-11-23 Tue 21-11-23
20 3.7 Curing 21 days Wed 22-11-23 Wed 20-12-23
21 3.8 Plinth Wall 5 days Thu 21-12-23 Wed 27-12-23
22 3.9 Wall Curing 7 days Thu 28-12-23 Fri 05-01-24
23 3.10 Demoulding 0.5 days Thu 21-12-23 Thu 21-12-23

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: House Schedulling Assi
Summary Manual Summary Rollup Progress
Date: Mon 04-09-23
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 1
ID Task WBS Task Name Duration Start Finish Qtr 3, 2023 Qtr 4, 2023
Mode Aug Sep Oct
24 3.11 Plinth Filling and Compacting 4 days Mon 08-01-24 Thu 11-01-24
25 4 Super Structure 198 days Fri 12-01-24 Tue 15-10-24
26 4.1 Column upto Lintel 26.5 days Fri 12-01-24 Mon 19-02-24
27 4.1.1 Column Shuttering 2 days Fri 12-01-24 Mon 15-01-24
28 4.1.2 Reinforcement 2 days Tue 16-01-24 Wed 17-01-24
29 4.1.3 Concreting 1 day Thu 18-01-24 Thu 18-01-24
30 4.1.4 Curing 21 days Fri 19-01-24 Fri 16-02-24
31 4.1.5 Demoulding 0.5 days Mon 19-02-24 Mon 19-02-24
32 4.2 Brick Wall upto Lintel 37 days Fri 19-01-24 Mon 11-03-24
33 4.2.1 Brick laying 30 days Fri 19-01-24 Thu 29-02-24
34 4.2.2 Wall Curing 7 days Fri 01-03-24 Mon 11-03-24
35 4.3 Lintel 43 days Tue 12-03-24 Thu 09-05-24
36 4.3.1 Lintel Formwork 3 days Tue 12-03-24 Thu 14-03-24
37 4.3.2 Reinforcement 3 days Fri 15-03-24 Tue 19-03-24
38 4.3.3 Electrical Conduit Placing 1 day Wed 20-03-24 Wed 20-03-24
39 4.3.4 Concreting 1 day Thu 21-03-24 Thu 21-03-24
40 4.3.5 Curing 14 days Fri 22-03-24 Wed 10-04-24
41 4.3.6 Demoulding 0.5 days Thu 11-04-24 Thu 11-04-24
42 4.3.7 Brick Laying 7 days Thu 11-04-24 Fri 19-04-24
43 4.3.8 Curing 14 days Mon 22-04-24 Thu 09-05-24
44 4.4 Beam and Slab 29 days Fri 10-05-24 Wed 19-06-24
45 4.4.1 Formwork 3 days Fri 10-05-24 Tue 14-05-24
46 4.4.2 Reinforcement 3 days Wed 15-05-24 Fri 17-05-24

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: House Schedulling Assi
Summary Manual Summary Rollup Progress
Date: Mon 04-09-23
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 2
ID Task WBS Task Name Duration Start Finish Qtr 3, 2023 Qtr 4, 2023
Mode Aug Sep Oct
47 4.4.3 Electrical Conduit Placing 1 day Mon 20-05-24 Mon 20-05-24
48 4.4.4 Concreting 1 day Tue 21-05-24 Tue 21-05-24
49 4.4.5 Curing 14 days Wed 22-05-24 Mon 10-06-24
50 4.4.6 Demoulding 0.5 days Tue 11-06-24 Tue 11-06-24
51 4.4.7 Parapet wall 3 days Tue 11-06-24 Thu 13-06-24
52 4.4.8 Terrace Flooring 4 days Fri 14-06-24 Wed 19-06-24
53 4.5 Exterior 42 days Thu 20-06-24 Fri 16-08-24
54 4.5.1 Plastering 20 days Thu 20-06-24 Wed 17-07-24
55 4.5.2 Curing 7 days Thu 18-07-24 Fri 26-07-24
56 4.5.3 Putty & Painting 15 days Mon 29-07-24 Fri 16-08-24
57 4.6 Interior 91 days Tue 11-06-24 Tue 15-10-24
58 4.6.1 Plumbing 12 days Tue 11-06-24 Wed 26-06-24
59 4.6.2 Electrical Works 15 days Thu 27-06-24 Wed 17-07-24
60 4.6.3 Doors & Windows 15 days Thu 18-07-24 Wed 07-08-24
61 4.6.4 Interior Plastering 10 days Thu 08-08-24 Wed 21-08-24
62 4.6.5 Curing 7 days Thu 22-08-24 Fri 30-08-24
63 4.6.6 Putty & Painting 15 days Mon 02-09-24 Fri 20-09-24
64 4.6.7 Flooring 10 days Mon 23-09-24 Fri 04-10-24
65 4.6.8 Fixtures & Appliances 7 days Mon 07-10-24 Tue 15-10-24
66 5 Landscape & Exterior Aspects 7 days Mon 19-08-24 Tue 27-08-24
67 5.1 Pathway & Driveway 4 days Mon 19-08-24 Thu 22-08-24
68 5.2 Planting 1 day Mon 19-08-24 Mon 19-08-24
69 5.3 Final Inspection 2 days Fri 23-08-24 Mon 26-08-24

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: House Schedulling Assi
Summary Manual Summary Rollup Progress
Date: Mon 04-09-23
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 3
ID Task WBS Task Name Duration Start Finish Qtr 3, 2023 Qtr 4, 2023
Mode Aug Sep Oct
70 5.4 Handing Over 1 day Tue 27-08-24 Tue 27-08-24

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: House Schedulling Assi
Summary Manual Summary Rollup Progress
Date: Mon 04-09-23
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 4
Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: House Schedulling Assi
Summary Manual Summary Rollup Progress
Date: Mon 04-09-23
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 5
Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: House Schedulling Assi
Summary Manual Summary Rollup Progress
Date: Mon 04-09-23
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 6
Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: House Schedulling Assi
Summary Manual Summary Rollup Progress
Date: Mon 04-09-23
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 7
Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: House Schedulling Assi
Summary Manual Summary Rollup Progress
Date: Mon 04-09-23
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 8