Eng Bin
Eng Bin
29 August 2013
S-LAY INSTALLATION
S-Lay
What is S-Lay?
J-LAY INSTALLATION
J-Lay
What is J-Lay?
configuration
No overbend ! ❑ Pipe stresses are maintained well within the
elastic limit
❑ Lower tension required, resulting in reduced
J-LAY
S-LAY
J-Lay
Typical Equipment Layout
J-Lay equipment
Top Tension layout varies with each
holding the vessel (depending on
pipe in place design of J-Lay tower)
but typically consist of:
• Welding & NDT (1-
2 stations)
• Field Joint Coating
Tensioner
J-lay Tower
(JLT) J-lay module
12m Pipe
buffer Loader
Arm
J-Lay
Welding of Single Joints to Form Double/ Quad Joints
Display Unit
Welding
J-Lay
Welding of New Quad-Joints to Preceding String
Travelling Travelling
Clamp Clamp
Tower
Clamp
Hang-off
Clamp
Conventional Pipeline Installation Methods
Reel Lay
Disadvantages:
• Higher steel wall thickness for allowable curvature during onshore spooling and
offshore installation
• Limited max outside diameter (typically 16”)
• Limitation of coating options
• Need for a spool base
S-Lay
EMAS AMC’s “LEWEK EXPRESS”
4 x 1200mT
Storage Reels
2 x WROVs
w/ TMS
2 x 1250mT
Carousels
2 x 600mT Winches
2 x 20mT Storage Reel
60mT PLET 125mT Secondary Winch
Moon Pool
Handling
19m L x 8m W
System
OPERATIONAL
Reel Lay 2014
Traditional vs Modern
Reel Lay Vessel
Modern:
• Pipe spools can be reeled
on dedicated spools and
transported offshore to be
loaded onto the vessel to
replenish pipe supply
• More pipes can be laid
• Rigid pipelines and SCR’s up to 16” (by reel lay)
• Umbilicals and flexibles
• Flexible and Rigid Jumpers
• Heavy Lift / Subsea Construction
– Topsides, Manifolds, Piles
Reel Lay
Lewek Constellation’s Reeling Capacity
PUSH-PULL METHOD
Push-Pull Method
Project Example – Ref. Geocean
• In this method, the required pipe string length is fabricated onshore and fitted with
buoyancy devices at a given spacing, then it is launched and finally towed to the desired
offshore location.
• After positioning and aligning of the pipe string, the buoyancy devices are stripped by
one of the tugs in a control manner so that the pipeline settles to seabed due to its own
weight in a controlled manner.
Surface Tow Method
Project Example – Location: Brunei
Towing to site
Surface Tow Method
Project Example – Connecting Pull head to Pre-Installed Line on Platform & Retrieval of
Stripping wire for Commencement of Pipelaying
Surface Tow Method
Project Example – Stripping of Buoyancy Drums
Surface Tow Method
Schematic: Stripping of Buoyancy Drums and Laying of Pipeline
Unconventional Pipeline Installation Methods
Bottom Pull Method (Landfall to Landfall)
Tanjong Penjuru
Project Requirement: (Singapore mainland)
• 8 Pipelines
• 2 Fiber Optic Cables
Bukom End
Drilling and Blasting Works along Pipeline Route to shatter rocks to enable Dredging
Bottom Pull Method (Landfall to Landfall)
Commencement of Pulling of Bundled Pipe
Linear Winch
Bottom Pull Method (Landfall to Landfall)
Pipeline Installation : Alignment and Tie-In of new String to Preceding String
Bottom Pull Method (Landfall to Landfall)
Pipeline Installation: Arrival of Pulling Head at Destination Point & Installation of
Risers
SHORE APPROACH BY
HDD
Shore Approach by HDD
What is HDD?
• HDD is a trenchless construction method utilizing equipment and techniques from horizontal
well drilling technology & conventional road boring
• 3 stages of HDD:
➢ Drilling an initial pilot hole with a down-hole navigation package, relaying the position & depth of
the drilling device
➢ Increasing the hole diameter by using different types of reamers depending upon ground conditions
➢ When the hole is opened to a suitable diameter, pulling the pipeline into position
• It has been used for offshore pipeline construction mainly for shore approach pipeline
installation, typically, for following reasons:
➢To avoid damaging and disturbing environmentally sensitive areas (mangrove swamp, home to
protected species, etc)
➢To avoid difficult terrain, and minimize construction cost, where applicable, etc.
Shore Approach Installation by HDD: Typical Concept
Lay Barge
Drilling of Pilot Hole • Pilot hole is drilled from shore based HDD equipment to a designated
“exit” point offshore
• A jet-head assembly is used at the “front” of the drill pipe
• On exiting the seafloor, compressed air is blown through the drill bit to
aid location of exit point
Reaming of Pilot Hole • Pilot hole is forward reamed using barrel reamers
• Hole diameter will be 50% larger than size of product pipe
Shore Approach by HDD
Operation Sequence
Hole Swabbing/ Cleaning • On completion of the reaming the bore hole will be swabbed with a
suitable size barrel swab
• The swab is advanced from the entry surface to the sub-sea exit location
and then back to the entry surface location
• High pressure sea water is discharged at the leading end of the swab as
it is advanced into the bore hole hydraulically clearing the bore hole of
debris
• The swab will verify hole gauge to a suitable size
Advantages: Disadvantages:
➢ Minimal environmental ➢ Requires good geophysical
damage and geotechnical surveys to
➢ Minimal 3rd party ensure soil condition is
interference and disruption suitable
➢ Can be undertaken from ➢ No post-installation
land or using sea-based maintenance of pipe
construction units
Other Unconventional Pipelay Techniques
68
Other Unconventional Pipelay Techniques
S-LAY INSTALLATION
Forces on Pipeline
S-Lay
Potential Failure Modes during Pipelay
Challenges:
Need very large
• Longer & Heavier Catenary lay vessel with
• Higher bending high tension
• Higher Tension requirement to hold Catenary requirement
• Pipe manufacturing and buckle arrestor design
(preference of seamless pipe which has lower fabrication tolerance;
supplementary requirement, etc)
• Other deepwater specific aspects: flooding, tension variations,
pipeline rotation, etc
Design:
• Remove (where possible) or reduce conservatism level
• Consider increased strain level in overbend
0.35%? some
consider 0.5%
• Stinger design – geometry and length, achievable radius,
number of roller supports for load distribution
Potential Failure Modes and Design Considerations
J-Lay
J-LAY INSTALLATION
Forces on Pipeline
F
R : Supports reactions
Seabed reaction
Tb : bottom tension – residual tension in the pipe
J-Lay
Potential Failure Modes and Design Considerations during Pipelay
Tower Bushing/
Clamp/ Tensioner to Design Considerations:
hold PIpe
• Setting of J-Lay Tower Angle and
Upper rollers to
Roller Clearances
“guide” pipeline
• Define maximum allowable sea state
i.e applicable operational window
• Define maximum allowable vessel
Lower rollers to
excursion
“guide” pipeline but
allowing anticipated
Typical J-Lay movement due to
Arrangement dynamic loads
Potential Failure Modes and Design Considerations
Reel Lay
• Reeling
• Straightening
• Laying
Gives cumulative
large plastic
strains up to 2%
which degrade
material fracture
resistance
Challenges:
Design specification
• Low thickness fabrication tolerance (D/t ratio) For successful reeling
• Low variation in yield stress operation, Contractor needs to
• Low Yield Strength /Ultimate Tensile Strength ratio accurately estimate the
• Apply high and steady back tension during reeling following:
• Cumulative strain build-up
Similar problem for girth welds • Potential for local buckling
• Over match weld properties to avoid excessive strain in weld • Resultant ovality
Handling Care • Crushing
• Care should be taken to ensure that back tension is
applied to the pipe when being reeled is not
sufficiently high as to crush the pipe layers beneath
• Another problem is that the reel must be held under
tension throughout the reeling-on, transport to site
and reeling-off process.
• The amount of stored energy in the larger reels can
be massive and failure of a section that maintains
this tension can result in uncontrolled release of this
energy.
• When this occurs, the pipe will uncontrollably spool
itself off the wheel.
Reel Lay
Potential Risks (associated with “traditional” reel-lay operation)
Coating damage
during spooling
Reel Lay
Potential Risks (associated with “traditional” reel-lay operation)
• Weld repairs into storage - when spooling on critical path, contractor sometimes
have to accept a weld repair as it would be quicker than chopping it out completely.
With Constellation, spooling will all be off critical path, so if there is a weld repair it
will just be chopped rather than repaired.
• Stalk handling coating damage – causes delay in spooling time
• Damaged FJC – causes delay in spooling time
• Risk of critical path welding failures
• Coating failures during spooling – again, these need to be repaired on critical path
• Reel walking: see earlier picture. Worker(s) walk on top of the reel as the pipe is being
spooled - highly questionable activity but sometimes manual intervention is required
to pack out the pipe.
• Conventional reel vessel typically reel at 2m per minute – restricted to spooling pipe
onto the reel on critical path as the reel is built into the vessel.
• With EMAS’s Constellation, above critical path risks are eliminated because spooling is
done independently (while vessel is busy installing pipe) and any delay caused by
above typically will not affect critical path activities
Reel Lay
Potential Risks (associated with “traditional” reel-lay operation)
Pipeline spooled
separately and
transported offshore to
be loaded to reel vessel
Reel Lay
Heavy Lift System on EMAS’s Constellation allows for Spool Replacement Offshore
SURFACE TOW
Surface Tow (Rentis) Method
Potential Failure Modes
60 100
60 100
40
40 50
50 20
20
0 0
0 0
-20
-50
σmax= 48%:
-20
-50 -40
-40 T = 15t
σmax= 63%: -60 -100
-60 T = 10t -100
-80 -150
-80 -150 -100
Pipeline Profile -200
-100 -120
Pipeline Profile -200 Bending Moment
-120 Bending Moment -140 -250
-140 -250 0 400 800 1200 1600 2000 2400 2800 3200 3600
0 400 800 1200 1600 2000 2400 2800 3200 3600 Horizontal Distance (ft)
Horizontal Distance (ft)
140 250
140 250
120 Pipeline Profile
120 Stage 6: total of 1000 m floatation drums removed
Bending Moment 200
Stage 4: total of 500 m floatation drums removed 200 100
100
σmax= 46%: 80
σmax= 28%: 150
60 60 100
100
40 40
50 50
20 20
0 0 0 0
-20 -20
-50 -50
-40 -40
-100 -60 -100
-60
-80 -80 -150
-150
-100 -100
Pipeline Profile -200 -200
-120 -120
Bending Moment
-140 -250 -140 -250
0 400 800 1200 1600 2000 2400 2800 3200 3600 0 400 800 1200 1600 2000 2400 2800 3200 3600
• Calm weather is very important for “Rentis” tow – do not launch the pipeline until good
weather window is certain
• Don’t always trust the weather forecast – we launched the pipeline bundle based on a 3-
day good weather window, but ‘hit’ the storm within 3 hours
• Allow for excess buoyancy drums as some may get dislodge during tow, especially if hit
by storm
• Do the pipelaying in the morning so that you have sufficient time to collect the oil
drums before sunset
Potential Failure Modes and Design Considerations
Bottom Pull Installation
BOTTOM PULL
INSTALLATION
Forces on Pipeline
Pulling Force
Friction Force
Bottom Pull
Potential Failures
Challenges:
Design:
• In event of liquefiable soils, attach buoyancy devices along Just enough buoyancy,
pull wire at engineered spacing for wire to self-dislodge not too many!
during high tide
• Oversize the linear winch
• Reduce number of buoyancy tanks for pipeline
Bottom Pull – Lesson Learnt
Excessive Buoyancy caused undesirable pipeline deflection in strong current during
night pull
Bottom Pull – Lesson Learnt
Uprooting buried cable and straightening cable before next pull
Bottom Pull – Lesson Learnt
Dislodging and straightening of cable was a continuous process in between pulls
Bottom Pull – Lesson Learnt
Installing oil drums along the entire pull cable along inter-tidal zone to self-dislodge
cable during rising tide
Bottom Pull – Lesson Learnt
HORIZONTAL DIRECTIONAL
DRILLING (HDD)
HDD
Potential Failure Modes
Stuck drill stem or pipe • Collapse of hole along the drill along the drill path, due to swelling of highly
string plastic clays, boulders, bentonic shales, coal seams
• Inadequate reaming to obtain optimal bore diameter for pull back
Lost tools and/ or drill • Twisting off of drill stem or metal failure of down hole tools
stands
Damaged pipe or • Inadequate reaming to obtain optimal bore diameter for pull back
coating • Excessive entry or exit angle for bend radius of the pipe string
• Sharp objects or casing present in bore
• Collapse of hole along the drill path
Ref: Canadian Association of Petroleum Producers, Guideline for Planning HDD for Pipeline
Construction, Sept 2004
HDD
Design Considerations
Geotechnical
Drill Path
• Length of borehole to be drilled
(As of early 2000’s, longest drill path is 1.8km, largest pipe is
1.2m OD)
• Radius of curvature allowing installation and
minimization of bending stress (Minimum radius = 1200 x
OD in meters)
• Reaming Diameter (1.5 x OD)
• Entry and Exit Angle
Thank You!
Questions?
Disclaimer: This material includes forward-looking statements prepared by Ezra Holdings Limited (“Company”). The opinions, forecasts, projections or other statements other than statements of historical fact, including, without limitation, estimates of
proved reserves of oil and gas, reserves potential and plans and objectives of management of the Company for financing, are forward-looking statements. Although the Company believes that the expectations reflected in such forward-looking
statements are reasonable, it can give no assurance that such expectations will prove to have been correct. All forward looking-statements contained in this presentation are expressly qualified in their entirety by the cautionary statements contained or
referred to in this section. Readers should not place undue reliance on forward-looking statements. Each forward looking statement speaks only as of the date of this presentation. Neither the Company nor any of its subsidiaries and associates
undertake any obligation to publicly update or revise any forward-looking statement as a result of new information, future events or other information. In light of these risks, results could differ materially from those stated, implied or inferred from the
forward-looking statements contained in this presentation.