Natf Reference Document Reporting and Verification of Generating Unit Reactive Power Capability For Synchronous Machines
Natf Reference Document Reporting and Verification of Generating Unit Reactive Power Capability For Synchronous Machines
Disclaimer
This document was created by the North American Transmission Forum (NATF) to facilitate
industry work to improve the reporting and verification of generating unit reactive power
capability for synchronous machines. NATF reserves the right to make changes to the information
contained herein without notice. No liability is assumed for any damages arising directly or
indirectly by their use or application. The information provided in this document is provided on an
“as is” basis. “North American Transmission Forum” and its associated logo are trademarks of
NATF. Other product and brand names may be trademarks of their respective owners. Copyright
2015. All rights reserved. This legend should not be removed from the document.
Open Distribution
Copyright © 2015 North American Transmission Forum. Not for sale or commercial use. All rights reserved.
Open Distribution
Table of Contents
Section 1. Generating Unit Reactive Power Capability Modeling Reference Document Scope….…3
Section 3. Determination of Generating Unit Reactive Power Limits for Use in Transmission
System Models…….…………………………………………………………………………………………….………5
Revisions
Date Versions Notes
04/30/2015 2015-1 Original Version
Modeling Reference Document - Reporting and Verification of Generating Unit Reactive Power
Capability for Synchronous Machines
Page 2
Open Distribution
Note 2: This Reference Document uses the term ‘Generator Entity’ to refer to both the Generator
Owner and Generator Operator. Depending on how a particular company is organized,
responsibilities may be assigned to either the Generator Owner or Generator Operator.
Note 3: This Reference Document does not create binding norms, establish mandatory reliability
standards or create parameters by which compliance with Reliability Standards are monitored or
enforced. In addition, this Reference Document is not intended to take precedence over any
regional procedure. It is recognized that individual Generator Owners and Transmission Owners
may use alternative and/or more specific approaches that they may deem more appropriate for
their generators and transmission systems.
It is important to recognize that the “generator” reactive power capability curve only represents the
capability of the electrical generator itself. The manufacturer generator reactive power capability
curve or D-curve does not take into account: a) the design of the auxiliary power system and its
coordination with the generator terminal voltage; b) the GSU transformer electrical characteristics;
c) the strength of the transmission system to which the generator is connected; d) the transmission
operating voltage and coordination with the GSU transformer tap setting; and e) generator
protection system settings. These five factors will affect the “generating unit” reactive power
capability. The distinction between the “Generator” reactive power capability and the “Generating
Unit” reactive power capability must be understood, evaluated and reported so the generating unit
can be modelled correctly in Transmission Operations and Planning studies. For additional
information on this concept see Appendix A: Understanding Generator and Generating Unit
Reactive Power Capability.
In addition to the above considerations, Generating Unit reactive power factor requirements are
generally governed by the Interconnection Agreement between the Generator Entity and the
Transmission Owner/Operator. These Interconnection Agreement requirements often define a
narrower band or range within a generating unit’s rated capability curves.
Transmission planners and operators use models of generating units as part of their responsibility
to ensure reliable and economic operation of the grid. Most present network analysis tools use
fairly simple representations to depict each unit’s reactive power capabilities at fixed minimum and
maximum reactive power limits. The lagging and leading generator reactive power capability
available to the transmission system is specific to each unit and can vary significantly based on
numerous factors. These simple representations do not typically take into account key variables
such as transmission system voltage, generator and auxiliary bus voltages, transformer tap settings,
MW output level, the impacts of excitation system controls and limiters, effects of cooling provided
by variable hydrogen pressure, ambient air, etc.
Modeling Reference Document - Reporting and Verification of Generating Unit Reactive Power
Capability for Synchronous Machines
Page 3
Open Distribution
Staged reactive power tests have been used to verify and document a generating unit’s reactive
power capability. It is important to recognize that the test results are representative of each unit’s
reactive power capability for the prevailing conditions at the time of the test. The same unit may
have significantly more or less reactive power capability under different operating conditions.
Therefore, tests performed under a single set of conditions may not be adequate to provide the full
picture of a unit’s reactive power capability. Consequently, the tests may result in reduced reactive
power capability in comparison to the actual reactive power capability achievable under different
sets of conditions.
Presently, there is no consistent, industry-wide approach for ensuring that generator voltage and
reactive power limits are determined and reported appropriately for use in the various types of
steady-state studies performed. Developing a reference document for verification and reporting of
generating unit reactive power capability for steady state studies performed by transmission
planning and operations has been identified by the North American Transmission Forum’s
Modeling Practices Group (NATF MPG) as a high priority initiative. The NATF Modeling Practices
Group’s (MPG) Generator Reactive Modeling Working Group (GRWG) reviewed the major factors
affecting the ability of a generating unit to produce lagging and leading reactive power. From this
review, the group is providing information for help in determining, verifying, reporting, and
modeling generating unit reactive power capabilities and associated limitations for use in steady-
state evaluations of Bulk Electric System (BES).
The reactive power limits used in the transmission planning and transmission operations power
flow simulations should be based upon the “Generating Unit” reactive power capability rather than
the “Generator” reactive power capability. An understanding of and distinction between
“Generator” and “Generating Unit” reactive power capability is provided in Appendix A:
Understanding Generator and Generating Unit Reactive Power Capability.
With proper coordination and data sharing, appropriate “Generating Unit” reactive limits can be
determined via simulations performed by the Generator Entity and/or the Transmission Planner.
The steps recommended for determining “Generating Unit” reactive limits are discussed in Section
3: Determination of Generating Unit Reactive Limits for Use in Transmission System Models.
Implementation of these limits, i.e. using them as a guideline for operation of generators or making
them mandatory, is a separate matter, however. Therefore, it is recommended that there be a joint
review of these limits between the Transmission Entity and the Generator Entity prior to their use.
On-Line unit performance should be reviewed and used to help validate the “Generating Unit”
reactive power limits and the models developed in Section 3. Validation can be based upon
Modeling Reference Document - Reporting and Verification of Generating Unit Reactive Power
Capability for Synchronous Machines
Page 4
Open Distribution
operational history data or staged-testing. These approaches are discussed in Section 4: Validation
of Generating Unit Reactive Power Capability. The test results or operational data can be compared
to the results obtained in Section 3 to refine the “Generating Unit” model and reactive power limits
to be used in the transmission planning and transmission operations power flow simulations.
Modeling of generator reactive power capability is important for various types of power flow (also
known as load flow) studies. Power flow analysis is performed for different objectives and with
various time horizons. An introduction to reactive power capability modeling and differences
between real-time operations, operational planning, and long-term planning studies is provided in
Appendix E: Transmission Study Horizons. While there should be consistency in modeling of
generating unit reactive power limits within certain types of studies, e.g. operations versus mid-
and long-range planning, the most suitable generating unit representation could vary e.g.,
consistent with expected voltage deviations from generator voltage schedules. Operations studies
may be performed in an intentionally conservative manner whereas planning studies with light or
heavy loads or with multiple overlapping contingencies could be performed with generating unit
reactive power capabilities expected with higher or lower transmission grid voltages than those
experienced during normal system conditions.
Transmission Entities perform a variety of operating and planning studies (See Appendix E for
additional discussion) and the representation of the generating unit varies in the different models
(See Appendix F: Representation of Generators in Power Flow models for additional discussion).
Transmission Entities need the generating unit reactive power capability limits at the generator
terminals and the point of interconnection to be provided in a consistent format so that they can
select appropriate limits to be modeled in their planning and operating studies over a range of
transmission system operating conditions including voltages. It is suggested that the limits be
developed following the approach outlined in this document and communicated, as necessary, on
both a generator capability curve (D-curve) as well as in a tabular format as described in Section
3.1, step 5, part 2.
Note: The reference document does not provide a “one size fits all” approach to methods
for determining “generating unit reactive power capability.” It does, however, provide
various methods for obtaining generator and generating unit limits that can be factored
into the Transmission modeling process. Examples of current processes from Forum
members are provided. The goal is to ensure that generating unit reactive power limits
are determined and reported appropriately for use in various types of transmission
system studies.
Modeling Reference Document - Reporting and Verification of Generating Unit Reactive Power
Capability for Synchronous Machines
Page 5
Open Distribution
Section 3.2 describes the modeling that could be performed by the Transmission Planner
and the data necessary from the Generator Entity.
Modeling Reference Document - Reporting and Verification of Generating Unit Reactive Power
Capability for Synchronous Machines
Page 6
Open Distribution
The following are the basic model components needed for a comprehensive study. Determination
of the specific station auxiliary system components to be modeled explicitly depend upon the
specific unit design and configuration being modeled. Typically, the model should include each
medium voltage bus along with low voltage buses whose operating voltage limits can potentially
limit the generator operating terminal voltage range.
• Generator (See the D-curve plot below (Figure 1) for this example)
Modeling Reference Document - Reporting and Verification of Generating Unit Reactive Power
Capability for Synchronous Machines
Page 7
Open Distribution
– MVAR production limits from D-curve (consider margins, voltage impact, tolerances) at
full (maximum) and minimum generator gross load
– MVAR absorption limits from Minimum Excitation Limiter settings (consider margins,
voltage impact, tolerances) at full (maximum) and minimum generator gross load
– Review Over Excitation Limiter (OEL), Field Current Limiter, Volts per Hertz (V/Hz),
armature (stator) current limiter, other limiter settings or alarms that could potentially
limit operation within the Generator reactive power capability curve or operating
voltage range
– Factor in other known reactive power limitations (ex: generator cooling, H2 pressure,
vibration, de-rated rotor, derated GSU transformer, generator bus derating, etc.)
Figure 1
Note that equipment problems and/or reductions in equipment ratings that cause VAR limitations
should be documented and reported for consideration of impacts to Operating and Planning
models (ex: turbine-generator vibration, de-rated generator rotor, generator or transformer cooler
degradation, bus connection hot spots or cooler issues).
Below (Figure 2) is an example of a power flow model developed for a typical fossil unit:
Figure 2
Note the foregoing model includes explicit representations of the generator, GSU transformer, unit
auxiliary transformers, medium voltage buses, medium to low voltage station service transformers,
and low voltage buses. The model also includes equivalents of the unit medium and low voltage bus
loads and the transmission system at the point of interconnection.
Scheduling of any tests should first be coordinated with the Transmission Operator. Data needed
for validation of the power flow model can include the following:
• Transmission System Bus Voltage (high side GSU voltage) at the time of the test or
operating data capture/snapshot
• Generator Voltage, MW, MVAR (or PF)
• Station Auxiliary Bus MW, MVAR (or Amp and PF) Load. This information may not be
readily available in some cases, especially for LV systems*
• Station Auxiliary Bus Voltages (This would include the medium voltage buses and low
voltage buses (575 V, 480 V). This information may not be readily available in some cases,
especially for LV systems *
* This information can often be obtained by field readings using available instrumentation.
If instrumentation is not available, reasonable estimates can be made based on reviews of
bus one line diagrams and discussions with plant operations staff.
All data should be taken/captured at the same time whether during a test or from a review and use
of operational data.
The following additional data can also be useful for comparisons with equipment design ratings
when reviewing for potential limitations that are not directly represented in the electrical power
flow simulations:
• Generator Field Amps, Field Volts, Field Temperatures
• Generator Cooling Parameters (H2 Pressure, Inlet Water/Air Temp, Stator Winding Temp,
etc. as applicable)
• GSU transformer winding and oil temperatures
• Ambient temperature
For historical operational data obtained, the transmission system voltage will typically be at or
near schedule. Transmission Operators will assist in determining the amount of voltage variation
that is acceptable. When scheduling tests or selecting operational data, the seasons and times of
day that are conducive to the required reactive power capabilities should be considered. It is
recommended to obtain at least two sets of data. The following are suggestions for a typical fossil
unit:
Set 1 – Typical high MVAR production with unit operating at or near normal full load MW.
Set 2 – Typical high MVAR absorption with unit operating at or near minimum stable MW load.
Note: This same Methodology is used for nuclear plant safe shutdown capability verification.
The NRC established the precedent for this method in Degraded Grid electrical system studies.
To illustrate, below (Figure 3) is a power flow model validation simulation for an example
sample fossil unit, as well as a table (Figure 4) that compares the model calculated results
versus operational data taken.
Figure 3
Modeling Reference Document - Reporting and Verification of Generating Unit Reactive Power
Capability for Synchronous Machines
Page 11
Open Distribution
Figure 4
Note that the generator and station auxiliary bus loads were adjusted to closely match the loads
from the field data. The model is validated if the calculated voltages from the power flow results
closely match the corresponding voltages from the field data.
Modeling Reference Document - Reporting and Verification of Generating Unit Reactive Power
Capability for Synchronous Machines
Page 12
Open Distribution
Figure 5
Figure 6
Modeling Reference Document - Reporting and Verification of Generating Unit Reactive Power
Capability for Synchronous Machines
Page 13
Open Distribution
Figure 7
Modeling Reference Document - Reporting and Verification of Generating Unit Reactive Power
Capability for Synchronous Machines
Page 14
Open Distribution
Figure 8
1. Determine Reactive Power Limits for Generator Full Load (Maximum) Gross MW and
Generator Minimum Gross MW
It is recommended that the Generating Unit reactive power capabilities be determined at the
following four points as a minimum:
Leading (absorbing) reactive power capability at normal full generator gross MW load;
Lagging (producing) reactive power capabilities at normal full generator gross MW load;
Leading (absorbing) reactive power capability at normal minimum generator gross MW
load;
Lagging (producing) reactive power capability at normal minimum generator gross MW
load.
Since a generating unit’s reactive power capabilities vary depending on unit and system
operating conditions, the Generator Entity should coordinate with the Transmission Planner to
establish the specific conditions or range of conditions for which these unit reactive power limit
points need to be determined. If the Transmission Planner does not specify the transmission
system voltages to be used, then at a minimum, it is recommended to determine reactive power
capabilities with the transmission system voltage at a realistic value.
That is, the system voltage should be between the TP’s min-allowed and specified values for
max–lagging tests, and between the max-allowed and specified values for max–leading tests.
This is opposite the direction naturally occurring during tests; MVAR export drives system
voltages higher, and MVAR import makes voltages lower. This tendency can be counteracted to
some degree by operating generators in a push-pull fashion, i.e. taking not-tested units to min
Modeling Reference Document - Reporting and Verification of Generating Unit Reactive Power
Capability for Synchronous Machines
Page 15
Open Distribution
MVAR when the tested until is at max MVAR, and vice versa. Some participation by the TOP will
be needed to attain the above-stated goal, however, by coordinating push-pull at other plants in
the area or manipulating transmission system capacitor banks, reactors, static VAR
compensators or load tap changers.
If the generating unit reactive power capability limits are less than indicated by the D curve,
additional simulations can be performed to determine the unit reactive power limits at other
transmission system voltages. If the Transmission Planner does not prescribe specific voltages
for the sensitivity analyses, the Generator Entity can perform additional simulations at
transmission voltages that produce generating unit reactive power limits that are comparable
to the limits indicated by the D curve. Additional leading (absorbing) reactive power capability
simulations should be performed for higher transmission voltages and additional lagging
(producing) reactive power capability simulations should be performed for lower transmission
voltages. These power flow simulations must demonstrate that generator and auxiliary bus
voltages remain within acceptable limits at the leading and lagging reactive power limits. It
must also be determined that the model captures the reason for less-than-D-curve test results
well enough that the other-voltage results can be relied-upon.
As an illustration:
For the typical unit the SS trend data along with field data recorded for the validation cases
were used to estimate SS bus loadings (MW & PF) for determining the unit’s reactive power
capabilities at summer full load MW operation using the validated load flow model.
The following power flow simulations evaluate the generating unit reactive power capabilities
for lagging (Figure 9) and leading (Figure 10) PF operation at transmission bus voltage
conditions prescribed by the Transmission Planner.
Modeling Reference Document - Reporting and Verification of Generating Unit Reactive Power
Capability for Synchronous Machines
Page 16
Open Distribution
Figure 9
Modeling Reference Document - Reporting and Verification of Generating Unit Reactive Power
Capability for Synchronous Machines
Page 17
Open Distribution
Figure 10
For the example unit, SS trend data along with field data recorded for the validation cases were
also used to estimate SS bus loadings (MW & PF) for determining the unit’s reactive power
capabilities at minimum load MW operation using the validated power flow model. The
following power flow simulations evaluate the unit reactive power capabilities for lagging
(Figure 11) and leading (Figure 12) PF operation at transmission bus voltage conditions
prescribed by the Transmission Planner in this instance:
Modeling Reference Document - Reporting and Verification of Generating Unit Reactive Power
Capability for Synchronous Machines
Page 18
Open Distribution
Figure 11
Figure 12
Modeling Reference Document - Reporting and Verification of Generating Unit Reactive Power
Capability for Synchronous Machines
Page 19
Open Distribution
Thus, by determining and reporting the calculated generator voltage limits above, the Generator
Entity is providing additional useful information to the TP/TOP/RC. Otherwise, they may assume
this generating unit is able to operate at a generator terminal voltage range of 95-105%. It
should be noted that generating unit operators typically monitor equipment voltage limits and
receive alarms if these limits are exceeded. The typical operator response is to adjust the
generator terminal voltage up or down, as appropriate, until the alarm is cleared.
Modeling Reference Document - Reporting and Verification of Generating Unit Reactive Power
Capability for Synchronous Machines
Page 20
Open Distribution
near-term impacts on the transmission system can be determined (Refer to NERC Standard
VAR-002-3). Limitations that are determined to be long term in nature should also be reported
to the Transmission Planner so the Transmission Planner can factor the generator unit reactive
power capability into Transmission Planning studies as appropriate.
2. Transmit Results to TP/RC
The Gross and Net Reactive Power Capability should be reported. The generator upper and
lower terminal voltage limits (discussed in Step 4) should also be reported, especially if the
generator is unable to operate over its full rated generator terminal voltage range of 95-105%.
The data may be reported to the Transmission Planner in a standard format. Results for the
example unit are summarized below in a format (Figures 13 and 14) for reporting to Plant
Operations Staff and Transmission Planning. The specific format can vary. However, the
specific report format may have to meet MOD-025 and applicable Regional criteria when
reporting results to Transmission Planning).
Figure 13
Modeling Reference Document - Reporting and Verification of Generating Unit Reactive Power
Capability for Synchronous Machines
Page 21
Open Distribution
Figure 14
It is recommended to also report the results in the D-curve format (Figure 15).
Modeling Reference Document - Reporting and Verification of Generating Unit Reactive Power
Capability for Synchronous Machines
Page 22
Open Distribution
Figure 15
A simplified power flow model developed for a coal-fired generating unit with two
UATs is shown below (Figure 16).
Modeling Reference Document - Reporting and Verification of Generating Unit Reactive Power
Capability for Synchronous Machines
Page 23
Open Distribution
Figure 16
Step 3 - Perform Simulations to determine Reactive Power Capability Limits due to Voltage
Constraints
The objective is to determine and provide reactive power limits throughout the MW output
range of the generator and throughout an appropriate range of transmission voltages. It is
recommended that the Generating Unit reactive power capabilities be determined at the
following four points as a minimum:
Leading (absorbing) reactive power capability at full generator gross MW load
Lagging (producing) reactive power capabilities at full generator gross MW load
Leading (absorbing) reactive power capability at minimum generator gross MW load
Lagging (producing) reactive power capability at minimum generator gross MW load
It is recommended to determine the generating unit reactive power capability limits with the
transmission system voltage at the scheduled value. If the generating unit reactive power
capability limits are less than indicated by the D curve, additional simulations can be performed
to determine the unit reactive power limits at other transmission system voltages. If the
Transmission Planner does not have prescribed voltages for the sensitivity analyses, they can
perform additional simulations at transmission voltages that produce generating unit reactive
power limits that are comparable to the limits indicated by the D curve. Additional leading
(absorbing) reactive power capability simulations should be performed for higher transmission
voltages and additional lagging (producing) reactive power capability simulations should be
performed for lower transmission voltages. These power flow simulations must demonstrate
that generator and auxiliary bus voltages remain within acceptable limits at the leading and
lagging reactive power limits.
To perform the necessary simulations, you need the following information from the Generator
Entity:
Generator maximum and minimum gross MW capabilities/limits
Unit Auxiliary load (MW and MVAR) at each UAT connection
Unit Auxiliary load may vary based upon MW output and unit auxiliary bus
voltages. More accurate results will be obtained if this dependency is
included in the simulations
Generator and Unit Auxiliary Bus Voltage Ratings and Operating Limits
The generator and unit auxiliary bus voltage limits modeled should include
any constraints imposed by operating limits of all down-stream lower
voltage equipment
Modeling Reference Document - Reporting and Verification of Generating Unit Reactive Power
Capability for Synchronous Machines
Page 25
Open Distribution
NERC standard VAR-002 requires that most generators be provided a voltage schedule to follow.
When transmission voltage is at the schedule value, the generator may be operating in either the
leading or lagging region.
1. Set Transmission Voltage at the Scheduled Transmission Voltage
– Set the generator output at the maximum gross MW output value
• Adjust generator MVAR output to determine the maximum reactive power
limit
• Adjust generator MVAR output to determine the minimum reactive power
limit
– Set the generator output at the minimum gross MW output value
• Adjust generator MVAR output to determine the maximum reactive power
limit
• Adjust generator MVAR output to determine the minimum reactive power
limit
When the transmission voltage is above the scheduled value, the generator should be operating in
the leading region, i.e. absorbing reactive power.
2. Set Transmission Voltage at a higher voltage*
– Set the generator output at the maximum gross MW output value
• Adjust generator MVAR output to determine the minimum reactive power
limit
– Set the generator output at the minimum gross MW output value
• Adjust generator MVAR output to determine the minimum reactive power
limit
When the transmission voltage is below the scheduled value, the generator should be operating in
the lagging region, i.e. producing reactive power.
3. Set Transmission Voltage at a lower voltage*
– Set the generator output at the maximum gross output value
• Adjust generator MVAR output to determine the maximum reactive power
limit
– Set the generator output at the minimum gross output value
• Adjust generator MVAR output to determine the maximum reactive power
limit
*The transmission high and low voltages selected for the simulation should provide reactive power
limits near the generators D-curve limits.
The results from the simulations for this generator are summarized below and shown below on the
D-curve: This 13.8 kV generator includes two 2.4 kV auxiliary buses (Note: Vg on the diagram
Modeling Reference Document - Reporting and Verification of Generating Unit Reactive Power
Capability for Synchronous Machines
Page 26
Open Distribution
identifies reactive power limits that are constrained by generator terminal voltage limits. Va on the
diagram identifies reactive power limits that are constrained by auxiliary bus voltage limits.). The
generator terminal voltage limits are +/- 5% of the nominal generator voltage and the allowable
auxiliary bus voltage range is 2,160 V - 2,530 V because of the 2,300 V motors connected to the
buses. The applicable voltage limits must be obtained from the Generator Entity and the auxiliary
medium voltage limits should consider the limitations of the downstream equipment. The reactive
power output in this simulation is limited to 45.55 MVAR or less because of high voltage on the AUX
3B bus.
The sensitivity of the maximum and minimum reactive power limits at various transmission voltage
levels can be determined through a series of simulations. The maximum and minimum reactive
power limits were determined for this generator with the transmission system at 141 kV (the
target scheduled value). The maximum was also determined with the transmission system voltage
lowered to 139 kV and the minimum was also determined with the transmission system voltage
increased to 144.9 kV (1.05 pu). The reactive power limits at the three selected transmission
voltages are shown on the generator D-curve below (Figure 17).
Modeling Reference Document - Reporting and Verification of Generating Unit Reactive Power
Capability for Synchronous Machines
Page 27
Open Distribution
Figure 17
The voltage sensitivity shows that the ability of the generating unit to regulate transmission voltage
improves when the transmission voltage deviates from the schedule. Therefore, setting Qmax and
Qmin in the power flow model at the 141 kV schedule limits would be conservative and would
provide pessimistic results when the transmission system voltage is different (higher or lower)
than the scheduled value.
Modeling Reference Document - Reporting and Verification of Generating Unit Reactive Power
Capability for Synchronous Machines
Page 28
Open Distribution
General
The Gross and Net Reactive Power Capability for generating units should be validated initially
upon commissioning. The Gross and Net Reactive Power Capability should be reviewed and
revalidated if warranted whenever there is a long term plant configuration change, following a
major equipment modification, following changes in GSU transformer and/or station auxiliary
transformer tap settings, following changes to the transmission system at or near the generating
unit Point of Interconnection to the transmission grid, or as agreed to by the Transmission
Provider and Generator Entity. Periodic re-validation is required by NERC in MOD-025-2.
Specific schedules and validation method must satisfy NERC and applicable Regional criteria.
The Transmission Provider should provide each Generator Entity with the applicable MVAR
limits used in the current Transmission Planning models to aid the Generator Entity in
establishing “expected” capabilities for the Generator Entity’s validation efforts.
The Gross and Net Reactive Power Capability (MVAR) should be validated at the gross continuous
full load MW capability and the minimum gross MW load at which the generating unit is normally
expected to operate. Reactive power capability determination should be coordinated between
the Generator Entity and Planning Coordinator and/or Transmission Planner, as appropriate.
The Gross and Net Reactive Power Capability should be validated with the unit operated with all
regularly used auxiliary equipment needed for normal unit operation in service.
Reactive power consumption by auxiliary facilities common among several units or an entire
plant (for example, coal-handling or lighting) should be recorded and be prorated among the
appropriate units as agreed between the Generator Entity and Planning Coordinator and/or
Transmission Planner, as appropriate.
Discretion may be necessary when estimating station service for small, unmanned hydro and
internal combustion stations, where station service may not be accurately metered and/or
recorded on an hourly basis.
The Gross and Net Reactive Power Capability should be determined separately for each
generating unit in a power plant if the maximum net output of each unit is independent of the
others. Two (2) or more units in a single station and/or two (2) or more stations whose
capability is limited by common elements and/or commonly assigned staff should have their
capabilities determined recognizing the limitation of those common elements [e.g., staffing, steam
headers, stacks and other boiler auxiliaries, condenser cooling equipment (e.g., spray modules,
pumps, screens, inlets, discharge canals, cooling towers), common river flows, head and tailrace
Modeling Reference Document - Reporting and Verification of Generating Unit Reactive Power
Capability for Synchronous Machines
Page 29
Open Distribution
water levels, common penstock, watershed, etc.]. This includes combined cycle units. This also
includes unit configurations where multiple generators share a common 2-winding GSU
transformer. Each unit should be assigned a rating by apportioning the combined plant(s)
capability among the affected units.
4.1 Methods
Validations of reactive power capabilities of generating units have been attempted using the
following methods:
Staged unit reactive power capability testing
Documentation and review of unit operational history data
The intent of this reference document is not to promote a particular method. Instead the goal is
to identify merits and limitations of each method to help identify best practices that will yield
confidence in the reactive power capability information used in planning and operational studies.
Modeling Reference Document - Reporting and Verification of Generating Unit Reactive Power
Capability for Synchronous Machines
Page 30
Open Distribution
to cause max-lagging tests to occur at high voltage and max-leading at low voltage, i.e. opposite
the situation for actual voltage control, which may not constitute a credible verification of
reactive power resources during the test period.
Reliable communication should be established and maintained between the Generator Operators,
Transmission Operators, and others as needed for the test duration.
The AVR and PSS, as applicable, should be in service for the unit being tested and adjacent units in
the same plant. The Transmission Operator should confirm the AVRs and PSSs are in service for
other units as appropriate.
Overexcited reactive power capability validation should be conducted for a minimum of one hour.
Data should be recorded for the duration (15 minute intervals minimum recommended) and at
completion of the test.
Data for the under excited reactive power capability validation may be recorded as soon as a limit
is encountered.
Steady real and reactive power output should be maintained during the data collection intervals.
For hydrogen-cooled generators, the hydrogen pressure should be at the maximum normal
operating pressure. If the maximum design hydrogen pressure cannot be achieved, then the
reason for this condition should be documented and the appropriate Generator Capability Curve
should be used.
If the full reactive power capability available for grid voltage support cannot be demonstrated
during testing, additional engineering evaluation as described in Sections 3.1 and 3.2 can be used
to verify expected reactive power capabilities are achievable.
Recording of Test Data
The following are typical test data that should be recorded:
1. Date of test, test start and test end times, and times each data set is taken.
2. Voltage schedule provided by the Transmission Operator, if applicable.
3. System interconnection bus actual kV.
4. GSU transformer high voltage winding kV (if significantly different from Item 3) and
output in MW and MVAR (or Amps and PF), if available.
5. GSU transformer winding and oil temperatures.
6. Generator gross kV, MW, MVAR (@ generator terminals) and applicable operating voltage
limitation.
7. Generator field current and voltage.
8. Exciter field current and voltage, where applicable.
9. Generator bus fed (power potential transformer) excitation system loading in MW and
MVAR (or Amps and PF), where applicable.
10. Each medium voltage station auxiliary bus kV and load in MW and MVAR (or Amps and
PF) and applicable operating voltage limitation.
11. Each instrumented 480 V and/or 600 V station auxiliary bus kV and load in MW and
MVAR (or Amps and PF) that may limit the overall unit capability.
12. Ambient air temperature and humidity.
13. Generator cooling parameters as applicable:
a. Stator winding temperatures
b. Rotor or field winding temperature.
c. H2 pressure for hydrogen cooled generators.
Modeling Reference Document - Reporting and Verification of Generating Unit Reactive Power
Capability for Synchronous Machines
Page 32
Open Distribution
Modeling Reference Document - Reporting and Verification of Generating Unit Reactive Power
Capability for Synchronous Machines
Page 33
Open Distribution
Aux system voltage limitations and the load (MW and MVAR) expected at the
two operating points (Some Planners ask for linearization constants relating
gross to net MWs)
b. The Planner or Generator Entity should obtain operating data with the generating
unit operating as close as possible to the planning cases to be reviewed including:
Generator MW, MVAR, Voltage
High Side of GSU MW and MVAR and Grid Voltage
Aux System Bus MW, MVAR and voltage (both the medium and low voltage
systems should be considered; e.g., 600 V and 480 V)
c. Perform model simulation cases and compare results to the operating data
d. Develop a plot of MVAR operating data vs. the capability curve and PRC-019
coordination calculation
Use of operational data for validating the Generator Entity and Transmission Planner models is
addressed in Sections 3.1 and 3.2. However, other methods of using operational data can be used
to help verify the model(s) reflect a generating unit’s reactive power capabilities under various
operating conditions and, therefore, aid the Transmission Planner in selecting the best model
parameters and limitations for use in planning and/or operational studies. As examples, a
number of plots are provided below to illustrate the use of operating data to evaluate the
historical reactive power output range of an actual unit.
Example 1 (Figure 18) - The average hourly MW and MVAR output of a typical generating unit is
shown in the chart below. For this unit, Transmission Planning revised the unit’s reactive power
capability limits based upon this data and discussions with the Generator Entity.
Figure 18
Modeling Reference Document - Reporting and Verification of Generating Unit Reactive Power
Capability for Synchronous Machines
Page 34
Open Distribution
Example 2 (Figure 19) – The Unit is scheduled to hold a target transmission system voltage of 141
kV. The average hourly MW and MVAR output of the unit when the transmission system voltage
was between 140.5 kV and 141.5 kV is shown in the chart below. In this chart, one can observe that
the unit’s maximum MVAR output is consistent with the value identified due to auxiliary bus
voltage limits.
Figure 19
Modeling Reference Document - Reporting and Verification of Generating Unit Reactive Power
Capability for Synchronous Machines
Page 35
Open Distribution
Example 3 (Figure 20) – The Unit did not maintain the target transmission system voltage of 141 kV
for several hours during the year. The average hourly MW and MVAR output of the unit when the
transmission system voltage was below 140.5 kV is shown in the chart below. When transmission
voltage is depressed, the units maximum MVAR output exceeds the value identified due to auxiliary
bus voltage limits at 141 kV transmission system voltage.
Figure 20
One can conclude from this type of data that the reactive power capability of a typical “generating
unit” varies with changing system conditions and is likely not coincident with the manufacturer’s
D-curve for the “electrical generator.” What these plots illustrate is the importance of the
aforementioned factors when establishing generating unit reactive power capabilities for use in
transmission planning and operations.
It is important to note that such operating data can be used in lieu of, or in conjunction with,
staged testing and/or power flow simulations to verify a unit’s actual capability under varying
system conditions. Depending on the actual transmission system and generating unit, this data
may or may not fully indicate what the unit is capable of doing under extreme system voltage
Modeling Reference Document - Reporting and Verification of Generating Unit Reactive Power
Capability for Synchronous Machines
Page 36
Open Distribution
conditions which are seldom encountered. In such cases, additional engineering study may be
needed. Additional testing may also be beneficial if system conditions can be selected that
facilitate the specific test objective(s). Both methods have benefits and potential drawbacks.
Modeling Reference Document - Reporting and Verification of Generating Unit Reactive Power
Capability for Synchronous Machines
Page 37
Open Distribution
Modeling Reference Document - Reporting and Verification of Generating Unit Reactive Power
Capability for Synchronous Machines
Page 38
Open Distribution
The plot below (Figure 21) is an example from NERC Standard PRC-019-1 and shows that some
limiter and protection device settings are more limiting than the generator D-curve. Typically, this
is the under (or minimum) excitation limiter. Other devices, such as loss of excitation (or loss of
field) protection settings can encroach on the lower segment of the D-curve. These settings are
critical for protection of the generator from being severely damaged due to excessive stator end-
iron heating, loss of excitation, or coming out of step (loss of synchronism) with the system.
Figure 21
Notes:
1. The typical plot above shows a single generator reactive power capability curve for a
specified set of conditions (e.g., operation at rated terminal voltage, frequency, MVA, and H2
pressure for a hydrogen cooled generator).
2. All generators do not have the same compliment of protection or limiter devices or
functions. Therefore, a generator-specific plot is recommended for each generator.
3. Some digital excitation systems may have over excitation or maximum excitation limiter
functions that can be programmed to re-calibrate based on H2 pressure input. Availability
depends on the age and manufacturer of the excitation system.
Modeling Reference Document - Reporting and Verification of Generating Unit Reactive Power
Capability for Synchronous Machines
Page 39
Open Distribution
4. Some digital excitation systems may have under excitation or minimum excitation limiter
functions that shift as a function of the actual generator terminal voltage. Availability
depends on the age and manufacturer of the excitation system.
2. “Generating Unit” Capability
It is important to recognize that the reactive power limits discussed in Sections 3.1 and 3.1.a only
represent the capability of the electrical generator itself with its applied generator, excitation
system and protection limits. The capability of an electrical generator interconnected to the
electrical power system is determined by the complete “generating unit” configuration including
the generator step-up (GSU) transformer, the generating unit auxiliary system, and other factors.
“Generating unit” reactive power capability, at any given set of system conditions and unit MW
output, can be significantly less than the thermal capabilities of the generator defined by the
generator D-curve. The generating unit reactive power capability relates to the amount of support
available for grid voltage control and is influenced by the following:
Transmission system voltage levels and transmission system short circuit MVA levels;
GSU transformer factors including impedance (MVAR losses) and voltage tap settings;
Station auxiliary transformer tap settings, loads (MW and MVAR or PF), and related
auxiliary bus voltage limitations;
Thermal or ampere ratings of equipment between the generator and the point of
interconnection (bus, breaker, switch, GSU transformer, etc.), if these are not rated to
support the full generator MVA rating.
When an electrical generator is interconnected to the electrical power system through a GSU
transformer to establish the “generating unit” configuration, the generating unit’s reactive power
capability is significantly impacted by the GSU transformer’s MVA rating, internal impedance,
winding voltage ratio (tap setting), and the operating voltage range of the system bus connection at
the high voltage side of the GSU transformer Electrical system studies are typically performed
during initial plant planning and design to select and optimize these critical GSU transformer
parameters for the specific generating unit being designed. This is necessary to ensure acceptable
voltage and reactive power support for the system. Appendix B provides details on how generating
unit reactive power capability is impacted by the GSU transformer and provides examples of the
impacts due to different GSU transformer tap settings.
Generator voltage operating limits provided by OEMs are typically 95 to 105% of the generator
nameplate voltage rating without de-rating the reactive capability of the machine. Exceeding these
voltage limits may cause damage to the generator and should not be intentionally exceeded in
meeting grid voltage schedule requirements. However, wider operating voltage bands may be
permissible with the appropriate MVA rating de-rate.
While generators are designed to operate between 95% - 105% of rated (nameplate) terminal
voltage on a continuous basis, many generators could have more restrictive operational terminal
voltage limits due to the fact these generators supply power to station auxiliary system equipment
directly from the generator through one or more Unit Auxiliary Transformers (UATs) as shown by
Point B in Figure 22 below.
Modeling Reference Document - Reporting and Verification of Generating Unit Reactive Power
Capability for Synchronous Machines
Page 40
Open Distribution
Figure 22
The medium and low voltage station buses and auxiliary equipment also have voltage limits that
must be observed for reliable operation of the generating unit and the auxiliary systems. Some
generating units employ load tap changing transformers in their auxiliary systems to minimize or
eliminate these impacts on the generator operating voltage range and reactive power capabilities.
However, most generating plant station auxiliary systems employ fixed tap transformers. There are
system design considerations and constraints other than voltage (station bus loadings, short circuit
limits, impact loadings, economics, etc.) that must be observed during plant design. Due to these
and the use of fixed tap transformers, the station auxiliary voltage limits when reflected upstream
through the UAT(s) can limit the generator operating voltage to a range less than 95 - 105% of
rated terminal voltage which are the generator design limits (Reference: IEEE C50.13). The
generator terminal voltage at any output is dependent on the GSU transformer (nominal voltages,
impedance and tap setting) and the transmission system voltage at the time.
For some Generator Entities, auxiliary bus voltage limits are typically based on 110% of motor
nameplate voltage (per NEMA MG-1) and between 92.5% and 95% of nominal bus voltage. [The
Generator Owner (GO) is ultimately responsible for establishing these bus voltage limits to ensure
safe and reliable operation of the station auxiliary system over a wide array of operating
conditions.].
The Generation Entity should consider any auxiliary power system limitations, if applicable, when
defining the expected unit capability (Qmax and Qmin) and allowed voltage operating bands to be
reported for Transmission Load Flow Models, as required by new NERC MOD-032 (was MOD-010).
Modeling Reference Document - Reporting and Verification of Generating Unit Reactive Power
Capability for Synchronous Machines
Page 41
Open Distribution
If there are more restrictive voltage limitations due to auxiliary equipment, the GO should define
that as a reduced allowed generator voltage band. These restrictions can be defined with system
voltage at nominal, minimum scheduled and maximum scheduled grid voltage. This would permit
the planning and operating models to respect those limitations when performing Planning and
Operating analyses. It is suggested any known limitations due to the equipment fed from these
busses be monitored appropriately by plant instrumentation and alarm limits, such that these will
be known to the plant operations staff during abnormal grid voltage conditions is applicable.
For example, nuclear site generator bus voltage operating limits may be restricted tighter than the
105% maximum for the generator due to NRC degraded grid design requirements. Another
example is a typical legacy fossil unit whose generator bus voltage operating range can limited to 5-
6% instead of the 10% range for the generator itself. This can be caused by a mix of 550V and 575V
motors on the low voltage buses which occurred due to changes in the industry standards for low
voltage motors.
Reactive power limits due to voltage constraints on the generator and the unit auxiliary system and
the dependence on transmission system voltage can be illustrated on the capability curve. The
figure below (Figure 23) shows an augmented Generator D-curve Reflecting Generator and/or
Auxiliary System Voltage Limitations attributable to High or Low Transmission POI Voltages.
Modeling Reference Document - Reporting and Verification of Generating Unit Reactive Power
Capability for Synchronous Machines
Page 42
Open Distribution
Figure 23
The sensitivity of the maximum and minimum reactive power limits at various MW output levels
and transmission voltage levels can be determined analytically or through a series of simulations.
The modeling and simulations required to establish the reactive power limits due to generator,
transmission and/or auxiliary system voltage constraints are discussed in Section 3.
Modeling Reference Document - Reporting and Verification of Generating Unit Reactive Power
Capability for Synchronous Machines
Page 43
Open Distribution
Figure 24
Modeling Reference Document - Reporting and Verification of Generating Unit Reactive Power
Capability for Synchronous Machines
Page 44
Open Distribution
MVA, MW, and MVAR capability is temperature dependent. Some generators are cooled by ambient
air (ex: combustion turbine or CT generators). Some are cooled by air that may be water cooled
(ex: hydro generators cooled by air cooled using river water). An example of an air cooled
combustion turbine (CT) generator capability curve is shown below (Figure 25).
Figure 25
The example CT unit here is name plated as 60 MVA for 15°C (59°F) inlet air. It can only be safely
operated at 55 MVA for its summer peak rated temperature of 43°C (109.4°F) inlet air. Therefore,
this unit should be modeled using the 43°C reactive power capability curve at its summer maximum
and minimum gross capability for summer peak transmission planning studies. If required, these
units can be modeled for winter conditions using the capability curve that reflects the expected
winter temperatures. The Generator Entity should provide information to support the use of a
different curve for summer ambient conditions if the generating unit has equipment, such as
chillers, misters or foggers, installed and operating to reduce the inlet air temperatures.
Modeling Reference Document - Reporting and Verification of Generating Unit Reactive Power
Capability for Synchronous Machines
Page 45
Open Distribution
An example of an air cooled hydro generator capability curve is shown below (Figure 26).
Figure 26
This example hydro generator has two MVA ratings: 87.5 MVA at 60°C rise above ambient (or inlet
air) temperature of 40°C (winding temperature of 100°C) and 100.625 MVA at 80°C rise above
ambient (or inlet air) temperature of 40°C (winding temperature of 120°C). Some hydro generators
have heat exchangers that cool the inlet air. If these inlet air coolers use river water for the coolant,
then the river water temperature is a factor in determining the operating temperature limits. It is
important that the Generator Entity specify which rating is used for each specific hydro unit. While
newer generators or generators with new windings may be capable of operation at the top rating,
some older hydro units may be limited to operation at lower ratings due to condition of the stator
and/or rotor windings.
Modeling Reference Document - Reporting and Verification of Generating Unit Reactive Power
Capability for Synchronous Machines
Page 46
Open Distribution
example, the generator operating voltage range was determined to be 95.2% to 102.9% of rated
generator terminal voltage of 25 kV. This voltage range, represented by the blue vertical lines on
the following charts, was determined from an engineering study of the station auxiliary system and
takes into account the generator bus-fed unit auxiliary transformer (UAT) and downstream station
service transformer (SST) tap settings, impedances, and connected station auxiliary bus loadings. A
review of the generator capability curve, excitation limiter settings, and generator operating history
indicate the generator is capable of operation between +486 MVARs and -306 MVARs across its
entire MW operating range. Observations for each chart are summarized below the corresponding
figure.
Figure 27
Modeling Reference Document - Reporting and Verification of Generating Unit Reactive Power
Capability for Synchronous Machines
Page 48
Open Distribution
Figure 28
Modeling Reference Document - Reporting and Verification of Generating Unit Reactive Power
Capability for Synchronous Machines
Page 49
Open Distribution
Figure 29
The 102.5% tap setting is obviously not the optimum setting for this unit. Either of the previous tap
settings appear acceptable, depending upon the specific transmission system needs. In fact, a tap
setting between the 97.5% tap and 100% tap could be another good choice.
Modeling Reference Document - Reporting and Verification of Generating Unit Reactive Power
Capability for Synchronous Machines
Page 50
Open Distribution
Modeling Reference Document - Reporting and Verification of Generating Unit Reactive Power
Capability for Synchronous Machines
Page 51
Open Distribution
The field OEL (Over Excitation Limiter) provides a control function limiting the field current to a
permissible value with regards to thermal overload, in order to protect the filed from damage due
to excessive heating. The maximum permissible value is a function of cooling air temperature,
hydrogen pressure or other parameters. The action of an Over Excitation Limiter (OEL), which
sometimes is referred to as a Maximum Excitation Limiter (MXL), may be immediate or delayed [1].
The field UEL (Under Excitation Limiter) is a function that either overrides the voltage regulator
action or adds to terminal voltage set-point, to maintain excitation such that generator output
remains above a preset level. Various terms have been applied, often descriptive of the measured
variable; minimum excitation limiter, under-excited reactive limit, and rotor angle limiter [1]. The
UEL is protecting the stator core end iron from damage due to excessive heating, and prevents
operation that could lead to the loss of synchronism. The UEL needs to be coordinated with setting
of loss-of-excitation protective relays to avoid tripping of the synchronous generator.
The stator current limiter is designed to protect the generator core and GSU transformer from
thermal damage due to excessive magnetic flux resulting from low frequency and/or overvoltage.
Sustained excessive magnetic flux can cause overheating and damage to the unit transformer and
generator core. The stator current limiter provides a function that can act to prevent the armature
(stator) current from exceeding a pre-set value, thereby avoiding thermal overloads, which can be
caused by a high reactive power at high active power levels.
The Volts per Hertz (V/Hz) limiter provides a function acting to prevent ratio of terminal voltage to
frequency from exceeding a pre-set level. The purpose is to prevent excessive magnetic flux in the
synchronous machine and connected transformers [1]. Both synchronous machines and
transformers are generally provided with V/Hz protection to avoid excessive magnetic flux density
levels. Damage due to excessive magnetic flux seems to occur most frequently when synchronous
machines are off-line prior to synchronization.
[1] IEEE Standard 421.1-2007 Standard Definitions for Excitation Systems for Synchronous
Machines, IEEE Power Engineering Society, 2007
Modeling Reference Document - Reporting and Verification of Generating Unit Reactive Power
Capability for Synchronous Machines
Page 52
Open Distribution
GSU Winding or Oil Temp Alarm Settings – Review of Set-points & Alarm Procedures, Periodic
Testing of Temperature Devices.
Generator & Exciter Limiter/Protection Mis-coordinations / Mis-calibrations – Review of
Settings, Offline Testing Calibrations - PRC-019
Potential Errors Due To Plant Instrumentation – Identify & Correct Problems via Ongoing
Monitoring, Calibration Checks
Voltage Instrumentation: Switchyard, Generator, SS Buses
VAR Instrumentation: Generator, SS Load Points
Current (Ampere) Instrumentation: SS Bus Load Points
Generator Field Voltage, Field Current
Modeling Reference Document - Reporting and Verification of Generating Unit Reactive Power
Capability for Synchronous Machines
Page 53
Open Distribution
Modeling Reference Document - Reporting and Verification of Generating Unit Reactive Power
Capability for Synchronous Machines
Page 54
Open Distribution
Modeling Reference Document - Reporting and Verification of Generating Unit Reactive Power
Capability for Synchronous Machines
Page 55
Open Distribution
Four configurations commonly used in power flow models are illustrated in the figure below
(Figure 30). The net power delivered to the transmission system is 100.41 MW and 76.98 MVAR in
each configuration.
Figure 30
Modeling Reference Document - Reporting and Verification of Generating Unit Reactive Power
Capability for Synchronous Machines
Page 56
Open Distribution
GEN A – This configuration has the generator connected directly to the transmission system
and does not model the GSU transformer, aux load or unit aux transformer. The generator
output (100.41 MW and 76.98 MVAR); therefore, equals the flow into the transmission system.
GEN B - This configuration includes the GSU transformer but not the aux load or unit aux
transformer. The generator output must be modeled at 101.00 MW and 92.28 MVAR because
of the GSU transformer losses.
GEN C - This configuration includes the GSU transformer and aux load but not the unit aux
transformer. The generator output must be modeled at 109.00 MW and 98.30 MVAR to supply
the aux load and the GSU losses.
GEN D - This configuration includes the GSU transformer, aux load and unit aux transformer.
The generator output is unchanged from GEN C but the aux load must be reduced to account
for unit aux transformer losses.
The recommended models should represent GSU transformers and include generator aux or station
service load.
Simulation of option GEN C or GEN D in the power flow model is recommended because P and Q are
the generator gross values. The gross values are: 1) directly comparable to the generator D-curve,
2) consistent with the values measured at the generator terminals, and 3) appropriate for transient
stability simulations. Option GEN C, however, does not provide the capability to monitor the aux
bus voltages in the power flow simulations. For option GEN C, the Transmission Planner may be
required to adjust the generator terminal limits to less than the standard +/-5% to ensure that the
voltages at the aux buses are maintained within the applicable limits. The Transmission Planner
should work with the Generator Entity to obtain the generator voltage limits and auxiliary bus
loadings and voltage limits.
Modeling Reference Document - Reporting and Verification of Generating Unit Reactive Power
Capability for Synchronous Machines
Page 57
Open Distribution
Modeling Reference Document - Reporting and Verification of Generating Unit Reactive Power
Capability for Synchronous Machines
Page 58
Open Distribution
Modeling Reference Document - Reporting and Verification of Generating Unit Reactive Power
Capability for Synchronous Machines
Page 59
Open Distribution
Modeling Reference Document - Reporting and Verification of Generating Unit Reactive Power
Capability for Synchronous Machines
Page 60