Work Activity Base Production Rates
Item Unit Base Rate Metric Base Rate
Grade Items
Mobilization Days 5
Clearing & Grubbing Acres 3 1
Demo. Of Buildings Each 1
Asbestos Rem.(Res./Small Commercial) Days 4
Asbestos Rem.(Large Commercial) Days 10
Demo. Of Asphalt Pave. S.Y. 1500 1254
Sawcut Pavement L.F. 800 244
Remove Curb& Gutter L.F. 600 183
Remove Exist. DI/Manhole & Assoc. Pipe Each 6
Temporary Detour Days 6
Roadway Excavation C.Y. 2000 1529
Excavation Small/Irregular Area Projects C.Y. 850 650
Excavation - Large quantity projects C.Y. 5000 3823
Drainage Corrug.Metal 18" L.F. 205 62
Drainage Concrete Pipe 15" L.F. 168 51
Drainage Conc. Pipe 18" L.F. 144 44
Drainage Conc. Pipe (24" to 54") L.F. 72 22
Drainage Conc. Pipe (60 in. & greater) L.F. 48 15
Inlets/Manholes Each 2
Minor Excavation (Drainage Structures) C.Y. 250 191
Box Culverts, Class A Conc. C.Y. 20 15
Box Culverts, Cast in Place L.F. 5 2
Box Culverts, Precast L.F. 20 6
Retaining Walls, Cast in Place L.F. 5 2
Major Retaining Walls S.F. 210 20
Sub-grade Stabilization S.Y. 8000 6689
Aggregate Base Tons 1360 1234
Aggregate Base Small/Irregular Projects Tons 680 617
Drainage Blanket Tons 1200 1089
Asphalt Base Tons 1175 1066
Asphalt Intermediate Tons 750 680
Asphalt Surface Tons 500 454
Milling/Flexible Pavement Planing (Max. 2") S.Y. 3000 2509
Curb & Gutter (Machine Placed) L.F. 800 244
Curb & Gutter (Hand Placed) L.F. 400 122
Curb& Gutter Radial (Hand Placed) L.F. 150 46
Concrete Entrance S.Y. 80 67
Sidewalk S.F. 1550 144
Concrete Driveway S.Y. 150 125
Entrance Pavement S.Y. 100 84
Barrier Walls, Slip Form L.F. 630 192
Concrete Repair S.Y. 30 25
Concrete Paving S.Y. 2500 2090
Slurry Seal S.Y. 8000 6689
Seeding Acres 2.5 1
Fencing L.F. 1000 305
Fine Grading S.Y. 2000 1672
Lime Stabilization S.Y. 6000 5017
Shoulder Construction L.F. 500 152
Slope Protection C.Y. 100 76
Underdrain L.F. 1500 457
Underdrain Outlet/Endwall Each 8
Utility 12" Ductile Iron L.F. 105 32
Utility 12" PVC L.F. 320 98
Directional Drilling L.F. 50 15
Traffic Items
Item Unit Base Rate Metric Base Rate
Initial Traffic Control Days 2
Ordering Signal Equip. Days 30
Major Traffic Signals Days/Intersec. 40
Pavement Markings L.F. 10,000 3048
Stop Bars, etc. L.F. 500 152
Arrows/Letters Each 50
Order Sign Material Days 60
Order Overhead Sign Struct. Days 80
Erecting Overhead Signs Days 10
Erecting Signs S.F. 1000 93
Ordering Lighting Material Days 60
Erecting Lighting Days/support 3
Guardrail L.F. 1500 457
Guardrail Terminals Each 2
Order Impact Attenuators Days 30
Install Impact Attenuator Each 3
Electrical Conduit L.F. 400 122
Electrical Wire L.F. 3500 1067
Precast concrete barrier L.F. 800 244