House Construction Scheduling Example
House Construction Scheduling Example
Page 1
ID Task WBS Task Name Duration Start Finish Qtr 3, 2023 Qtr 4, 2023
Mode Aug Sep Oct
24 3.11 Plinth Filling and Compacting 4 days Mon 08-01-24 Thu 11-01-24
25 4 Super Structure 198 days Fri 12-01-24 Tue 15-10-24
26 4.1 Column upto Lintel 26.5 days Fri 12-01-24 Mon 19-02-24
27 4.1.1 Column Shuttering 2 days Fri 12-01-24 Mon 15-01-24
28 4.1.2 Reinforcement 2 days Tue 16-01-24 Wed 17-01-24
29 4.1.3 Concreting 1 day Thu 18-01-24 Thu 18-01-24
30 4.1.4 Curing 21 days Fri 19-01-24 Fri 16-02-24
31 4.1.5 Demoulding 0.5 days Mon 19-02-24 Mon 19-02-24
32 4.2 Brick Wall upto Lintel 37 days Fri 19-01-24 Mon 11-03-24
33 4.2.1 Brick laying 30 days Fri 19-01-24 Thu 29-02-24
34 4.2.2 Wall Curing 7 days Fri 01-03-24 Mon 11-03-24
35 4.3 Lintel 43 days Tue 12-03-24 Thu 09-05-24
36 4.3.1 Lintel Formwork 3 days Tue 12-03-24 Thu 14-03-24
37 4.3.2 Reinforcement 3 days Fri 15-03-24 Tue 19-03-24
38 4.3.3 Electrical Conduit Placing 1 day Wed 20-03-24 Wed 20-03-24
39 4.3.4 Concreting 1 day Thu 21-03-24 Thu 21-03-24
40 4.3.5 Curing 14 days Fri 22-03-24 Wed 10-04-24
41 4.3.6 Demoulding 0.5 days Thu 11-04-24 Thu 11-04-24
42 4.3.7 Brick Laying 7 days Thu 11-04-24 Fri 19-04-24
43 4.3.8 Curing 14 days Mon 22-04-24 Thu 09-05-24
44 4.4 Beam and Slab 29 days Fri 10-05-24 Wed 19-06-24
45 4.4.1 Formwork 3 days Fri 10-05-24 Tue 14-05-24
46 4.4.2 Reinforcement 3 days Wed 15-05-24 Fri 17-05-24
Page 2
ID Task WBS Task Name Duration Start Finish Qtr 3, 2023 Qtr 4, 2023
Mode Aug Sep Oct
47 4.4.3 Electrical Conduit Placing 1 day Mon 20-05-24 Mon 20-05-24
48 4.4.4 Concreting 1 day Tue 21-05-24 Tue 21-05-24
49 4.4.5 Curing 14 days Wed 22-05-24 Mon 10-06-24
50 4.4.6 Demoulding 0.5 days Tue 11-06-24 Tue 11-06-24
51 4.4.7 Parapet wall 3 days Tue 11-06-24 Thu 13-06-24
52 4.4.8 Terrace Flooring 4 days Fri 14-06-24 Wed 19-06-24
53 4.5 Exterior 42 days Thu 20-06-24 Fri 16-08-24
54 4.5.1 Plastering 20 days Thu 20-06-24 Wed 17-07-24
55 4.5.2 Curing 7 days Thu 18-07-24 Fri 26-07-24
56 4.5.3 Putty & Painting 15 days Mon 29-07-24 Fri 16-08-24
57 4.6 Interior 91 days Tue 11-06-24 Tue 15-10-24
58 4.6.1 Plumbing 12 days Tue 11-06-24 Wed 26-06-24
59 4.6.2 Electrical Works 15 days Thu 27-06-24 Wed 17-07-24
60 4.6.3 Doors & Windows 15 days Thu 18-07-24 Wed 07-08-24
61 4.6.4 Interior Plastering 10 days Thu 08-08-24 Wed 21-08-24
62 4.6.5 Curing 7 days Thu 22-08-24 Fri 30-08-24
63 4.6.6 Putty & Painting 15 days Mon 02-09-24 Fri 20-09-24
64 4.6.7 Flooring 10 days Mon 23-09-24 Fri 04-10-24
65 4.6.8 Fixtures & Appliances 7 days Mon 07-10-24 Tue 15-10-24
66 5 Landscape & Exterior Aspects 7 days Mon 19-08-24 Tue 27-08-24
67 5.1 Pathway & Driveway 4 days Mon 19-08-24 Thu 22-08-24
68 5.2 Planting 1 day Mon 19-08-24 Mon 19-08-24
69 5.3 Final Inspection 2 days Fri 23-08-24 Mon 26-08-24
Page 3
ID Task WBS Task Name Duration Start Finish Qtr 3, 2023 Qtr 4, 2023
Mode Aug Sep Oct
70 5.4 Handing Over 1 day Tue 27-08-24 Tue 27-08-24
Page 4
Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Page 5
Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Page 6
Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Page 7
Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Page 8