DIRECT COST ANALYSIS SHEET FOR - 20cm HCB WALL

PROJECT BENIYOS Hotel and Apartment LABOR HRLY OUTPUT


DESCRIPTION 20cm HCB WALL HOURLY OUTPUT 1.25 m²/hr
ITEM Area RESULTANT 10.00 m²/day
QUANTITY 1.00 m²
MATERIAL COST LABOR COST EQUIPMENT COST
Indexed hourly Hourly rental
Type of material Unit Qty Rate Cost/unit Labor by trade No. UF Hourly cost Type of Equipment No. UF Hourly cost
cost rate
HCB m2 12.00 40.00 480.00 Mason 1.00 1 62.50 62.50 Tools 1 1 5.00 5.00
Cement m2 0.07 1,500.00 105.00 DL 1.00 1 31.25 31.25 -
Sand m3 0.02 1,500.00 30.00 - -
- - -
TOTAL 615.00 TOTAL 93.75 TOTAL 5.00

Material unit cost 615.00 Manpower unit cost 75.00 Equipment unit cost 4.00

DIRECT COST OF WORK ITEM 694.00 ETB/m²

Profit and over head cost 35% 242.90 ETB/m²

Total Unit Price 937.00 ETB/m²


Remark:

DIRECT COST ANALYSIS SHEET FOR - Electrical light points15cm wide HCB WALL
PROJECT BENIYOS Hotel and Apartment LABOR HRLY OUTPUT
DESCRIPTION Electrical light points15cm wide HCB WALL HOURLY OUTPUT 1.25 m²/hr
ITEM Area RESULTANT 10.00 m²/day
QUANTITY 1.00 m²
MATERIAL COST LABOR COST EQUIPMENT COST
Indexed hourly Hourly rental
Type of material Unit Qty Rate Cost/unit Labor by trade No. UF Hourly cost Type of Equipment No. UF Hourly cost
cost rate
HCB m2 12.00 39.00 468.00 Mason 1.00 1 62.50 62.50 Tools 1 1 5.00 5.00
Cement m2 0.05 1,500.00 75.00 DL 1.00 1 31.25 31.25 -
Sand m3 0.02 1,500.00 22.50 - -
- - -
TOTAL 565.50 TOTAL 93.75 TOTAL 5.00

Material unit cost 565.50 Manpower unit cost 75.00 Equipment unit cost 4.00

DIRECT COST OF WORK ITEM 644.50 ETB/m²

Profit and over head cost 35% 225.58 ETB/m²

Total Unit Price 871.00 ETB/m²