Ad 1090116
Ad 1090116
Ad 1090116
14. ABSTRACT
This document describes procedures for conducting environmental and performance tests for fixed photovoltaic systems
used in fixed and dismounted operations. These tests involve characterizing performance under various solar incidence
conditions as well as under unique environmental abuse conditions.
15. SUBJECT TERMS
Renewable power systems, power quality, photovoltaic, solar simulator, irradiance, PV, IV curve
16. SECURITY CLASSIFICATION OF: 17. LIMITATION OF 18. NUMBER 19a. NAME OF RESPONSIBLE PERSON
ABSTRACT OF
a. REPORT B. ABSTRACT C. THIS PAGE
PAGES
Unclassified Unclassified Unclassified 19b. TELEPHONE NUMBER (include area code)
SAR 77
Standard Form 298 (Rev. 8-98)
Prescribed by ANSI Std. Z39-18
(This page is intentionally blank.)
U.S. ARMY TEST AND EVALUATION COMMAND
TEST OPERATIONS PROCEDURE
*
Test Operations Procedure 09-2-291 23 January 2020
DTIC AD No.
Page
Paragraph 1. SCOPE................................................................................... 2
1.1 Overview ............................................................................... 2
1.2 Sequence of Tests .................................................................. 2
2. TEST METHODS ................................................................. 5
2.1 Initial Inspection and Performance Characterization ............ 5
2.2 Safety ..................................................................................... 18
2.3 Mechanical and Thermal Stresses ......................................... 30
2.4 Physical Stresses (To The Module Packaging When
Deployed ............................................................................... 48
2.5 Damp Heat ............................................................................. 54
2.6 Final Inspection and Characterization ................................... 55
3. DATA REQUIRED ............................................................... 56
4. PRESENTATION OF DATA ............................................... 56
1. SCOPE.
1.1 Overview.
a. This test series is for solar panels whose output is electrical energy, and applies to
rigid, semi-rigid, and flexible types. A representative random sampling should be made. Solar
panels/modules are to be subjected to electrical characterization, physical inspection, and testing
assessing durability, environmental exposure, and safety. An overall sequence of test events
outlined in this Test Operations Procedure (TOP) is shown in Figure 1.
b. The overall Safety; Mechanical and Thermal Stresses; Physical Stresses (to the module
packaging when deployed); and Damp Heat test flows shown in Figure 1 have been broken down
into individual subtests with the specific test methods of each outlined in Section 2 of this TOP.
The sequence of the individual subtests has been structured to minimize the overall test duration
and optimize the assessment of each test module.
The test sequence is outlined in Figures 2 through 7. The individual block numbering on each
figure is associated with the corresponding subtest paragraph numbers in Section 2 of this TOP.
2
TOP 09-2-291
23 January 2020
Figure 2. Test sequence number 2.1: Initial Inspection and Performance Characterization.
3
TOP 09-2-291
23 January 2020
Figure 5. Test sequence number 2.4: Physical Stresses (to the module
packaging when deployed).
4
TOP 09-2-291
23 January 2020
Figure 7. Test sequence number 2.6: Final Inspection and Performance Characterization.
2. TEST METHODS.
This test is organized into two parts. Method 1: “Light Soaking” describes how to stabilize a
module via light soaking and how the test levels differ for different cell technologies. Method 2:
5
TOP 09-2-291
23 January 2020
“Light Soaking Check” describes how to check the performance of a single module before and
after light soaking, to see whether or not all products in that group need to be stabilized.
Both light soaking and the light soaking check require the following instrumentation:
a. A continuous light source for light soaking that operates within the intensity range of
200 to 1,200 watts per meter squared (W/m2). Outdoor illumination (natural sunlight) may be
utilized. The light source must not exhibit non-uniformity larger than ±10 percent over the test
module area.
b. A sensor to monitor the irradiance of the continuous light source. The sensor must be
mounted in the plane of the test module.
(2) To an insolation level determined by the cell technology used in the test module,
as specified in Table 1.
6
TOP 09-2-291
23 January 2020
b. The light soaking check adds a current-voltage measurement to the test procedure.
Test conditions for the current-voltage procedure are found in paragraph 2.1.2.
(1) Check the exposure requirements using Table 1. Requirements differ depending
on the cell technology used in the test module, and whether the light soaking is being utilized as
part of an initial stabilization (i.e., first measurement of the product, before stress is applied) or a
final stabilization (i.e., after stress has been applied).
(2) If Table 1 indicates that stabilization is not required, record “not required” in the
appropriate fields of the test report, and do not perform any of the remaining steps.
(3) Mount the test module in front of the continuous light source, with the output
open-circuited. If the module is exposed to humidity, cover the connectors so that they do not
corrode due to the light soak. Such corrosion could lead to increased resistance and an incorrect
subsequent power measurement.
(4) Log the irradiance (kW/m2) normal to the module surface, tracking the insolation
(kW-hr/m2) in real time.
(5) Continue this procedure until the exposure equals or exceeds the amount listed in
column “Minimum Initial Exposure” of Table 1. The requirements differ based on the cell
technology utilized in the test module.
(6) For cell types that are prone to metastability (i.e., reversible changes with light
soaking), the conditions just prior to measurement are important. These cell types show a
requirement in columns “Continuous Exposure at >200W/m2 Just Before Measurement” and
“Longest Time Between Light Soaking and Current-Voltage” of Table 1. For cell types showing
a requirement in column “Continuous Exposure at >200W/m2 Just Before Measurement”, there
must be some continuous illumination at irradiance >200W/m2 just before current-voltage
measurement. In other words, one cannot light soak the module; let it sit overnight in the dark,
then measure it first thing in the morning. Before moving the test module to current-voltage
measurement, the irradiance on the module must be continuously higher than 200W/m2 for the
exposure specified in column “Continuous Exposure at >200W/m2 Just Before Measurement”.
(7) Once the module is removed from the light soak, the current-voltage curve must
be measured within the time period specified in column “Longest Time Between Light Soaking
and Current-Voltage” of Table 1.
7
TOP 09-2-291
23 January 2020
�𝑃𝑃𝑓𝑓𝑓𝑓𝑓𝑓𝑓𝑓𝑓𝑓 − 𝑃𝑃𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖 �
𝛥𝛥𝛥𝛥 = 100 𝑥𝑥 (Equation 1)
𝑃𝑃𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖
(7) If |∆P| = >5, then all modules of this product type that are being tested as a part of
this TOP must undergo light soaking (per Method 1) before any IV measurement.
This test does not depend on specifications from the procurement document. Light soaking is
performed according to the requirements associated with the cell technology utilized in the test
module.
The following items shall be recorded in the test report each time this procedure is performed:
(1) Pinitial.
(2) Pfinal.
(3) ∆P in percent.
8
TOP 09-2-291
23 January 2020
b. Standard procedures exist for measuring IV curves of photovoltaic (PV) modules with
very high accuracy (±1%), as in International Electrotechnical Commission (IEC) 61215-21** and
related documents. However, the IEC procedures may require expensive equipment (e.g., a flash
simulator producing uniform irradiance or an extensive set of calibrated reference modules).
This test procedure is aimed at determining whether a test article undergoes ~20% change in
performance after stress. Thus, a total uncertainty of approximately ±5% is acceptable for these
power output determinations, and requirements are modified accordingly to make this test
accessible to a number of laboratories. Any laboratory performing this test must have completed
the “Test Lab Self-Documentation for Current-Voltage Measurement,” which is a required
component of the reporting for this test.
a. Light source with the characteristics specified in the Test Lab Self-Documentation for
Current-Voltage Measurement (Appendix A), (hereafter referred to as “Self-Documentation
Procedure” or “SDP”).
e. Means for light soaking (paragraph 2.1.1.3), if the light soaking check has indicated
that all modules of this product type need stabilization.
9
TOP 09-2-291
23 January 2020
a. If the light soaking check (paragraph 2.1.1.3.b) on one module of this product type has
indicated that stabilization is needed, perform light soaking (paragraph 2.1.1.3.a). All steps
below are to be performed only according to the methods that were used to achieve acceptable
uncertainty, as detailed in the laboratory’s self-documentation. Any modifications to the test
laboratory’s procedures (e.g., new light source) requires a new self-documentation.
b. Prepare the light source. This preparation may include warming up the simulator,
setting simulator irradiance using a reference module, selecting times of suitable weather for
outdoor measurement, and measuring the irradiance for systems where it is not set to
1000 W/m2.
c. Position the module for exposure to irradiance from the light source.
f. Record a graph of current versus voltage, and the parameters maximum power (Pmp),
Voc, Isc, Imp, Vmp, and ff.
Current-voltage measurements are to be performed at standard test conditions, and do not require
further specifications from the procurement document.
The test report shall include a graph of current vs. voltage, as well as the values of Pmp, Voc, Isc,
Imp, Vmp, and ff.
The Wet Leakage Current test is designed to determine whether the module can withstand wet
environments without any degradation of the module insulation and to ensure the moisture does
10
TOP 09-2-291
23 January 2020
not penetrate the module electrical components, resulting in module failure. Testing shall be
conducted in accordance with IEC 61215-2, Module Quality Test (MQT)-15 unless otherwise
described within this section.
The instrumentation and apparatus outlined in IEC 61215-2, MQT-15 are sufficient for this test.
No modifications or adaptations to the instrumentation/apparatus stated in IEC 61215-2,
MQT 15 are required.
Prior to the start of the Wet Leakage Current test, the module surface temperature shall be
stabilized at standard ambient test conditions as described in Military Standard (MIL-STD)-810H2
and provided below:
Testing shall be conducted in accordance with IEC 61215-2, MQT-15. No modifications to the
test procedures outlined in IEC 61215-2, MQT-15 are required as part of this TOP.
The test report shall contain a comparison to the collected insulation resistance with respect to
module size in regard to the minimum allowable insulation resistance (either provided by the
procurement agency or that outlined in IEC 61215-2, MQT-15) and a comparison to all other
wet-leakage current tests conducted on the same module throughout the test sequence.
11
TOP 09-2-291
23 January 2020
b. This test uses the method of IEC 60891:20093 clause 4, either indoors (clause 44) or
outdoors (clause 43). The module may be assumed to be linear (as defined in IEC 60904-104),
and thus the test method applicable, for irradiances greater than 500 W/m2.
The instrumentation and apparatus outlined in IEC 60891:2009, clause 4.2, are sufficient for this
test.
For either the indoor or outdoor test method, irradiance shall be greater than 500 W/m2, and
temperature over the module under test shall vary by at least 30 °C (54 °F).
Testing will be performed in accordance with IEC 60891:2009, clause 4.4 (indoor test method),
or clause 4.3 (outdoor test method).
Temperature coefficients are measured for energy generation predictions. Procurement agencies
may desire to specify maximum values for temperature coefficients (i.e., maximum decrease in
output with increasing temperature), but such specifications are not required.
Graphs of Pmp vs. T, Isc vs. T, and Voc vs. T shall be included in the test report. The linear fit
used to extract temperature coefficient from these plots shall also be included in the graph. The
extracted values for temperature coefficients of Pmp, Isc, and Voc shall be reported. Example data
are shown in Figures 8 and 9. The data in Figures 8 and 9 were taken from T. J. Silverman, M.
G. Deceglie, B. Marion, S. Cowley, B. Kayes, and S. Kurtz, “Outdoor performance of a thin-film
gallium-arsenide photovoltaic module,” in 2013 Institute of Electrical and Electronics Engineers
(IEEE) 39th Photovoltaic Specialists Conference (PVSC), June 2013, pp. 0103 - 0108.
12
TOP 09-2-291
23 January 2020
Figure 8. Pmp as a function of module temperature measured outdoors for two different modules
(red and blue). Linear fits used to extract temperature coefficients of Pmp are also shown.
Figure 9. Voc as a function of module temperature measured outdoors for two different modules
(red and blue). Linear fits used to extract temperature coefficients of Voc are also shown.
13
TOP 09-2-291
23 January 2020
𝐺𝐺
𝑇𝑇𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚 = 𝑇𝑇𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎 + (𝑈𝑈0 + 𝑈𝑈1𝑣𝑣 )
(Equation 2)
where:
Tmodule= the module temperature in °C.
Tambient = the ambient air temperature in °C.
G = global irradiance in the module plane of incidence (W/m2).
U0 = coefficient relating irradiance and module temperature (W/ °C-m2).
U1v = coefficient relating wind speed and module temperature (W/ °C-m2).
b. This model was developed by Faiman5 and has been the subject of several
experimental studies6,7. It differs from the IEC “normal module operating temperature (NMOT)”
procedure in that different mounting configurations can be applied, less data filtering are utilized,
and the test period is fixed and of relatively short duration. Also, two mounting configurations
are considered - mounted as the product is designed, and a mounting representing worst-case
misuse.
Worst-case mounting is used to examine potential damage to the product if it is used in a manner
for which it is not designed, such as being draped over a vehicle. The worst-case mounting is
illustrated in Figure 10. The module is attached to a 3.2 millimeter (mm) (1/8-inch) thick
aluminum plate. The front of the aluminum plate is covered with flat black paint. The
aluminum plate is sized such that it extends 304.8 ± 25.4 mm (12 ± 1 inch) beyond the edge of
the module in all directions. The 304.8 mm (12 inch) are measured perpendicular to the module
edges, as shown by the red arrows in Figure 10. The aluminum plate may be one continuous
piece, or it may be formed from multiple pieces. If multiple pieces are used, the pieces shall be
held via rear brackets with edges flush and in positive pressure with one another, to maximize
lateral heat conduction. R30 insulation shall be adhered to the back of the plate. The aluminum
plate shall be mounted at 37 ± 5 degrees relative to horizontal.
14
TOP 09-2-291
23 January 2020
Figure 10. Schematic illustration of test fixture for simulated worst-case mounting.
a. A means to mount the module in the manner specified by the procurement document.
c. A resistive load sized such that the modules will operate near their maximum power
point at STC, or an electronic Maximum Power Point Tracker (MPPT).
e. An anemometer that functions in the range of at least 0.25 - 10 meters per second
(m/s). It shall be installed approximately 1 m above the top of the module and mounted as close
to the module as possible without shading the module.
f. An ambient temperature sensor, with a time constant less than 5 minutes, installed in a
shaded enclosure with good ventilation near the wind sensor.
15
TOP 09-2-291
23 January 2020
g. A thermal imaging device capable of surveying the surface of the module with a
numerical readout to qualitatively locate any abnormally hot cells.
h. A thermocouple attached to the back side of each module. The thermocouple shall be
placed as close to the module center as possible while being located directly behind a solar cell.
The thermocouple shall not be placed directly behind electrically inactive areas, such as the
space between solar cells. The thermocouple shall also not be placed behind a hot cell, as
described in paragraph 2.1.5.3.
The module shall be exposed to outdoor conditions mounted in the manner specified by the
procurement document, with instrumentation described in the previous section, for 28 days.
a. Select the thermocouple location on the module via infrared image. Subject the
module to illumination of at least 400 W/m2, either in natural sunlight or a class BBB (or better)
steady-state solar simulator. Short-circuit the module by either directly connecting the output
wires together or by fabricating a jumper wire to connect the positive and negative terminals.
After the module has reached steady-state temperature (less than 2 °C (3.6 °F) change after
10 minutes), use the thermal imager to survey the entire front surface of the module. Using the
color scale and the center focus temperature readout, identify and record the location of any cells
that are more than 10 °C hotter than other cells on the module.
b. Apply the thermocouple to the back of module. If the cell closest to the module center
was not identified as a hot cell in the previous step, center the thermocouple behind this cell and
attach it to the module. If the cell closest to the module center is a hot cell, choose the next
closest cell that is not hot, and center the thermocouple behind this next-closest cell.
c. Mount the module in the manner specified by the procurement document and connect
the resistive or MPPT load as described in the instrumentation section.
d. Utilizing a second module, repeat the steps in paragraphs 2.1.5.3.a through 2.1.5.3.c,
this time utilizing the worst-case mounting configuration described in paragraph 2.1.5.1.1.
f. Continue the exposure for a total of 28 days. Clean the modules weekly, during times
when irradiance is below 400 W/m2 (low-irradiance data are not used in the calculation).
16
TOP 09-2-291
23 January 2020
(1) Reject all data taken when irradiance was below 400 W/m2.
(2) Reject all data taken when wind speed was greater than 10 m/s or less than
0.25 m/s.
h. From the remaining data, for each module, create 5-minute running averages for wind
speed, module temperature, ambient temperature, and irradiance. The 5-minute running
averages must not contain any missing data points. Thus, every rejected data point from step
2.1.5.3.g. creates at least a 5-minute window where there are no running average data points.
i. Use the 5-minute running averages to create an x-y scatter plot for each module where
x = v and y = G/(Tmodule–Tambient). Variables are defined in Equation 2 (paragraph 2.1.5).
j. For each module, use linear regression analysis to determine the slope (U1v) and
intercept (U0) of the model.
k. These two sets of coefficients are then used for predictions of temperature and the
resulting energy yield for the product mounted in this manner in specific locations.
The procurement agency shall be responsible for defining all aspects of the end-use mounting
configuration. Parameters to be specified include the following:
a. The type of mounting or support structure for the module. If the back of the module
will be in contact with the mounting structure or some material other than air, as much
information as possible shall be specified to describe the material behind the module. Some
examples of acceptable descriptions include “open-air rack-mounted,” “attached to vinyl-coated
polyester temper-tent surface,” “supported by nylon backpack,” and “supported by natural
earth surface such as sand or dirt”.
b. The expected tilt of the module relative to horizontal when deployed. Some examples
of acceptable descriptions include “racking is angled approximately to 35 degrees,” “tent roof
slopes at 30 degrees relative to horizontal,” “pack is expected to be slanted such that module
will be perpendicular to irradiance at solar noon”, and “earthen surface is horizontal”.
c. Any further information that may affect temperature in deployment conditions. For
example, if the module is applied to a heated tent, the minimum and maximum tent skin
temperature should be specified.
a. The load type (resistive or MPPT). If a resistive load is used, record the resistance in
ohms.
17
TOP 09-2-291
23 January 2020
c. The location of the thermocouple on the back of each module. Include images if
necessary.
d. The start and end dates and times of the outdoor exposure.
e. The highest and lowest average wind speeds used to make the scatter plot.
f. The highest and lowest average irradiances used to make the scatter plot.
g. A description of any equipment malfunctions that occurred during the test period and
how the malfunction was rectified.
i. A description of any visible defects in the modules that developed during the outdoor
exposure.
2.2 Safety.
The high voltage test is intended to verify that the panel has proper electrical material and
component selection and design for the intended system design voltage. Testing shall be
conducted in accordance with IEC 61215-2 (MQT 03 (Insulation Test)), unless otherwise
described within this section.
The instrumentation and equipment outlined in IEC 61215-2 (MQT 03) are sufficient for this
test. A calibrated, current-limited insulation resistance tester with the following capability is
required:
a. Array voltage < 50 Volts direct current (VDC): 500 VDC maximum.
b. Array voltage > 50 VDC: 1000 VDC plus twice the maximum voltage of the array.
Perform high voltage testing at ambient conditions within the ranges provided below:
18
TOP 09-2-291
23 January 2020
The procedures described in IEC 61215-2 (MQT 03) shall be followed for modules to be fielded
singly or in parallel. For arrays connecting multiple modules in series, the system voltage used
in this test shall be defined as the maximum voltage of the series array.
a. For modules with an area of less than 0.1 m2, the insulation resistance shall not be less
than 400 MΩ.
b. For modules with an area larger than 0.1 m2, the measured insulation resistance times
the area of the module shall not be less than 40 MΩ/m2.
Any dielectric breakdown (diminishing of the electrical resistance during testing) will be noted.
Visible physical damage, such as surface tracking, incurred during testing should be documented
with photographs.
a. This test records bypass and blocking diode functionality before and after stress.
Stress levels are similar to those applied in IEC 61215-2 MQT 18.2; however, tests are modified
so that special modules with extra leads to access diodes that may be potted or embedded in
laminate are not required. It is assumed that such special samples may be difficult to obtain for
new lightweight products, and thus requiring the special samples would cause unacceptable
delays in the test cycle.
b. The difference between bypass and blocking diodes is illustrated in Figure 11. Bypass
diodes are placed in parallel with a solar cell(s), so that power is not dissipated in a shaded solar
cell when solar cells in series with that cell are illuminated and continue to produce current. The
current-producing cells may be either within the same module, or in another module connected
in series with the partially-shaded module. A blocking diode prevents power dissipation in a
shaded string of cells when another string in parallel with the shaded string still produces
voltage. The voltage-producing string may be either within the same module, or in another
module connected in parallel with the partially-shaded module.
19
TOP 09-2-291
23 January 2020
c. Means for applying a current equal to 1.25 times the STC short-circuit current of the
module, throughout the test.
d. Infrared camera with sufficient spatial resolution to identify individual bypass diodes
and temperature resolution of 5 °C or better.
This is a multi-step test. As described in the next section, test conditions involve, sequentially:
c. Application of Voc.
20
TOP 09-2-291
23 January 2020
f. Application of Voc.
a. Pre-stress power assessment. Measure the module pre-stress power output as per
paragraph 2.1.2. If a power measurement was performed on this module at the conclusion of the
preceding test, that measurement may be used as the pre-stress power.
b. Pre-stress thermography.
(1) With the module in the dark and at 25 ± 10 °C (77 ± 18 °F), apply Isc to the
module (to make Isc flow through the bypass diodes, the positive voltage of the power supply
will be connected to the negative module terminal).
(3) Set the temperature scale on the infrared (IR) camera such that readings from all
parts of the module are valid (no area is off-scale low or high, but otherwise as narrow as
possible). Leave the scale set this way for the remainder of the test.
(4) Record a thermal image over each bypass or blocking diode in the module.
Record the scale with the image. If possible, count how many diodes are warm, i.e., operational.
If diodes are all in a potted junction box, their thermal images may not be distinct.
(1) If the module does not contain blocking diodes, and procurement requirements do
not mandate parallel connection of modules in deployment, skip step c, and record “not
applicable” for the forward current.
(2) If the module does contain blocking diodes, or procurement requirements indicate
that there will be parallel connection of modules during deployment, apply the module’s open
circuit voltage at STC to the module terminals while the module is in the dark (positive terminal
of power supply to positive terminal on module). Allow the current to stabilize for 10 minutes.
Record this forward current flow while the voltage is applied. If the current is < 100 milliamp
(mA), record “< 100 mA”. Caution: If the module does not contain blocking diodes, or they are
not working properly, this may be a destructive test.
d. Stress. Heat the module to 75 ± 5 °C (167 ± 9 °F). Apply a current to the module
equal to 1.25 times the short circuit current (i.e., 1.25 x Isc) ± 2 percent of the module as
measured at STC while maintaining the module temperature at 75 ± 5 °C (the positive voltage of
21
TOP 09-2-291
23 January 2020
the power supply will be connected to the negative module terminal). Maintain the current flow
for 1 hour.
e. Post-stress thermography.
(1) With the module in the dark and at 25 ± 10 °C (77 ± 18 °F), apply Isc to the
module (to make Isc flow through the bypass diodes, the positive voltage of the power supply
will be connected to the negative module terminal).
(3) With the temperature scale still set as determined in step 2.2.2.3.b(3), record a
thermal image over each bypass or blocking diode in the module. Record the scale with the
image. If possible, count how many diodes are warm, i.e., operational. If diodes are all in a
potted junction box, their thermal images may not be distinct.
(4) Note any of the following changes, which are indicative of a diodes failing in the
open condition, between the pre- and post-stress images:
(1) If the module does not contain blocking diodes and procurement requirements do
not require parallel connection of modules in deployment, skip step f, and record “not
applicable” for the forward current.
(2) If the module does contain blocking diodes, or procurement requirements indicate
parallel connection of modules in deployment, apply the module’s open circuit voltage at STC to
the module terminals while the module is in the dark. (Positive terminal of power supply to
positive terminal on module.) Allow the current to stabilize for 10 minutes. Record this forward
current flow while the voltage is applied. If the current is < 100 mA, record “< 100 mA”.
Caution: If the module does not contain blocking diodes, or they are not working properly, this
may be a destructive test.
22
TOP 09-2-291
23 January 2020
(1) Measure the post-stress module power output as per paragraph 2.1.2. Calculate
the module power loss using Equation 3.
(2) Record post-stress power and the percent power loss. Significant power loss may
be an indicator of bypass diodes failed in the closed position.
h. Post-stress visual inspection. The module should be inspected for any visual defects,
and the results recorded in the test report.
i. Post-stress wet leakage current. The wet leakage current test (paragraph 2.1.3) should
be repeated, and data recorded in this section of the test report.
e. Whether any signs of bypass diode failure in the open state are allowed.
Diode verification data shall be reported as shown in Table 2. An example of data that might
complete the table are shown in blue.
23
TOP 09-2-291
23 January 2020
24
TOP 09-2-291
23 January 2020
a. The partial shading test determines the effects of shading or partially shading a single
cell to screen for excessive heating that may damage the module and to determine the power loss
due to shading. The test is accomplished in three steps:
(1) The two highest and two lowest temperature cells are selected using an IR image.
This step is described in paragraph 2.2.3.3.1, Cell Selection Procedure.
(2) For each selected cell, the percent shading that causes Imp to flow through the
illuminated, short-circuited, module is identified. This step is described in paragraph 2.2.3.3.2,
Shade Determination Procedure.
(3) For each selected cell, the identified percent shading is applied for an extended
time at elevated temperature. This step is described in paragraph 2.2.3.3.3, Extended Exposure
Procedure.
b. The partial shading test is related to IEC 61215-2, MQT 09 “Hot-spot endurance test”,
but with several important differences. First, cell selection is accomplished via examination of
an IR image rather than the time-consuming process of taking an IV curve with each cell in the
module successively shaded. Second, a performance check is performed after the shading in this
test flow. Third, there is no dry insulation test (IEC 61215-2 MQT 03) at the end of the shading
stress. Fourth, this test is performed identically for any type of internal wiring (series, parallel,
etc.), with only one option for how to select worst-case shading.
a. Thermal imaging device capable of surveying the surface of the module with a
numerical readout to quantitatively identify the hottest cells.
b. Light source with an irradiance that can be maintained at 1,000 ±100 W/m2. Natural
sunlight or a class BBB (or better) steady-state solar simulator may be used.
d. A means to shade a single cell in the module in increments of no more than 10 percent,
such as opaque covers that shade between 10 and 100 percent of a single cell for the module
design under test.
25
TOP 09-2-291
23 January 2020
The worst-case shading conditions shall be applied for 1 hour for each of the selected cells, with
the average module temperature maintained at 50 ± 10 °C (122 ± 18 °F), and the illumination
maintained at 1,000 ± 100 W/m2.
Subject the module to the required test conditions, and place the module under a short circuit
condition by either directly connecting the output wires together or by fabricating a jumper wire
to connect the positive and negative terminals. After the module has reached steady-state
temperature (less than 2 °C (3.6 °F) change after 10 minutes), use the thermal imager to survey
the entire front surface of the module. Using the color scale and the center focus temperature
readout, identify and record the two highest and two lowest temperature cells on the module;
these cells will be used in the remainder of the test.
a. To stress the sample as much as possible, it is desirable to dissipate the largest possible
amount of power in the partially-shaded cell. There is not one universal “most damaging” partial
shading percentage. The shading conditions that produce exactly the largest possible power
dissipation are a function of the number of cells and bypass diodes in a module and the IV
characteristics of the cells and bypass diodes.
b. Achieving maximum power dissipation requires maximizing the product of the current
and the (reverse) voltage in the partially-shaded cell. Shading too much of the cell can cause
current (and thus dissipated power) to be very small, whereas shading too little of the cell causes
the reverse voltage (and thus the dissipated power) to be small. For typical cell characteristics,
maximum power dissipation occurs when cell shading decreases the current through the short-
circuited string slightly, commonly from Isc to Imp. A precise determination of the current at
which maximum power dissipation is achieved would require a detailed knowledge of the cell
and bypass diode forward and reverse characteristics. Thus, reducing the current through the
string from Isc to Imp is used in this test method as an approximation of the worst possible shading
condition when individual cells are not electrically accessible.
c. The impact of multiple parallel strings of cells on the current must be taken into
account so that applied stress is consistent across module types. For an illustration of parallel
strings, see Figure 11 in the diode verification test, which shows a module with three parallel
strings. When one cell in a string is shaded, the other strings will still generate current normally,
so that reducing the current in the partially-shaded string to the worst condition relates to the
module Isc and Imp as follows in Equation 4:
26
TOP 09-2-291
23 January 2020
(𝐼𝐼𝑠𝑠𝑠𝑠 −𝐼𝐼𝑚𝑚𝑚𝑚 )
𝐼𝐼𝑚𝑚𝑚𝑚𝑚𝑚𝑢𝑢𝑙𝑙𝑙𝑙 @𝑤𝑤𝑤𝑤𝑤𝑤𝑤𝑤𝑤𝑤 𝑠𝑠ℎ𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎 = 𝐼𝐼𝑠𝑠𝑠𝑠 − (Equation 4)
𝑛𝑛
where:
n = the number of parallel strings
27
TOP 09-2-291
23 January 2020
e. Shading may be performed using discrete masks (for any cell) or a single mask that
extends beyond the cell edge (only for edge cells). Masks shall be the same width as the cell and
be placed such that increasing shading proceeds upward from the lower edge of the cell.
Shading using discrete masks is illustrated in Figures 13a and b. Shading of a monolithically-
integrated cell that extends to the module edge, using a mask that is larger than the cell, is
illustrated in Figures 13c and d. The orientation of the module with respect to some feature (e.g.,
junction box, rear label, front label, etc.) shall be noted.
Figure 13. Cell shading for discrete cells at a. 20-percent shading, and b. 60-percent shading,
and for monolithically-integrated cells at c. 20-percent shading, and d. 60-percent shading.
28
TOP 09-2-291
23 January 2020
f. The following steps shall be used to determine the worst-case percent shading:
(1) Determine n, the number of parallel strings in the module, using any of the
methods presented in the preceding paragraphs.
(2) Calculate the worst-case shading current (Imodule @ worst shading) for this module
according to Equation 4.
(3) For each of the four cells selected in the previous section, perform steps (a)
through (e) below:
(a) Expose the module to steady-state known irradiance in the range of 1000 ±
100 W/m2.
(b) Short-circuit the module, and monitor its current throughout this test. If intensity
is not equal to 1000 W/m2, correct the measured current for the intensity difference.
(c) Apply approximately 10-percent shading to the selected cell and note the current
through the module.
(e) Revert to the shading that is one size smaller than the final mask from step f (i.e.,
the largest mask for which the intensity-corrected module current is greater than or equal to
Imodule @ worst shading). This mask shall be used for the extended exposure. If the smallest
mask (e.g., 10-percent shading) already decreases the current to less than Imodule @ worst
shading, use this smallest mask for extended exposure.
d. Apply the worst case shading condition, as determined in paragraph 2.2.3.3.2, to the
first cell.
29
TOP 09-2-291
23 January 2020
g. Repeat steps d, e, and f for the second, third, and fourth selected cells.
The procurement agency shall be responsible for defining the following parameters:
a. The infrared images used to select the hottest and coolest cells, with the location of the
selected cells marked.
b. The orientation of the module during the infrared testing and extended shading with
respect to some module feature such as junction box, rear label, front label, etc.
c. The percent shade applied to each of the selected cells during the 1-hour exposure
period.
d. Any damage that occurred during the test shall be noted, with photos if applicable.
f. The maximum temporary electrical power loss during shading of any one cell, in
percent.
b. If indoor exposure is available, this method is recommended rather than the outdoor
method. Because of the elevated and controlled temperature utilized during indoor exposure, it
has both more reproducibility and higher-stress than the outdoor exposure.
30
TOP 09-2-291
23 January 2020
a. Means to mount the test module so that it is oriented close to the optimum for the local
latitude.
b. A solar irradiation monitor accurate to ± 5 percent, mounted in the plane of the module
within 1 m of the test module.
c. A resistive load sized such that the module will operate near its maximum power point
or an electronic MPPT.
d. Insulating material (such as foam) that can be applied to the entire back of the module.
a. Mount the test module outdoors in an area that is free of shading. The tilt (angle with
horizontal) and azimuth (angle with north. should be chosen to maximize irradiance and thus
minimize the exposure test time.
c. Apply an insulating material (such as foam) to the entire back of the module, in order
to increase the module temperature during test.
d. Attach the resistive load or electronic maximum power point tracker to the module.
e. Subject the module to an irradiation totaling between 352 and 469 kWh/m2, as
measured by the monitor. This total irradiation corresponds to a UV dose between 15 and
20 kWh/m2.
31
TOP 09-2-291
23 January 2020
a. Inspect the module for any visual defects, and record the results in the test report.
b. Repeat wet leakage current test (paragraph 2.1.3) and record data in this section of the
test report.
b. If the item is intended for cumulative outdoor exposure >1 year, it is recommended
that the procurement document specify no visual defects and a resistance > 40 MΩ/m2.
After the UV exposure test, the data shown in Table 4 shall be recorded. An example of data
that might complete the table is shown in blue.
250 Mohm-m2
32
TOP 09-2-291
23 January 2020
The intent of the hail test is to determine whether PV modules are capable of withstanding the
impact of 1-inch hail without incurring any physical damage, permanent deformation, or
degradation in performance. The test procedures in this TOP were derived from IEC 61215-2
(MQT 17), and American Society for Testing and Materials (ASTM) E1038-108.
a. Launcher. A launcher capable of propelling a selected ice ball at the specified speed
within ± 5 percent will be used (Figure 14). The aiming accuracy of the launcher will be verified
to ensure it is sufficient for the ice ball to strike the specified impact area; otherwise, the
surrounding area will be masked for protection from inadvertent impacts.
b. Speed Meter. A speed sensor capable of measuring ice ball speed to within
± 2 percent will be used (Figure 15).
33
TOP 09-2-291
23 January 2020
Figure 15. Representative laser intervalometer used to measure the ice ball speed.
c. Molds. Molds made from silicone rubber or expanded polystyrene will be used for
casting ice balls of appropriate diameter (Figure 16).
Figure 16. Representative ice ball mold, clamped during ice making.
34
TOP 09-2-291
23 January 2020
d. Freezer. A test environmental chamber capable of making ice balls in the molds at a
controlled temperature of -10 ± 5 °C (14 ± 9 °F) shall be used.
f. Weight and Dimensions. A scale will be used to determine the ice ball mass to within
± 1 percent, and a caliper will be used to determine the ice ball size.
g. High-speed video. High speed video capable of recording the impact of ice balls on
the panel will be used. The video shall be able to be played back by the test team in near real-
time in order to verify the location of impact.
a. Prior to the start of the hail test, the module surface temperature shall be stabilized at
controlled ambient temperature and relative humidity conditions as described in MIL-STD-
810H and provided below:
b. Ice Ball Preparation. In deviation from the IEC standard, the following procedures
shall be used to determine acceptable ice balls:
(1) The molds shall be used to make a quantity of 50 ice balls. After making the ice
balls, the molds shall be separated, and any ice balls that are visually deformed or cracked should
be discarded.
(2) The weight and diameter of the remaining spherical ice balls shall be measured,
and the measurements shall be compared with the allowable weight and diameter ranges for a 1-
inch ice ball from ASTM E1038, outlined in Table 5. These data shall be used to determine
whether the ice balls are within the allowable range through statistical analysis with a 90-percent
confidence level.
35
TOP 09-2-291
23 January 2020
c. After verifying the method used to make the ice balls is sufficient, ice balls to be used
for the test shall be made, removed from their molds, and any visually deformed or cracked ice
should be discarded. All remaining ice balls shall be placed in the storage container and
removed just prior to placing into the launcher to limit ice melting and/or unwanted cracking of
the ice prior to the test shot.
Testing shall be conducted in accordance with IEC 61215-2 (MQT 17), with the following
modifications:
a. Each ice ball does not need to be measured before testing as long as the procedures
used to make the balls is proven to produce ice balls within the allowable range outlined in
Table 5. At the time of test, and prior to loading into the launcher, test personnel shall verify that
the ice balls contain no cracks visible to the unaided eye.
b. Cooling of the launcher apparatus that makes contact with the ice ball shall be allowed
if test facility safety regulations require more than 60 seconds to elapse between the removal of
the ice ball from the container, ice ball launch, and the impact of the ice ball with the module.
c. High-speed video shall be used to assist in the verification of the location of impact.
a. Any deviation in IEC 61215-2 not already outlined in this section of the TOP.
b. Impact locations other than those outlined in Table 4 and Figure 14 of IEC 61215-2.
The following data shall be collected and presented as part of the hail test.
36
TOP 09-2-291
23 January 2020
The loose cargo vibration test is designed to determine the effects of the transportation life cycle
on the module. More specifically, the test is designed to determine whether the module can
withstand the effects of transportation in trucks, trailers, or tracked vehicles, while not secured to
the carrying vehicle, without damage or degradation of performance.
Unless otherwise specified in the procurement document, loose cargo vibration testing should be
performed at standard ambient conditions as described in MIL-STD-810H, Part One, paragraph
5.1 and provided below:
The procedures outlined in MIL-STD-810H, Test Method 514.8, paragraph 4.5, Procedure II
(paragraph 4.5.3) should be followed. The module should be packaged as it normally would be
for transportation. The required fencing, module orientations, and module positioning will be
dependent on the specific module under test. See MIL-STD-810H, Test Method 514.8,
Annex C, paragraph 2.2, for further information. Exposure levels are not tailorable and should
be performed as described in MIL-STD-810H, Test Method 514.8.
The procurement document must specify exposure duration. An exposure duration of 20 minutes
per orientation equates to 240 kilometers (km) (150 miles) of loose cargo transportation. The
expected material transportation life cycle should be used to define the total exposure duration.
See MIL-STD-810H, Test Method 514.8, Annex C, paragraph 2.2.f for further information. The
procurement document need not specify exposure levels. Exposure levels are not tailorable and
should be performed as described in MIL-STD-810H, Test Method 514.8. If no duration is
specified by the procurement agency, a minimum of 20 minutes shall be utilized.
37
TOP 09-2-291
23 January 2020
a. Photograph of solar panels (and transit cases if applicable) before and after loose
cargo.
2.3.4 Drop.
The intent of the drop test is to determine the structural and functional integrity of a panel
subjected to drop while being transported (in transit case) or while being deployed. Testing shall
be conducted in accordance with MIL-STD-810H, Test Method 516.8, Shock, Procedure IV -
Transit Drop; however, this section of the TOP outlines and modifies the procedures to represent
the drop conditions typically encountered during PV panel transit and setup. All panels shall be
tested with these drop heights and conditions to ensure all PV systems are being tested to the
same parameters regardless of system weight, size, deployment mechanism, and material.
Shock and impulse data are not typically collected during drop testing, so no specific
instrumentation is required other than test apparatus required for dropping and slinging the item,
such as a quick release hook or drop tester. The drop surface shall be normal to the direction of
the impact and nominally flat.
The required transit drop test heights for various types of PV, separated by the manner in which
the PV is typically transported, are presented in Table 6. The two categories are as follows:
38
TOP 09-2-291
23 January 2020
The required deployment drop test heights for various types of PV are presented in Table 7.
These drop test conditions are to represent drop conditions that may be experienced when the
panels are being removed from their transit case just prior to deployment.
39
TOP 09-2-291
23 January 2020
Figure 17. Non-man portable, deployment drop test heights (rigid panels) (representative drop
configurations).
a. Measure the module pre-drop power output and panel efficiency as per
paragraph 2.1.2. If a power measurement was performed on this module at the conclusion of the
preceding test, that measurement may be used as the pre-drop panel efficiency test
b. The transit drop testing outlined in Table 6 shall be conducted prior to conducting the
deployment drop tests outlined in Table 7. Transit drop testing shall be conducted with the PV
modules configured in their transit case or bag as delivered to the Warfighter. Multiple PV
modules may be required to conduct this testing if they are typically deployed with more than
one module per transit case. If multiple PV panels need to be subjected to the transit drop test,
each should be characterized for pretest performance as outlined in paragraph 2.1.2. If transit
drop testing is not applicable, proceed to step g.
c. Perform the required transit drops outlined in Table 6 using the apparatus and
requirements of paragraphs 2.3.4.1 and 2.3.4.2.
d. Document impact point or surface of each drop and any obvious damage to the transit
case. The PV modules do not need to be removed from the transit case after each drop.
e. After completing the last drop outlined in Table 6, remove the modules from the
transit case and inspect for any obvious damage to the modules.
40
TOP 09-2-291
23 January 2020
f. Measure the module post-drop panel efficiency as per paragraph 2.1.2. If multiple
modules were tested during transit drop testing, the output power of each panel shall be
measured.
g. Perform the required deployment drops outlined in Table 7 using the apparatus and
requirements of paragraphs 2.3.4.1 and 2.3.4.2.
h. Document impact point or surface of each drop and any obvious damage to the
module.
i. Measure the module post-deployment drop panel efficiency as per paragraph 2.1.2. If
multiple modules were tested during transit drop testing, the output power of each panel shall be
measured.
The following items must be specified in the individual procurement document for the module:
a. Any deviation in the number of drops or drop heights outlined in this TOP.
The following data shall be collected and presented as part of the drop test.
d. Any damage.
e. Photographs.
The junction box is the electrical transition point and stress relief between the panel and the
external connector wire. The junction box pull strength test is designed to determine whether the
module junction box can withstand pull force exerted on it during operation either from manual
pulling on the box, wind gusts, or while being removed from stowage. There should not be any
visible damage of the junction box module or loss of electrical continuity or module
performance. Reference test IEC 61215-2 (MQT 14 (4.1(4)) Robustness of Terminations.
41
TOP 09-2-291
23 January 2020
The instrumentation required for this test consists of an apparatus that can be used to apply a pull
force on the junction box cable. This force is defined by a 100-pound (lb) weight or spring
gauge with a 100-lb range. Clamps should be used to hold the module and allow for uniform
distribution of the load across the module in opposition to the pulling force; grommets on the
module can be used (this is not a grommet load test). The module electrical leads should also be
clamped near the connector. The 100-lb (445-Newton (N)) pull strength may be increased or
decreased based on panel size and as determined in actual use; this change shall be provided by
the procurement agency.
The integrity of the connector junction box should be examined prior to loading; any blemishes
or non-functional flaws in the box and cable should be noted. The module should be dry and at
room temperature. Clamping locations should be applied and tested for grip strength; they
should be set to oppose the direction of the pull on the junction box. Testing should be
conducted at the following standard ambient conditions.
A test apparatus should be assembled with enough room to allow for free movement of the
pulling force, as shown in Figure 18. Necessary safety precautions should be taken when
handling large pull forces and weights. Note that the connector cable may pull free from the
junction box, and debris may come away in all directions.
Figure 18. Weight pull (left) and spring scale pull (right) test setups.
42
TOP 09-2-291
23 January 2020
b. Connect clamps and grommet hold downs of test module as necessary to oppose pull
force on junction box.
e. Apply pull force for a period of 10 ± 1 seconds; note any elongation of the cable, bare
or exposed wiring and damage to junction box.
f. Remove the clamp, remove the module from the apparatus, and inspect the module for
physical damage to wiring and junction box.
g. Test continuity of cable; if access to the wires is not possible, measure module
performance.
h. Orient the apparatus 90 degrees and repeat the test for all three orthogonal directions,
pulling upward and sideways.
The procurement agency shall outline any deviations from this TOP, notably any specific
changes in terms of pull force, direction of pull, and test duration.
The following data shall be collected and presented as part of the junction box strength test.
The panel folding test is designed to assess the durability of panel folding under a predetermined
number of fold cycles and various environmental conditions. The electrical conductors internal
to the panel are expected to degrade under certain number of folding and unfolding cycles.
Further, flexible panels with polymer encapsulation will delaminate further degrading the overall
performance of the panel.
43
TOP 09-2-291
23 January 2020
Thermocouples shall be connected to the front and back of the panel. A thermocouple shall be
attached to record the ambient temperatures. To measure electrical performance, test leads shall
be connected to the output of the panel.
The required conditions are at temperatures of 25 ± 2 °C (77 ± 3.6 °F). Folding tests conducted
in a low- or high-temperature environment are optional and maybe selected by the procuring
agency.
Specific test procedures shall be developed based on the panel design, and those procedures shall
be approved by the procurement agency prior to test conduct. Test procedures may vary based
on the number of physical folds per panel (i.e., bifold, trifold, map-like folded panels, etc.).
These test procedures shall include the following:
b. Any unique mounting or holding of the panel while conducting of the individual folds.
c. Value for objective and threshold performance criteria (e.g., panel must be 80 percent
operational after test).
The following data shall be collected and presented as part of the panel folding test:
44
TOP 09-2-291
23 January 2020
a. Thermal cycling accelerated testing helps determine whether the module can withstand
thermal mismatch, fatigue, and other stresses caused by repeated changes of temperature. In
particular, it helps pull open mechanical weaknesses (such as cell cracks or failing solder bonds)
created during other stress tests (e.g., drop test) so that these weaknesses are evident in the final
power evaluation. Thermal cycling mimics day/night thermal cycling that the product will
experience in the field. It is performed in an accelerated manner (i.e., more extreme upper and
lower temperatures), so that several years of product lifetime may be examined in a test lasting
only days. The test time and stress levels in this test are based on a desired three to five year
deployed product lifetime, and published analyses of solder bond fatigue as a function of field
exposure and accelerated stress. (See, for example, publications by N. Bosco, et al.9)
b. The test procedure is based largely on IEC 61215-2 (MQT 11), with a few important
differences:
(1) The number of thermal cycles is adjusted downward to match the desired product
lifetime.
c. Current is not applied during the test for two reasons. First, the procurement cycle is
likely to be significantly (or indefinitely) delayed if the manufacturer is required to provide
special modules that do not contain blocking diodes and thus allow the IEC-specified current to
be applied. Second, the addition of current flow to the IEC thermal cycling test has shown not to
result in more modules failing the test. (See, for example, G. TamizhMani et al.10)
b. Means for mounting or supporting the module(s) in the chamber, so as to allow free
circulation of the surrounding air. The thermal conduction of the mount or support shall be low,
so that for practical purposes, the module(s) are thermally isolated.
45
TOP 09-2-291
23 January 2020
Samples shall undergo 22 cycles of the type described in Figure 9 of IEC 61215-2. The thermal
cycle extends from -40 to 85 °C (-40 to 185 °F), with a cycle time between 3 and 6 hours.
Twenty-two cycles at these temperatures are calculated, for solder bond fatigue, to be roughly
the equivalent of a 3-year exposure in Tucson, Arizona (a stressful climate for thermal cycling).
The test shall be performed as described in paragraph 4.11.3 of IEC 61215-2, with the following
exceptions:
a. There shall be no current flow during the test. Disregard instructions related to current
flow.
c. It is preferable that flexible modules are mounted in the chamber fully deployed (i.e.,
unfolded). However, if fully unfolding the module is not possible due to space constraints in the
chamber, the module should be unfolded as much as space allows, and the configuration
documented in the chamber. Modules should not be packed tightly in the chamber. Air must be
able to circulate between them.
The procurement agency shall specify a minimum performance retention (e.g., 80 percent) for
each module that undergoes a “mechanical and thermal stress” sequence (e.g., drop test +
thermal cycling + humidity freeze).
a. If modules were subjected to test in any configuration other than fully unfolded, a
photo and/or description of the mounting configuration shall be included.
b. Any deviation from the intended thermal cycle, or interruptions of the cycle, during
the test shall be noted.
c. The panel shall be visually inspected after the test. Any change in physical appearance
of the module shall be noted.
46
TOP 09-2-291
23 January 2020
a. The humidity freeze test helps determine the ability of the module to withstand freeze-
thaw cycles. The test may also make apparent damage that has happened in previous mechanical
stressing, if water penetrates the package and then expands. For example, a small backsheet
crack may occur during the panel folding test. During the humidity-freeze test, as water freezes
and thaws inside the crack, the crack may become substantially enlarged.
b. The test procedure is based largely on IEC 61215-2 (MQT 12), with a few important
differences:
(1) Current is not applied during the test. The procurement cycle is likely to be
significantly (or indefinitely) delayed if the manufacturer is required to provide special modules
that do not contain blocking diodes and thus allow the IEC-specified current to be applied.
Required equipment is described in IEC 61215-2, section 4.12.2.a through c. (Item d from
61215-2 section 4.12.2 is not needed, since current is not applied in this variation of the test.)
Samples shall undergo 10 cycles of the type described in Figure 10 of IEC 61215-2. The thermal
cycle extends from -40 to 85 °C (-40 to 185 °F), and a controlled 85-percent relative humidity
while at the elevated temperature of 85 °C (185 °F), with a cycle time around 24 hours.
The test shall be performed as described in IEC 61215-2, section 4.12.3, with the following
exceptions:
a. There shall be no current flow during the test. Disregard instructions related to current
flow, including attaching a power supply.
b. It is preferable that flexible modules are mounted in the chamber fully deployed (i.e.,
unfolded). However, if fully unfolding the module is not possible due to space constraints in the
chamber, the module should be unfolded as much as space allows, and the configuration
documented in the chamber. Modules should not be packed tightly in the chamber. Air must be
able to circulate between them.
47
TOP 09-2-291
23 January 2020
The procurement agency shall specify a minimum performance retention (e.g., 80 percent) and
maximum wet leakage current for each module that undergoes a “mechanical and thermal stress”
sequence (e.g., drop test + thermal cycling + humidity freeze).
a. If modules were subjected to test in any configuration other than fully unfolded, a
photo and/or description of the mounting configuration shall be included.
b. Any deviation from the intended thermal cycle, or interruptions of the cycle, during
the test shall be noted.
c. The panel shall be visually inspected after the test. Any change in physical appearance
of the module shall be noted.
d. Modules shall be evaluated for efficiency, wet leakage current later in the test flow, as
a part of final inspection and characterization, but not as a part of this test.
The salt fog test is performed to determine the effectiveness of protective coatings and finishes
on materials. It may also be applied to determine the effects of salt deposits on the physical and
electrical aspects of materiel.
No specific test instrumentation is required for salt fog testing other than that which is outlined in
MIL-STD-810H (Test Method 509.7), or needed to characterize pre- and post-module
performance with the corresponding sections of this TOP.
Unless otherwise specified in the procurement document, salt fog testing should be performed
following the procedures outlined in MIL-STD-810H, Test Method 509.7, paragraph 2.2.
Follow the procedures outlined in MIL-STD-810H, Test Method 509.7, paragraph 4.5. Testing
should be conducted in the operational configuration with all connections made, and surrogate
connectors are to be used when necessary. Unless otherwise specified in the procurement
48
TOP 09-2-291
23 January 2020
document, the salt fog procedure is not tailorable and should be performed as described in
MIL-STD-810H, Test Method 509.7.
The following items must be specified in the individual procurement document for the module:
a. Any deviation in the temperature of the exposure zone for the test item.
b. Any deviation in the time duration for salt fog exposure of the test item.
a. Photographs of the pre- and post- salt fog inspections including damage (if applicable).
2.4.2 Immersion.
The immersion test is performed to determine whether materiel can withstand full or partial
immersion in water and operate following immersion.
Any water that penetrates into the materiel or packaging is not able to be collected during testing,
so no specific test instrumentation is required for immersion testing other than that which is
required for the test to be conducted, such as a chamber with graduated measurements and a
thermometer.
Unless otherwise specified in the procurement document, immersion testing should be performed
in salt water following the procedures outlined in MIL-STD-810H, Test Method 512.6,
Paragraph 2.3.
49
TOP 09-2-291
23 January 2020
Follow the procedures outlined in MIL-STD-810H, Test Method 512.6, paragraph 4.4,
Procedure I (paragraph 4.4.2). Testing should be conducted in two conditions: with the test item
packaged as it normally would be for transportation, and in transportation configuration but not
in a transit or shipping case. Unless otherwise specified in the procurement document, the
immersion procedure should be performed as described in MIL-STD-810H, Test Method 512.6,
and the test item should be conditioned to a temperature 27 °C (49 °F) above the water
temperature to represent exposure to solar heating immediately prior to immersion.
The following items must be specified in the individual procurement document for the module:
c. Any deviation in the depth at which the test item is immersed in water.
The contamination by fluids test is designed to determine how the module is affected by
exposure to contaminating fluids that may be encountered during its life cycle.
No specific test instrumentation is required for contamination by fluids testing other than that
which is outlined in MIL-STD-810H (Test Method 504.3), or needed to characterize pre- and
post- module performance with the corresponding sections of this TOP.
50
TOP 09-2-291
23 January 2020
Unless otherwise specified in the procurement document, contamination by fluids testing shall be
performed at standard ambient conditions as described in MIL-STD-810H, Part One,
paragraph 5.1, and provided below:
Follow the procedures outlined in MIL-STD-810H, Test Method 504.3, paragraph 4.5.5
(Procedure I). Unless otherwise specified in the procurement document, total exposure time is
8 hours. If exposure to multiple fluids is required, use different sections of the module for each
fluid. MIL-STD-810H, Test Method 504.3, Procedure I is tailorable. Exposure times,
temperatures, fluids, and methods (sequential/simultaneous) can all be modified to best represent
the expected module life cycle environment or to best assess expected module weaknesses.
The procurement document must specify contamination fluids. Contamination fluids may be
selected from the list of fluids in MIL-STD-810H, Table 504.3-I, but contamination fluids need
not be limited by those listed in that table. The procurement document may specify exposure
time, fluid temperature, test item temperature, ambient temperature, sequential or simultaneous
exposure, and cleaning methods known to not damage the module.
Any deterioration should be noted. Deterioration may include softening, color changes,
cracking, or dissolving of material. Any deterioration incurred during testing should be
documented with photographs.
a. Dust (< 150 μm particle size) testing is performed to help determine the ability of
materiel to resist the effects of dust that may obstruct openings, penetrate into cracks, crevices,
joints, and to assess the effectiveness of filters (where applicable).
b. Sand (150 to 850 μm particle size) testing is performed to help assess the ability of
materiel to be stored and operated in blowing sand conditions without degrading performance,
effectiveness, reliability, and maintainability due to abrasion (erosion) or clogging effects of
large, sharp-edged particles.
51
TOP 09-2-291
23 January 2020
c. Unless otherwise specified in the procurement document, sand and dust testing should
be conducted following the procedures outlined in MIL-STD-810H, Test Method 510.7,
paragraph 2.3. If larger modules are to be tested, procedures shall be derived from
TOP 01-2-62111.
No specific test instrumentation is required for sand and dust testing other than that which is
outlined in MIL-STD-810H (Test Method 510.7), or needed to characterize pre- and post-module
performance with the corresponding sections of this TOP.
Unless otherwise specified in the procurement document, sand and dust testing should be
performed following the procedures outlined in MIL-STD-810H, Test Method 510.7,
paragraph 2.3
Follow the procedures outlined in MIL-STD-810H, Test Method 510.7, paragraph 4.1 for dust
testing and paragraph 4.2 for sand testing. Testing should be conducted in the operational
configuration.
The following items must be specified in the individual procurement document for the module:
2.4.4.5 Blowing Sand and Dust - Data Required and Sample Data.
a. Photographs of the pre- and post- sand and dust inspections including damage (if
applicable).
52
TOP 09-2-291
23 January 2020
2.4.5 Fungus.
The fungus test is designed to determine the extent to which the module will support fungal
growth and how that fungal growth may affect module performance during its life cycle. Key
objectives are to determine whether the module will support fungal growth, how rapidly the
fungus will grow on the module, how the fungus may affect the module either directly or
indirectly, whether the module can be stored effectively in a field environment, and whether
there is a simple method of cleaning the fungus from the module. Potential direct and indirect
effects of fungal growth are outlined in MIL-STD-810H, Test Method 508.8, paragraph 2.1.1.
The instrumentation, facilities, and controls outlined in MIL-STD-810H (Test Method 508.8) are
sufficient for this test. No modifications or adaptations are required.
Unless otherwise specified in the procurement document, the required test conditions are
outlined in MIL-STD-810H (Test Method 508.8).
The procedures outlined in MIL-STD-810H (Test Method 508.8) shall be followed. This test
should not be performed on a module that has previously undergone salt fog, sand and dust, or
humidity testing. The post-test inspection should be performed immediately at the end of the
incubation period. If the module must be removed from the chamber for the inspection and
operation to be performed, they must be completed within 4 hours. If it takes longer than 4 hours
to complete the inspection and operation, the module should be returned the chamber or a similar
humid environment for a minimum of 2 hours before completing the inspection and operation.
Additional information can be found in MIL-STD-810H, Test Method 508.8, paragraphs 4.5.3
and 4.5.4. The module shall be decontaminated in accordance with MIL-STD-810H, Test
Method 508.8, Annex A, prior to other testing or return of the module to the procurement office.
The minimum test duration is 28 days. Since indirect and interference effects are unlikely to
occur in that relatively short time frame, the procurement office may want to consider extending
the duration to 84 days if a greater amount of certainty in determining fungal growth effects is
desired. Substitution of fungus species is not recommended. Additional species may be used. If
additional species are used, their selection should be based on prior knowledge of specific
material deterioration. Additional information can be found in MIL-STD-810H, Test
Method 508.8, paragraph 2.2.2.
53
TOP 09-2-291
23 January 2020
Chamber temperature and humidity versus time should be recorded. Photographs and narrative
descriptions of fungal growth should be captured. Any deterioration or damage to the module
should be noted. Any deterioration incurred during testing should be documented with
photographs. Any effects on performance should be documented on the module as it is received
from the chamber and after removal of fungal growth.
a. The damp heat test is designed to determine the ability of the module to withstand the
effects of long-term penetration of humidity. In published studies, humidity has been observed
to cause delamination, increased transparent conductor resistance, increased electrically
conductive adhesive resistance, or decreases in semiconductor minority carrier lifetime in some
products. The test uses high levels of relative humidity and temperature to accelerate these
processes; i.e., 1 hour in test is equivalent to more than 1 hour of field exposure. This
acceleration allows one to learn about product behavior over time periods that are longer than the
procurement cycle. The test is designed to promote the diffusion of water vapor through the
pristine module package. It is not intended to investigate liquid water penetration into a
damaged package.
b. This test is based on that included in IEC 61215-2 (MQT 13), which refers to
procedures in IEC 60068-2-7812. Two differences distinguish this test from MQT 13: the test
duration is shortened, and flexible modules may be stressed in a partially-folded configuration if
necessary due to space constraints. The duration of the test should be equivalent to 3 years of
exposure in Miami for the least moisture-stable CuInxGa1-xSe2 modules, based on published
measurements and calculations13.
The sample shall be exposed to conditions of 85-percent relative humidity (RH) and 85 °C
(185 °F) for a period of 400 hr (~17 days).
a. Test procedures are described in IEC 60068-2-78, Section 4.1, with the following
modifications: the exposure time shall be for a period of 400 hr, with a tolerance of +19 hours,
- 0 hours.
54
TOP 09-2-291
23 January 2020
b. Modules shall not be packed tightly in the chamber. Air must be able to circulate
between them. It is preferable that flexible modules are mounted in the chamber fully deployed
(i.e., unfolded). However, if fully unfolding the module is not possible due to space constraints
in the chamber, the module should be unfolded as much as space allows, and the configuration
documented in the chamber.
The procurement agency shall specify a minimum performance retention (e.g., 80 percent) for
modules subjected to this stress. Performance (i.e., power output) after stress is measured during
the “final inspection” portion of the test flow.
a. If modules were tested in any configuration other than fully unfolded, a photo and/or
description of the mounting configuration shall be included.
b. Any deviation from the intended test conditions, or interruptions of the exposure,
during the test shall be noted.
c. The panel shall be visually inspected after the test. Any change in physical appearance
of the module shall be noted.
d. Modules shall be assessed for efficiency and wet leakage current later in the test flow,
as a part of final inspection and characterization, but not as a part of this test.
Testing shall be conducted in accordance with paragraph 2.1.1 of this TOP. The data will be
compared with pretest light soak data.
Testing shall be conducted in accordance with paragraph 2.1.2 of this TOP. The data will be
compared with pretest efficiency data to determine whether any performance was degraded as a
result of testing.
A final wet leakage current test shall be conducted on each PV module in accordance with
paragraph 2.1.3 of this TOP. The data will be compared with pretest wet leakage current data
and the provided minimum allowable insulation resistance.
55
TOP 09-2-291
23 January 2020
3. DATA REQUIRED.
4. PRESENTATION OF DATA.
Examples of data presentation are provided in the various subtests and Appendix A.
56
TOP 09-2-291
23 January 2020
Prior to measuring current-voltage (IV) curves to be used in the Photovoltaic Test Operations
Procedure (PVTOP), the lab performing the IV test must document their proficiency in IV
measurement best practices by performing the steps below. The resulting report is to be
provided as supplemental information with every PVTOP test report in which that lab has
performed IV measurements. The requirements for the report are detailed specifically in the last
section, titled “Self-Documentation Checklist”.
As long as there is no change in the test lab’s IV procedure, the test lab may attach the same self-
documentation to a PVTOP report over the course of executing many such tests and reports.
The self-documentation must be performed again if there is any change in the lab’s IV
measurement procedure. Any hardware change other than connectors to the panel requires the
self-documentation be performed again. Examples of hardware changes that would require the
self-documentation to be performed again would be use of a different power supply, solar
simulator, reference module, or meter. Procedural changes (such as changes in how one
positions the module on the simulator, or changes to the values of the power supply settings in
the software) also require the self-documentation to be performed again.
The sections below describe requirements for best practices to be satisfied for the total
uncertainty in power output to be less than or equal to ±5 percent.
Written (either on paper or online) instructions for how to position the sample (or reference
module) relative to the irradiance source must exist. These instructions must be detailed enough
that anyone operating the IV tester would position a module with previously un-encountered
dimensions in the same way. The instructions might specify, for example, where to put module
edges or the center. For sample positioning to be completely reproducible, the instructions must
also specify how to orient the longer versus shorter dimension, and toward which side the
junction box should be positioned. For modules that are unfolded, the instructions must specify
how to maintain a flat surface during measurement.
a. Uniformity.
(1) The uniformity of the light source shall be documented over the largest
dimensions that will be used in PVTOP measurements. The test lab shall create an irradiance
map to be included in the self-documentation, using a small reference cell. The reference cell
used for the intensity map cell shall not measure more than 10 cm on a side, and irradiance
measurements shall be evenly spaced and made at most in 10-cm steps. The largest area that will
be used for module measurement shall be outlined on the irradiance map. This largest area is
A-1
TOP 09-2-291
23 January 2020
called the “allowable test area” in the description below. An example of such an irradiance map
is shown in Figure A-1.
Figure A-1. Example irradiance map also showing largest allowable test area
(dotted yellow lines).
(c) Gave = average of all the irradiance measurements in the allowable test area.
(3) The exact relationship between spatial nonuniformity in irradiance and percent of
uncertainty depends on the spatial distribution, the test module design, reference module design,
and the calibration procedure. A rough estimate is given here based on simulations reported in
the literature from: C. Monokroussos, D. Etienne, K. Morita, V. Fakhfouri, J. Bai, C. Dreier, U.
Therhaag, W. Herrmann, “IMPACT OF CALIBRATION METHODOLOGY INTO THE
POWER RATING OF C-SI PV MODULES UNDER INDUSTRIAL
CONDITIONS” EUPVSEC 28, 2013, DOI: 10.4229/28th EUPVSEC 2013-4DO.1.1.
A-2
TOP 09-2-291
23 January 2020
(4) If the written instructions set the light source intensity via calibration to the
reference module short-circuit current, then the percent uncertainty due to spatial nonuniformity
of irradiance is:
(5) If the written instructions set the light source intensity via calibration to the
reference module maximum power current, then the percent uncertainty due to spatial
nonuniformity of irradiance is:
(6) The literature referenced in paragraph A.2.a(3), and related studies, provide more
information on how calibration to reference module Imp rather than Isc affects uncertainty.
b. Irradiance.
The light source shall be capable of maintaining an average irradiance between 800 and
1100 W/m2. IV measurements shall only be conducted when irradiance is in this range. The
irradiance for each measurement shall be recorded. If, during calibration, the irradiance is
increased to match the reference module current, it may be recorded as 1000 W/m2. If
measurements are not taken at 1000 W/m2, a method to correct the IV curve to the correct
intensity will be performed and documented in the instructions.
c. Short-Term Stability.
(1) The test lab shall establish written start-up procedures for the light source that are
supported with measurements. The minimum allowable time between turning on the light source
and intensity calibration or measurement shall be clearly specified.
(2) The light source shall exhibit adequate stability over the course of a typical
measurement period, after following the written start-up procedures. For self-documentation,
the test lab shall measure the IV curve of a single module every five minutes over the course of
one hour. All the short-circuit current values resulting from this measurement series (i.e., at least
13 values) shall be plotted as a function of elapsed time. If the test lab believes that a typical
operation period to measure a set of products is longer than one hour, then the stability test
A-3
TOP 09-2-291
23 January 2020
should be executed over that longer time period. The graph of short-circuit current versus time
shall be included in the self-documentation report.
(3) Calculation of the uncertainty due to intensity stability shall be performed using
the short-circuit current values from the graph. The following quantities shall be calculated or
identified:
(a) Isc,average = average short-circuit current = sum of all values / number of values.
(d) Uint = ± % uncertainty due to intensity stability = 100 x (Imax - Imin) / (2 x Isc,average).
(4) The description of light-source start-up applies to the simulator, rather than
outdoor measurement. Measurement utilizing a simulator is recommended due to the additional
challenges of outdoor measurement. These challenges are related to temperature control, finding
times of sufficient irradiance, finding times when irradiance is stable over the course of one
measurement (typically clear-sky days), and stability of measurement equipment exposed to
ambient temperatures and sunlight. If outdoor measurement is performed, the criteria for
choosing acceptable measurement days or times shall be documented in the operating
instructions. The acceptable irradiance range for measurement is the same for indoor or outdoor
measurements: 800 to 1100 W/m2. The operating instructions shall also specify how real-time
intensity monitoring is used to correct the raw outdoor IV curve to 1000 W/m2. The one-hour
stability graph described at the beginning of this section shall be generated with the outdoor data,
following the written instructions, including the prescribed intensity correction. The percent
uncertainty due to intensity stability shall then be calculated from the graph in the same way
described above.
A.3. TEMPERATURE.
A-4
TOP 09-2-291
23 January 2020
b. The following information shall be identified for the self-documentation report and
associated calculations:
(3) ‘T correction’ = “Yes” or “No” = Does written and automated procedure use
temperature coefficients to correct the IV curve to 25 °C (77 °F)?
(5) If ‘T correction’ = “Yes”, then UT = {(0.4)2 + [(Tmax - Tmin ) x 0.4 x 0.1 /2]2}0.5
c. The above calculation for UT makes the conservative (i.e., resulting in a low UT)
assumptions of ± 1 °C offset between the measured and actual module temperature, power
temperature coefficients of -0.4 percent per degree K, and typical uncertainty in temperature
coefficients of approximately ± 10 percent relative. Information derived from:
C. Monokroussos et al., “Energy Rating of Commercial Mono- and Polycrystalline PV-modules
in accordance with IEC 61853 -1,-2,-3 and Impact on the Annual Energy Yield”, 33rd
EUPVSEC, 25th - 27th Sep. 2017, Amsterdam, Netherlands.
a. The test lab shall utilize a reference module to calibrate the light source intensity.
Requirements exist on the reference module size, calibration history, and spectral response. A
test lab may utilize more than one reference module. Each reference module shall meet these
requirements.
b. Ideally, the reference module size, cell arrangement, and cell technology matches that
of the products to be tested. Reference modules shall have a total area of at least 0.5 m2.
c. Each reference module shall have a documented calibration history. This history shall
involve no more than one secondary calibration step beyond an accredited test laboratory. An
accredited test laboratory may be one that is accredited to International Organization for
Standardization (ISO) 1702514 standards for calibration of modules, or one that is certified to
perform IEC 61215-2. Examples of test labs in the United States that meet these criteria are the
NREL Photovoltaic Cell and Module Performance group, UL, RETC, CFV, DNVGL, and
Intertek. In a secondary calibration step, a non-accredited tester, but one who has performed
self-documentation procedures, uses a module calibrated by an accredited lab to establish the
A-5
TOP 09-2-291
23 January 2020
Results in Acceptable
Reference Module
Reference Module History Comments
for Self-
Documentation?
Yes
University of
No Springfield is not
accredited
Yes
Manufacturer data is
not an acceptable
No
substitute for an
accredited measurement
A-6
TOP 09-2-291
23 January 2020
e. The spectral response of reference modules shall be adequately matched to the test
device to keep error from spectral mismatch low. Such matching may be achieved by either
using a reference module that has very similar spectral response to the test module, or by
utilizing a “spectral mismatch factor,” which is particular to the tester’s light source, and
accounts for how different technologies yield different currents for that light source.
f. Information on how to calculate and use a spectral mismatch factor can be found on-
line (for example, https://www.nrel.gov/pv/text-spectral-mismatch-corrections.html ,
https://www2.pvlighthouse.com.au/calculators/spectral%20mismatch%20calculator/spectral%20
mismatch%20calculator.aspx , and http://assets.newport.com/webDocuments-
EN/images/Spectral_Mismatch-App_Note_51.PDF) and in the literature. Note that the spectral
mismatch factor is particular to the tester’s light source. Thus, a tester cannot simply use the
spectral mismatch factor that an accredited lab has provided, which is specific to the light source
at the accredited lab. Calculation and utilization of a spectral mismatch factor will require the
spectral responses (quantum efficiencies) of the test and the reference modules, as well as the
simulator spectrum. Quantum efficiencies may be measured by the test lab, provided by the
manufacturer, or taken from the literature if information from cells of the same materials and
structure is available.
g. If the test lab will utilize spectral mismatch correction, the details of this correction
shall be documented. The self-documentation shall contain a graph of the light source intensity
and the reference module(s) spectral response(s). The written operator instructions shall describe
when and how to apply the spectral mismatch correction.
A-7
TOP 09-2-291
23 January 2020
i. Adhering to the requirements of Table A-2 may imply that a test lab has completed the
self-documentation for some, but not all, cell technologies. For example, suppose a test lab uses
one Si reference module but has no knowledge of their light source spectrum (which would be
required to perform a spectral mismatch correction). Then, as described in Table A-2, the test
lab is equipped to measure x-Si or CIGS modules, but not CdTe, a-Si, or GaAs.
The electronics used to perform the current-voltage sweep shall be capable of measuring from
zero voltage (i.e., short-circuit current) to open-circuit voltage (i.e., zero current). The procedure
shall yield a single IV curve and single values for the parameters Voc, Isc, Vmp, Imp, Pmp, and ff.
Obtaining the IV curve and parameters shall not require any subjective judgment from the
operator or any other personnel, such as choosing a “best” value out of a family of curves. The
IV curve shall be free from major artifacts: In tracing from low voltage to high voltage, the
current must decrease monotonically. There must not be portions of the IV curve where current
increases with voltage. Such glitches may result from the electronics or the light source, but are
not characteristics of a solar panel without integrated electronics. All steps necessary for
obtaining the IV sweep shall be documented in the instructions.
A-8
TOP 09-2-291
23 January 2020
b. The power output from each of the six measurements shall be tabulated in the self-
documentation. The largest and smallest power measurement from this data set shall differ by no
more than 5 percent (i.e., (Plargest – Psmallest)/ Plargest < 0.05.
c. If long-term repeatability does not meet the above requirement, the test lab will not
meet the ± 5 percent total uncertainty requirement, even if state-of-the-art values are achieved for
all components of uncertainty specified in this document.
It is recommended, though not required in the self-documentation, that test labs also trade
modules on a yearly basis to check for agreement in power output measurements. In those
experiments, the PVTOP IV procedure should be performed, including ascertaining whether
stabilization is needed for a given product. An individual lab testing against a manufacturer label
or datasheet value is not considered sufficient, as many cases have been observed where the
module power output is more than 5 percent different than the nameplate value, or a very wide
range for power output is stated on the nameplate.
In order to minimize the likelihood of operator error, two requirements must be met. First, all
procedures must be documented (as described in previous sections), and this documentation must
be gathered in one place. Second, all operations that can reasonably be automated should be
accomplished by software. Such operations are likely to include, at a minimum, changing power
supply settings and operating the power supply, adjusting the simulator intensity to match the
reference module output, recording temperatures, and correcting IV curves for temperature or
intensities not at standard conditions.
A-9
TOP 09-2-291
23 January 2020
The test lab will have the ability to perform light soaking, as described in the PVTOP procedure,
for stabilization prior to the IV curve.
a. The total measurement uncertainty, Utotal, will be estimated using the various
components of uncertainty obtained in the previous section using the following formula:
b. To perform IV measurements for the PVTOP, the lab must achieve Utotal < 5 (i.e., total
measurement uncertainty is < ± 5 percent).
A-10
TOP 09-2-291
23 January 2020
Please evaluate the following by the requirements detailed in the preceding sections.
A-11
TOP 09-2-291
23 January 2020
Signature Date
• Graph of irradiance versus position, including location of largest allowable test area.
• List of qualifying reference modules by cell type, identifier (e.g. serial number), location of
primary calibration, and location of secondary calibration (if applicable).
• Tabulated data from the long-term reproducibility check.
Test lab: Each time you complete the self-documentation process, please mail or e-mail a copy
of this checklist, with the required attachments, to the following addresses:
A-12
TOP 09-2-291
23 January 2020
John Wills
U.S. Army Aberdeen Test Center
358 Michaelsville Road
APG, MD 21005-5059
[email protected]
and
David Scheiman
Optoelectronics & Radiation Effects Branch, Code 6818;
Electronics Science & Technology Division; Bldg. 208, Rm 145
4555 Overlook Ave. SW
Washington DC 20375
[email protected]
A-13
TOP 09-2-291
23 January 2020
A-14
TOP 09-2-291
23 January 2020
APPENDIX B. ABBREVIATIONS.
AM Air Mass
ASTM American Society for Testing and Materials
ATEC U.S. Army Test and Evaluation Command
°C degrees Celsius
C5ISR U.S Army Combat Capabilities Development Command,
Command, Control, Communications, Computers, Cyber,
Intelligence, Surveillance and Reconnaissance Center
CIGS copper indium/gallium di-selenide
cm centimeter
°F degrees Fahrenheit
ff fill factor
km kilometer
kW-hr/m2 kilowatt - hour per meter squared
lb pound
m meter
mA milliamp
m/s meters per second
MIL-STD Military Standard
mm millimeter
MPPT Maximum Power Point Tracker
MQT Module Quality Test
N Newton
nm nanometer
NMOT Normal Module Operating Temperature
B-1
TOP 09-2-291
23 January 2020
APPENDIX B. ABBREVIATIONS.
RH Relative Humidity
UV ultraviolet
B-2
TOP 09-2-291
23 January 2020
APPENDIX C. REFERENCES.
1. IEC 61215, Terrestrial Photovoltaic (PV) Modules - Design Qualification and Type
Approval, 9 March 2016.
6. Koehl, Michael; Heck, Markus; Wiesmeier, Stefan; and Wirth, Jochen, “Modeling of the
nominal operating cell temperature based on outdoor weathering,” Solar Energy
Materials & Solar Cells 95(201(1)) 1638–1646.
7. Muller, Matthew; Marion, Bill; and Rodriguez, Jose, “Evaluating the IEC 61215 Ed.3
NMOT Procedure Against the Existing NOCT Procedure with PV Modules in a Side-by-
Side Configuration,” Proceedings of the IEEE Photovoltaics Specialists Conference 38-
201(2).
9. Bosco, Nick; Silverman, Timothy J.; Kurtz, Sarach, “Climate specific thermomechanical
fatigue of flat plate photovoltaic module solder joints,” Microelectronics Reliability 62,
(2016), 124-129.
11. TOP 01-2-621, Outdoor Sand and Dust Testing, 6 February 2009.
12. IEC 60068-2-78, Basic Environmental Testing Procedures - Part 2-78: Tests - Test Cab:
Damp Heat, Steady State, 30 October 2012.
C-1
TOP 09-2-291
23 January 2020
APPENDIX C. REFERENCES.
13. Dennis J. Coyle, Holly A. Blaydes, Rebecca S. Northey, James E. Pickett, Kaustubh R.
Nagarkar, Ri-An Zhao, James O. Gardner, “Life prediction for CIGS solar modules part
2: degradation kinetics, accelerated testing, and encapsulant effects,” Prog. Photovolt:
Res. Appl. 2013; 21:173–186.
14. ISO 17025, General Requirements for the Competence of Testing and Calibration
Laboratories, 2017.
C-2
TOP 09-2-291
23 January 2020
D-1
TOP 09-2-291
23 January 2020
D-2
TOP 09-2-291
23 January 2020
Forward comments, recommended changes, or any pertinent data which may be of use in
improving this publication to the following address: Policy and Standardization Division
(CSTE-CI-P), U.S. Army Test and Evaluation Command, 6617 Aberdeen Boulevard, Aberdeen
Proving Ground, Maryland 21005-5001. Technical information may be obtained from the
preparing activity: Support Equipment Division (TEAT-WFE), U.S. Army Aberdeen Test
Center, Aberdeen Proving Ground, Maryland 21005-5059. Additional copies can be requested
through the following website: https://www.atec.army.mil/publications/documents.html, or
through the Defense Technical Information Center, 8725 John J. Kingman Rd., STE 0944, Fort
Belvoir, VA 22060-6218. This document is identified by the accession number (AD No.)
printed on the first page.