Part-2 Power Generation Economics
Part-2 Power Generation Economics
UNIT COMMITMENT
Multiple Choice Type Questions
1.
Five 200 MW plants are
connected to a grid having a
the generators are operating
at a lagging pf of 0.85, peak demand of 1000 VA. If
the spinning reserve is
a) 0 MW
b) 50 MWN WBUT 2011]
Answer: (c) c) 150 MW d) 250 MW
2. A storage type power
plant is essential for
betterment of a grid that suffers from
a) very low peak [WBUT 2011]
demand
b) very high peak
demand but high load
c)very high peak demand but factor
d) very low peak demand low load factor
but high load factor
Answer: (b)
3. Unit commitment is
a) a must before we solve WBUT 2014]
b) a short term problem economic operation problem
of maintenance scheduling
c) more meaningful for
thermal units
d) all of these
Answer: (d)
4. For long term hydrothermal
a) A head variation can
problem
be ignored WBUT 2014]
b) transmission loss cannot
be
c) unit commitment should be ignored
d) all of these taken into account
Answer: (d)
D
Short Answer Type Questions
1.What do you mean by unit commitment
problem? Discuss the Importance
Spinning Reserve' as related to unit commitment of
problem. WBUT 2008]
OR,
Discuss briefly about unit commitment and spinning
reserve. WBUT 2009]
Answer:
Unit Commitment (UC)
It is not conomical to run all the
units available all the time. To determine
plant that should operate for a particular load is the the nits of a
problem of unit commitment
This problem is of importance for thermal plants as (UC).
for other types of generation
hydro; their operating cost and start-up times are negligible so such as
that their on-off status is
not important.
PGE-51
POPULARPUBLICATIONS
is to impose priority
ordering; wherein
A simple but sub-optimal approach to the problem in order as
loaded first to be followcd by the less cflicicnt units
the most efficient unit is
the load increases. most cconomical
highly time-consuming way of finding the
A straightforward but combinations
load demand, is to try all possible
combination of units to meet a particular of each
load: to divide the load optimally among the units
supply this most cconomical
of units that can use the coordination cquations, so as to find the
Combination by of has the
combination: then, to determine the combination, which
operating cost of the can be achieved
among all these. Considerable computational saving
lcast operating cost method for comparing the
branch and bound or a dynamic programming
by using
combinations as certain combinations need not be tried at all.
economics of
Answer:
Constraints in Unit Commitment:
1. Thermal Unit Constraints: Thermal.units require a trained lot of crew to
operate the
units. A thermal power plant undergoes a gradual temperature change and this needs
some time intervals to bring the unit on line. As a result, the following constraints arise:
i Minimum up time: It states that there should be a minimum time of operation on
when the unit runs. It is not desired to turn off immediately after it is brought
line.
ii. Minimum down time: Once the thermal unit is decommissioned, there would be
aminimum time before it can be recommissioned.
iii. Crew constraints: If a plant consists of more than one unit, both the units cannot
be turned on simultaneously as there is usually not enough staff to attend both the
units.
PGE-52
POWERGENERATION ECONOMICS
iv. Operational constraints: In
energy must be consumed operation of thermal units,
a certain amount of
to bring the unit on-line. This cnergy docs not
any elfcctive power result in
generation and in unit
treatcd as Start up cost. commitment problem, it has
been
2. Spinning Reserve: Spinning
reserve is defined as follows:
Spinning reserve
P-Pina-P,at any interval oftime.
Spinning reserve must be
maintained
unacceptable decline in frequency, so that the loss of one or more units does not cause
i.e., there must be sufficient
unit is lost, other unit can make reserve such that if one
up for the loss in a specified
time period.
3. Hydro-constraints: As wve
pointed out that unit commitment
importance for the scheduling of problem is of much
thermal units it is not the
that cannot be completely separated meaning of unit commitment
from the scheduling of a
The operation of hydro-thermal hydro-unit.
system having both hydro and
for more complex as hydro-plants thermal plants, however
have negligible operation
operate. Under constraints of costs. but are required to
water available for hydro-generation
time. in a given period of
The problem of minimizing the
operating cost of a hydrothermal
one of minimizing the fuel system can be viewed as
cost of thermal plants. Under
availability for hydro-generation the constraint of water
over a given period of operation.
4.Fuel Constraints: A system in which
constraint that require them to some units have limited fuel
burn a specified amount of fuel on else have
most challenging unit commitment in a given time presents
problem. a
PGE-53
POPULAR PUBLICATIONS
hydrothermal
losses. To find the schedules for
transmission
intake losses, incremental presumed that:
operating period, it is
plants for time duration during the of time producing the
water is used over the given period
1)a desired amount of
maximum amount of energy and cost of the thermal units
will be
hence the generation
n) the fuel input and
minimum. sets of co-ordination equations which will
there will be two
With the above end in vicw, and the other set for the
scheduling- one set for the thermal units
be solved for optimum
and the remaining
hydro units. n-controllable generators m are stcam plants
Let us consider that out of co-ordination equations
are
units. Then the
7-m) are hydro generator
dP SP
... (2)
R +of-1=0 j=m+1,m+2,
H
Here
the ith steam unit
P =output in MW of hydroelectric unit.
P Output in MW ofjth
ith steam unit.
transmission loss associated with the
=Incremental
5P
with the jth hydropower unit.
=Incremental transmission loss associated
8 Pa
unit in Rs/M Wh.
=Incremental cost for the ith thermal
dPg
Rdd-i=0
P
PGE-54
POWER GENERATION ECONOMICS
3rd
Part:
The downside of keeping a spinning-reserve
sufficient generating units running in the grid will ensure that
above their Minimum Stable there are
times to allow the total output Generation levels at all
to be quickly reduced by specified
(There may be a variety of reasons a number of MWN.
for such a requirement for example
possibility of demands being lower than to cover the
their forecast values.)
5. Discuss the various types
of Unit Commitment method.
Answer: WBUT 2012, 2015]
The major available method for unit commitment
can be grouped as follows:
Deterministic techniques
Meta-heuristic techniques
Hydrothermal coordination
Deterministic approach includes priority list,
inter/mixed-integer programming
dynamic and linear programming, branch-and-bound method,
method, decomposition technique,
and colony system and Lagrangian relaxation.
PGE-55
POPULAR PUBLICATIONS
neural networks,
fuzzy logic. artificial
include cxpert system,simulated anncaling. tabu scarch and
Meta-heuristic approaches programming.
geneticalgorithm. cvolutionary
technique). method comprising three
memetic algorithm (hybrid solved using "cquivalcncing" like
be
Large scale UCP can also and disaggregation.
solution
steps: aggregation,
the optimum hourly
Hydrothennal Coordination hydro scheduling is to dctermine
problem of short-term flows through generating stations, reservoir
The hyvdro units, water maxinmize the energy
production from
generation production of objective is to
leveis. The
releases and storage as part of
hydro resources. hydro scheduling is to be done
system. short-term the solution
In a hydrothermal hydrothermal coordination problen requires schedules.
hydrethermal coordination. The as the hydro
generation dispatch as well
for the thernal unit
commitments and
production cost subject to mecting the load
minimize the thermal the hydrothermal
The objective here torequirements. Most of the methods for solving
is
and other generation decomposition methods involving the unit
based on procedure depends on
coordination probiem are problems. The coordination
sub
commitment and hydro scheduling
heuristic decomposition, combined Lagrangian
method used like
the decomposition programming. genetic algorithm etc.
relaxation and network flow
in economic load
scheduling.
Computational method [WBUT 2012]
6. Develop a simple
Answer:
Plant Scheduling: controllable system will
production of electric energy in an n-machine
The total cost of
be given by:
C=C-.0)Rs/hour
. (1)
f.Pa)+S,(Paa)+.+S,PRs/hour
provided
Pi=1, 2,., n), so that C is minimized
Our problem is to select n variables simultaneously satisfied. As we have
and inequality constraints are
certain equality one
not affect fuel cost, there will be only
already observed that the reactive power does
by:
equality constraint to be satisfied. This is given
power supplied by base load units.
Pa =total power demand on the system-total
= group of generators
= Power demanded from the controllable
Pp
(2)
i.e. 2-P=0 (3)
1.e., glaa )=0
PGE-56
POWERGENERATION ECONOMICS
where, g is a function.
Along with this cquality constraint,
n number of inequality constraints need to be
satisficd. These are:
umnn<Piuma i=1,2,.. (4)
Rcferring back to Eqn. (1) we observe
that we are to optimize C. a function of n
variables, by independently
sclecting (n-1) variables, the other variable gets
automatically fixed by the equality
constraint Eqn. (2).
The mathematical procedure to find
constrained optimum i.e. optimization technique is
given below for ready reference.
Let us consider a scalar cost function given
by
C=J,X)
are n independent variables. The
(5)
.
,...X, problem is to find out the maximum or
minimum value of C.
The total differential dc may be expressed
as:
dc=d+dx,+
dx d,
x, .. (6)
For an optimal value of C, the total differential
must be zero. This condition demands that
all the partial derivatives in
x,(i=1.2...n) must be zero because the variables are
independent of each other and there is no
constraint in their variation. So. the condition
for optimization is:
O=0 for i =1, 2,..n ... (7)
If the problem is now modified by stating that C is
to be optimized subject to the
condition (constraint) tdhat the equation below be satisfied.
8 ,X2...",) =0 (8)
The above equation is an equality constrain equation.
On partial differentiation of the
above equation, it is obtained
... (10)
PGE-57
POPULARPUBLICATIONS
optimum
terms vithin parentheses are to be zero. The
then all the n
lf dc has to be zero.
conditions are then:
= .(11)
-=0
Sx Sx,
for
i 1,2..
1) variables i.e. x,X..
Eqn. (8) will yield (n+
and .
These n equations and the constraint
a)+
8Pa
SPa)+JPa)++SPa)
8fPa)- O=(IC), .(17)
PGE-58
POWERGENERATION ECONOMICS
The optimum condition, therefore, is
obtained when we make sure
controllable generators operatc that all the individual
at equal incremental production
time, the generated powers add up costs and at the same
to the power demanded from
The condition can bc graphically depicted the controllable group.
on the incremental cost curve
1. The optimum condition as shown in Fig.
to be satisficd for a certain
Pa +Paa+..+ Pa IC value 1, such that
t.. + Pin
= Py-
C
(2)
Poa Po Pa Pro
Pa
Fig:1 Graphical depiction optimum
of condition incremental curve
Pais the real power at the point where the horizontal
line drawn form the IC axis at
distance 1 from the origin, cuts the a
ith incremental curve.
We have not yet taken any
cognizance to the n inequality
operating strategy should be that constraints of Eqn. (4). The
if one or several generators reach
be operated at those limits their limits, these will
and the rest of the generators
cost rule. should satisfy equal incremental
If we use a quadratic cost function given
by Eqn. (1) the condition
scheduling or optimum dispatch - is:
for optimum
So P -
B+27,, Pa =2
27
for i=1,2,..n
.(20)
(21)
From the equality constraint
of Eqn. (2)
Pa-Po
or,
2
P,+
or,
(22)
2i 2
The value
of 2 obtained in Eqn. (22) is substituted in Eqn. (21) to obtain
the
of generation. scheduling
PGE-59
POPULARPUBLICATIONS
Spinning
reserve=synchronized units at Losses at that time J
a particular time
synchronized unit
the power generation of the f"
reserve, Pi.
Let P be the spinning
the system:
load on the system and P, the total loss of
P the total
Pi. -,+P) failure of one or more units does
not.
be maintained so that the
The spinning reserve must one unit fails, there imust be an ample
cause too far a drop in system frequency. Simply, if time period.
units to make up for the loss in a specified
reserve on the other load demand, orit
be a given a percentage of forecasted peak
The spinning reserve must most heavily loaded unit in a given
period of
taking up the loss of the
must be capable of
sufficient
time.
function of the probability of not having
It can also be calculated
as a
PGE-60
POWERGENERATION ECONOMICS
Answer:
"
1
Part:
In operational
scheduling of
the unit commitment. electric power generation,
It involves the most important
schedulcs of generating determining the problems is
units to be used start up and shut down
- 168 hours) period. to meet forecasted demand (ONIOFF)
The aim is to minimize over a short-term (24
and reserve requircments total production cost
while observing a to meet system demand
a complex mathematical large set of operating
optimization problem constraints. In fact it is
variables. Prior to having both integer and continuous
solve
should be solved because the economic dispatch problem.
only unit commitment
the unit commitment solution those units which were allocated to generating problem
can be considered
for power generation.
duties by
2 Part:
Economic load dispatch
economically distributes
Load as it rises to the the actual system.
various units already
set of units to be available online. But the UC problem
to supply the predicted plans for the best
future time periods. or forecast load of the
system over
9. Explain Thermal Unit
Down Time and Crew constraints with emphases to Minimum Up
Constraints. What is 'cooling' Time, Minimum
and 'Banking' of Boilers?
Answer WBUT 2017]
Part: Refer to Question No. 2 of Short
Answer Type Questions.
9nd
part:
Cooling: Open evaporative cooling
HVAC or industrial processes, systems are an essential
part of most commercial
however these well aerated
scrub dust and organic material water systems essentially
from the cooling air stream. setting
environment for corrosion, fouling. up a perfect
scaling. microbial activity
formation. Accordingly a good and bio-film
water treatment program is
regulatory compliance, but also not only essential for
to extend asset longevity,
minimize operating costs and mitigate optimize pant efficiency,
pathogen related public health
Banking of boilers: Boiler Bank Tubes risks.
are Bent to Shape Tubes
Generating Tubes where Water is converted or Steam
to Steam. Boiler Bank
mixture of water and steam. Fabricated Tubes carry a
from Tubes in various sizes
bending of these tubes is generally to and shapes,
larger Radius hence they need
Bending Expertise to avoid wrinkles, surface some Tube
cracking, irregularities, ensuring
life of tube resulting in smooth and efticient long
operation of the Boiler.
PGE-61
POPULARPUBLICAIONS
Explain the difference between the Unit Commitment and the Economic
2 a) WBUT 2009]
Dispatch problem.
Answer:
general, involved the consideration of economy of
The optimal system operation, in
fossil-fuel plants, optimal releases of
operation, system security, emissions at certain conflicting
these considerations may make for
water at hydro generation, etc. All
for optimal system operation. We
requirements and usually a compromise has to be made
called the economic dispatch problem.
consider the economy of operation only, also of
aim in the economic dispatch problem is to minimize the total cost
The main
power (production cost) at various stations while satisfying the loads and
generating real thermal
losses in the transmission links. For simplicity we consider the presence of
the which
in the beginning. We will consider the presence of hydro plants,
plants only there is negligible operating cost at
a
with thermal plants. While
operate in conjunction
PGE-62
POWER GENERATION ECONOMICS
hydro plant, there is a limitation of availability
of water over a period of time, which must
be uscd to save maximum fuel at the
thermal plants.
The specified variables are real and
reactive powers at PQ buses, real powers
magnitudes at PV buses and voltage and voltage
magnitudc and angle at the slack bus.
variables to be specified for The additional
load flow solution are the
transforners. If the specified variables tap settings of regulating
are allowed to vary in a region
practical considerations (upper constrained by
and lower limits on active and reactive
voltage limits and range of transformer generations bus
tap settings). there results an infinite number
load flow solutions, cach pertaining of
to one set of values of specified
choice in some sense of the values variables. The "best'
of specified variables leads to the "best' oad
solution. Economy of operation is flow
naturally predominant in determining
generation to cach station for various allocation of
system load levels. The first problem in
system parlance is called the "unit commitment' power
(UC) problem and the second is called
the load scheduling' (LS) problem. One
must first solve the UC problem before
proceeding with the LS problem.
PGE-63
POPULARPUBLICATIONS
-P
where P, = Load demand
N=Number of units committed at a particular hour
PGE-65
POPULARPUBLICATIONS
PGE-67
POPULARPUBLICATIONS
PGE-68
POWERGENERATION ECONOMICS
Answer:
a) Unit commitment:
In operational scheduling
of electric power generation,
the unit commitment. It involves the most important problems is
determining the start
schedules of generating units up and shut down (ON/OFF)
to be uscd to meet
- 168 hours) period. The aim is forecasted demand over a short-term (24
to minimize total production
and reserve requirements while cost to meet system demand
observing a large set
a complcx mathematical optimization of operating constraints. In fact it is
variables. Prior to solve problem having both integer and continuous
the ceconomic dispatch
should be solved beccause only problem. unit commitment problem
those units which were
the unit commitment solution can allocated to generating duties by
be considered for power
generation.
Constraints of Unit Conmitnent
Problems
UCP is a practical problem and
must take into account a
constraints. These constraints large number of practical
are system, device/operational
Again, these are broadly categorized and environmental type.
as equality and inequality
Equality constraint is described constraints.
by the system power
export) also known as demand balance (demand plus loss and
constraint i.e.,
PGE-69
POPULAR PUBLICATIONS
b) Spinning reserve:
on line (running) must have a definito
To meet contingencies, the capacity of units
times. This margin is called spinning reserve. It
márgin over the load requirements at all
demand upto a certain extent of probable loss of
ensures continuity by mceting the load
used, based on past cxperience, Patton's
generation capacity. While rules of thumb are
promising.
analytical approach to this problem is the most
with operating time and since a unit which
Since the probability of unit outrage increases hours
a particular time has to be started several
is to provide the spinning reserve at
be treated in totality over a period of one
ahead, the problem of security of supply has to
complete certainty. Also, the spinning
day. Furthermore, the loads are never known with
stations of the system and not
reserve has to be provided at suitable generating
necessarily at every generating station.
other, so
f=-2Vg
well, giving
The two vectors are equal, so all of their components are as
=0
For all k =l. -n, where the constant 2 is called the language multiplier.
in n+1 unknowns, which is
The extremum is then found by solving the n+1 equations
be so useful.
done without inverting g, which is why language multipliers can
For muliple constraints gl = 0,g2 = 0.*,
+24l +2,Vr2 +=0
Physical Signifcance:
When you want to maximize (or minimize) a multivariable function f(x,y,..subject
to the constraint that another multivariable
function equals a constant, g(x,y,")=C,
follow these steps:
function L as follows:
Step 1: Introduce a new variablel, and define a new
L(ry2)=f(%y,..)-2(g(%,),.)--c)
PGE-70
POWER GENERATION ECONOMICS
This function L is called
the "Lagrangian", and
"Lagrange multiplier". the new variable A is referred to as a
PGE-71
POPULARPUBLICATIONS
ECONOMIC LOAD
DISPATCH
PGE-72
POWERGENERATION ECONOMICS
Answer: (c)
BnP'a
m= =l P.P
15. At stack bus, which one of the foltowing combinations of variable is specified?
WBUT 2013]
b) P.Q c) pM d) O.M
Answer: (a)
PGE-73
PUBLICATIONS
POPULAR WBUT 2013]
d) unity matrix
is a matrix
16. Normally Zmatrix
b) sparse matrix
c) full
a) null matrix
Answer: (c) two units in a plant are
characteristics of the Rs/MWh.
incremental cost 0.15p, +3.0
17. The Rs/MHWh, lc, = is WBUT 2013]
Ie =0.1p, +8.0 optimum sharing of the load
100 MW, the
When the total load is P2
P40 MW 60 MW
a) 66.7 MW
b) 33.3 MW 40 MW
c) 60 MW 33.3 MW
d) 66.7 Mw
Answer: (a) incremental transmission loss is
factor of a plant is unity, its WBUT 2013, 2014, 2017]
18. If the penalty d) none of these
c) zero
b)-1.0
a) 1.0
Answer: (Cc)
is 60Hz then change
in
rated frequency
regulation is 5.1 and the WBUT 2014, 2015]
19. If the speed d) none of these
frequency is c)5 Hz
b) 6 Hz
a) 3 Hz
Answer: (a)
of
power system is carried out on the basis WBUT 2014]
20. Economic operation of cost b) equal area criterion power
fuel
a) equal incremental d) all units sharing equal
c) equal fuel cost criterion
Answer: (a)
upon WBUT 2015]
representation, the loss depend
21. In transmission loss b) load
a) generation
parameters d) total power system
c) transmission
Answer: (c)
generator with highest positive incremental
23. For economic
operation, the [WBUT 2017]
transmission loss will operate at
incremental cost of production
a) The lowest positive
b) The lowest negative
incremental cost of production
c) The highest positive
incremental cost of production
d) None of these
Answer: (a)
to plant 2. The loss coefficients
24. In atwo plant system, the load is connected WBUT 2017]
a) B, B,B, are non zero
zero
b) B, and B are non zero but B,is
PGE-74
POWERGENERATION ECONOMICS
c) B, and B},are non
zero but B,, is zero
d) B,is non zero but
B,and B, are zero
Answer: (d)
2
+
2
L|
27 2x.003125
7.92 7.85
2x.00388
7.97
2x.00964
PGE-75
POPULAR PUBLICATIONS
dispatch
condition for optimum schcduling or optimum
From the
10.5395 7.92 2.6195 2.6195x 160 =419.12 MW
1-
Pa44 271 2x.003125 2x.003125
= 346.5824 MW
10.5395-7.85 2.6895x 128.865
Ps 2x.00388 2x.00388
2 2.56955 2.5695x51.867 = 133.2722 MW
- B_10.5395-7.97 =
Pas
Pas27 2x.00964 2x.00964
generators, 1 and 2, for
supplied by two 200MW
load of 300 MW is
2. A constant
fuel cost are
which the respective incremental
dC0.2P; +40
d'a
dC=0.2P, +30
MW is scheduled
in Rs/h if a load of 220
Calculate the extra cost incurred WBUT 2014]
asP P =110MW.
Answer
-0.2P +40
dP
d-0.2P, +30
dPo
Now for economic operation of the units
dC dC
dPa dP
=0.2P +30
0.2/P +40
Or, 0.2(P-P)=-10
of P-P --50
P+ 300
50
Pa-P
2/P 250
MW
125
P =175 MW
PGE-76
POWERGENERATION ECONOMICS
P Plant output
(R+Pa)
30 50
30 25 55
30 40
40 45 85
50 50 100
100 175
100 120 220
For a total load of 220 MW unit I should
take up to 100 MW and unit 2 should supPply
120 MW. For cqual distribution
each unit supplies 110 MW.
The cost of generation for each unit are
C-Jac,ldl, ) dP, = JIC, dP = J{0.2P +40)
JP =0.2P
+40P +k, Rs./h
C Jdc,Idk,)dP = {C dP= {(0.2P, +30
where k and k, are constants.
dr, =0.2P +30P +k Rs.h
PGE-77
PUBLICATIONS
POPULAR
Answer:
=30+7R+0.004P Rs/hr.
F
Rs/hr.
F= 450+7.3P +0.0025P
+0.003 Rs/hr.
F 600+6.6P
Here power demand
P=500MW
Cost coeficients:
A-7 0.004
B 7.3 =0.0025
B =3.6 0.003by the cquation
is given
The incremental fuel cost 7.3 6.6
+
2x0.004 2x0.0025 2x0.003
22L + 1
2x0.004 2x0.0025 2x0.003
27 27 2, 500+(875+1460+1099.9S6)
500+(7x125+7.3x 200+6.6x 166.66)
491.66
125+200+166.66
500+3434.956 3934.956-8.003
491.66 491.66
scheduling or optimum dispatch
From the condition for optimum
=125MW
P 2x0.004
271
P =8-7.3 =0.7x
2x0.0025
200=140 MW
PGE-78
POWER GENERATION ECONOMICS
5. Explain the problems
of economic load dispatch. How
settled? the problems can be
Answer: [WBUT 2017]
1" Part: Refer to
Question No.
2nd Part: Refer to Question No. 8(b) of Long Answer Type Questions.
3(a) of Long Answer Type Questions.
6. What are the advantages of
Indian interconnected power interconnected power System? What is the name of
Indian power System? What system? How many Zones are interconnected in
are the names of those
Bengal has been included? zones? In which zone West
Answer: [WBUT 2017]
1 " part:
The connection of several generating
stations in parallel is known as interconnected
system. The advantages are as follows: grid
Exchange of Peak Loads:
An important advantage of interconnected
station can be exchanged. If the load system is that the peak load of the power
curve of a power station shows a peak
is greater than the rated capacity demand that
of the plant, then the excess load can be
stations interconnected with it. shared by other
PGE-79
POPULAR PUBLICATIONS
Questions
Long Answer Type
load dispatch for a power
co-ordination equation for optimum factor.
1. a) Derive the
and hence an expression for penalty
system including transmission losses
economic operation of the generating
significance of penalty factor in WBUT 2008]
What is the
plant? OR, a function of
a power system can be expressed as
of the assumptions
Show that transmission loss generators in the system. State
outputs of the WBUT 2009
the active power
you make. OR,
generation.
for transmission loss as a function of plant
Derive the expression WBUT 2013, 2015]
..(2)
--P=0
=
plants
where k= total number of generating
generation ofith plant
all buses (system load demand)
P = sum of load demand at
P =total system transmission loss.
To solve the problem, we write the Lagrangianas
ca)-h-a
iel
in this section
(3)
0-d-+i-0, k . (5)
ad4+2=0,
dla
i=1,2,.,
the output of only one plant
can
Rearranging Eqn. (5) and recognizing that changing
affect the cost at only that plant, we have
PGE-80
POWER GENERATION ECONOMICS
dC
dP dC
= or, L,= l, i=1,2,, k (6)
dP
1
where
(1-8P,/dPa) (7)
is called the penalty factor of the ith plant.
The Lagrangian multiplier 2 is in rupees per megawatt-hour,
when fuel cost is in rupees
per hour. Eqn. (6) implies that minimum fuel
cost is obtained, when the incremental fuel
cost of each plant multiplied by its penalty factor is
the same for all the plants.
The(k +1) variables (Pa Pezs.Pa,2) can be obtained from k potential dispatch
b) A power system consists of two 100 MW units whose input cost data are
represented by the equations:
C =0.05P +20P, +800 Rupees I hour
C =0.06P+15P,+1000 Rupees / hour
Total received power PR 150 MW. WBUT 2008]
Answer:
The incremental production costs of both the units are
dC
(0.05x 2)P + 20 Rs. per MWhr
dP
= (0.06 x 2)P, +15 Rs. per MWhr
dP
Now for economic operation of the units
dCdC,
dP dP
1.e., 0.1R +20 = 0.12P +15 (1
=150 MW (2)
and +P
Solution of these equations
=59.1M
P=90.90MW
PGE-81
POPULAR PUBLICATIONS
4 1115.75
-2.369
1-.578
1 200
Penalty factor of the plant 2
= 4.378
1OP1115.75 1-.7716
oPGr 150
i=Rs 130 per MWh
dPa =
Incremental fuel cost of plant ' is G l=130x 2.369 308.0568 Rs/MWhr
dC
Incremental fuel cost of plant 2 is
dPa
OG,)
dC =130x4.378 =569.14
dPo
Total incremental fuel cost is, (308.0568 +569.14) = 877.1968 Rs/MWh.
PGE-82
POWER GENERATION ECONOMICS
3. a) Develop a
simple computer approach
problem. for solving the economic dispatch
Answer: WBUT 2010
Economic Load Dispatch
The cconomic load dispatchby Newton-Raphson Method:
problem can be defined
by equation
F=f(x, u)
.(la)
s(x,a)=0
h(x, u) s0 (16)
...(lc)
minu Smax
XminX S max
subjected to the power balance
equation (2) and the power limit constraint,
Minimize F(P)=E(«/+BP+1)
Subjected to
F (2)
as P,
P SPS Pa
and 7, are the cost coefficients,
for i= 1,
2,3,..., NG where,
Pond, = total load demand of the
system,
P=real power generation at ith generator bus,
NG=total number of generators,
Pactive power loss in the transmission lines.
Transmission line loss can be
expressed as
NG NG NG
=B+BP, +2P B, P, (3)
The Lagrange function to obtain optimal
power generation being given
NG
by
P )-.(P.)+2| R+-2.| NG
4)
The necessary condition for optimization
is given by
(5)
PGE-83
POPULAR PUBLICATIONS
and
A L OL
.. (7b)
OAdP
for i=1, 2, 3,.., NG
Equations (7a) and (7b) can then be written in a matrix form as
8L L_ 1
oPP P2 || AP aP
(8a)
L_ 8LA OL
or, [HrHAr
H
or, HChange in control variables=J (8b)
where H and are called Hessian and Jacobian matrix, respectively. The order of
different submatrices of |H| matrix and their interrelationships are given below:
Order of | Hre= NGxNG
Order of
H= NGxI and#J=[H,
Order of [H]=1x1
The order of different sub-matrices of |J| matrix are given below:
Order of I= NGx1
Order of [ J]= Nxl
The first order derivatives required for equations (7a) and (76) are given belor
L)L),oR-|
PGE-84
POWERGENERATION ECONOMICS
NG
(20.+)+2+28,P. k
(9a)
L =22.B 22B
OPO (106)
oPor
for = 1, 2,3,..., NG; k =1, 2,3,..., NG but
i *k i
The second order derivatives of equation (9a) with respect to l are given in equation (IOc)
8L L_ o-1+B,+2B,= NG
.. (10c)
k=l
for i = 1, 2,3,.., NG
The second order derivatives of equation (9b) with respect to l are obtained as:
L =0 (10d)
Economic load dispatch problem may be solved by solving equation (8a) or (8b) using
equations (9a) - (10d). The flowchart, in order to find economic generation schedule
using Newton-Raphson method, is shown in figure 1.
PGE-85
POPULAR PUBLICATIONS
Start
Read,
1. Total no. of generators, NG, total load = Paad
PGE-86
POWERGENERATTON ECONOMICS
tol e?
kpkp +1 Using equation (3), compute
transmission line loss. P
-
No Is Compute Totat cost of generation
kp> KPMAX NG
=
A
Yes
PGE-87
POPULAR PUBLICATIONS
It is
S(2.=0 where i =
Ax .. Sxn
+higher order terms =0
|)
(4)
L
Sx,
or in vector matrix form
S+J'Ar° =0 .. (5)
where Jis the Jacobian Matrix evaluated at r.
In compact notation,
Sx (6)
In eqn. (5)Ar" is the vector of approximate correction.
This can be written in the formn
ar=
(") (7)
PGE-89
POPULAR PUBLICATIONS
Answer: as
In general fom, the transmission loss can be expressed ... (1)
=PBP +P'B, + Boo
loss formula.
Eqn. () is the generalised transmission
equation considering transmission loss.
Flow chart for the solution of coordination
PGE-90
POWER GENERATION ECONOMICS
Start
Read
Total no. of generator buses, NG
2. Total no. of buses, NB
3.
.6 P.0; for each bus, i.e., for
i= 1,2,3,. NB
j=NG+
j=NG+1|
where aji =
for i= 1,2,3,.. NG and (NG+1)XNG+1)
Z.
Compute and store. [p] = Real =Ic¥ [*BusC]\«
Compute and store the transmiss ion line loss,
P
Pe1
Ps2
LPs.Pe2PsNG JUB|
PsNG
Stop
Fig: 1
Flowchart to find out loss cocflicients (i.e., [B} matrix) and transmission line loss
PGE-91
PUBLICATIONS
POPULAR
In a system
ofN sources, always
ER,,+E8+B J=l
i cocfficients or
B-coefficients (Nx M matrix) and is
PI
LOAD
plants are
cost of the WBUT 2012]
The incremental production
al=0.05P, +20
di-0.025R +I
+15,
dP
not be affected
by
in the line will
Answer: alone, therefore the losses
at bus 2
Since the load is
generator of plant 2. =0
=B,R as B, = B, =0and B
15.625 B, x 125
B, =.001
Now coordination
equation
dR
+L=
=.001p or =002P
where P
equation for plant
I we get
Substituting in the coordination
0.025+15+ 2x.002=2
or, 0.025P +0.048P +15 =24
or, .073/ =9
or,
R=123.28 MW
coordination equation for plant 2
and from the
0.05P +20 = 24
PGE-93
POPULARPUBLICATIONS
Plant 2
7.
Plant PG D
LoadLoad PD
PGI
transmitted from plant 1 to the
figure. If 100 MW is generation for
system is shown in incurred. Find the required 25/MWH
A two bus of 10 MW is system is Rs.
load, a transmission loss the
by the load when below:
power recelved
each plant and the are given
incremental fuel cost of the two plants
The
L=0.02P +16.0 Rs/MWH
dPa WBUT 2014]
+20.0 Rs/MWH
=0.04P
PL., Therefore,
Answer: any effect on
load is at bus 2 alone, P2 will not have
Since the
and B =0=B
B=0
Hence, P = B,R
Since, Po = 0, Pa=R
=10MW
For, P =100MW, P
or, B,,
=0.001(MW)
ie,
i.e 10 B,(100)
1
For plant
0.02P+16.00 = -A(1-BR)
=2(1-28,la) (1)
and for plant 2 becomes
0.04P+20.00=
we get
Substituting the value of B, and i=25,
P=128.57 MW
P2=125.00MW
The transmission power loss is
P=B,=0.001x(128.57) =16.53MW
PGE-94
POWERGENERATION ECONOMICS
and the load is
PD2P =
+Pa-P 128.57 +125 -16.53=237.04 MW
8. a) How input-output
efficiency and Heat-rate curve of a generator can be represented? Explain
(H.R.) the
b) If n-number of generators curve.
cost of generation will be are running in parallel,
minimum? then under what conditions,
c) The input-output curve
of a 10 MW station is expressed
I= 4x10° (10+8L+0.41 )where as followsS:
l is the input KJ/hour
(i) Without plotting and Lis the output in MW.
any curve find the load at
occurs? which the minimur efficiency
(i) Find the increase in input
required to increase the
5 MW by means of
input-output curve and also by station output from 3 to
incremental rate curve.
Answer: WBUT 2017]
a) The energy input can be obtained
by measuring the coal INPUT
tonnage used during the hour and then
energy content in MBTU/ton. The multiplying by the coal Fuelrate
plot the fuel input can be MBTU/hr
plotted in MBTU/hr as a function R
of the
MW. Such a plot is called an input-output power output P, in
curve.
OUTPUT P
Heat-rate Curve: The heat rate curve plots
the heat energy required per MWH
generated electrical output for the of
generator as a function of
the generator's MW output. Thus,
the heat rate curve
indicates the efficiency of the unit
over its operating range.
Generally, units are least efficient
at the minimum and
maximum portions of their MW output capability
efficient somewhere in the middle and most
of their operating range.
The vertical axis is plotted in MBTUMWH
and the
horizontal axis is plotted in MW. You may interpret
the heat
rate for a generator producing X MW as follows:
the heat (Output) Mw
rate indicates the amount of heat input energy
per MWH of generation required. to
produce X MW of power.
The lower this number, the less input energy is
required to produce each MWH of
electricity.
or,
=4x108+04
Efficiency =pur
Output
Input
Efficiency, 7=-4x10+8+0.4L
when+8+0.4L is minimum
will be maximum
Theefficiency L
d+8+0.4L|=0
1004 0
following
9. Write short notes on thé wBUT 2009, 2010
2011)
a) Reactive power
optimization WBUT 2010,
ioau dispatch
b) Economic load
orof economic operation
operation wwithout consider
c) Algorithm for computer solution WBUT 2013]
2014
losses in the system peak load plants WBUT 2013, 20141
d) Load sharing between
base load and WBUT
e) Active and reactive
power optimization WBUT2014
curve
) Predicted load
PGE-96
POWER GENERATION ECONOMICS
Answer:
a) Reactive power optimization:
The power flow solution calculates power
flows and dctermines bus voltages at an
operating point. However, it is left to the
engineering judgement of the system planner to
determine optimum way of system operation
considering operating objectives, operating
and cquipment constraints. Such an
cxercise is very tedious and time consuming for a
practical system with large number of operating
controls and constrairts. A properly
designed optimal power flow solution provides the
best and most optimum practical
solution to achicve improvement in a single
or multiple hierarchical objectives while
respecting various constraints on the system operation.
An OPF can determine the most
effective subset of controls and their solution for a
given operating condition to improve
the specified objectives. OPF can consider different
objectives for improvement such as
transmission loss minimization, voltage stability improvement
and minimization of
system operating cost.
OPF/RPO analysis module of Power Application is
based on the dual LP programming
approach and has the following features:
Newton-Raphson load flow for solution at an operating point.
OPF/RPO solution of multiple-islanded systems. The
solution is available for
each of the islands having a reference (slack) node.
The reference node is
automatically identified by the algorithm as the largest
generator node in each
island.
Choice of objectives for the OPF/RPO (Transmission loss minimization,
Voltage
Stability improvement, Removal of operating violations, Economic
dispatch).
Optimal load flow.
OPF/RPO control options are active power injections, reactive power
injections,
shunt compensations, series compensations. phase shifters, transformer taps.
OPF/RPO sensitivity calculations with respect to the performance objective
provides information for suitable location of shunt reactive power compensation
and also identifies most effective controllers for optimization.
No limits on the number of study cases and related reports in a single execution
of the program.
However, a practical ELD must take ramp rate limits, prohibilcd operating zones, valye
to provide the
point loading eftccts and multi fuel options into consideration
a non-convex
completeness for the ELD problem formulation. The resulting ELD
1s
by the traditional
optimization problem. which is a challenging one and cannot be solved
solved by dynamic
methods. An ELD problem with valve point loading has also been
power systems
programming (DP). Though promising results are obtained in small sized
while solving it with DP. it unnecessarily raises the length of solution procedure resulting
in stipulated time frames.
in its vulnerability to solve large size ELD problems
such as Genetic
Moreover. evolutionary and behavioural random search algorithms
been
Algorithm (GA). Particle Swarm Optimization (Ps0) etc, have previously
implemented on the ELD problem at hand. In addition, an integratcd parallel GA
incorporating ideas form simulated annealing (SA) and Tabu search (TS) techniques was
parameter. Yalcinoz
also proposed in utilizing generator's output power as the encoded
has used a real-coded representation technique along with arithmetic genetic operators
and elitistic selection to yield a quality solution. GA has been deployed to solve ELD
with various modifications over the years. In a similar attempt, a unit independent
encoding scheme has also been proposed based on cqual incremental cost criterion. In
spite of its successful implementation, GA does posses some weaknesses leading to
longer computation time and less guaranteed convergence, particularly in case of epistatic
objective function containing highly correlated parameters.
This paper proposes a new optimization approach, to solve the ELD
using a hybrid
Bacterial Foraging (BF) - Differential Evolution (DE) algorithm, which is a recently
emergcd stochastic optimization technique. Passion proposed the Bacterial Foraging
optimization technique, where the social foraging behaviour of Escherichia coli (those
living in our intestines) has been studied thoroughly. On the other hand DE is a simple
Genetic Algorithm (GA), which implements a differential mutation operator that
distinguishes it form traditional GA. In this work the chemotaxis step of bacterial
foraging is made adaptive and merged with the DE in order to tackle real world problems
in a more elegant way.
Step 3: To computeP°
PGE-98
POWERGENERATION ECONOMICS
[Usually
2P- P. = c S0.001 (a tolerance)
tillP-P .
Step 6: 1f P" becomes greater than
P, in step 4, a new value of A'=
assigned and then it is required to
2°-
AA] is
proceed to step 2. Computational
loop is continued till
2-P6.
Step 7: To stop, if step 4 is satisfied.
If the effects of power limits are to be considered,
a partial modification is needed in
algorithm. As 2 is increased or decreased the
in the iterative process,
if a particular
generator loading P reaches the prescribed
limit (P or P) its loading from
now is
held fixed at this value and the balance
of the load demand is then shared between
remaining generation on equal incremental the
cost basis. This operation is also said to be
optimal.
PGE-99
POPULAR PUBLICATIONS
Fig. 1
shows a load duration curve.
kWpoat
Ape
d (kW)
2
Load duration
curve
Atu KWa
Time (hours)
Fig: 1
Load duration curve of the pilants
PGE-100
POWER GENERATION ECONOMICS
In this case the total
operating cost of the combination is given as:
Ca, ta, +bkW,+b.kW+GA
Now, if the base power is tC, (3)
cxtended by the amount d(k\W)
cost of thc combination will of to line 2', the total operating
modify as follows:
C a, +a, +b,(kW, + dkW)
+b,(kW,-dkW)
+(4e+dkWxh)c, +(4,dkWxh)c . (4)
The change in cost,
C-C=(h, -b,)ck\W +(G -<,)dkWxh
The optimum condition requirements (5)
are that above change must
be zero. 1.e.,
h4 C2-C
(6)
Thus it is possible to share the
load between the plants due
operation is effected. to which overall economy in
The method described above for
distributing the load among the
interconnccted system can be two power plants in an
used for any type of plants
(i) Thermal and hydro, (iii) Nuclear and as (i) Thermal and diesel,
hydro and so on.
e) Active and reactive power
optimization:
Reactive power optimization is an
important function both in planning
day-to-day opcrations of power for the future and
systems. It uses all the reactive
judiciously, while planning suitable power sources
location and size of VAR compensation
With increasing fuel costs and in a system.
capital investments, economics
and scheduling have a tremendous of reactive power planning
effect on the profitable and
power system. reliable operation of a
Electric power systems all over the world
are moving towards deregulated
markets. To control fequency, stability, electricity
security and voltage profile of the
ensure the generation and transmission, system and to
ancillary services like frequency control,
control and system restart are needed. network
Reactive power and voltage control is
ancillary services to maintain voltage profile one of the
through injecting or absorbing
power in electricity market. A number reactive
of optimization techniques have been
the literature to solve the reactive power optimization proposed in
problems.
To minimize the active power loss and
the voltage deviation under some operational
constraints, reactive power optimization in power
system nced fnd a optimal solution,
containing the reactive pover output of generators
(or voltage of generators V), the
reactive power compensation capacity (including the capacity
of shunt capacitors Q, and
reactance 0,) and transformer tap-settings (7). lt has a
significant influence on security
and economic operation of power systems.
The augmented objective function is to minimize the
active power loss AP and
voltage deviation AV, the
PGE-101
POPULAR PUBLICATIONS
F=min
(1)
AP
cocllicicnt of nodal voltage
node number and is the equivalent
where n is the
is the maximum voltage of
node i, min s the minimum
deviation Al,. Supposing m
AV, is given as below:
Ar=
-
voltage of node i, the definition of
0
(>m
(mSV,s ) (2)
(<) constrains in the
and reactive power balance
Equality constraints contain active
following.
AP=P-P-V2"(G,cos6, +B,sin,)=0 (3)
cos
AQ -0, +N,AQ, -N,AQ, -V2Y(G,sin6, -B, 6,)=0
Pand Q, are
and reactive power supply of bus i,
where Pa and Q are active power
bus i and j, 0, is
reactive load of bus i, V and V, is the voltage module of
active and
i and j. AQ, and AQ,
are the unit capacity of
the difference angle between bus
and N, are working span of capacitor
and
capacitor and reactance of bus i. N,
reactance of bus i.
Inequality constraints contain:
NmSN SNamas
SNpm
mSNu
Tye7, S1,
QmSQa SQinas
S SS
where a, Na, Ng, , are voltage of generator, working span of capacitor, working
are
reactance and transformer tap. All of them are control variables. Q and S,
span of
branch ij and they are state
reactive power output of generator i and power flow on
variables.
PGE-102
POWER GENERATION ECONOMICS
Predictive Load Curve:
Unit commitment refcrs to
committing a generating unit to be
clectricity during a specific time online and generating
slot, so that the generation requirements
can be met and other EMS of the system
functions can take necessary
as thermal units require action. Generating stations such
quite an amount of time
gencrate the required voltage to come up to the required speed,
and get synchronized to the
committcd, it should be available system. Once the unit isS
to supply load; however. to leave
committed all the time becomes the generating unit
an expensive affair. It makes
commit the units when they much more sense to de-
are not required. Once the
depending on the requirement, it is load forecasting is done,
committed and de-committed economical to know when each
for specific time slots. unit is to be
Unit IV
Unit I11
Unit I
Fig: 1
Unit commitment of four generating stations
Fig. 1 ilustrates a simple unit commitment
example where four units are supplying the
load on the system and the units are committed
and made available, de-committed
turned off and when there is a demand as seen from and
the predicted load curve.
The unit commitment problem is not as simple as
discussed above, as each power utility
will be working under a large number of constraints
and laws and these have to be nuilt
into the unit commitment problem, so that an
optimal economical schedule is available
for the operations.
Keeping ample spinning reserve as per the directive of the regulatory
authority in each
country is a constraint. Spinning reserve is the ditference between
the total generation
capacity available of all the units online (spinning) and the load supplied
including the
losses. It gives an indication of how much extra capacity the
system possesses to take
care of an emergency, whether the sudden loss of a
generating unit or a transmission line.
Each utility will have norms for the percentage of generation or
load as spinning reserve.
ypically, the reserve is equivalent to the largest generation unit, so that the sudden loss
of any unit can be handled. The spinning reserve could also be a mix of stations that can
be quick started with traditional thermal plants. The
spinning reserve can also be
PGE-103
POPULARPUBLICATIONS
PGE-104