Jica Cost Estimate
Jica Cost Estimate
Jica Cost Estimate
Foreword .................................................................................................................................................... v
Abbreviations and Acronyms........................................................................................................................ vi
Glossary of Terms ......................................................................................................................................... vi
1. Introduction ......................................................................................................................................... 1
1.1 Background and Objectives......................................................................................................... 1
1.2. Structure of Cost Estimation Manual .......................................................................................... 1
1.3. PBC Works and Instructed Works .............................................................................................. 2
1.4. Cost Structure for Estimation ..................................................................................................... 3
1.5. Definition of SRUQ and P/R ........................................................................................................ 5
2. Role of Cost Estimation Administrator ................................................................................................ 5
3. PDCA Cycle for Cost Estimation ........................................................................................................ 6
4. Cost Estimation Methods of PBC Works............................................................................................. 7
5. Cost and Other Affiliated Surveys ....................................................................................................... 8
5.1. Unit Rates .................................................................................................................................... 8
5.1.1. Labour Cost ...................................................................................................................... 9
5.1.2. Vehicle Cost ...................................................................................................................... 9
5.1.3. Fuel Cost ........................................................................................................................... 9
5.1.4. Material Cost ..................................................................................................................... 9
5.2. Survey on 6 Major Labour Based Works ..................................................................................... 10
5.2.1. Productivity Survey ........................................................................................................... 10
5.2.2. Miscellaneous Cost Survey ................................................................................................ 18
5.3. Patrol and Self-Inspection (Self-Control Unit) Survey ................................................................. 18
5.4. Survey on Other PBC Works ...................................................................................................... 20
5.4.1. Damage Inventory Survey ................................................................................................. 20
5.4.2. Percentage Survey ............................................................................................................. 21
5.4.3. How Survey is Used in Cost Estimation............................................................................ 21
5.5. Survey on Percentage Add-ons on Indirect Cost and Overhead & Profit ................................... 22
5.6. Survey on Standardized Quantities-for 6 Major Labour Based Works........................................ 22
6. Analytical Results Based on Surveys Conducted .................................................................................. 26
6.1. Unit Rates .................................................................................................................................... 26
6.2. SRUQs for 6 Major Labour Based Works ................................................................................... 26
6.3. Data on Percentage Add-ons on Indirect Cost and Overhead & Profit ...................................... 30
6.3.1. Indirect Cost ..................................................................................................................... 30
6.3.2. Overhead & Profit ............................................................................................................. 30
7. Manual Revisions ................................................................................................................................. 30
Appendix 1 COST Estimation System 2015 For Cost Estimation Administrators .................................... 31
Appendix 2 Cost Estimation Parameters 2015.......................................................................................... 46
Appendix 3 Concept of SRUQ / Productivity Rate (P/R)........................................................................... 49
Appendix 4 Form 1 Site Layout ................................................................................................................. 52
Appendix 5 Form 2 Work Record Form ................................................................................................... 53
Appendix 6 Form 3 Productivity Survey Summary Form (Excel).............................................................. 54
Appendix 7 Information on Volume 3 for Contractors’ Reference Use .................................................... 55
Appendix 8 Training Results for PR Survey done by JICA/KRB in September and October 2015 ............. 56
Appendix 9 Recommendations by KRB on Indirect Cost, Overhead/Profit and Build-up of Unit Rates ... 92
The concept of performance based contracting in road maintenance and management has been adopted in
Kenya and was commenced in 2010 on a pilot basis. However, the method of estimating cost of works under
performance based contracts was not clear as it was based on traditional method of road maintenance. It was
therefore noted that a more scientific and accurate way of cost estimation of PBC road maintenance contracts
need to be formulated since these types of contracts differ from the traditional maintenance contracts. To
this end, JICA under the Project for strengthening of capacity on road maintenance and management through
contracting (phase 2), embarked on the noble task of developing this manual.
The manual has been prepared based on surveys conducted on the ongoing performance based contracts and
wide stakeholder consultations. The manual does not only provides scientific method of estimating the cost of
PBC road maintenance works but also provides survey techniques for collection of data necessary for regular
updating of the manuals. The manual consist of three volumes. Volume 1 is tailored to be used by the Road
Administrator (KRB) who provide estimation parameters and will be in charge of updating of the database. Volume
2 will be used by the road authorities for estimation of Project Cost i.e. determining the ceiling price for purposes
of budget allocation, planning and tendering. Volume 3 has been prepared specifically for contractors who will be
interested in tendering for PBC works. In volume 3, a deliberate move was taken to exclude information on unit
prices and percentages of indirect cost, overheads/profits which the contractors are required to provide during
the tendering processes. A computer program known as COSTES for PBC 2015 was also developed with data
collected from surveys on the ongoing PBC contracts. The computer program will be used with the manual to
ease rigorous computation processes. Explanations on how to operate the program have been appended in the
manual.
It is hoped that this manual will be very useful in implementation of this new concept of road maintenance and
will be beneficial to both the clients and the contractors.
I urge all stakeholders to make proper use of the manual in costing of PBC road maintenance works to arrive at
more accurate cost of PBC contracts, thus guaranteeing value for money and best return to the taxpayer.
Finally, I recognize and acknowledge with appreciation the National Working Group and Sub-Working Group
members who provided their valuable advice through a series of meetings during the period of formulating this
manual. I am particularly grateful to the JICA team for their technical assistance in achieving this milestone and
for their overall assistance in capacity building for road maintenance and management. Special gratitude goes to
all road authorities and other government agencies which include KRB, KeNHA, KURA, KeRRA, KWS, KIHBT,
NCA and PPOA for their valuable support in the development of this manual.
Glossary of Terms
Actual Quantity Refers to the actual quantity of work and service for each service criteria
executed by the contractor to achieve the specified service level.
Simple Quantity Refers to the targeted quantity of work and services for each service criteria
to be executed by the contractor as per the contract drawings.
General Maintenance Refers to all works and services (mainly off-carriageway) required to be
performed by the contractor under the performance based contract.
Initial Mobilization Period This is the period during the initial stages of the contract when the contractor
makes interventions to bring the road to maintainable conditions.
Routine Maintenance Period This is the period after the expiry of the initial mobilization period when
the contractor undertakes routine maintenance activities.. The activities are
performed to maintain the performance standards of the road and to achieve
specified service levels.
1. Introduction
Based on the nature of various requirements, Instructed Works are a combination of the following works and
services as indicated in Table 1-3.
This Manual has been prepared principally to estimate the cost of PBC Works for which no standard procedure
for cost estimation was addressed in the previously issued “Cost Estimation Manual for Road Maintenance Works
2011”, popularly referred to as the COSTES Manual 2011.
This Manual is a new edition and focuses exclusively on the PBC Works. It tries to correctly estimate labour-
based works and services based on surveys conducted on on-going PBC projects. The Manual therefore reflects
the result of the surveys and recommends methods of standard estimation procedures using the results obtained
x = a+b+c
Total Project Cost
a) Direct Cost
X*16%
d) VAT
The structure of a typical project is shown in Figure 1-2 for cost estimation purpose under COSTES for PBC
2015. The Direct Cost in this case consists of PBC Works, Instructed Works and Haulage Cost.
Item Cost
Total Project Cost (VAT(16%) Inclusive) 12=10+11
Project Cost 10=7+8+9
Direct Cost 7=4+5+6
PBC Works 4=1+2+3
Patrol and Self Inspection under Road Safety 1
Major 6 Labor Based Work under Road Durability 2
4 3 2 1 Other PBC Works 3
Instructed Works 5
Haulage Cost of Major 6 Labor Based Work 6
Indirect Cost 8
Overhead & Profit 9
VAT(16%) 11
Figure 1-2 Cost Estimation Structure under COSTES for PBC 2015
Example:
Grass cutting of 10,000m2 is completed in 5 man-days. That is 5 persons each completing 2,000m2 on a given day.
SRUQ = 5 man-days/ 10,000 m2 = 0.0005 man-day/m2
Productivity Rate (P/R) = 2,000m2 / man-day
Table 2-1 gives the Plan, Do, Check, Action (PDCA) cycle for cost estimation related activities
Road
Item Contents Frequency
Authorities
Unit Rates Survey
(Coordination and
Indirect Cost and
referral with KNBS1 Every Year
Overhead & Profit
Cost index, etc)
C (Check) Surveys
Survey KRB
SRUQ(by work item)
Productivity Survey SRUQ(by Road Every Year
Revision
Authority)
Manual
P (Plan) Planning the budget for next year projects Every Year KeNHA,
Manual
KURA,
D (Do) Cost Estimation for the project Every Year KeRRA, KWS
Field
Cost Data Collection Cost Data Collection
survey
Data
analysis A
Manual
Revision Manual revision Manual revision
activity activity
New fiscal
year
manual
publication
Budgeting
Using 2015 manual Using 2016 manual
cost
estimation
for each
2015 manual 2016 manual 2017 B
contract
The second stage requires estimating the cost of the Indirect Cost and the Overhead & Profit
No Item
1 Grass Cutting
D) Vegetation O ∆
E) Structures ∆ O
Road Durability
F) Road Furniture ∆ O
from surveys by the cost estimation administrator or provisional rates by referring to similar items may be used.
However, those rates should be revised immediately the official rates become available.
For cost estimation using the Manual, collection of the unit rates indicated in Table 5-2 is required. These unit
rates apply for 6 Major Labour Based Works and Self Control Unit (Patrol and self-inspection), but these are not
applicable to the Other PBC Works.
The Productivity Survey is conducted and the result is compiled for each road authority by the cost estimation
administrator.
This is the survey to understand how much of work output is produced and completed for a given manpower.
Examples:
Work Output: Grass Cutting P/R: xx m2/ man day
Cross Culvert De-silting P/R: yy m/man day
Carriageway Cleaning P/R: zz m2/man day.
7. Safety will be observed throughout the survey. Surveyors will always wear reflective safety jackets and
helmets to enhance safety. Surveyors are also required to be cautious of the traffic to avoid accidents.
8. Pictures are taken for each activity and grouped into respective roads. Pictures will be taken before,
during and after completion of every activity. Pictures are also taken to show how the survey was
carried out. Please refer to Chapter 5.2.1.3.
Work Frequency
This is the survey to understand the number of frequencies required to maintain the work output to achieve the
prescribed service levels.
Examples:
Work Frequency: xx times /month, or yy times/day
This survey is performed based on interviews with contractors and also by continual monitoring of SRUQ survey
above.
Location: Weather:
Form 1: Site Layout Sheet Produce 1)Typical Cross sections 2) Work Team Info 3) Work Items 4) Work
Progress per Hour and 5) Others by hand during the survey on site.
Date Weather
Location Contractor's Name
Work Item Number of Workers Start time End time Working Hrs Work Measurement
Form 2: Work Survey Form Produce 1)Start Time 2)End Time 3)Working Hours 4) Work Output 5) Remarks
by hand during the survey on site.
To fill only the number of workers who are engaged in PBC works
Total number of workers or equipment shall tally the number of workers or equipment for PBC works on site.
To specify structures to be maintained
To fill the maintained Q'ty which includes places/areas that don’t require any actual maintenance works
13
Figure 5-1 Standard Survey Forms for SRUQ survey (Forms 1, 2 and 3)
COST AND OTHER AFFILIATED SURVEYS
Simple Quantity Actual Quantity Work Difficulty Foreman Supervisor Labors (4) (5)
Simple Actual
SRUQ SRUQ Remarks
Worked Items
(man day/Qty) (man day/Qty) (Equipment)
Q'ty Unit Q'ty (Vol) Unit nos nos nos working hours
-Heavy
Remarks Remark
-Normal
a b -Light c d e f j=e×f Man day ps = j / 7a pa= j / 7b
VOLUME 1: MANUAL FOR COST ESTIMATION ADMINISTRATORS
Pcs Pcs 0 0
Cross Culvert(1)
m m Light 0 0
2)
Pcs Pcs 0 0
Cross Culvert(2)
m m 0 0
Carriage De-sliting(1) 621.2 m2 Lx1.0(m) 184.6 m2 Normal 1 4.5 4.5 0.642857143 0.0010 0.0035
6)
Carriage De-sliting(2) 621.2 m2 Lx1.0(m) 178.1 m2 1 4 4 0.571428571 0.0009 0.0032
To fill only the number of workers who are engaged in PBC works Man Day
Total number of workers or equipment shall tally the number of workers or equipment for PBC works on site.
To fill the maintained Q'ty which includes places/areas that don’t require any actual maintenance works
Note) To use one sheet per day
To fill only the number of workers who are engaged in PBC works
Total number of workers or equipment shall tally the number of workers or equipment for PBC works on site.
To specify structures to be maintained
17
To fill the maintained Q'ty which includes places/areas that don’t require any actual maintenance works
COST AND OTHER AFFILIATED SURVEYS
Miscellaneous cost is a cost required to: 1) obtain necessary tools and equipment for carrying out the work; 2)
acquire safety equipment and gears; and 3) acquire tools and equipment for inspection. An example is indicated
in Table 5-4 below.
The Manual recommends the value of 5% on top of the total labour cost. However, this can be improved by
conducting the Miscellaneous Cost Survey to determine the standard percentage based on each road authority,
region and contract.
Client/Road Authority
– Project Manager
– Assistants
Formal
Inspection
Contractor
Self-Control Unit
Corrective (SCU Leader & SCU Inspector)
– Data collection/data
Order
collection coordination
– Communication
Payment – Patrol
– Self Inspection
Road Manager
Execution Units
(Foreman, Supervisor, Worker)
– Execution of work
– Progress control
– Quality control
– BoQ works
*1 Up to 10km: SCU leader conducts both patrol and self-inspection (1 vehicle required)
*2 Up to 50km (standard) : SCU leader conducts patrol and self-inspection with one inspector (1 vehicle required)
*3 Over 50km: SCU leader and an assistant conduct patrol and self-inspection. An inspector conducts patrol in other roads under
contract at same time (2 vehicles required).
Repair of Carriageway Simple Quantity, Period of Maintenance, Age of Road, Number of Lanes, Thickness of
Asphalt Pavement, Damage Inventory, Probable Quantity
Repair of Shoulder Simple Quantity, Period of Maintenance, Age of Road, Thickness of Asphalt Pavement,
Damage Inventory, Probable Quantity
Repair of Structures Simple Quantity, Period of Maintenance, Damage Inventory, Probable Quantity
Repair of Road Furniture Simple Quantity, Period of Maintenance, Damage Inventory, Probable Quantity
Repair of Profile and Road Width Simple Quantity, Period of Maintenance, Damage Inventory, Probable Quantity
Repair of Embankment and Slopes. Simple Quantity, Period of Maintenance, Damage Inventory, Probable Quantity
The Manual proposes three ways of cost estimation for Other PBC Works and surveys to obtain data/informa-
tion to enable such cost estimation must be conducted. It is important to understand the precise volume of work
inputs such as labour, materials and equipment resources for a volume of work output to achieve the specific
service levels as well as the volume of work output itself are important. However, we must acknowledge that it is
understandably difficult to determine the volume of the work output for each work on its own. Therefore, collec-
tion of damage inventory and computation of damage probabilities through this survey becomes important as well.
By understanding the past maintenance record of damages and compiling them into the damage inventory, the
probability of each repair such as pothole repair, rutting repair, shoulder repair and road furniture repair can be
placed in a database to be provided by the cost estimation administrator.
This probability of each repair is termed as the damage probability and the probable quantity may be computed
by multiplying the simple quantity and the damage probability of repairs necessary under Other PBC Works by
the cost estimator from information in the database.
For compiling the damage inventory, the following survey needs to be established completely from scratch as
no information is available in Kenya at this moment. The damage inventory survey is conducted in the following
order:
1. Selection of Roads for Obtaining Damage Inventory
The selected road should possess typical features of roads in Kenya which is being maintained under
PBC. The road authority in charge and the cost estimation administrator will need to agree that the
selected road will be used for the damage inventory throughout the duration of the PBC project.
2. Cooperation with PBC Contractor
The PBC contractor responsible for maintaining the road will be informed that the selected road
will be used as a model project for collection of the damage inventory for Other PBC Works, The
contractor will be informed of usefulness which the study will serve for the road authority.
3. Damage Inventory Survey
Based on the progress on site, the contractor will inform the representative of the road authority on
the volume of Other PBC Works which the contractor periodically carries out. The representative
will then pass the information to the cost estimation administrator. Inventories of repairs carried out
on damages will be recorded by the cost estimation administrator in a standardized form indicating
the magnitude of damage and ensuing details of repair recorded with the anticipated cost incurred by
the contractor. This is the input required for the damage inventory.
4. Compilation of Database
Upon completion of the PBC project, all information collected in the damage inventory under the
project can be compiled into a database by computing the number of damages recorded per project,
per year and per km/year. Computing the amounts required for repair recorded per project, per year
and per km/year for each work under Other PBC Works will also be made. This database will become
the damage probability database. In case, the model project is in multiple numbers, the database will
be more useful in future.
The percentage survey is a survey following the result of Damage Inventory Survey.
This is the survey using the database established under Damage Inventory Survey to quantify the cost required
for repair of damages as a percentage of the direct cost of the PBC project.
This survey may be carried out without using the result of Damage Inventory Survey by collection of data through
interviewing contractors undertaking PBC projects for which the Other PBC Works are a part of the scope.
For the Six (6) Major Labour Based Works and Self- Control Unit, quantification of work outputs are comparatively
simple as such works are of repetitive nature and one can be able to adopt standard work frequencies to obtain
work outputs.
For quantifying work outputs for “Other PBC Works”, a concept of probable quantities is introduced instead of
computing work outputs using work frequencies.
The probable quantity for Other PBC Works can be computed using the following formula:
Probable Quantity = Simple Quantity x Damage Probability
This is based on the understanding that various work outputs under Other PBC Works are of random occurrence
and the impact of damage is also inconsistent.
In case, the damage probability is set higher than the reality, cost estimation will be higher; and in case, that the
damage probability is set lower than the reality, cost estimation falls short of what is actually required. In order to
minimize occurrence of such, it should be high priority to collect vital information as quick as possible.
The Manual recommends that works utilizing such probable quantities should not be treated as Other PBC
Works, but as a part of Instructed Works so that the risk is borne by the road authority at this stage. This measure
should be taken until such a time that a stable database of Other PBC Works is available.
Example:
Pothole repair: Simple Quantity (Paved Area) 1,000m2×Damage Probability 5%
= Probable Quantity 50m2
Km Post repair: Simple Quantity (Km Posts) 100 nos. x Damage Probability 3%
=Probable Quantity 3 nos,
Difference of cost computation method is indicated in Table 5-8.
1 6 Major Labour Based Essentially the work is off carriageway Quantity *×Productivity×Unit Rate×Work
Works (Table 4-2) and labour based. Frequency
(*length of drains, area of grass cutting etc.)
2 Patrol and Self-Inspection For patrolling under Road Usability Quantity *×Productivity×Unit Rate×Work
(Self Control Unit) and for self-inspection. Frequency
(* Road Length)
3 Other PBC Works Works involving non-labour based Probable Quantity = Simple Quantity x Damage
work. Probability
5.5. Survey on Percentage Add-ons on Indirect Cost and Overhead & Profit
This section covers the survey required to determine the percentage add-ons to determine the costs of Indirect
Cost and Overhead & Profit.
Indirect Cost and Overhead & Profit are the costs to cover items indicated in Table 1-4 and are generally
computed as percentages of: the Direct Cost for the Indirect Cost; and the sum of the Direct Cost and the
Indirect Cost for the Overhead & Profit. The percentages are generally smaller when the contract amount is
large and it is larger when the amount is small.
The survey to understand what desirable percentages to apply must be conducted by the cost estimation
administrator. For deriving such percentages, the cost estimation administrator requires to conduct interviews
with PBC contractors to determine the amount the contractors actually incur as Indirect Costs and Overhead
& Profit in relation to the actual amount the contractor incurs on the Direct Cost. The survey needs to be
established completely from first principles as no information is available in Kenya at this moment.
In case the above survey is not possible, the percentage add-on can be established by collecting tendered prices
on recent road construction projects in Kenya as the benchmark. There are sums indicated in Bill No. 1 General
and Preliminaries which covers the cost of the indirect work. Normally, overhead & profit are spread all over
the bill of quantities. Since PBC projects do not require major site establishment costs, the percentage for road
construction project should be computed by deducting such site establishment costs from Bill No.1.
Works on a Kilometre (KM) format. Such KM Standardized quantities are computed in simple quantity for each
road authority in this survey. Similarly, the percentage ratios of such simple and actual quantities for various road
facilities have been also computed by Productivity Survey so that the cost estimation method using only a project
length as an acquired parameter can be used. The details of cost estimation methods using KM Standardized
Quantities are explained in Vol. 2 for Government Cost Estimators together with other two methods.
This section covers the survey method for obtaining a list of standardized quantities for road facilities for each
road authority.
The survey for road facilities is conducted in the following order:
1. Selection of Roads for Obtaining Standardized Quantities
The selected road should possess typical features of roads in Kenya.
The selected road should be simple in its own nature and PBC is either being implemented or to be
implemented. Selected roads thus become the Standardized Road.
2. Selection of Survey Section
Survey sections will be selected taking into consideration that the section is simple in its own nature.
Either a section or sections maybe selected. However, each section should be at least 1km in length
and the total section should be between 3km to 5km in length.
These sections thus become the Standardized Road Section.
3. Computation of Simple Quantities for Each Road Facility
The Standardized Road Section will also be surveyed for simple quantities for each road facility, based
on the following computation methods
i. Grass Cutting: The length of the Standardized Road Section × (The road reserve – Carriage Way
– Side Walk – Lined ditch) See Figure 5-3.
ii. Cross Culvert: The total metre length of cross culverts regardless of whether maintenance is
required or not in the Standardized Road Section.
iii. Catch Basin: The total number of catch basins regardless of whether maintenance is required or
not in the Standardized Road Section.
iv. Lined Ditch: The total length of Lined Ditches regardless of whether maintenance is required or
not in the Standard Road Section.
v. Unlined Ditch: The total length of Unlined Ditches regardless of whether maintenance is required
or not in the Standard Road Section.
vi. Carriageway: The paved length of the Standardized Road Section ×1.0m × 2 × No of lanes.
(1.0m for de-silting purpose)
OUTER ZONE INNER ZONE VEGETATION FREE ZONE INNER ZONE OUTER ZONE
Note 1 (Unlined Ditch)
2m : Straight
/outside curve VEGETATION OUTER ZONE
5m : Inside Curve FREE NOZE (Lined Ditch)
Boundary
Lined/Unlined Ditch
KeNHA
Item Unit (1) Simple Quantity/1km (2) Actual Quantity/1km (3) Actual/Simple %
1) Grass Cutting m 2
6055 2,018.3 33%
KM Standardized Quantities for each road authority are indicated in Table 5-10. The KM Standardized Quantities
in a simple quantity format and the percentage of actual quantity/simple Quantity have been derived from the
survey. In addition, KM Standardized Quantities in an actual quantity have been computed.
In case some information is lacking from the survey due to unavailability of suitable projects in hand, a certain
common sense judgment must be provided during the survey analysis as outlined in Chapter 6.
Table 5-10 KM Standardized Quantities in a Simple Quantity for Each Road Authority (2015)
KeNHA
KeNHA (2×2Lanes)
KURA
Item Unit Simple Quantity/1km Actual/Simple Actual Quantity/1km
Grass Cutting m 2
6819 33% 2,273.0
Cross Culvert m 100 64% 64.5
Catch Basin Pcs 50 33% 16.7
Lined Ditch m 1400 50% 696.5
Unlined Ditch m 200 35% 70.9
Carriageway m2 2000 32% 639.0
KeRRA
Item Unit Simple Quantity/1km Actual/Simple Actual Quantity/1km
Grass Cutting m 2
2310 33% 777.0
Cross Culvert m 10 64% 6.5
Catch Basin Pcs 10 33% 3.3
Lined Ditch m 0 -
Unlined Ditch m 1800 35% 638.3
Carriageway m 2
0 -
Note: Figures are from survey on the Unpaved Road.
KWS
Item Unit Simple Quantity/1km Actual/Simple Actual Quantity/1km
Grass Cutting m2 2310 33% 770.0
Cross Culvert m 10 64% 6.5
Catch Basin pcs 10 33% 3.3
Lined Ditch m 0 -
Unlined Ditch m 1800 35% 638.3
Carriageway m2 0 -
Heavy 0 0 0.00 0 0 0.00 12 12 0.00 1 1 1.14 0 0 0.00 327 305 23.20 133 128 4.10 3,646 1,513 37.68 745 208 4.67 74 52 0.19 0 0 0.00
Normal 22,666 4,481 10.72 7,602 2,228 3.93 27 16 0.36 0 0 0.00 0 0 0.00 2,556 881 21.21 1,217 321 5.50 1,253 368 8.69 687 164 3.81 3,649 1,620 16.45 2,054 702 3.44
Light 18,997 1,905 2.96 16,132 2,470 2.38 0 0 0.00 11 11 0.48 0 0 0.00 4,432 2,681 4.12 3,892 1,917 3.49 0 0 0.00 0 0 0.00 6,891 1,940 8.17 5,934 1,655 4.27
Heavy 0 0 0.00 0 0 0.00 4 4 4.00 1 1 1.00 0 0 0.00 9 9 9.00 3 3 3.00 14 14 14.00 2 2 2.00 0 0 0.00 0 0 0.00
counts Normal 11 11 11.00 6 6 6.00 2 2 2.00 0 0 0.00 0 0 0.00 11 11 11.00 6 6 6.00 9 9 9.00 5 5 5.00 12 12 12.00 7 7 7.00
Light 7 7 7.00 5 5 5.00 0 0 0.00 7 7 7.00 0 0 0.00 13 13 13.00 8 8 8.00 0 0 0.00 0 0 0.00 15 15 15.00 11 11 11.00
ANALYTICAL RESULTS BASED ON SURVEYS CONDUCTED
Using information as summarized in Table 6-1, Table 6-2 is prepared by arranging data according to work
category, labour inputs (in man-days) and Work Difficulty Levels. By summation of data into various categories
and then dividing them by Simple Quantity and Actual Quantity and P/Rs are obtained. From P/Rs, SRUQS are
obtained through computation.
Based on difference of Work Difficulty Levels, applicable SRUQs and P/Rs are used for cost estimation.
Initial Mobilization Period: SRUQs and P/Rs under Heavy
Wet Season: SRUQs and P/Rs under Normal
Dry Season: SRUQs and P/Rs under Light
Using information derived in Table 6-2, Table 6-3 is produced for use by cost estimators.
Table 6-2 Compilation of SRUQs, P/Rs, Percentage Ratio of Simple Quantity/Actual Quantity ((Simple/Actual)
%)
The top section computes the field data to applicable field SRUQs for both simple and actual quantities together
with the field percentage ratio of simple quantity/actual quantity.
The bottom section illustrates correction exercises necessary to obtain all applicable SRUQS and P/Rs for both
simple and actual quantities together with the adjusted percentage ratio of simple quantity/actual quantity.
Correction exercises are required at this stage as sufficient data to cover the entire sphere of activities has not
been obtained under the survey. Therefore, a certain common sense judgment must be provided to recover
such deficiencies.
Summary of SRUQ
SRUQ
Person* P/R SRUQ Simple/ Actual/ P/R SRUQ SRUQ
Work Item Level Simple Actual (Actual)
day (Actual) (Actual) Actual Simple (Simple) (Simple) (Simple)*1000
*1000
Heavy No Data
Grass Normal 30,224 6,687 14.499 461.2 0.002168167 2.17 2,399.2 0.000416808 0.42
Cutting (m2) Light 35,129 5,876 5.336 1,101.3 0.000907981 0.91 5,729.0 0.00017455 0.17
Total(Ave.) 65,353 12,563 20 633.4 0.001578725 1.58 520% 19% 3,295.0 0.000303494 0.30
Heavy 12 12 1.619 7.4 0.134916667 134.92 11.5 0.08688808 86.89
Cross Normal 19 8 0.142 55.5 0.018028933 18.03 86.1 0.011610866 11.61
Culvert (m) Light No Data
Total(Ave.) 31 20 2 11.3 0.088513999 88.51 155% 64% 17.5 0.057004161 57.00
Heavy 1 1 1.143 0.9 1.142857143 1,142.86 0.9 1.142857143 1,142.86
Catch Basin Normal No Data
(pcs) Light 11 11 0.475 23.2 0.043194805 43.19 23.2 0.043194805 43.19
Total(Ave.) 12 12 2 7.4 0.134833333 134.83 100% 100% 7.4 0.134833333 134.83
Heavy 460 433 27.299 15.9 0.063070622 63.07 31.9 0.031306995 31.31
Lined Side Normal 3,773 1,202 26.713 45.0 0.022230222 22.23 90.6 0.011034638 11.03
Ditch (m) Light 8,324 4,598 7.609 604.3 0.001654675 1.65 1,217.5 0.000821347 0.82
Total(Ave.) 12,557 6,233 62 101.1 0.009886347 9.89 201% 50% 203.8 0.004907385 4.91
Heavy 4,391 1,722 42.350 40.7 0.02459982 24.60 114.7 0.008718194 8.72
Unlined Side Normal 1,924 517 12.452 41.5 0.024101616 24.10 117.1 0.00854163 8.54
Ditch (m) Light No Data
Total(Ave.) 6,315 2,238 55 40.8 0.024484818 24.48 282% 35% 115.2 0.008677437 8.68
Heavy No Data
Carrageway Normal 5,703 2,322 19.893 116.7 0.008568364 8.57 365.5 0.002736169 2.74
De-silting
(m2) Light 12,825 3,595 12.442 288.9 0.003460832 3.46 904.8 0.001105161 1.11
Total(Ave.) 18,528 5,917 32 183.0 0.005464973 5.46 313% 32% 573.0 0.001745151 1.75
After Correction
SRUQ SRUQ
P/R SRUQ (Actual) Actual/ P/R SRUQ (Simple)
Work Item Level (Actual) Remarks (Actual) *1000 Simple/Actual Simple (Simple) (Simple) *1000
Assumption
100 10.00 300.0 0.003333333 3.33
Heavy (From Normal and Little) 0.01
Grass
Cutting Normal 461 0.002168167 2.17 1,383.7 0.000722722 0.72
(m2) Light 1,101 0.000907981 0.91 3,304.0 0.00030266 0.30
Total(Ave.) 633 0.001578725 1.58 300% 33% 1,900.3 0.000526242 0.53
Heavy 7 0.134916667 134.92 (Assumption: 3:1) 11.5 0.08688808 86.89
Normal 55 0.018028933 18.03 86.1 0.011610866 11.61
Cross
Culvert (m) Assumption
100 10.00 155.3 0.006440129 6.44
Light (From Heavy and Normal) 0.01
Total(Ave.) 11 0.088513999 88.51 155% 64% 17.5 0.057004161 57.00
Heavy 1 1.142857143 1,142.86 2.6 0.380952381 380.95
Assumption
Catch Basin Normal 5 200.00 15.0 0.066666667 66.67
(From Heavy and Little) 0.2
(pcs)
Light 23 0.043194805 43.19 69.5 0.014398268 14.40
Total(Ave.) 7 0.134833333 134.83 300% 33% 22.2 0.044944444 44.94
Heavy 16 0.063070622 63.07 (Assumption; 3:1) 31.9 0.031306995 31.31
Lined Side Normal 45 0.022230222 22.23 90.6 0.011034638 11.03
Ditch (m) Light 604 0.001654675 1.65 1,217.5 0.000821347 0.82
Total(Ave.) 101 0.009886347 9.89 201% 50% 203.8 0.004907385 4.91
Heavy 41 0.02459982 24.60 114.7 0.008718194 8.72
Unlined Normal 41 0.024101616 24.10 117.1 0.00854163 8.54
Side Ditch Assumption
(m) 600 1.67 1,693.0 0.000590668 0.59
Light (From Lined Side Ditch Little) 0.001666667
Total(Ave.) 41 0.024484818 24.48 282% 35% 115.2 0.008677437 8.68
Assumption
50 20.00 156.6 0.006386678 6.39
Heavy (From Normal and Little) 0.02
Carrageway
De-silting Normal 117 0.008568364 8.57 365.5 0.002736169 2.74
(m2) Light 289 0.003460832 3.46 904.8 0.001105161 1.11
Total(Ave.) 183 0.005464973 5.46 313% 32% 573.0 0.001745151 1.75
6.3 Data on Percentage Add-ons on Indirect Cost and Overhead & Profit
6.3.1 Indirect Cost
The cost estimation administrator is required to determine the percentage add-ons based on the survey carried
out in accordance with Chapter 5. By collection of sufficient data and interviews with contractors who participated
in past PBC projects, a percentage add-on can be determined.
The Manual recommends a percentage of Indirect Cost as 30% over the Direct Cost (Refer to Appendix 9). This
is the default value used in COSTES for PBC 2015. The percentage is based on other classical road contracts in
Kenya.
In Japan, the standard values of the indirect cost percentage on public road infrastructure projects are indicated
in Table 6-4.
Table 6-4 Percentage Add-ons on Indirect Cost and Overheads & Profits in Japan
6 Manual Revisions
This section describes the timing of revisions required so that the Manual is maintained and continues to serve
its useful purpose.
Vol. 1 Administrators
— Revision is necessary whenever Cost Surveys are amended.
— Yearly revision of Cost Estimation Parameters 2015.
Vol. 2 Government Cost Estimators
— Revision is necessary whenever work/service items are added or excluded.
— Yearly revision of Cost Estimation Parameters 2015.
Vol. 3 Contractors
— Revision is necessary to synchronize with the revision made in Vol.2.
— Yearly revision of Cost Estimation Parameters 2015 for Use by Contractors.
Appendix 1 COST Estimation System 2015 For Cost Estimation Administrators .................................... 33
Appendix 2 Cost Estimation Parameters 2015.......................................................................................... 46
Appendix 3 Concept of SRUQ / Productivity Rate (P/R)........................................................................... 49
Appendix 4 Form 1 Site Layout ................................................................................................................. 52
Appendix 5 Form 2 Work Record Form ................................................................................................... 53
Appendix 6 Form 3 Productivity Survey Summary Form (Excel)................................................................ 54
Appendix 7 Information on Volume 3 for Contractors’ Reference Use .................................................... 55
Appendix 8 Training Results for PR Survey done by JICA/KRB in September and October 2015 ............. 56
Appendix 9 Recommendations by KRB on Indirect Cost, Overhead/profit and Build-up of Unit Rates ... 92
Other PBC Works (Optional)
COSTES PBC Works Editor Select Required Work Item and input/modify price & quantity
Instructed Works (Optional)
COSTES Instructed Works Editor Select Instructed Work Item and input/modify price & quantity
Output
(Legend)
Procedure
Program Window Name User Input
Figure 2.2 – Basic Data input and Program flow inside the COSTES2015
password
username Selection from “Road
Letter String (any numbers of characters including number,
Authority”, “Contrac
Main menu recognizes
alphabet, symbols)
password Letter String (anypassword
numbers of characters in
Road Authority Links to the list of “Road “Road Authority” in “Others” Table -
Authority” in “Others”
Table
SRUQ: One of the list consists Specifies types of work. Values are for: “GC (Grass 1.5/5.2/6.2
of “GC”, “CC”, “BC”, Cutting)”, “CC (Cross Culvert”, “BC (Catch Basin
“LD”, “UD”, “CW” Cleaning)”, “LD (Lined Ditch Cleaning”, “UD (Unlined
ditch Cleaning)”, and “CW (Carriage Way Cleaning)”.
IMP/Routine_ Selection from “IMP” or Initial Mobilization Period (IMP) or Routine Maintenance
Maintenance_Period “RMP” Period (RMP)
SRUQ Decimal Number/ 0 to Defined as how many labour-days are necessary for
100 doing each task for pre-determined unit when carrying
(any number of decimal out maintenance to SIMPLE quantity.
places)
SRUQ2 Decimal Number/ 0 to Defined as how many labour-days are necessary for
100 doing each task for pre-determined unit when carrying
(any number of decimal out maintenance to ACTUAL quantity.
places)
Quantity/1km Decimal Number/ 0 to Defined as the quantity of subject maintenance work 5.6
100 per km. This value is collected through survey.
(any number of decimal
places)
Year Numeric value / 2010 The year when the Productivity Rate / SRUQ is -
to 2030 surveyed
The Work_Difficulty_Level allocated to IMP and RMP, in accordance with the prevailing season, are as follows:
Wet Normal
RMP
Dry Light
Users can calculate work quantities by choosing one of the following formulas in COSTES:
1: Quantity per km: SRUQ (Standard Resource Usage per Quantity)* (Simple quantity per km)* (Project
Length)
2: Simple quantity input: SRUQ (Standard Resource Usage per Quantity) for SIMPLE Quantity *(Simple
Quantity input)
3: Actual quantity input: SRUQ for ACTUAL Quantity input * (Actual Quantity input)
In the case of 2 and 3 above, users have to collect the information of total quantity of the project prior to the
cost estimation.
Conversion between Productivity Rate and Standard Resource Usage per Quantity is described in Clause 1.5 of
the Manual.
Item Selection from “Labour”, Classification of each item (Category) Labour, Machinery, or 5.1
“Machinery”, or ”Material” Material
Location Letter String Tables should complete 11 sets of unit price data for each 5.1
area. At present “Nairobi, Mombasa, Kisumu” and (All other
area) are listed as sample.
Code Letter String Sample data. Allocate unique code number (not used for the 5.1
current COSTES).
Name Selection from specified list DO NOT Change the name for 11 price set. 5.1
“Labours”, “Supervisors”(Foreman)”, “Fuel”, “SCU Leader”,
“SCU Inspector”, “Driver”, “Vehicle (Pick up)”, “Foreman”,
“Fuel”, “Vehicle (2ton Truck)”
Type: Selection from specified list “Petrol” or “Diesel” for Fuel. “Operating Loss” for Vehicle. 5.1
Blank for others
Unit Automatic selection linked to Unit for each item. Current COSTES does not use it. 5.1
the “Name”
Source Letter String For reference purpose. Current COSTES does not use it. 5.1
Survey Year Numeric value / 2010 to 2030 The year when the unit price was surveyed and collected. 5.1
COSTES automatically selects the latest year’s unit price if
unit price was surveyed for several years.
Area Letter String Area is necessary if the same work item has a different 5.4
value
Category Selection from “Road Usability”, Category is based on Table 4-19 in the manual 4/5.4
“Road User Comfort”, or “Road
Durability”
Service Scope Selection from A) through to H) Category is based on Table 4-19 in the manual vol.2 4/5.4
Work Item Letter String Category is based on Table 4-19 in the manual but 5.4
expressed as “Service Criteria”
Survey Year Numeric value / 2010 to 2030 The year when each item was collected. COSTES 5.4
recognizes the latest year’s unit price if the same item
has different value by surveyed year
Unit Price Numeric value / 0 to 1000000 Current COSTES does not use Unit Price (Future 5.4
Option)
If the COSTES file set is distributed to contractor
candidates, unit price should be zero for all items
in the database.
Code Letter String COSTES does not use the code but may be necessary
for the arrangement of items
Unit Rate Numeric value / 0 to 1,000,000 Rate for each item per specified unit
If the COSTES file set is distributed to contractor
candidates, unit rate should be zero for all items
in the database.
Work Item Letter String Category for the item. Suffix as xx. Is preferred
Area Letter String Area is necessary if the same work items have different
values
Survey Year Numeric value / 2010 to 2030 The year when each item was collected. COSTES
recognizes the latest year’s unit price if the same item
has different value by surveyed year
When this option is “YES”, COSTES generates not only PDF format cost estimation sheets but also excel
format raw-data.
9. Data Distribution
9.1 For Road Authority Officials (Client)/ 8.2 For Contractor Candidates
The difference of database between two user categories is whether the database has “Price” information or not.
Price information is included in “UnitPrice1”, “Other PBC Works”, and “Instructed Works” tables.
Road Authorities can use the pre-surveyed unit price as standard value. Then they can check the price before
performing cost estimation and modify if possible. Contractor candidates have to register all price sets by their
own survey or responsibility. No price data will be given.
COSTES program can automatically open the jicadata database because the password is included in the program
and almost impossible to open the jicadata database unless one has the password. However, distribution
version to the contractor candidates should not include any price data for security purposes. In this case, it is
recommended that administrators should create two types of database: (1) one including price information:
and, (2), another without price information. Please do not remove all the columns of price information because
COSTES have to recognize all data fields regardless of the column value.
P/R(Simple) SRUQ(Simple)
Work item Level Unit Unit
Heavy 300.0 0.0033
Normal 1,383.7 0.0007
Grass Cutting (m2) m2/md md/m2
Light 3,304.0 0.0003
Total(Ave.) 1,900.3 0.0005
Heavy 11.5 0.0869
Normal 86.1 0.0116
Cross Culvert (m) m/md md/m
Light 155.3 0.0064
Total(Ave.) 17.5 0.0570
Heavy 2.6 0.3810
Normal 15.0 0.0667
Catch Basin (pcs) pcs/md md/pcs
Light 69.5 0.0144
Total(Ave.) 22.2 0.0449
Heavy 31.9 0.0313
Normal 90.6 0.0110
Lined Side Ditch (m) m/md md/m
Light 1,217.5 0.0008
Total(Ave.) 203.8 0.0049
Heavy 114.7 0.0087
Normal 117.1 0.0085
Unlined Side Ditch (m) m/md md/m
Light 1,693.0 0.0006
Total(Ave.) 115.2 0.0087
Heavy 156.6 0.0064
Normal 365.5 0.0027
Carrageway De-silting (m2) m2/md md/m2
Light 904.8 0.0011
Total(Ave.) 573.0 0.0017
* use for COSTES
KeNHA (2×2Lanes)
Item Unit Simple Quantity/1km Actual/Simple Actual Quantity/1km
Grass Cutting m2 12110 33% 4,036.7
Cross Culvert m 200 64% 129.0
Catch Basin Pcs 20 33% 6.7
Lined Dich m 400 50% 199.0
Unlined Ditch m 2800 35% 992.9
Carriageway m2 4000 32% 1,278.0
Note: Figures are from survey on the Paved Road
KURA
Item Unit Simple Quantity/1km Actual/Simple Actual Quantity/1km
Grass Cutting m 2
6819 33% 2,273.0
Cross Culvert m 100 64% 64.5
Catch Basin Pcs 50 33% 16.7
Lined Dich m 1400 50% 696.5
Unlined Ditch m 200 35% 70.9
Carriageway m 2
2000 32% 639.0
Note: Figures are from survey on the Paved Road
KeRRA
Item Unit Simple Quantity/1km Actual/Simple Actual Quantity/1km
Grass Cutting m 2
2310 33% 777.0
Cross Culvert m 10 64% 6.5
Catch Basin Pcs 10 33% 3.3
Lined Dich m 0 -
Unlined Ditch m 1800 35% 638.3
Carriageway m 2
0 -
Note: Figures are from survey on the Unpaved Road
KWS
Item Unit Simple Quantity/1km Actual/Simple Actual Quantity/1km
Grass Cutting m 2
2310 33% 770.0
Cross Culvert m 10 64% 6.5
Catch Basin pcs 10 33% 3.3
Lined Dich m 0 -
Unlined Ditch m 1800 35% 638.3
Carriageway m 2
0 -
Note: Figures are from survey on the Unpaved Road
3. Unit Rates
Note
i
COLUMN 2 in the Labour Institution Act dated the 20th May, 2015
ii
COLUMN 4 in the Labour Institution Act dated the 20th May, 2015. Column 3 has been used to estimate General labour rate
in the case of Other Areas after considering the market rates.
iii
Factor for market price
iv
Fees of Mechanical and Technical Services of MOTI Mechanical and Transport Division
Truck flat-bed (2.5-5 ton); (1,480×7hrs×25days+3000×5days×0.7iii) = 191,800 Pick Up (4x4);
1,050×4hrs×30days×0.7iii = 88,200
v
Pump Price for Sep-Oct 2015 from Energy Regulatory Commission
4. Percentage Add-ons(%)
% 5.0 30 10 16.0
Unit rates
Direct Cost
SRUQ is the conversion rate from Q’ty1 / Work Volume to Q’ty2 / Basic Items (means breakdown of labour,
equipment, material required for the work). Examples of SRUQ for concrete mixing are shown in the following
table.
Table A3-2 Example of SRUQ (concrete mixing)
(per 10m3)
Quantity 1 Concrete m3 - - -
Sand m 3
5.5 200 Ksh 1100 5% loss included
Unit Rates
for concrete
mixing
462.5 Ksh/m3
Work Items Scope of Work Unit Q’ty1 P/R Q’ty2 (Labour, Materials, etc)
Two samples for work items / Q’ty1 for PBC road maintenance works are shown below.
Table A3-4 Work Items and SRUQ for PBC Road Maintenance (individual)
Grass cutting Cutting, Piling, loading m2 Area for grass cutting P/Rlme man day L/M/EE
Clearing obstructions Picking up, piling, hauling m2 Area of carriage way P/Rlme man day L/M/EE
Desilting Picking up, piling, hauling m Length or number of P/Rlme man day L/M/EE
drainages
Cleaning cleaning, piling, hauling m2 Maintained area P/Rlme man day L/M/EE
Pruning trees Pruning, hauling m2 Area of carriage way P/Rlme man day L/M/EE
Table A3-5 Work Items and SRUQ for PBC Road Maintenance (average)
Maintenance works All work items m2 Maintained area SRUQlme man day L/M/EE
Figure A3-2 Example of SRUQ =5 (persons day/10000m2) and SRUQ= 10 for maintenance Works
Location: Weather:
Work Item Number of workers Start time End time workin hours Work measurement Work volume Unit Remark
APPENDIX 6
54
Remarks
Worked Items Q’ty working SRUQ SRUQ
Q’ty Unit Unit -Heavy nos nos nos (Equipment)
(Vol) hours (man day/ (man day/
Remarks -Normal Remark Qty) Qty)
-Light
a b c d e f j=e×f Man day ps = j / 7a pa= j / 7b
Grass Cutting(1) / Left m2 m 2
GW x L
1)
Grass Cutting(2) / Right m2 m2 GW x L
Pcs Pcs
Cross Culvert(1)
m m
2)
Pcs
Cross Culvert(2)
m
Catch Basin / Cover(1) Pcs
Catch Basin / Cover(2) Pcs
3)
Catch Basin / No cover(1) Pcs
Catch Basin / No cover(2) Pcs
Lined Side Ditch(1) m L
4)
Lined Side Ditch(2) m L
The computer system COSTES for PBC 2015 is to be used in conjunction with Volumes 1 and 2, whereas
COSTES for PBC 2015 for Contractors is to be used especially for cost estimators from private contractors
using Volume 3.
Since the Cost Estimation Manual for Road Maintenance under Performance Based Contracts has been developed
essentially for use by government officials and Volume 3 has been prepared for reference use by contractors, the
following restrictions have been placed on Volume 3 to safeguard information which should only be confidential
to government officials.
(This applies same as for COSTES for PBC 2015 for Contractors.)
1. Cost Estimation Parameters 2015 used in Volume 3 has no information on unit rates and percentage
add-ons. However, Volume 3 has information on productivity rates such as SRUQs and P/Rs only.
Volumes 1 and 2 have all information.
In COSTES for PBC 2015, cost estimators for contractors are required to use their own unit rates and
percentage add-ons to obtain the Project Cost.
2. For cost estimation for the 6 Major Labour Based Works, Volumes 1 and 2 includes three types of cost
estimation including the type using KM Standardized Quantity. Volume 3 does not include the type
using KM Standardized Quantity.
Form-2
Form-3
Productivity Survey Summary Form Labour Based Works
Location Kerugoya Client KURA Site Kerugoya - Hit Transporters Weather Sunny Initial Mobilization Period / Routine Maintenance No. 69
Width of Road 12.50 m Width of Carriage 6m Left Lined Ditch 0m Right Lined 0m Grass Cutting Width 6.50 m Total 0m Number of Labors 0 Men
Reserve (Wr) Way (Wc) (LL) Ditch (RL) (GW)=(Wr)-(Wc)-(LL)-(RL) Length 10/1/2015
Note: 389.88006
272.916042
To use one sheet per day
To fill only the number of workers who are engaged in PBC works
Total number of workers or equipment shall tally the number of workers or equipment for PBC works on site.
To specify structures to be maintained
To fill the maintained Q'ty which includes places/areas that don’t require any actual maintenance works
Form-2
Form-3
Productivity Survey Summary Form Labour Based Works
Location Kerugoya Client KURA Site KeNHA rd Weather Sunny Initial Mobilization Period / Routine Maintenance No. 70
Width of Road Width of Carriage Left Lined Ditch Right Lined Grass Cutting Width Total
21.20 m 6m 0m 0m 15.50 m 0m Number of Labors 0 Men 20/2/2015
Reserve (Wr) Way (Wc) (LL) Ditch (RL) (GW)=(Wr)-(Wc)-(LL)-(RL) Length
Form-1
Form-2
Form-3 Form-3
Form-3
Productivity Survey Summary Form Labor Based Works
Location Nairobi Client KURA Site Processional way Weather Sunny Initial Mobilization Period / Routine Maintenance
Width of Road Left Lined Ditch Right Lined Grass Cutting Width Number of
37.90 m Width of Carriage Way (Wc) 7.2 m 0m 1.2 m 29.50 m Total Length 0m 0 men 2015/10/5
Reserve (Wr) (LL) Ditch (RL) (GW)=(Wr)-(Wc)-(LL)-(RL) Labors
Simple Quantity Actual Quantity Work Difficulty Foreman Supervisor Labors (4) (5)
Simple Actual
SRUQ SRUQ Remarks
Worked Items
Q'ty Unit Q'ty (Vol) Unit nos nos nos working hours (man day/Qty) (man day/Qty) (Equipment)
-Heavy
Remarks Remark
-Normal
a b -Light c d e f j=e×f Man day ps = j / 7a pa= j / 7b
Total 2 2 2
Note) To use one sheet per day 0.3 1day = 7 working hours
To fill only the number of workers who are engaged in PBC works Man Day
Total number of workers or equipment shall tally the number of workers or equipment for PBC works on site.
To specify structures to be maintained
To fill the maintained Q'ty which includes places/areas that don’t require any actual maintenance works
Form-1
Form-2
Form-2
Form-3 Form-3
Form-3
Productivity Survey Summary Form Labor Based Works
Location Kerugoya Client KURA Site KeNHA rd Weather Sunny Initial Mobilization Period / Routine Maintenance No. 66 (C)
Width of Road Left Lined Ditch Right Lined Grass Cutting Width Number of
21.20 m Width of Carriage Way (Wc) 6m 0m 0m 15.20 m Total Length 0m 0 men 2015/10/2
Reserve (Wr) (LL) Ditch (RL) (GW)=(Wr)-(Wc)-(LL)-(RL) Labors
Simple Quantity Actual Quantity Work Difficulty Foreman Supervisor Labors (4) (5)
Simple Actual
SRUQ SRUQ Remarks
Worked Items
Q'ty Unit Q'ty (Vol) Unit nos nos nos working hours (man day/Qty) (man day/Qty) (Equipment)
-Heavy
Remarks Remark
-Normal
a b -Light c d e f j=e×f Man day ps = j / 7a pa= j / 7b
Note) To use one sheet per day 0.4 1day = 7 working hours
To fill only the number of workers who are engaged in PBC works Man Day
Total number of workers or equipment shall tally the number of workers or equipment for PBC works on site.
To specify structures to be maintained
To fill the maintained Q'ty which includes places/areas that don’t require any actual maintenance works
APPENDIX 8
62
Lined Side Ditch(1) Lined Side Ditch(2) Unlined Side ditch(1) Unlined Side ditch(2) Carriage De-sliting(1) Carriage De-sliting(2)
Grass Cutting1 Grass Cutting2 Cross Culvert(1) Catch Basin / No Cover(1) Catch Basin / No cover(2)
/de-silted volume /de-silted volume / de-silted volume / de-silted volume / de-silted area / de-silted area
Name of Project
Length m2 md m2 md pcs pcs pcs m m m m m2 m2
RA
Maintained Simple Actual Labour Simple Actual Labour Simple Actual Labour Simple Actual Labour Simple Actual Labour Simple Actual Labour Simple Actual Labour Simple Actual Labour Simple Actual Labour Simple Actual Labour Simple Actual Labour
Person Person Person Person Person Person Person Person Person Person Person
day day day day day day day day day day day
1 Kirichwa(1) KURA 200.0 2,800.0 337.9 1.00 Normal 200.0 12.9 1.71 Normal 200.0 7.5 0.90 Normal 200.0 97.2 1.71 Normal 200.0 85.0 1.71 Normal
2 kirichwa(2) KURA 370.5 4,075.5 664.9 3.57 Normal 1.0 1.0 1.14 Heavy 370.5 28.0 4.29 Normal 370.5 70.5 3.75 Normal 370.5 70.5 3.75 Normal
3 Kirichwa(3) KURA 303.0 3,333.0 168.8 0.29 Normal 3,333.0 178.2 0.14 Normal 303.0 189.0 2.57 Normal 303.0 110.0 1.71 Normal 303.0 90.0 0.86 Normal 303.0 43.4 0.57 Normal
COST ESTIMATION MANUAL FOR PERFORMANCE BASED ROAD MAINTENANCE CONTRACT
4 Excel Industries KURA 331.0 331.0 39.0 0.86 Normal 331.0 29.0 0.86 Normal 331.0 50.0 0.48 Light 331.0 119.7 0.14 Light
5 Likoni Rd KURA 112.8 282.0 268.4 1.14 Normal 564.0 456.8 1.14 Normal
6 Dennis Prit Rd KURA 210.0 2,079.0 91.0 0.74 Normal 192.4 109.0 1.24 Normal 210.0 31.5 0.66 Normal 210.0 31.5 0.66 Normal
7 Dorobo Rd KURA 304.0 1,124.8 447.7 1.47 Normal 1,124.8 478.8 0.67 Normal 304.0 91.2 0.86 Normal 486.4 347.4 0.57 Normal
8 Jabavu Lane KURA 236.0 967.6 484.2 0.43 Normal 967.6 94.0 0.33 Normal 236.0 125.6 0.86 Normal 236.0 73.7 1.05 Normal 236.0 71.0 0.43 Normal 236.0 40.5 0.64 Normal
9 Theta Lane KURA 65.0 84.5 52.0 0.29 Normal 84.5 49.2 0.86 Normal
10 Processional Way 1st day KURA 483.4 5,680.0 873.5 1.14 Light 5,680.0 948.7 1.14 Light 483.4 483.4 0.29 Light 483.4 115.6 0.29 Light 483.4 119.7 0.57 Light
11 Processional Way 2nd day KURA 126.3 1,484.0 647.9 0.86 Normal 1,484.0 948.7 0.64 Normal
12 Ralph Bunche Rd KURA 352.6 4,513.3 350.3 0.29 Light 4,513.3 398.7 0.36 Light 352.6 64.0 0.29 Normal 352.6 211.6 1.00 Normal 352.6 154.7 0.71 Normal
13 Access to Excel undust1 KURA 435.5 435.5 88.3 0.52 Normal 435.5 266.6 0.29 Light 435.5 265.7 0.93 Light 435.5 44.1 0.14 Light
14 Access to Excel undust2 KURA 111.1 111.1 96.1 0.43 Light
15 Eastern Bypass service lane KURA 245.5 245.5 245.5 0.57 Light 245.5 54.0 0.29 Light
16 Excel Indust20150303(1). KURA 225.6 2,639.5 1,266.6 0.64 Normal 225.6 67.6 0.81 Normal 225.6 67.7 0.59 Normal 225.6 30.6 0.29 Normal
17 Excel Indust20150303(2). KURA 166.3 166.3 166.3 0.33 Light
18 eastern service lane KURA 169.0 169.0 169.0 0.86 Normal
19 Eastern Bypass (SL1) KURA 316.0 316.0 163.1 3.57 Normal
20 Eastern Bypass (SL2) KURA 230.0 598.0 598.0 2.14 Normal
21 Link rd off airport n/s KURA 3.0 3.0 3.0 1.14 Heavy
22 Service lane near cabanas KURA 294.3 3,796.5 51.9 0.29 Normal 294.3 90.1 1.14 Light
23 Service Lane KURA 210.7 210.7 22.7 1.14 Light
24 Link rd off airport n/s KURA 5.4 5.4 5.4 1.71 Heavy
25 Eastern Bypass SL KURA 77.6 77.6 46.9 1.79 Normal
TRAINING RESULTS FOR PR SURVEY DONE BY JICA/KRB IN SEPTEMBER AND OCTOBER 2015
26 Mombasa Rd-Eastern Bypass KURA 200.7 200.7 150.7 3.36 Normal
27 4th Ngong Avenue KURA 374.6 52.0 52.0 0.14 Light 70.2 70.2 0.14 Light 374.6 112.4 0.74 Normal
28 5th Ngong Avenue KURA 384.6 384.6 14.6 0.04 light 384.6 65.3 0.29 Normal
29 3rd Ngong Avenue KURA 158.7 53.1 53.1 0.05 Light 158.7 15.9 0.14 Normal 158.7 31.7 0.29 Normal
30 Jabavu Road KURA 667.5 1,802.3 25.0 0.02 Light 122.0 122.0 0.19 Light 667.5 209.9 0.71 Light 667.5 251.5 0.71 Light
31 1st Ngong Avenue KURA 320.0 320.0 84.9 0.25 Light 320.0 31.8 0.11 Light
32 3rd Ngong Avenue KURA 165.0 145.0 72.0 0.29 Light 165.0 82.5 0.14 Light
33 Muringa road KURA 272.7 886.3 40.0 0.07 Light 886.3 24.0 0.12 Light 272.7 159.4 0.36 Light 272.7 127.0 0.40 Light 272.7 72.7 0.29 Light 272.7 136.4 0.14 Light
34 Ndemi Road KURA 640.0 640.0 341.3 0.33 Light 640.0 205.8 0.33 Light 640.0 184.8 0.29 Light 640.0 188.7 0.29 Light
35 Statehouse Road KURA 1,499.2 1,499.2 456.7 0.57 Light 1,499.2 552.5 0.43 Light 1,499.2 449.8 1.14 Light 1,499.0 434.2 1.14 Light
36 Turbo Road KURA 435.6 53.9 53.9 1.57 Heavy 435.6 139.8 1.19 Normal
37 Elgeyo Marakwet Rd KURA 621.2 621.2 350.2 0.57 Light 621.2 522.9 0.60 Light 621.2 184.6 0.64 Light 621.2 178.1 0.57 Light
38 Makindi Rd KURA 498.6 498.6 96.8 0.36 Light 498.6 68.1 0.31 Light
39 Elgeyo Marakwet Rd KURA 79.8 79.8 69.4 0.10 Light
40 Gacharage-DB Thika KeRRA 39.7 39.7 39.7 1.05 Heavy
41 Kangema - Kiriaini Rd KeRRA 259.7 259.7 102.7 3.04 Heavy
42 Gacharage-DB Thika KeRRA 732.4 1,062.0 732.4 0.67 Light 1,062.0 664.7 0.52 Light 732.4 271.0 3.86 Heavy 732.4 195.5 3.86 Heavy
43 Kangema - Kiriaini Rd KeRRA 153.4 153.4 153.4 3.38 Heavy
44 Gacharage-DB Thika KeRRA 220.4 220.4 220.4 1.38 Heavy
45 Kangema - Kiriaini Rd KeRRA 901.8 901.8 161.8 2.71 Heavy
46 Gacharage-DB Thika KeRRA 134.0 134.0 134.0 1.33 Heavy
47 Kangema - Kiriaini Rd KeRRA 438.2 1.0 1.0 0.01 Light 438.3 158.7 2.23 Heavy
48 Gacharage-DB Thika KeRRA 150.1 1.0 1.0 0.09 Light 150.1 150.1 1.71 Heavy
49 Kangema - Kiriaini Rd KeRRA 56.9 56.9 56.9 2.38 Heavy
50 Kisii-kilgoris(boroko) KeNHA 16.6 1.0 1.0 0.12 Heavy 16.6 16.6 4.70 Heavy
51 Kisii-kilgoris(Magena) KeNHA 4.3 4.3 4.3 7.28 Heavy
52 Kisii-kilgoris(Magena) KeNHA 5.8 3.3 3.3 4.57 Heavy 5.8 5.8 2.14 Heavy
53 Kisii-kilgoris(Ogembo) KeNHA 439.0 3,029.1 746.3 0.36 Light 3,029.1 867.1 0.36 Light
54 Kisii-kilgoris(Nyangusu) KeNHA 6.4 1.0 1.0 0.05 Heavy 6.4 6.4 3.39 Heavy
55 Kisii-kilgoris(Menyinkwa) KeNHA 516.7 12.0 1.0 0.02 Normal 516.7 21.7 4.70 Heavy
56 Kisii-kilgoris(near kisii town) KeNHA 131.1 6.9 6.9 0.12 Normal 131.1 100.7 4.33 Normal
57 Kisii-kilgoris(near kisii town) KeNHA 213.0 2,023.5 638.6 0.40 Light 2,023.5 231.9 0.40 Light 213.0 54.4 3.07 Normal 213.0 19.5 0.86 Normal
58 Kisii-kilgoris(Menyinkwa) KeNHA 376.9 376.9 8.9 0.36 Normal
59 Kisii-kilgoris(kisii town) KeNHA 130.7 1.0 1.0 0.14 Light 65.4 36.2 0.74 Normal 65.4 13.0 0.64 Normal
60 Kisii-kilgoris(kisii town) KeNHA 140.4 70.2 58.8 1.33 Heavy 70.2 65.4 1.33 Heavy
61 Lanet njoro (pipeline) KeNHA 74.5 74.5 20.3 0.40 Normal
62 Lanet njoro (near pipeline) KeNHA 87.6 1.0 1.0 0.05 Light 85.7 85.7 0.19 Light 87.6 26.3 0.19 Light
63 Lanet njoro (Nakuru twn) KeNHA 215.2 4.5 4.5 0.21 Heavy 4.0 4.0 0.11 Light 107.6 96.9 2.50 Heavy 107.6 118.3 1.01 Light
64 Lanet njoro (pipeline) KeNHA 32.7 19.9 19.9 1.81 Heavy 12.8 12.8 0.81 Heavy
65 Lanet njoro (Nakuru twn) KeNHA 129.0 1.0 1.0 0.02 Light 61.7 61.7 2.71 Heavy 67.3 67.3 0.86 Normal
66(A) Lanet njoro (pipeline)(A) KeNHA 42.8 21.4 20.5 0.56 Normal 21.4 12.0 0.63 Normal
66(B) Lanet njoro (pipeline)(B) KeNHA 42.8 21.4 7.7 0.77 Normal 21.4 6.5 0.14 Normal
66(C) Lanet njoro (pipeline)(C). KeNHA 21.8 21.4 13.9 0.85 Normal
67 Lanet njoro (pipeline) KeNHA 20.0 10.0 6.1 0.49 Normal 10.0 6.9 0.46 Normal
68 Lanet njoro (Nakuru twn) KeNHA 74.3 5.5 5.5 1.24 Heavy 2.0 2.0 0.05 Light 17.8 17.8 0.38 Heavy 56.5 56.5 0.62 Heavy
69 Kerugoya1 KURA 15.5 15.5 0.05 Normal 74.3 52.0 0.19 Heavy
70 Kerugoya2 KURA 43.70 22.68 0.14 Normal 7.7 7.7 0.21 Normal
71 Processional Way KURA
72 Kerugoya3 KeRRA 639.2 538.9 0.43 Normal 940.00 737.50 0.43 Normal
Heavy 0 0 0.00 0 0 0.00 12 12 1.62 1 1 1.14 0 0 0.00 327 305 23.20 133 128 4.10 3,646 1,513 37.68 745 208 4.67 74 52 0.19 0 0 0.00
Normal 23,306 5,020 0.00 8,542 2,966 4.36 27 16 0.36 0 0 0.00 0 0 0.00 2,556 881 21.21 1,217 321 5.50 1,253 368 8.69 352 164 3.81 3,649 1,620 16.45 2,054 702 3.44
Light 18,997 3,406 2.96 16,132 2,470 2.38 0 0 0.00 11 11 0.48 0 0 0.00 4,432 2,681 4.12 2,869 1,917 3.49 0 0 0.00 0 0 0.00 6,891 1,940 8.17 5,934 1,655 4.27
Heavy 0 0 0 0 0 0 4 4 4 1 1 1 0 0 0 9 9 9 3 3 3 14 14 14 2 2 2 1 1 1 0 0 0
counts Normal 11 11 11 7 7 7 3 3 3 0 0 0 0 0 0 11 11 11 6 6 6 10 10 10 5 5 5 12 12 12 7 7 7
Light 7 7 7 5 5 5 0 0 0 7 7 7 0 0 0 13 13 13 8 8 8 0 0 0 0 0 0 15 15 15 11 11 11
1.3. Example of P/R Computation Form
TRAINING RESULTS FOR PR SURVEY DONE BY JICA/KRB IN SEPTEMBER AND OCTOBER 2015
1.3. Updated P/R Computation Form for additional P/R Survey
Summary of SRUQ
Simple Actual Person*day P/R(Actual) SRUQ(Actual) SRUQ(Actual)*1000 Simple/Actual Actual/Simple P/R(Simple) SRUQ(Simple) SRUQ(Simple)*1000
Heavy No Data
Normal 31,847 7,986 4.355 1,833.8 0.000545328 0.55 8,859.7 0.000112871 0.11
Grass Cutting(m2)
Light 35,129 5,876 5.336 1,101.3 0.000907981 0.91 5,321.1 0.000187932 0.19
Total(Ave.) 66,976 13,863 10 1,430.5 0.00069906 0.70 483% 21% 6,911.3 0.00014469 0.14
Heavy 12 12 1.619 7.4 0.134916667 134.92 10.4 0.096419045 96.42
Normal 27 16 0.356 43.6 0.022921452 22.92 61.0 0.01638096 16.38
Cross Culvert(m)
Light No Data
Total(Ave.) 39 28 2 13.9 0.071703396 71.70 140% 71% 19.5 0.051243283 51.24
Heavy 1 1 1.143 0.9 1.142857143 1,142.86 0.9 1.142857143 1,142.86
Normal No Data
Catch Basin(pcs)
Light 11 11 0.475 23.2 0.043194805 43.19 23.2 0.043194805 43.19
Total(Ave.) 12 12 2 7.4 0.134833333 134.83 100% 100% 7.4 0.134833333 134.83
VOLUME 1: MANUAL FOR COST
Heavy 460 433 27.299 15.9 0.063070622 63.07 29.3 0.034084132 34.08
Normal 3,773 1,202 26.713 45.0 0.022230222 22.23 83.2 0.012013482 12.01
Lined Side Ditch(m)
Light 7,301 4,598 7.609 604.3 0.001654675 1.65 1,118.3 0.000894206 0.89
Total(Ave.) 11,534 6,233 62 101.1 0.009886347 9.89 185% 54% 187.2 0.005342702 5.34
Heavy 4,391 1,722 42.350 40.7 0.02459982 24.60 108.2 0.009245418 9.25
Normal 1,605 532 12.500 42.6 0.023489081 23.49 113.3 0.008827966 8.83
Unlined Side Ditch(m)
Light No Data
Total(Ave.) 5,997 2,254 55 41.1 0.024337549 24.34 266% 38% 109.3 0.009146848 9.15
Heavy No Data
Normal 5,703 2,322 19.893 116.7 0.008568364 8.57 365.5 0.002736169 2.74
Carrageway De-silting(m2)
Light 12,825 3,595 12.442 288.9 0.003460832 3.46 904.8 0.001105161 1.11
A8-8
Total(Ave.) 18,528 5,917 32 183.0 0.005464973 5.46 313% 32% 573.0 0.001745151 1.75
ESTIMATION ADMINISTRATORS
After Correction
P/R(Actual) Remarks SRUQ(Actual) SRUQ(Actual)*1000 Simple/Actual Actual/Simple P/R(Simple) SRUQ(Simple) SRUQ(Simple)*1000
Heavy 100 Assumption(From Normal and Little) 0.01 10.00 300.0 0.003333333 3.33
Normal 1,834 0.000545328 0.55 5,501.3 0.000181776 0.18
Grass Cutting(m2)
Light 1,101 0.000907981 0.91 3,304.0 0.00030266 0.30
Total(Ave.) 1,430 0.00069906 0.70 300% 33% 4,291.5 0.00023302 0.23
Heavy 7 0.134916667 134.92 (Assumption;3:1) 10.4 0.096419045 96.42
Normal 44 0.022921452 22.92 61.0 0.01638096 16.38
Cross Culvert(m)
Light 100 Assumption(From Heavy and Normal) 0.01 10.00 139.9 0.007146563 7.15
Total(Ave.) 14 0.071703396 71.70 140% 71% 19.5 0.051243283 51.24
Heavy 1 1.142857143 1,142.86 2.6 0.380952381 380.95
Normal 5 Assumption(From Heavy and Little) 0.2 200.00 15.0 0.066666667 66.67
Catch Basin(pcs)
Light 23 0.043194805 43.19 69.5 0.014398268 14.40
Total(Ave.) 7 0.134833333 134.83 300% 33% 22.2 0.044944444 44.94
Heavy 16 0.063070622 63.07 (Assumption;3:1) 29.3 0.034084132 34.08
Normal 45 0.022230222 22.23 83.2 0.012013482 12.01
Lined Side Ditch(m)
Light 604 0.001654675 1.65 1,118.3 0.000894206 0.89
Total(Ave.) 101 0.009886347 9.89 185% 54% 187.2 0.005342702 5.34
Heavy 41 0.02459982 24.60 108.2 0.009245418 9.25
Normal 43 0.023489081 23.49 113.3 0.008827966 8.83
Unlined Side Ditch(m)
Light 600 Assumption(From Lined Side Ditch Little) 0.001666667 1.67 1,596.5 0.000626388 0.63
Total(Ave.) 41 0.024337549 24.34 266% 38% 109.3 0.009146848 9.15
Heavy 50 Assumption(From Normal and Little) 0.02 20.00 156.6 0.006386678 6.39
Normal 117 0.008568364 8.57 365.5 0.002736169 2.74
Carrageway De-silting(m2)
Light 289 0.003460832 3.46 904.8 0.001105161 1.11
APPENDIX 8
Total(Ave.) 183 0.005464973 5.46 313% 32% 573.0 0.001745151 1.75
63
2. Analysis of PR Survey
APPENDIX 8
64
P-1
Surveyed Length
Sta. 0+000
Sta. 0+200
Sta. 0+400
Sta. 0+600
Sta. 0+800
Sta. 1+000
Boundary Normal 8 mh Normal 9 mh
TRAINING RESULTS FOR PR SURVEY DONE BY JICA/KRB IN SEPTEMBER AND OCTOBER 2015
Normal 12000m2 50m
Heavy 7 mh
Surveyed Width
Lined Ditch W=1.0m 200 mh
Heavy
6 mh
h 2 mh h 2 mh
Side Walk
15m
h h
18m 2 mh
Carriage Way 2 mh 18m
Side Walk
Note)
Condition Grass Cutting Cross Culvert Linded Ditch Unlined Ditch Carriage Way
No Grass / No Silt
TRAINING RESULTS FOR PR SURVEY DONE BY JICA/KRB IN SEPTEMBER AND OCTOBER 2015
P-2
Sta. 0+000 Surveyed Length
Sta. 0+200
Sta. 0+400
Sta. 0+600
Sta. 0+800
Sta. 1+000
Boundary Normal 10 mh Normal 11 mh
Surveyed Width
Lined Ditch W=1.0m 210 mh
Normal
2 mh
h 1 mh h 1 mh
VOLUME 1: MANUAL FOR COST ESTIMATION ADMINISTRATORS
Side Walk
Normal 1 0m mh Normal 0 5m 6 mh
A8-10
Side Walk
Note)
Condition Grass Cutting Cross Culvert Linded Ditch Unlined Ditch Carriage Way
No Grass / No Silt
APPENDIX 8
65
2.1.3. P-3 Project (2 lanes paved Road)/3
APPENDIX 8
66
P-3
Surveyed Length
Sta. 0+000
Sta. 0+200
Sta. 0+400
Sta. 0+600
Sta. 0+800
Sta. 1+000
COST ESTIMATION MANUAL FOR PERFORMANCE BASED ROAD MAINTENANCE CONTRACT
Surveyed Width
Lined Ditch W=1.0m 800 mh
Heavy
8 mh
Heavy 50 mh Heavy 100 mh
Side Walk
h 0 5m 0 5 mh h 0 5m 1 mh h 0 5m 2 mh
15m
Heavy
TRAINING RESULTS FOR PR SURVEY DONE BY JICA/KRB IN SEPTEMBER AND OCTOBER 2015
Heavy
18m 20 mh
Carriage Way 18 mh 18m
h 1 0m 1mh h 0 5m mh
A8-11
Side Walk
Note)
Condition Grass Cutting Cross Culvert Linded Ditch Unlined Ditch Carriage Way
No Grass / No Silt
TRAINING RESULTS FOR PR SURVEY DONE BY JICA/KRB IN SEPTEMBER AND OCTOBER 2015
P-4 Project (2 lanes
P-4
Surveyed Length
Sta. 0+000
Sta. 0+200
Sta. 0+400
Sta. 0+600
Sta. 0+800
Sta. 1+000
Boundary Heavy 20 mh Heavy 26 mh
h 1500m2 h 2000m2
h 2000m2 20 mh
20 mh 15 mh
h 1 000m2 50m
h 0 5 mh
Surveyed Width
Lined Ditch W=1.0m 50 mh
h
VOLUME 1: MANUALA8-12
0 5 mh
Heavy 40 mh Heavy 65 mh
Side Walk
Side Walk
Note)
Condition Grass Cutting Cross Culvert Linded Ditch Unlined Ditch Carriage Way
No Grass / No Silt
APPENDIX 8
67
2.1.5.
2.1.5.P-5 P-5
Project (2 lanes
(2paved
lanesRoad)/5
APPENDIX 8
Project paved Road)/5
68
P-5
Surveyed Length
Sta. 0+000
Sta. 0+200
Sta. 0+400
Sta. 0+600
Sta. 0+800
Sta. 1+000
Boundary h 1 mh h 1 mh
COST ESTIMATION MANUAL FOR PERFORMANCE BASED ROAD MAINTENANCE CONTRACT
Surveyed Width
Lined Ditch W=1.0m 150 mh
Heavy
10 mh
Normal 20 mh Normal 0 mh
Side Walk
TRAINING RESULTS FOR PR SURVEY DONE BY JICA/KRB IN SEPTEMBER AND OCTOBER 2015
A8-13
Side Walk
Note)
Condition Grass Cutting Cross Culvert Linded Ditch Unlined Ditch Carriage Way
No Grass / No Silt
TRAINING RESULTS FOR PR SURVEY DONE BY JICA/KRB IN SEPTEMBER AND OCTOBER 2015
2.1.6. P-6 Project (2 lanes paved Road)/6
P-6
Surveyed Length
Sta. 0+000
Sta. 0+200
Sta. 0+400
Sta. 0+600
Sta. 0+800
Sta. 1+000
Boundary h 2 mh h 1 mh
Surveyed Width
Lined Ditch W=1.0m 800 mh
VOLUME 1: MANUAL FOR COST ESTIMATION ADMINISTRATORS
Normal
1 mh
Heavy 50 mh Heavy 70 mh
Side Walk
h 0 5m 1 mh h 0 5m 1mh h 0 5m 2 mh
15m
Normal Normal
18m 2 mh
Carriage Way 2 mh 18m
h 1 0m 1mh h 0 5m mh
A8-14
Side Walk
Note)
Condition Grass Cutting Cross Culvert Linded Ditch Unlined Ditch Carriage Way
No Grass / No Silt
APPENDIX 8
69
2.1.7.
2.1.7. P-7 Project (2 lanes pavedpaved
Road)/7Road)/7
APPENDIX 8
P-7 Project (2 lanes
70
P-7
Sta. 0+000 Surveyed Length
Sta. 0+200
Sta. 0+400
Sta. 0+600
Sta. 0+800
Sta. 1+000
Boundary Heavy 40 mh Heavy 40 mh
COST ESTIMATION MANUAL FOR PERFORMANCE BASED ROAD MAINTENANCE CONTRACT
Surveyed Width
Lined Ditch W=1.0m 1000 mh
hl
1 mh
Heavy 90 mh Heavy 100 mh
Side Walk
TRAINING RESULTS FOR PR SURVEY DONE BY JICA/KRB IN SEPTEMBER AND OCTOBER 2015
A8-15
Side Walk
Note)
Condition Grass Cutting Cross Culvert Linded Ditch Unlined Ditch Carriage Way
No Grass / No Silt
TRAINING RESULTS FOR PR SURVEY DONE BY JICA/KRB IN SEPTEMBER AND OCTOBER 2015
2.1.8. P-8 Project (2 lanes paved Road)/8
P-8
Surveyed Length
Sta. 0+000
Sta. 0+200
Sta. 0+400
Sta. 0+600
Sta. 0+800
Sta. 1+000
Boundary Normal 15 mh Normal 15 mh
VOLUME 1: MANUAL FOR COST ESTIMATION ADMINISTRATORS
h 1500m2 h 2000m2
h 2000m2 10 mh
10 mh 10 mh
h 14000m2 50m
h 1 mh
Surveyed Width
Lined Ditch W=1.0m 80 mh
hl
1 mh
h 1 mh h 2 mh
Side Walk
h 0 5m 1 mh h 1 0m 2mh h 0 5m 2 mh
15m
h h
18m 2 mh
Carriage Way 2 mh 18m
h 1 0m 1mh h 0 5m 2 mh
A8-16
Side Walk
Note)
Condition Grass Cutting Cross Culvert Linded Ditch Unlined Ditch Carriage Way
No Grass / No Silt
APPENDIX 8
71
2.1.9. P-9 Project (4 lanes paved Road)/1
APPENDIX 8
72
Sta. 0+200
Sta. 0+400
Sta. 0+600
Sta. 0+800
Sta. 1+000
COST ESTIMATION MANUAL FOR PERFORMANCE BASED ROAD MAINTENANCE CONTRACT
Normal 6,000m2 80 mh
Normal 1800m2 0 mh Normal 2,500m2
Normal 40 mh
50m
1 mh Normal 1 mh
Lined Ditch W=1.0m
Normal 2 mh
Normal 20 mh Normal 0 mh Normal 10 mh
Side Walk
Surveyed Width
Heavy 0 5m 6mh
TRAINING RESULTS FOR PR SURVEY DONE BY JICA/KRB IN SEPTEMBER AND OCTOBER 2015
11m
Normal Normal
30m 30m
mh
Carriage Way mh 30m Normal 30m
4 mh
Heavy 1 0m 25 mh
Heavy 0 5m 6mh
A8-17
Heavy 0 5m 4 mh
11m
Heavy 0 5m 40 mh
Side Walk
Note)
Condition Grass Cutting Cross Culvert Linded Ditch Unlined Ditch Carriage Way
No Grass / No Silt
TRAINING RESULTS FOR PR SURVEY DONE BY JICA/KRB IN SEPTEMBER AND OCTOBER 2015
2.1.10. P-10 Project (4 lanes paved Road)/2
Sta. 0+200
Sta. 0+400
Sta. 0+600
Sta. 0+800
Sta. 1+000
Boundary h 2 mh h mh
VOLUME 1: MANUAL FOR COST ESTIMATION ADMINISTRATORS
h 8,000m2 45 mh
h 2,000m2 17 mh h 1,500m2
h 15 mh
50m
0 5 mh h 0 5 mh
Lined Ditch W=1.0m
h 1 mh
Normal 40 mh Normal 70 mh Normal 10 mh
Side Walk
Surveyed Width
h 1 0m mh
11m
h h
30m 30m
2 mh
Carriage Way 2 mh 30m h 30m
2 mh
h 1 0m mh
h 0 5m mh
A8-18
h 0 5m mh
11m
h 0 5m 6 mh
Side Walk
Note)
Condition Grass Cutting Cross Culvert Linded Ditch Unlined Ditch Carriage Way
No Grass / No Silt
APPENDIX 8
73
2.1.11. P-1 Project (2 lanes unpaved Road)/1
APPENDIX 8
74
P-11 (Unpaved)
Surveyed Length
COST ESTIMATION MANUAL FOR PERFORMANCE BASED ROAD MAINTENANCE CONTRACT
Sta. 0+000
Sta. 0+200
Sta. 0+400
Sta. 0+600
Sta. 0+800
Sta. 1+000
Boundary
Surveyed Width
Lined Ditch W=1.0m
h 4 mh h mh
TRAINING RESULTS FOR PR SURVEY DONE BY JICA/KRB IN SEPTEMBER AND OCTOBER 2015
Side Walk
15m
Normal Normal
18m 2 mh
Carriage Way 2 mh 18m
A8-19
Side Walk
Note)
Condition Grass Cutting Cross Culvert Linded Ditch Unlined Ditch Carriage Way
No Grass / No Silt
TRAINING RESULTS FOR PR SURVEY DONE BY JICA/KRB IN SEPTEMBER AND OCTOBER 2015
2.1.12. P-1 Project (2 lanes unpaved Road)/2
P-12 (Unpaved)
Surveyed Length
Sta. 0+000
Sta. 0+200
Sta. 0+400
Sta. 0+600
Sta. 0+800
Sta. 1+000
Boundary
Heavy 40 mh
10m
7 mh Heavy 9 mh
Surveyed Width
Lined Ditch W=1.0m
Normal 15 mh Normal 16 mh
Side Walk
15m
Heavy Heavy
18m 20 mh
Carriage Way 15 mh 18m
A8-20
Side Walk
ESTIMATION ADMINISTRATORS
Note)
Condition Grass Cutting Cross Culvert Linded Ditch Unlined Ditch Carriage Way
No Grass / No Silt
APPENDIX 8
75
APPENDIX 8 TRAINING RESULTS FOR PR SURVEY DONE BY JICA/KRB IN SEPTEMBER AND OCTOBER 2015
2.2.
2.2. Examples of Form-3
Ex-samples of Form-3
2.2.1.
2.2.1. P-1P-1
Project (2 lanes paved Road)/1
Project (2 lanes paved Road)/1
Form-3
Productivity Survey Summary Form Labor Based Works
2.2. Location Ex-samples of Form-3
P-1 Client P-1 Site P-1 Weather Sunny Initial Mobilization Period / Routine Maintenance No. 66 (C)
Width of Road Left Lined Ditch Right Lined Grass Cutting Width Number of
65.00 m Width of Carriage Way (Wc) 15 m 1m 0m 49.00 m Total Length 1000 m 0 men 2015/10/12
Reserve (Wr) (LL) Ditch (RL) (GW)=(Wr)-(Wc)-(LL)-(RL) Labors
2.2.1. P-1 Project (2 lanes paved Road)/1 Asset Quantity Labour Input SRUQ
Simple Quantity Actual Quantity Work Difficulty Foreman Supervisor Labors (4) (5)
Simple Actual
SRUQ SRUQ Remarks
Form-3 Worked Items
(Equipment)
Q'ty Unit Q'ty (Vol) Unit nos nos nos working hours (man day/Qty) (man day/Qty)
Productivity Survey Summary Form Labor Based Works -Heavy
Remarks Remark
-Normal
Location P-1 Client a P-1 Site b P-1
-Light Weather
c Sunny d e f Initial Mobilization
j=e×f Period / Routine
Man day ps Maintenance
= j / 7a pa= j / 7b No. 66 (C)
Width of Road Left Lined Ditch Right Lined Grass Cutting Width Number of
Grass (Wr) 65.00 m
Cutting(1) / Left Width of Carriage Way (Wc)
50,000.0 15
m2m GW x L (LL) 119,000.0
m m2(RL) Normal0 m 49.00 m Total Length 1 1000 m272 0 men 2015/10/12
Reserve Ditch (GW)=(Wr)-(Wc)-(LL)-(RL) Labors 272 38.85714286 0.0008 0.0020
1)
Grass Cutting(2) / Right m2 GW x L m2 0 0 #DIV/0! #DIV/0!
Asset Quantity Labour Input SRUQ
Pcs Pcs 0 0 #DIV/0! #DIV/0!
Cross Culvert(1)
54.0 Simple
m Quantity Actual
36.0Quantitym Light Work Difficulty Foreman Supervisor 1 Labors 4 4 0.571428571 (4)
0.0106 (5)
0.0159
2) Simple Actual
SRUQ SRUQ Remarks
Worked Items Pcs Pcs 0 0 #DIV/0! #DIV/0!
Cross Culvert(2) Q'ty Unit Q'ty (Vol) Unit nos nos nos working hours (man day/Qty) (man day/Qty) (Equipment)
m m -Heavy 0 0 #DIV/0! #DIV/0!
Remarks Remark
-Normal
Catch Basin / Cover(1) 3.0a Pcs 2.0b Pcs Heavy-Light c d e 1 f 13 j=e×f 13 1.857142857
Man day ps0.6190
= j / 7a 0.9286
pa= j / 7b
Catch Basin / Cover(2) Pcs Pcs 0 0 #DIV/0! #DIV/0!
3) Grass Cutting(1) / Left 50,000.0 m2 GW x L 19,000.0 m2 Normal 1 272 272 38.85714286 0.0008 0.0020
1) Catch Basin / No cover(1) Pcs Pcs 0 0 #DIV/0! #DIV/0!
Grass Cutting(2) / Right m2 GW x L m2 0 0 #DIV/0! #DIV/0!
Catch Basin / No cover(2) Pcs Pcs 0 0 #DIV/0! #DIV/0!
Pcs Pcs 0 0 #DIV/0! #DIV/0!
Lined Side
Cross Ditch(1)
Culvert(1) 600.0 m L 240.0 m Light 1 4 4 0.571428571 0.0010 0.0024
4) 54.0 m 36.0 m Light 1 4 4 0.571428571 0.0106 0.0159
2) Lined Side Ditch(2) m L m 0 0 #DIV/0! #DIV/0!
Pcs Pcs 0 0 #DIV/0! #DIV/0!
UnlinedCulvert(2)
Cross Side ditch(1) 640.0 m L 240.0 m Normal 1 17 17 2.428571429 0.0038 0.0101
5) m m 0 0 #DIV/0! #DIV/0!
Unlined Side ditch(2) m L m 0 0 #DIV/0! #DIV/0!
Catch Basin / Cover(1) 3.0 Pcs 2.0 Pcs Heavy 1 13 13 1.857142857 0.6190 0.9286
Carriage De-sliting(1) 1,000.0 m2 Lx1.0(m) 140.0 m2 Normal 1 8 8 1.142857143 0.0011 0.0082
6) Catch Basin / Cover(2) Pcs Pcs 0 0 #DIV/0! #DIV/0!
3) Carriage De-sliting(2) 1,000.0 m2 Lx1.0(m) 180.0 m2 1 11 11 1.571428571 0.0016 0.0087
Catch Basin / No cover(1) Pcs Pcs 0 0 #DIV/0! #DIV/0!
Total 7 329 329
Catch Basin / No cover(2) Pcs Pcs 0 0 #DIV/0! #DIV/0!
Note)
Lined Side Ditch(1) To use one sheet per day L 47.0 1day = 7 working hours
600.0 m 240.0 m Light 1 4 4 0.571428571 0.0010 0.0024
4) To fill only the number of workers who are engaged in PBC works Man Day
Lined Side Ditch(2) m tally the number Lof workers or equipment for PBC works
Total number of workers or equipment shall m on site. 0 0 #DIV/0! #DIV/0!875
Total
1,000.0 m2 Lx1.0(m) 180.0 m2 1
7
11
329
11
329
1.571428571 0.0016 0.0087
Note) To use one sheet per day 47.0 1day = 7 working hours
To fill only the number of workers who are engaged in PBC works Man Day
Form-3
Total number of workers or equipment shall tally the number of workers or equipment for PBC works on site. 875
Productivity Survey Summary Form Labor Based Works
To specify structures to be maintained 122.5
Location To fill the maintained Q'ty
P-2 which includes places/areas that don’t require any actual
Client Site maintenance works Weather Sunny Initial Mobilization Period / Routine Maintenance No. 66 (C)
Width of Road Left Lined Ditch Right Lined Grass Cutting Width Number of
65.00 m Width of Carriage Way (Wc) 15 m 1m 0m 49.00 m Total Length 1000 m 0 men 2015/10/12
Reserve (Wr) (LL) Ditch (RL) (GW)=(Wr)-(Wc)-(LL)-(RL) Labors
2.2.2.
2.2.2. P-2P-2
Project (2 lanes
Project (2paved
lanesRoad)/2
paved Road)/2 Asset Quantity Labour Input SRUQ
Simple Quantity Actual Quantity Work Difficulty Foreman Supervisor Labors (4) (5)
Simple Actual
SRUQ SRUQ Remarks
Form-3 Worked Items
(Equipment)
Q'ty Unit Q'ty (Vol) Unit nos nos nos working hours (man day/Qty) (man day/Qty)
Productivity Survey Summary Form Labor Based Works -Heavy
Remarks Remark
-Normal
Location P-2 Client a Site b -Light Weather
c Sunny d e f Initial Mobilization
j=e×f Period / Routine
Man day ps Maintenance
= j / 7a pa= j / 7b No. 66 (C)
Width of Road Left Lined Ditch Right Lined Grass Cutting Width Number of
Grass (Wr) 65.00 m
Cutting(1) / Left Width of Carriage Way (Wc)
50,000.0 15
m2m GW x L (LL) 120,000.0
m m2(RL) Normal0 m 49.00 m Total Length 1 1000 m294 0 men 2015/10/12
Reserve Ditch (GW)=(Wr)-(Wc)-(LL)-(RL) Labors 294 42 0.0008 0.0021
1)
Grass Cutting(2) / Right m2 GW x L m2 0 0 #DIV/0! #DIV/0!
Asset Quantity Labour Input SRUQ
Pcs Pcs 0 0 #DIV/0! #DIV/0!
Cross Culvert(1)
54.0 Simple
m Quantity Actual
36.0Quantitym Light Work Difficulty Foreman Supervisor 1 Labors 3 3 0.428571429 (4)
0.0079 (5)
0.0119
2) Simple Actual
SRUQ SRUQ Remarks
Worked Items Pcs Pcs 0 0 #DIV/0! #DIV/0!
Cross Culvert(2) Q'ty Unit Q'ty (Vol) Unit nos nos nos working hours (man day/Qty) (man day/Qty) (Equipment)
m m -Heavy 0 0 #DIV/0! #DIV/0!
Remarks Remark
-Normal
Catch Basin / Cover(1) 3.0a Pcs 2.0b Pcs Normal
-Light c d e 1 f 4 j=e×f 4 0.571428571
Man day ps0.1905
= j / 7a 0.2857
pa= j / 7b
Catch Basin / Cover(2) Pcs Pcs 0 0 #DIV/0! #DIV/0!
3) Grass Cutting(1) / Left 50,000.0 m2 GW x L 20,000.0 m2 Normal 1 294 294 42 0.0008 0.0021
1) Catch Basin / No cover(1) Pcs Pcs 0 0 #DIV/0! #DIV/0!
Grass Cutting(2) / Right m2 GW x L m2 0 0 #DIV/0! #DIV/0!
Catch Basin / No cover(2) Pcs Pcs 0 0 #DIV/0! #DIV/0!
Pcs Pcs 0 0 #DIV/0! #DIV/0!
Lined Side
Cross Ditch(1)
Culvert(1) 600.0 m L 280.0 m Light 1 2 2 0.29 0.0005 0.0010
4) 54.0 m 36.0 m Light 1 3 3 0.428571429 0.0079 0.0119
2) Lined Side Ditch(2) m m 0 0 #DIV/0! #DIV/0!
Pcs Pcs 0 0 #DIV/0! #DIV/0!
UnlinedCulvert(2)
Cross Side ditch(1) 640.0 m L 280.0 m Normal 1 21 21 3 0.0047 0.0107
5) m m 0 0 #DIV/0! #DIV/0!
Unlined Side ditch(2) m m 0 0 #DIV/0! #DIV/0!
Catch Basin / Cover(1) 3.0 Pcs 2.0 Pcs Normal 1 4 4 0.571428571 0.1905 0.2857
Carriage De-sliting(1) 1,000.0 m2 Lx1.0(m) 160.0 m2 Normal 1 9 9 1.285714286 0.0013 0.0080
6) Catch Basin / Cover(2) Pcs Pcs 0 0 #DIV/0! #DIV/0!
3) Carriage De-sliting(2) 1,000.0 m2 160.0 m2 Normal 1 9 9 1.285714286 0.0013 0.0080
Catch Basin / No cover(1) Pcs Pcs 0 0 #DIV/0! #DIV/0!
Total 7 342 342
Catch Basin / No cover(2) Pcs Pcs 0 0 #DIV/0! #DIV/0!
Note)
Lined Side Ditch(1) To use one sheet per day L 48.9 1day = 7 working hours
600.0 m 280.0 m Light 1 2 2 0.29 0.0005 0.0010
4) To fill only the number of workers who are engaged in PBC works Man Day
Lined Side Ditch(2) m tally the number of workers or equipment for PBC works
Total number of workers or equipment shall m on site. 0 0 #DIV/0! #DIV/0!
777.7777778
Unlined Side ditch(1) To specify structures to be 640.0
maintained m L 280.0 m Normal 1 21 21 3 0.0047 124.4444444
0.0107
5) To fill the maintained Q'ty which includes places/areas that don’t require any actual maintenance works
Unlined Side ditch(2) m m 0 0 #DIV/0! #DIV/0!
Note) To use one sheet per day 48.9 1day = 7 working hours
To fill only the number of workers who are engaged in PBC works Man Day
Total number of workers or equipment shall tally the number of workers or equipment for PBC works on site. 777.7777778
To specify structures to be maintained 124.4444444
To fill the maintained Q'ty which includes places/areas that don’t require any actual maintenance works
A8-21
TRAINING RESULTS FOR PR SURVEY DONE BY JICA/KRB IN SEPTEMBER AND OCTOBER 2015 APPENDIX 8
Labors (4)
SRUQ
(5)
Simple Actual
SRUQ SRUQ Remarks
Worked Items
Q'ty Unit Q'ty (Vol) Unit nos nos nos working hours (man day/Qty) (man day/Qty) (Equipment)
Form-3 -Heavy
Remarks Remark
Productivity Survey Summary Form Labor Based Works -Normal
a b -Light c d e f j=e×f Man day ps = j / 7a pa= j / 7b
Location P-3 Client Site Weather Sunny Initial Mobilization Period / Routine Maintenance No. 66 (C)
Grass Cutting(1) / Left 50,000.0 m2 GW x L 19,000.0 m2 Heavy 1 1350 1350 192.8571429 0.0039 0.0102
Width of Road Left Lined Ditch Right Lined Grass Cutting Width Number of
1) 65.00 m Width of Carriage Way (Wc) 15 m 1m 0m 49.00 m Total Length 1000 m 0 men 2015/10/12
Reserve (LL) Ditch (RL) (GW)=(Wr)-(Wc)-(LL)-(RL) Labors
Grass (Wr)
Cutting(2) / Right m2 GW x L m2 0 0 #DIV/0! #DIV/0!
Catch Basin
Note)/ No cover(2) To use one sheet per day Pcs Pcs 0
232.1 0 1day
#DIV/0! #DIV/0!
= 7 working hours
Carriage De-sliting(1) 1,000.0 m2 Lx1.0(m) 140.0 m2 Light 1 3.5 3.5 0.5 0.0005 0.0036
Note) To use one sheet per day 232.1 1day = 7 working hours
Form-3
To fill only the number of workers who are engaged in PBC works Man Day
Productivity Survey Summary Form Labor Based Works
Total number of workers or equipment shall tally the number of workers or equipment for PBC works on site. 2000
To specify structures to be maintained / Routine Maintenance 280
Location P-4 Client Site Weather Sunny Initial Mobilization Period No. 66 (C)
To fill the maintained Q'ty which includes places/areas that don’t require any actual maintenance works
Labors (4)
SRUQ
(5)
Simple Actual
SRUQ SRUQ Remarks
Worked Items
Q'ty Unit Q'ty (Vol) Unit nos nos nos working hours (man day/Qty) (man day/Qty) (Equipment)
Form-3 -Heavy
Remarks Remark
Productivity Survey Summary Form Labor Based Works -Normal
a b -Light c d e f j=e×f Man day ps = j / 7a pa= j / 7b
Location P-4 Client Site Weather Sunny Initial Mobilization Period / Routine Maintenance No. 66 (C)
Grass Cutting(1) / Left 50,000.0 m2 GW x L 18,500.0 m2 Light 1 105 105 15 0.0003 0.0008
Width of Road Left Lined Ditch Right Lined Grass Cutting Width Number of
1) 65.00 m Width of Carriage Way (Wc) 15 m 1m 0m 49.00 m Total Length 1000 m 0 men 2015/10/12
Reserve (LL) Ditch (RL) (GW)=(Wr)-(Wc)-(LL)-(RL) Labors
Grass (Wr)
Cutting(2) / Right m2 GW x L m2 0 0 #DIV/0! #DIV/0!
Catch Basin
Note)/ No cover(2) To use one sheet per day Pcs Pcs 0
42.6 0 1day
#DIV/0! #DIV/0!
= 7 working hours
Note) To use one sheet per day 42.6 1day = 7 working hours
To fill only the number of workers who are engaged in PBC works Man Day
Total number of workers or equipment shall tally the number of workers or equipment for PBC works on site. 280
To specify structures to be maintained 39.2
To fill the maintained Q'ty which includes places/areas that don’t require any actual maintenance works
A8-22
APPENDIX 8 TRAINING RESULTS FOR PR SURVEY DONE BY JICA/KRB IN SEPTEMBER AND OCTOBER 2015
2.2.5. P-5 Project (2 lanes paved Road)/5 Simple Quantity Actual Quantity Work Difficulty Foreman Supervisor Labors (4) (5)
Simple Actual
SRUQ SRUQ Remarks
Worked Items
Q'ty Unit Q'ty (Vol) Unit nos nos nos working hours (man day/Qty) (man day/Qty) (Equipment)
Form-3 -Heavy
Remarks Remark
-Normal
Productivity Survey Summary Form a Labor Based Works b -Light c d e f j=e×f Man day ps = j / 7a pa= j / 7b
Location P-5 Client Site Weather Sunny Initial Mobilization Period / Routine Maintenance No. 66 (C)
Grass Cutting(1) / Left 50,000.0 m2 GW x L 19,000.0 m2 Normal 1 245 245 35 0.0007 0.0018
1)Width of Road Left Lined Ditch Right Lined Grass Cutting Width Number of
Grass Cutting(2) / 65.00 m
Right Width of Carriage Way (Wc) 15
m2m GW x L (LL) 1m m2(RL) 0m 49.00 m Total Length 1000 m 0 men#DIV/0! 2015/10/12
Reserve (Wr) Ditch (GW)=(Wr)-(Wc)-(LL)-(RL) Labors 0 0 #DIV/0!
Carriage De-sliting(2)
1,000.0
1,000.0
m2
m2
Lx1.0(m) 160.0
140.0
m2
m2
Heavy 1
1
27
19
27
19
3.857142857
2.714285714
0.0039
0.0027
0.0241
0.0194
Form-3 Note) To use one sheet per day 52.6 1day = 7 working hours
To fillForm
Productivity Survey Summary only the number of workers who are engagedLabor
in PBC works
Based Works Man Day
Total number of workers or equipment shall tally the number of workers or equipment for PBC works on site. 259.2592593
Location P-6 Client Site Weather Sunny Initial Mobilization Period / Routine Maintenance No. 66 (C)
To specify structures to be maintained 41.48148148
2.2.6.
Width of Road
Reserve (Wr)
P-6 Project (2 lanes paved Road)/6
65.00 m
To fill the maintained Q'ty which includes places/areasLeft
Width of Carriage Way (Wc) 15 m
thatLined
don’tDitch
(LL)
require any actual maintenance
1m
Rightworks
Lined
Ditch (RL)
0m
Grass Cutting Width
(GW)=(Wr)-(Wc)-(LL)-(RL)
49.00 m Total Length 1000 m
Number of
Labors
0 men 2015/10/12
2.2.6. P-6 Project (2 lanes paved Road)/6 Simple Quantity Actual Quantity Work Difficulty Foreman Supervisor Labors (4) (5)
Simple Actual
SRUQ SRUQ Remarks
Worked Items
Q'ty Unit Q'ty (Vol) Unit nos nos nos working hours (man day/Qty) (man day/Qty) (Equipment)
Form-3 -Heavy
Remarks Remark
-Normal
Productivity Survey Summary Form a Labor Based Works b -Light c d e f j=e×f Man day ps = j / 7a pa= j / 7b
Location P-6 Client Site Weather Sunny Initial Mobilization Period / Routine Maintenance No. 66 (C)
Grass Cutting(1) / Left 50,000.0 m2 GW x L 19,400.0 m2 Heavy 1 1300 1300 185.7142857 0.0037 0.0096
1)Width of Road Left Lined Ditch Right Lined Grass Cutting Width Number of
Grass Cutting(2) 65.00 m
/ Right Width of Carriage Way (Wc) 15
m2m GW x L (LL) 1m m2(RL) 0m 49.00 m Total Length 1000 m 0 men#DIV/0! 2015/10/12
Reserve (Wr) Ditch (GW)=(Wr)-(Wc)-(LL)-(RL) Labors 0 0 #DIV/0!
Note) To use one sheet per day 205.3 1day = 7 working hours
To fill only the number of workers who are engaged in PBC works Man Day
Total number of workers or equipment shall tally the number of workers or equipment for PBC works on site. 1750
To specify structures to be maintained 245
To fill the maintained Q'ty which includes places/areas that don’t require any actual maintenance works
A8-23
TRAINING RESULTS FOR PR SURVEY DONE BY JICA/KRB IN SEPTEMBER AND OCTOBER 2015 APPENDIX 8
Labors (4)
SRUQ
(5)
Simple Actual
SRUQ SRUQ Remarks
Worked Items
Q'ty Unit Q'ty (Vol) Unit nos nos nos working hours (man day/Qty) (man day/Qty) (Equipment)
Form-3 -Heavy
Remarks Remark
Productivity Survey Summary Form Labor Based Works -Normal
a b -Light c d e f j=e×f Man day ps = j / 7a pa= j / 7b
Location P-7 Client Site Weather Sunny Initial Mobilization Period / Routine Maintenance No. 66 (C)
Grass Cutting(1) / Left 50,000.0 m2 GW x L 19,400.0 m2 Heavy 1 1530 1530 218.5714286 0.0044 0.0113
Width of Road Left Lined Ditch Right Lined Grass Cutting Width Number of
1) 65.00 m Width of Carriage Way (Wc) 15 m 1m 0m 49.00 m Total Length 1000 m 0 men 2015/10/12
Reserve
Grass (Wr)
Cutting(2) / Right m2 GW x L (LL) Ditch (RL)
m2 (GW)=(Wr)-(Wc)-(LL)-(RL) Labors
0 0 #DIV/0! #DIV/0!
Catch Basin
Note)/ No cover(2) To use one sheet per day Pcs Pcs 0
268.3 0 1day
#DIV/0! #DIV/0!
= 7 working hours
To fill only the number of workers who are engaged in PBC works Man Day
Lined Side Ditch(1) 600.0 m L 360.0 m Heavy 1 190 190 27.14285714 0.0452 0.0754
4) Total number of workers or equipment shall tally the number of workers or equipment for PBC works on site. 333.3333333
Lined Side Ditch(2) To specify structures to be maintained m m 0 0 #DIV/0! #DIV/0!
66.66666667
Unlined Side ditch(1) To fill the maintained Q'ty which
640.0includesm
places/areas that don’t
L require any actual 400.0
maintenance works
m Heavy 1 80 80 11.42857143 0.0179 0.0286
5)
Unlined Side ditch(2) m m 0 0 #DIV/0! #DIV/0!
Note) To use one sheet per day 268.3 1day = 7 working hours
Form-3
To fill only the number of workers who are engaged in PBC works Man Day
Productivity Survey Summary Form Labor Based Works
Total number of workers or equipment shall tally the number of workers or equipment for PBC works on site. 333.3333333
Location To specify structures to
P-8 be maintained
Client Site Weather Sunny Initial Mobilization Period / Routine Maintenance 66.66666667 No. 66 (C)
To fill the maintained Q'ty which includes places/areas that don’t require any actual maintenance works
2.2.8.
Width of Road
Reserve (Wr) P-8 Project (2 lanes paved Road)/8
65.00 m Width of Carriage Way (Wc) 15 m
Left Lined Ditch
(LL)
1m
Right Lined
Ditch (RL)
0m
Grass Cutting Width
(GW)=(Wr)-(Wc)-(LL)-(RL)
49.00 m Total Length 1000 m
Number of
Labors
0 men 2015/10/12
Labors (4)
SRUQ
(5)
Simple Actual
SRUQ SRUQ Remarks
Worked Items
Q'ty Unit Q'ty (Vol) Unit nos nos nos working hours (man day/Qty) (man day/Qty) (Equipment)
Form-3 -Heavy
Remarks Remark
Productivity Survey Summary Form Labor Based Works -Normal
a b -Light c d e f j=e×f Man day ps = j / 7a pa= j / 7b
Location P-8 Client Site Weather Sunny Initial Mobilization Period / Routine Maintenance No. 66 (C)
Grass Cutting(1) / Left 50,000.0 m2 GW x L 19,500.0 m2 Light 1 110 110 15.71428571 0.0003 0.0008
Width of Road Left Lined Ditch Right Lined Grass Cutting Width Number of
1) 65.00 m Width of Carriage Way (Wc) 15 m 1m 0m 49.00 m Total Length 1000 m 0 men 2015/10/12
Reserve
Grass (Wr)
Cutting(2) / Right m2 GW x L (LL) Ditch (RL)
m2
(GW)=(Wr)-(Wc)-(LL)-(RL) Labors
0 0 #DIV/0! #DIV/0!
Catch Basin
Note)/ No cover(2) To use one sheet per day Pcs Pcs 0
22.4 0 1day
#DIV/0! #DIV/0!
= 7 working hours
Lined Side Ditch(1) To fill only the number of workers who are engaged in PBC works
L
Man Day
600.0 m 320.0 m Light 1 3 3 0.428571429 0.0007 0.0013
4) Total number of workers or equipment shall tally the number of workers or equipment for PBC works on site. 1400
Lined Side Ditch(2) To specify structures to be maintained m m 0 0 #DIV/0! #DIV/0!224
Note) To use one sheet per day 22.4 1day = 7 working hours
To fill only the number of workers who are engaged in PBC works Man Day
Total number of workers or equipment shall tally the number of workers or equipment for PBC works on site. 1400
To specify structures to be maintained 224
To fill the maintained Q'ty which includes places/areas that don’t require any actual maintenance works
A8-24
APPENDIX 8 TRAINING RESULTS FOR PR SURVEY DONE BY JICA/KRB IN SEPTEMBER AND OCTOBER 2015
2.2.9. P-9 Project (4 lanes paved Road)/1 Simple Quantity Actual Quantity Work Difficulty Foreman Supervisor Labors (4) (5)
Simple Actual
SRUQ SRUQ Remarks
Worked Items
Q'ty Unit Q'ty (Vol) Unit nos nos nos working hours (man day/Qty) (man day/Qty) (Equipment)
Form-3 -Heavy
Remarks Remark
-Normal
Productivity Survey Summary Form a Labor Based Works b -Light c d e f j=e×f Man day ps = j / 7a pa= j / 7b
Location P-9 Client Site Weather Sunny Initial Mobilization Period / Routine Maintenance No. 66 (C)
Grass Cutting(1) / Left 53,000.0 m2 GW x L 11,260.0 m2 Normal 1 170 170 24.28571429 0.0005 0.0022
1)Width of Road Left Lined Ditch Right Lined Grass Cutting Width Number of
Grass (Wr) 65.00 m
Cutting(2) / Right Width of Carriage Way (Wc) 22
m2m GW x L (LL) 1m m2(RL) 0m 42.00 m Total Length 1000 m 0 men#DIV/0! 2015/10/12
Reserve Ditch (GW)=(Wr)-(Wc)-(LL)-(RL) Labors 0 0 #DIV/0!
Carriage De-sliting(2)
2,000.0
2,000.0
m2
m2
Lx1.0(m) 240.0
300.0
m2
m2
Heavy 1
1
37
44
37
44
5.285714286
6.285714286
0.0026
0.0031
0.0220
0.0210
Form-3 Note) To use one sheet per day 49.9 1day = 7 working hours
Productivity Survey Summary
To fillForm
only the number of workers who are engagedLabor Based Works
in PBC works Man Day
Total number of workers or equipment shall tally the number of workers or equipment for PBC works on site. 378.3783784
Location P-10 Client Site Weather Sunny Initial Mobilization Period / Routine Maintenance No. 66 (C)
To specify structures to be maintained 45.40540541
2.2.10. P-10 Project (4 lanes paved Road)/2 Simple Quantity Actual Quantity Work Difficulty Foreman Supervisor Labors (4) (5)
Simple Actual
SRUQ SRUQ Remarks
Worked Items
Q'ty Unit Q'ty (Vol) Unit nos nos nos working hours (man day/Qty) (man day/Qty) (Equipment)
Form-3 -Heavy
Remarks Remark
-Normal
Productivity Survey Summary Form a Labor Based Works b -Light c d e f j=e×f Man day ps = j / 7a pa= j / 7b
Location P-10 Client Site Weather Sunny Initial Mobilization Period / Routine Maintenance No. 66 (C)
Grass Cutting(1) / Left 53,000.0 m2 GW x L 12,580.0 m2 Light 1 85 85 12.14285714 0.0002 0.0010
1)Width of Road Left Lined Ditch Right Lined Grass Cutting Width Number of
Grass (Wr) 65.00 m
Cutting(2) / Right Width of Carriage Way (Wc) 22
m2m GW x L (LL) 1m m2(RL) 0m 42.00 m Total Length 1000 m 0 men#DIV/0! 2015/10/12
Reserve Ditch (GW)=(Wr)-(Wc)-(LL)-(RL) Labors 0 0 #DIV/0!
Note) To use one sheet per day 32.1 1day = 7 working hours
To fill only the number of workers who are engaged in PBC works Man Day
Total number of workers or equipment shall tally the number of workers or equipment for PBC works on site. 1750
To specify structures to be maintained 315
To fill the maintained Q'ty which includes places/areas that don’t require any actual maintenance works
A8-25
TRAINING RESULTS FOR PR SURVEY DONE BY JICA/KRB IN SEPTEMBER AND OCTOBER 2015 APPENDIX 8
2.2.11. P-11 Project (2 lanes unpaved Road)/1 Asset Quantity Labour Input SRUQ
Simple Quantity Actual Quantity Work Difficulty Foreman Supervisor Labors (4) (5)
Simple Actual
Form-3 Worked Items SRUQ SRUQ Remarks
Q'ty Unit Q'ty (Vol) Unit nos nos nos working hours (man day/Qty) (man day/Qty) (Equipment)
Productivity Survey Summary Form Labor Based Works
-Heavy
Remarks Remark
-Normal
Location P-11 Client Site Weather Sunny Initial Mobilization Period / Routine Maintenance No. 66 (C)
a b -Light c d e f j=e×f Man day ps = j / 7a pa= j / 7b
Width of Road Left Lined Ditch Right Lined Grass Cutting Width Number of
65.00 m Width of Carriage Way (Wc) 15 m 1m 0m 49.00 m Total Length 1000 m 0 men 2015/10/12
Reserve
Grass (Wr)
Cutting(1) / Left 10,000.0 m2 GW x L (LL) 2,000.0 Ditch (RL)
m2 Normal
(GW)=(Wr)-(Wc)-(LL)-(RL)
1 33 Labors
33 4.714285714 0.0005 0.0024
1)
Grass Cutting(2) / Right m2 GW x L m2 0 0 #DIV/0! #DIV/0!
Asset Quantity Labour Input SRUQ
Pcs Pcs 0 0 #DIV/0! #DIV/0!
Cross Culvert(1) Simple Quantity Actual Quantity Work Difficulty Foreman Supervisor Labors (4) (5)
54.0 m 36.0 m Normal 1 4 4 0.571428571 0.0106
Simple 0.0159
Actual
2) SRUQ SRUQ Remarks
Worked Items
Q'ty Pcs
Unit Q'ty (Vol) Pcs
Unit nos nos nos working hours 0 0 #DIV/0! #DIV/0! (Equipment)
(man day/Qty) (man day/Qty)
Cross Culvert(2)
-Heavy
m Remarks m Remark 0 0 #DIV/0! #DIV/0!
-Normal
Catch Basin / Cover(1) 3.0a Pcs 2.0b Pcs -Light
Normal c d e 1 f 4 j=e×f 4 Man day
0.571428571 ps0.1905
= j / 7a pa= j / 7b
0.2857
Catch
Total Basin / No cover(2) Pcs Pcs 6 48 48
0 0 #DIV/0! #DIV/0!
Note) To use one sheet per day 6.9 1day = 7 working hours
To fill only the number of workers who are engaged in PBC works Man Day
Form-3 Total number of workers or equipment shall tally the number of workers or equipment for PBC works on site. #DIV/0!
Productivity Survey Summary Form
To specify structures to be maintained Labor Based Works #DIV/0!
To fill the maintained Q'ty which includes places/areas that don’t require any actual maintenance works
Location P-12 Client Site Weather Sunny Initial Mobilization Period / Routine Maintenance No. 66 (C)
Width of Road Left Lined Ditch Right Lined Grass Cutting Width Number of
2.2.12. P-12 Project (2 lanes unpaved Road)/2 Asset Quantity Labour Input SRUQ
Simple Quantity Actual Quantity Work Difficulty Foreman Supervisor Labors (4) (5)
Simple Actual
Form-3 Worked Items SRUQ SRUQ Remarks
Q'ty Unit Q'ty (Vol) Unit nos nos nos working hours (man day/Qty) (man day/Qty) (Equipment)
Productivity Survey Summary Form Labor Based Works
-Heavy
Remarks Remark
-Normal
Location P-12 Client Site Weather Sunny Initial Mobilization Period / Routine Maintenance No. 66 (C)
a b -Light c d e f j=e×f Man day ps = j / 7a pa= j / 7b
Width of Road Left Lined Ditch Right Lined Grass Cutting Width Number of
65.00 m Width of Carriage Way (Wc) 15 m 1m 0m 49.00 m Total Length 1000 m 0 men 2015/10/12
Reserve
Grass (Wr)
Cutting(1) / Left 10,000.0 m2 GW x L (LL) 2,300.0 Ditch (RL)
m2 Heavy
(GW)=(Wr)-(Wc)-(LL)-(RL)
1 170 Labors
170 24.28571429 0.0024 0.0106
1)
Grass Cutting(2) / Right m2 GW x L m2 0 0 #DIV/0! #DIV/0!
Asset Quantity Labour Input SRUQ
Pcs Pcs 0 0 #DIV/0! #DIV/0!
Cross Culvert(1) Simple Quantity Actual Quantity Work Difficulty Foreman Supervisor Labors (4) (5)
54.0 m 36.0 m Heavy 1 35 35 5 0.0926
Simple 0.1389
Actual
2) SRUQ SRUQ Remarks
Worked Items
Q'ty Pcs
Unit Q'ty (Vol) Pcs
Unit nos nos nos working hours 0 0 #DIV/0! #DIV/0! (Equipment)
(man day/Qty) (man day/Qty)
Cross Culvert(2)
-Heavy
m Remarks m Remark 0 0 #DIV/0! #DIV/0!
-Normal
Catch Basin / Cover(1) 3.0a Pcs 2.0b Pcs Heavy-Light c d e 1 f 16 j=e×f 16 Man day
2.285714286 ps0.7619
= j / 7a pa= j / 7b
1.1429
Catch
Total Basin / No cover(2) Pcs Pcs 6 252 252
0 0 #DIV/0! #DIV/0!
Note) To use one sheet per day 36.0 1day = 7 working hours
To fill only the number of workers who are engaged in PBC works Man Day
Total number of workers or equipment shall tally the number of workers or equipment for PBC works on site. #DIV/0!
To specify structures to be maintained #DIV/0!
To fill the maintained Q'ty which includes places/areas that don’t require any actual maintenance works
APPENDIX 8
82
Lined Side Ditch(1) Unlined Side ditch(1) Carriage De-sliting(1) Carriage De-sliting(2)
Grass Cutting1 Cross Culvert(1) Catch Basin / No Cover(1)
COST ESTIMATION MANUAL FOR PERFORMANCE BASED ROAD MAINTENANCE CONTRACT
Person day Person day Person day Person day Person day Person day Person day
1 P-1 KRB 1,000.0 50,000.0 19,000.0 42.00 Normal 54.0 36.0 0.57 Light 3.0 2.0 1.86 Heavy 600.0 240.0 0.57 Light 640.0 240.0 2.43 Normal 2,000.0 320.0 2.71 Normal
2 P-2 KRB 1,000.0 50,000.0 20,000.0 42.00 Normal 54.0 36.0 0.43 Light 3.0 2.0 0.57 Normal 600.0 280.0 0.29 Light 640.0 280.0 3.00 Normal 2,000.0 320.0 2.57 Normal
3 P-3 KRB 1,000.0 50,000.0 19,000.0 192.86 Heavy 54.0 36.0 5.43 Heavy 3.0 2.0 2.00 Heavy 600.0 360.0 21.43 Heavy 640.0 360.0 9.29 Heavy 2,000.0 300.0 1.07 Light
4 P-4 KRB 1,000.0 50,000.0 18,500.0 15.00 Light 54.0 36.0 0.36 Light 3.0 2.0 0.14 Light 600.0 240.0 15.00 Heavy 640.0 280.0 6.43 Heavy 2,000.0 260.0 5.71 Heavy
5 P-5 KRB 1,000.0 50,000.0 19,000.0 35.00 Normal 54.0 36.0 0.86 Normal 3.0 2.0 2.71 Heavy 600.0 360.0 7.14 Normal 640.0 240.0 0.29 Light 2,000.0 300.0 6.57 Heavy
6 P-6 KRB 1,000.0 50,000.0 19,400.0 185.71 Heavy 54.0 36.0 0.57 Normal 3.0 2.0 0.29 Normal 600.0 280.0 17.14 Heavy 640.0 280.0 0.43 Light 2,000.0 260.0 1.14 Light
7 P-7 KRB 1,000.0 50,000.0 19,400.0 218.57 Heavy 54.0 36.0 5.71 Heavy 3.0 2.0 0.29 Light 600.0 360.0 27.14 Heavy 640.0 400.0 11.43 Heavy 2,000.0 320.0 5.14 Heavy
8 P-8 KRB 1,000.0 50,000.0 19,500.0 15.71 Light 54.0 36.0 0.57 Light 3.0 2.0 0.29 Light 600.0 320.0 0.43 Light 640.0 320.0 4.29 Normal 2,000.0 280.0 1.14 Light
9 P-9 KRB 1,000.0 53,000.0 11,260.0 24.29 Normal 120.0 90.0 1.43 Normal 4.0 3.0 0.57 Normal 880.0 440.0 8.57 Normal 680.0 320.0 3.43 Normal 4,000.0 540.0 11.57 Heavy
TRAINING RESULTS FOR PR SURVEY DONE BY JICA/KRB IN SEPTEMBER AND OCTOBER 2015
10 P-10 KRB 1,000.0 53,000.0 12,580.0 12.14 Light 120.0 90.0 0.86 Light 4.0 3.0 0.29 Light 880.0 640.0 15.71 Normal 680.0 280.0 0.71 Light 4,000.0 760.0 2.43 Light
11 P-11 KRB 1,000.0 10,000.0 2,000.0 4.71 Normal 54.0 36.0 0.57 Normal 3.0 2.0 0.57 Normal 720.0 440.0 1.00 Light
12 P-12 KRB 1,000.0 10,000.0 2,300.0 24.29 Heavy 54.0 36.0 5.00 Heavy 3.0 2.0 2.29 Heavy 720.0 400.0 4.43 Normal
A8-27
Heavy 160,000 60,100 621.43 162 108 16.14 12 8 8.86 2,400 1,240 80.71 1,920 1,040 27.14 10,000 1,420 29.00 0 0 0.00
Normal 213,000 71,260 148.00 282 198 3.43 13 9 2.00 2,360 1,440 31.43 3,320 1,560 17.57 4,000 640 5.29 0 0 0.00
Light 153,000 50,580 42.86 336 234 2.79 13 9 1.00 1,800 840 1.29 2,680 1,240 2.43 10,000 1,600 5.79 0 0 0.00
Heavy 3 3 3 2 2 2 3 3 3 4 4 4 3 3 3 3 3 3 0 0 0
counts Normal 3 3 3 2 2 2 2 2 2 1 1 1 3 3 3 2 2 2 0 0 0
Light 2 2 2 4 4 4 3 3 3 3 3 3 2 2 2 3 3 3 0 0 0
2.4. P/R Computation Form for Ex-samples of PR Survey Results
TRAINING RESULTS FOR PR SURVEY DONE BY JICA/KRB IN SEPTEMBER AND OCTOBER 2015
2.4. P/R Computation Form for Ex-samples of PR Survey Results
Summary of SRUQ
Simple Actual Person*day P/R(Actual) SRUQ(Actual) SRUQ(Actual)*1000 Simple/Actual Actual/Simple P/R(Simple) SRUQ(Simple) SRUQ(Simple)*1000
Heavy 160,000 60,100 621.429 96.7 0.01033991 10.34 279.6 0.003576508 3.58
Normal 213,000 71,260 148.000 481.5 0.002076901 2.08 1,392.0 0.000718387 0.72
Grass Cutting(m2)
Light 153,000 50,580 42.857 1,180.2 0.000847314 0.85 3,412.0 0.00029308 0.29
Total(Ave.) 526,000 181,940 812 224.0 0.00446458 4.46 289% 35% 647.6 0.001544269 1.54
Heavy 162 108 16.143 6.7 0.149470899 149.47 9.7 0.103479853 103.48
Normal 282 198 3.429 57.8 0.017316017 17.32 83.4 0.011988012 11.99
Cross Culvert(m)
Light 336 234 2.786 84.0 0.011904762 11.90 121.3 0.008241758 8.24
Total(Ave.) 780 540 22 24.2 0.041402116 41.40 144% 69% 34.9 0.028663004 28.66
Heavy 12 8 8.857 0.9 1.107142857 1,107.14 1.3 0.757518797 757.52
Normal 13 9 2.000 4.5 0.222222222 222.22 6.6 0.152046784 152.05
Catch Basin(pcs)
Light 13 9 1.000 9.0 0.111111111 111.11 13.2 0.076023392 76.02
VOLUME 1: MANUAL FOR COST
Total(Ave.) 24,000 3,660 40 91.3 0.010948478 10.95 656% 15% 598.9 0.001669643 1.67
ESTIMATION ADMINISTRATORS
After Correction
P/R(Actual) Remarks SRUQ(Actual) SRUQ(Actual)*1000 Simple/Actual Actual/Simple P/R(Simple) SRUQ(Simple) SRUQ(Simple)*1000
Heavy 97 0.01033991 10.34 290.1 0.003446637 3.45
Normal 481 0.002076901 2.08 1,444.5 0.0006923 0.69
Grass Cutting(m2)
Light 1,180 0.000847314 0.85 3,540.6 0.000282438 0.28
Total(Ave.) 224 0.00446458 4.46 300% 33% 672.0 0.001488193 1.49
Heavy 7 0.149470899 149.47 (Assumption;3:1) 9.7 0.103479853 103.48
Normal 58 0.017316017 17.32 83.4 0.011988012 11.99
Cross Culvert(m)
Light 84 0.011904762 11.90 121.3 0.008241758 8.24
Total(Ave.) 24 0.041402116 41.40 144% 69% 34.9 0.028663004 28.66
Heavy 1 1.107142857 1,107.14 2.7 0.369047619 369.05
Normal 5 0.222222222 222.22 13.5 0.074074074 74.07
Catch Basin(pcs)
Light 9 0.111111111 111.11 27.0 0.037037037 37.04
Total(Ave.) 2 0.456043956 456.04 300% 33% 6.6 0.152014652 152.01
Heavy 15 0.065092166 65.09 (Assumption;3:1) 28.6 0.034927504 34.93
Normal 46 0.021825397 21.83 85.4 0.011711189 11.71
Lined Side Ditch(m)
Light 653 0.001530612 1.53 1,217.6 0.000821304 0.82
Total(Ave.) 31 0.032224026 32.22 186% 54% 57.8 0.017290941 17.29
Heavy 38 0.026098901 26.10 79.0 0.012654013 12.65
Normal 89 0.011263736 11.26 183.1 0.005461205 5.46
Unlined Side Ditch(m)
Light 511 0.001958525 1.96 1,053.1 0.000949588 0.95
Total(Ave.) 81 0.012276786 12.28 206% 48% 168.0 0.005952381 5.95
Heavy 49 0.020422535 20.42 321.1 0.003114437 3.11
Normal 121 0.008258929 8.26 794.0 0.001259487 1.26
Carrageway De-silting(m2)
Light 277 0.003616071 3.62 1,813.4 0.000551451 0.55
APPENDIX 8
Total(Ave.) 91 0.010948478 10.95 656% 15% 598.9 0.001669643 1.67
83
3. Analysis of Standardized Quantity Survey
APPENDIX 8
84
Sta. 0+000
Sta. 0+200
Sta. 0+400
Sta. 0+600
Sta. 0+800
Sta. 1+000
Boundary
Side Walk
11.0m
13m 13m
TRAINING RESULTS FOR PR SURVEY DONE BY JICA/KRB IN SEPTEMBER AND OCTOBER 2015
Side Walk
Boundary
TRAINING RESULTS FOR PR SURVEY DONE BY JICA/KRB IN SEPTEMBER AND OCTOBER 2015 APPENDIX 8
Cross Culvert m 39
0+000 0 13 11 19 0 32
0+200 200 1 15 11 16 2 28 30 6,000 6,000
0+400 200 1 14 11 16.5 2 27.5 27.75 5,550 11,550
0+600 200 1 15 11 15 2 27 27.25 5,450 17,000
0+800 200 0 11 11 17 2 26 26.5 5,300 22,300
1+000 200 0 12 11 18 0 30 28 5,600 27,900
Left Right
Length Length
Lined or Lined or
From To From To
Unlined Unlined
Lined Unlined Lined Unlined
Left Right
At Number At Number
0 + 160 1 0 + 160 1
0 + 450 1 0 + 560 1
0 + 760 1 0 + 760 1
Total 3 Total 3
At Length (m)
0 + 160 13
0 + 560 13
0 + 760 13
Total 39
APPENDIX 8
88
Sta. 0+000
Sta. 0+200
Sta. 0+400
Sta. 0+600
Sta. 0+800
Sta. 1+000
COST ESTIMATION MANUAL FOR PERFORMANCE BASED ROAD MAINTENANCE CONTRACT
Boundary
Side Walk
10m
1.5m Median
TRAINING RESULTS FOR PR SURVEY DONE BY JICA/KRB IN SEPTEMBER AND OCTOBER 2015
21m 21m
10m
Side Walk
A8-33
Boundary
TRAINING RESULTS FOR PR SURVEY DONE BY JICA/KRB IN SEPTEMBER AND OCTOBER 2015 APPENDIX 8
Cross Culvert m 42
LOC+M+ROC-
LLD LOC LCW M RCW ROC RLD Average Average
LLD-RLD
0+200 200 2.5 16.0 10.0 1.5 10.0 18.0 2.0 31.0 33.3 6,650.0
0+400 200 2.5 12.0 10.0 1.5 10.0 17.0 2.0 26.0 28.5 5,700.0
0+600 200 2.5 20.0 10.0 1.5 10.0 18.0 2.0 35.0 30.5 6,100.0
0+800 200 0.0 14.0 10.0 1.5 10.0 20.0 0.0 35.5 35.3 7,050.0
1+000 200 0.0 14.0 10.0 1.5 10.0 28.0 0.0 43.5 39.5 7,900.0
33,400.0
Note) LOC : Left Off Carriageway
Left Right
Length Length
Lined or Lined or
From To From To
Unlined Unlined
Lined Unlined Lined Unlined
A8-35
90 COST ESTIMATION MANUAL FOR PERFORMANCE BASED ROAD MAINTENANCE CONTRACT
TRAINING RESULTS FOR PR SURVEY DONE BY JICA/KRB IN SEPTEMBER AND OCTOBER 2015 APPENDIX 8
Left Right
At Number At Number
0 + 160 1 0 + 160 1
0 + 450 1 0 + 560 1
Total 2 Total 2
At Length (m)
0 + 160 21
0 + 560 21
Total 42
KRB has reviewed the CEM submitted vide email on 17th September, 2015. KRB would like
to commend JICA for the well prepared guidelines which will contribute to improvement
in planning and implementation of procurement of road maintenance works in the
country.
KRB recommends for a further review of the following unit rates in the cost estimation
manual:
1. Indirect Cost – The example given in Table 6.4 is for projects in Japan and may not be
applicable in Kenyan context. It is recommended that a review of road infrastructure
projects is carried out to determine the % of indirect costs. In the interim, it is
proposed that the percentage of indirect cost is set to a maximum 30% of direct cost,
just like other classical road contracts.
2. Overhead & Profit – The example given in Table 6.4 is for projects in Japan and
may not be , applicable, in Kenyan context. It is recommended that a review of
road, infrastructure projects is, carried out to determine the % of indirect costs In
the interim, it is proposed that the maximum percentage for profit and overheads
margin is set at 10% of direct and indirect cost. The manual should also clearly state
that the profit margin and other overheads include those directly incurred by the
contractor but not the client. .
4. Vehicle Costs – These rates should be based on rates from Government Mechanical
and Transport Services of Ministry of Transport and Infrastructure, Mechanical and
Transport Division as reviewed from time to time.
5. Fuel Cost – The fuel rates used should be those provided by the Energy Regulatory
Commission of Kenya.
Yours faithfully,
CP A Rashid Mohamed,
General Manager, Finance
FOR: EXECUTIVE DIRECTOR
Name Organization
Eng. Francis Gitau Ministry of Transport and Infrastructure
Eng. Wilson Kosgey Kenya Roads Board
Eng. Margaret Ogai Kenya Roads Board
Eng. Tom Omai Kenya Roads Board
Maureen Wangui Kenya National Highways Authority
Winnie Owiti Kenya National Highways Authority
Opuge Ephraim Kenya National Highways Authority
Eunice Wanjiru Kenya National Highways Authority
Julius Kaliti Kenya Institute of Highways and Building Technology
Walter Ochieng Kenya Wildlife Services
Eng. Maurice Akech National Construction Authority
Chris Gachanja Public Procurement Oversight Authority
Advisors
Hiroshi Tsujino JICA Chief Advisor P.E Jp.
Hidetsugu Ikeda JICA Expert
Takashi Nakajima JICA Short Term Expert, P.E Jp.
Hiroshi Mita JICA Short Term Expert, P.E Jp.
Yoshihisa Noda JICA Short Term Expert, P.E Jp.
Yoriko Kawakami JICA Short Term Expert
Takumi Uno JICA Short Term Expert
Robert Mutai JICA/Consultant, Kenya Staff
Jared N. Onyoni JICA/Consultant, Kenya Staff
Name Organization
Eng. P. M. Mwinzi Ministry of Transport and Infrastructure
Eng. Francis Gitau Ministry of Transport and Infrastructure
Kenji Yokota JICA – Kenya Office
Dr. Steve Mogere JICA – Kenya Office
Eng. Margaret Ogai Kenya Roads Board
Eng. George M. Kiiru Kenya National Highways Authority
Opuge Ephraim Kenya National Highways Authority
Winnie Owiti Kenya National Highways Authority
Eng. Amos Ombok Kenya Urban Roads Authority
Eng. N. N. Nganga Kenya Rural Roads Authority
Julius Kaliti Kenya Institute of Highways and Building Technology
Eng. Maurice Akech National Construction Authority
Walter Ochieng Kenya Wildlife Services
Chris Gachanja Public Procurement Oversight Authority
Hiroshi Tsujino JICA Chief Advisor P.E Jp.
Hidetsugu Ikeda JICA Expert