Considertion in On-Line Processing
Considertion in On-Line Processing
By
VICTOR SOKOLOV
INTRODUCTION
In recent years there has been considerable interest in the subject of On-Line
Processing of Power Transformers, particularly in reclamation of oil, drying
out and regeneration of insulation. In 1992 nine Doble’s Clients responded
that they perform reconditioning on units while they are energized.
(Questionnaire 1992)
Now one can see an obvious tendency towards implementation of On-Line
procedures on the transformers up to 500 kV .
Plain economical benefit encourages fast developing processing technique.
Besides traditional processing equipment, some special Processing systems
have appeared: Fluidex, Pall, Velcon,”Dry Keep”,etc.
Some processing methods have had a positive experience during the last 25-
40 years
In the former Soviet Union the permanent regeneration system (cartridges
filled with silica-gel) have been specified for all transformers above 2.5 MVA;
Autotransformers 1150 kV and some special transformers 750 and 500 kV
(with elevated intensity of electrical stresses) have been equipped with the
permanent filter systems) which has been in operation over 25 years.
The first positive experience with On-Line drying out of 500kV transformers
was introduced in the USSR in early 70th (utilizing molecular sieves).
There has been a positive experience with On-Line degassing of 330-750 kV
transformers in some Ukrainian utilities (Donbassenergo, Dneprenergo).
However there are several relaxing factors, which make some technical
and psychological obstacles to wide implementation of On-Line
procedures:
1
• Risk of failure due to possible introduction into the tank air,
bubbles,particles or other impurities;loss of oil level; occurrence of static
electrification
• Risk of failure while processing “unhealthy” transformer
• Very long time (in some cases) of treatment (very costly process); e.g.
drying out may last several months, and accordingly cause a high costs of
processing procedures
OBJECTIVES OF PROCESSING
RECONDITIONING THE NATURALLY DETERIORATED
TRANSFORMERS:
•
• Aged oil,
• Contamination of cellulose insulation with oil aging products
• Saturation with air
• Moisture contamination
• Particles contamination
• Elimination of PCB
2
• The most important procedures with the goal to Extend the Life are
extraction of moisture and particles, extraction of aggressive aging
products from oil, and (particularly important) desorption and extraction of
oil aging products from solid insulation.
• In some cases (aging the oil particularly) a modeling the process is
necessary to select the optimal and efficient technology (For example,
selection of the type, and amount of the clay)
• The process is always can be minimized if the real condition of the
transformer is taken into account
CONDITION OF A TRANSFORMER
Water, oxygen, oil aging products (acids particularly) and particles of
different origin are agents of degradation, which can shorten
transformer life significantly under impact of thermal, electric,
electromagnetic and electrodynamics stresses.
Processes of insulation deterioration involve slow diffusion of water, gases,
and aging products and therefore affect basically only a part of insulation
structure, so called “thin structure” (paper insulation of turn and coils,
pressboard sheets, etc., which comprises typically 40-60% of the total mass.
”Active portion “of insulation is typically much lesser in transformers 35-110
kV then in 160-400 kV. Simplification of a transformer to just of two-
component system (mass of oil – mass of solid insulation) leads to
overestimation of a problem.
For instance solid insulation in LTC consists basically of waterproof material
and ingress water remains in oil predominantly. Few people are trying to
predict water content in solid insulation of LTC using moisture equilibrium
data.
A similar picture is in the most 35 -69 or even 110 kV transformers where an
amount of water- adsorbing- insulation is relatively small. Thus, 30 ppm of
water in oil at 20 C dos not really mean that water content in insulation is over
5 %. That is practically impossible. This water has been rather accumulated in
oil or “waiting” on the bottom of the tank.
Rate of cellulose deterioration (depolimerization) is proportional to
water content and acid number. Thus, estimation of “Loss of Life” is
sound only if both of these factors are taken into account.
It is impossible to restore aging decomposition of cellulose insulation, but it is
quite feasible to recover reversible change in the insulation condition and
practically restore the initial safety margin.
It is also possible to reduce the rate of further insulation deterioration. It is
apparent that Rehabilitation means in the first instance cleaning and cleansing
the transformer body, namely removing moisture, particles, aging by-products
and absorbed gases.
It ‘s always important to distinguish between a natural deterioration
(under impact of temperature, oxygen, mechanical friction, ingress of air
and moisture through the breathing system provided by design) and
Abnormal deterioration when a defect is involved. In the latter case
identification of the defect and its correction (or advisement to correct) is
important.
3
The following typical cases would occur:
• Elevated water in oil associated with ingress of free water through
insufficient sealing (e.g. draw lead bushings). Tightness test by means of
producing some extrapressure is a good tool to assess and eliminate the
problem.
• Excessive aging of oil ( particularly in sealed transformer) can be
associated with local or general overheating. DGA test may recognize the
problem.
• Presence of metal particles and carbon is typically caused by wearing the
pumps or localized overheating. DGA, vibration and acoustic tests may
help to recognize the problem.
Assumption of high water content in solid insulation may be confirm or
rejected by means of Water Heat Run Test [14]. This method is very useful in-
service tool to recognize condition of equipment and to select a proper
processing.
Fairly bad condition of a transformer should not be an obstacle to
perform On-Line processing with the goal to improve its condition. If a
transformer is in operation and stands operational stresses,
improvement of its condition can not bring any harm. The question
comes only: how thoroughly precaution measures have been foreseen..
One should consider that practically all impurities are distributed in certain
proportion between oil and solid insulation. Significant amount of gases and
oil aging products are concentrated in cellulose.
Oil is a water-transferring medium. Water presents in oil in soluble form and
also in “hydrate” form being absorbed by polar aging products (aromatics) and
particles. However using Karl Fisher method we measure practically only
dissolved water not bounded water. Thus we typically underestimate water
content particularly in aged oil.
Sometimes just only thoroughly filtering the oil may reduce water content.
Dielectric safety margin of both major and minor insulation of a transformer
contaminated with water is determined by dielectric strength of the oil.
Dangerous effect of soluble water is a sharp reduction of dielectric strength of
oil with increasing saturation percent due to increasing conductivity of the
particles available. The fewer particles content the weaker effect of water on
dielectric strength of oil.
The effective processing shall incorporate drying and filtering procedures
simultaneously
If to come from the worst to the better from point of view improvement of the
dielectric safety margin I would advise the following ranking:
• Do not allow bubbles
• Remove free water
• Remove particles, particularly large and conductive ones
4
• Remove dissolve water
• Remove oil aging product
• Drying of oil
• Oil degassing
• Oil reclamation
• Oil filtering
• Purification of insulation through filtering of oil
• Drying of insulation through drying of oil
• Regeneration (desludging) insulation using oil as a solvent
• PCB elimination
Active methods incorporate force moving the oil through filter, vacuum-
degassing machine, fuller’s earth towers, etc. This approach allows to monitor
and accelerate the process but have some disadvantages (adjustment,
maintenance, operator’s service, loss of power)
Passive methods incorporate typically a system of some cartridges filled with
sorbent and connected to the tank or to the coolers (see “Dry Keep”). The
passive process is much more economical but lasts longer.
5
Drying and Degassing oil using thermal-vacuum process
The process incorporates removing from the oil the certain volume of gas:
(air) and water vapor. Parameters of the process (oil flow rate, residual
pressure and temperature) shall be coordinated with characteristics of
vacuum pump (displacement) to remove amount of air and vapor available
Oil typically contains 9-11% of air and 3-5% of water vapor
10ppm (g/to) of water is equal to (1.2-1.3)% of volume concentration.
1 gram of water at residual pressure of 1mm Hg takes approximately 1 m3 of
volume (at 0.5 mm Hg-accordingly 2 m3)
To remove 11% of dissolved air and 50 PPM of water at 60C and 0.5 mm Hg,
using flow rate 5m3 per hour, the displacement of vacuum pump must be
more then 1080 m3 per hour.
Parameters of the process shall be monitored in such a way to remove the
desirable amount of “water-gas” mixture per one pass
Degassing process may be optimized using the most effective stage of the
process.
One can define two degassing stages in vacuum degassing plant
• Intensive extraction from the oil under vacuum dissolved air and water
inevitably cause foaming, which provides intensive diffusive emission of
gas, and vapor out of oil. This is the most effective stage of degassing. It
does not require high vacuum and high temperature.
• Relatively slow gas diffusion out of flowing layer while oil is flowing down
from spray nozzles or spraying to produce the mist. This process needs in
comparatively high temperature and vacuum.
However its important not to allow the foam get out of vacuum chamber.
Typical volume of oil foam is 8 times as large as volume of the oil itself and
time constant of foam sedimentation is about 60 sec.
One can show that to meet above mentioned requirements flow rate of the oil
shell be equal to 8 of volumes of vacuum chamber.
However foaming tendency of different oils is rather different. Some general
guidelines has been suggested by Doble which does not recommend to use
the oil having foaming tendency more then 150 ml (test by D892)
Drying and degassing of oil does not require very high temperature and
vacuum. Average oil temperature 40-50C and vacuum 1-0.5 mmHg are
sufficient to reach adequate dryness.
Effectiveness of both On-Line and Off-Line procedures are practically equal
6
Really, to get low moisture content one must maintain a very low relative saturation of oil.
WS = W0 exp. (- B / T)
Where W 0 and B are constants, which are typically different for different oils,
mainly due to difference in aromatic content. Some information about
estimated solubility constants and saturated water content are shown in the
Table beneath
Knowing the aromatic content one can easily select the parameters of
solubility
Oil #3 may use as prototype of aged oil.
One can see that for oils #1and #2 50 ppm of water at 20C is over then
saturated level
However at 40C 50ppm corresponds to ≈ 50% of relative saturation, and at
70C only to 16-18%.
To get water content in cellulose about 2%, relative saturation of the “hot” oil
shall be ϕ < 8%. Assuming maintaining water content of oil within the
transformer 15 PPM, e.g. for oil # 2 we may estimate the starting temperature
of drying process:
T=
(− B ) = (− 3841) (
= 328 K ≈ 55 C )
Woil 15
ln ln
ϕ ⋅Wo 0.08 ⋅ 23.08 ⋅10 6
One can show then to achieve moisture content in cellulose of 1% the drying
temperature shall be over 70C and process shall allow maintaining water
content in oil less then 10 ppm.
Experience has shown that drying out of insulation really contaminated with
water by means of circulating oil through dehydrator needs high temperature
and very long time and practically much less effective and efficient than
methods of drying out of transformer free of oil.
On the other hand, On-Line procedures are definitely more efficient then Off-
Line because of possibility to utilize internal losses of a transformer as source
of heating.
On-Line processing may be really very efficient in case using” passive
methods” [1]. Two cartridges filled with molecular sieves of 200 kg may
7
extract during several months about 40 kg of water, so that to dry effectively a
transformer rated 200-300 MVA.
Oil filtering
OIL Reclaiming
Similar to drying of oil this is a widespread processing method for both Off-
Line and On-Line application.
On-line procedures are more efficient because of possibility to use internal
losses of a transformer to heat the oil
One must consider some disadvantages of the methods:
• A large amount of waste
8
• Loss of oil during reclamation (what is more sensitive in case of energized
unit)
• Limited amount of oil processed with one charge
• Risk of introduction the clay crumb into the tank (more critical for
energized unit)
Passive mode methods with installation of some cartridges filled with
adsorbents could be sometimes much more efficient and safe.
Experience has shown a very good effectiveness of so called” reclaiming
without waste” using Fuller’s earth reactivation technology. In Czech Republic
e.g. several of tens transformers have been reconditioned up to the level
better then a quality of new oil (what is really feasible) .About 30% of the units
have been processed On-Line.
9
Three parameters shall be considered:
• Ratio of final and initial concentration of contaminant;
• Ratio of flow rate and total volume of oil in the transformer;
• Ratio of inlet and outlet concentration of contaminant per one pass of
treatment into the processing machine
The most important parameter, which determines effectiveness of the process
is relative rate of contaminant, removed per one pass, namely:
Ratio of input and output water, ratio of particles, ratio of oil aging
characteristics (Neutralization Number, interfacial tension, PF, Resistivity)
For example, if the system reduces the water content from the input 50 ppm
to output 10 ppm per one pass with flow rate 2 m3 per hour, the time to reduce
water to 10 ppm in the transformer of 20 m3 will take 20 hours. That is equal
to processing two volume of oil in the transformer). If processing equipment
removes only 50% of input contaminant per one pass such time will take 32
hours.
Another important parameter to be monitored is ratio of flow rate and the
volume of oil to be treated.
Both of abovementioned parameters are variable that’s why it is very
important to arrange On-Line monitoring of processing characteristics.
I would recommend the following approach:
• Check the initial condition (concentration contaminants to be removed;)
• Define the desirable final condition;
• Define the optimal parameters of processing: flow rate, temperature,
and vacuum, which give the maximal rate of removing contaminant;
• Estimate the time of process;
• Evaluate the possible life of adsorbents and filters elements to be
replaced during the total time of processing;
• Arrange monitoring of abovementioned basic parameters of processing
and auxiliary parameters (temperature, flow rate, vacuum.)
Utilization of On-Line sensors is of importance:
• Water sensor.
• Resistivity sensor; I believe that that is the most convenient characteristic
to monitor oil reclaiming process.
• Gas sensor to monitor degassing of transformers having excessive gas
(faulty gases) concentration.
Special study [15,16] has shown that reclamation process is the most
effective if to reclaim the oil, which have few nonacid polar, independently of
the IFT and Neutralization Number reached during service aging.
It should be also considered that low value of NN and high value of IFT does
not guaranty good behavior of the oil after reclamation if nonacid polar are
presented.
SAFETY PROBLEMS
10
How to minimize the risk of reducing dielectric withstands strength due
to possible introduction into the tank foreign impurities
Consider minimal volume of oil in the transformer, taking into account possible
loss of oil during reclamation (replacement of waist clay)
Watch oil level; consider the oil level gauge
Consider in some case arrangement of a metal standpipe to minimize the loss
of oil
Consider automatic shut down controls
REFERENCES
11
2.Abel Pereira, Bonnevile Power Administration.
”Safe handling Procedures for insulating oil with High Concentration of
combustible gases”-Proceedings of the DOBLE 1996 Conference,Sec 5-7
•
4.Myers, S.D., “Transformer Life can be extended”,Minutes of the 1982
DOBLE Conference,Sec 6.6
12
13