Suppl. Operating Instructions
Suppl. Operating Instructions
Suppl. Operating Instructions
:
9971320894 / 000200 + 000300
Supplementary operating instructions, dismantling of mechanical seal, make Burgmann SHPV10/74-E
Pump design with one-piece lantern
1122.825/2-10
HPH
Circulation Out/In
Cooling Outlet
Cooling Outlet
Drain
D00222
412.52 O-ring
412.53 O-ring
412.54 O-ring
412.55 O-ring
472.54 Spring-loaded ring
475.55 Seat ring 433.02
477.54 Spring
2
HPH
Place O-ring 421.15 into the corresponding keyway in the bear-
ing bracket lantern 344.
Install the complete stationary assembly (seal cover 471.01
and spring-loaded ring 472.54 plus the necessary springs and
other small parts).
Tighten bolts 921.21 in accordance with table 1.
Take care not to squeeze O-ring 412.15.
Coat hub with Molycote.
The torques given in the table are determined on the basis of a friction coefficient m = 0.12.
After repeated tightening of the threads and in case of good lubrication the values should be reduced by 15 to 20 %.
The values given in the table do not apply if general drawings or other instructions state different values.
3
HPH