CBD For Electrical and Gypsum Board-New
CBD For Electrical and Gypsum Board-New
CBD For Electrical and Gypsum Board-New
Material unit cost 615.00 Manpower unit cost 75.00 Equipment unit cost 4.00
DIRECT COST ANALYSIS SHEET FOR - Electrical light points15cm wide HCB WALL
PROJECT BENIYOS Hotel and Apartment LABOR HRLY OUTPUT
DESCRIPTION Electrical light points15cm wide HCB WALL HOURLY OUTPUT 1.25 m²/hr
ITEM Area RESULTANT 10.00 m²/day
QUANTITY 1.00 m²
MATERIAL COST LABOR COST EQUIPMENT COST
Indexed hourly Hourly rental
Type of material Unit Qty Rate Cost/unit Labor by trade No. UF Hourly cost Type of Equipment No. UF Hourly cost
cost rate
HCB m2 12.00 39.00 468.00 Mason 1.00 1 62.50 62.50 Tools 1 1 5.00 5.00
Cement m2 0.05 1,500.00 75.00 DL 1.00 1 31.25 31.25 -
Sand m3 0.02 1,500.00 22.50 - -
- - -
TOTAL 565.50 TOTAL 93.75 TOTAL 5.00
Material unit cost 565.50 Manpower unit cost 75.00 Equipment unit cost 4.00