IC WBS With Gantt Chart

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 1

WORK BREAKDOWN STRUCTURE WITH GANTT CHART

PROJECT
CALAWIS PROJECT
TITLE

PROJECT
MELVIN SALAO
MANAGER

COMPANY
MMES CONSTRUCTION
NAME

DATE FEB. 28 2022 PHASE ONE PHASE TWO PHASE THREE PHASE FOUR

START
WBS NUMBER TASK TITLE MANPOWER DUE DATE DURATION % of TASK WEEK 1 WEEK 2 WEEK 3 WEEK 4 WEEK 5 WEEK 6 WEEK 7 WEEK 8 WEEK 9 WEEK 10 WEEK 11 WEEK 12
DATE
COMPLETE
M T W TH F S M T W R F S M T W TH F S M T W R F S M T W TH F S M T W TH F S M T W H F S M T W TH F S M T W TH F S M T W TH F S M T W TH F S M T W TH F S

SLUDGE BUFFER TANK/BACKWASH


1 60
BUFFER TANK
1.1 STRUCTURAL WORKS

1.1.1 Rebar 02/28/2022 2/4/2022 7 WEEKS 0%


1.1.2 Form works 7/3/2022 9/4/2022 7 WEEKS 0%
1.1.3 Concrete 10/3/2022 04/13/2022 7 WEEKS 0%
1.2 ARCHITECTURAL WORKS

1.2.1 Water Stop 0%


1.2.2 Rubber Concrete 03/28/2022 3 WEEKS 0%
1.2.3 Provision of Lintel Beam 11/4/2022 1 WEEK 0%
1.2.4 Concrete topping to roof 04/18/2022 2 WEEKS 0%
1.2.5 CHB Walls 04/20/2022 1 WEEK 0%
1.2.6 Plastering walls 04/22/2022 1 WEEK 0%
1.2.7 Painting 04/18/2022 3 WEEKS 0%
1.2.8 Nosing

2 SLUDGE DEWATERING 40
2.1 STRUCTURAL WORKS

2.1.1 Rebar 02/28/2022 2/4/2022 7 WEEKS 0%


2.1.2 Form works 7/3/2022 9/4/2022 7 WEEKS 0%
2.1.3 Concrete 10/3/2022 04/13/2022 7 WEEKS 0%
2.2 ARCHITECTURAL WORKS

2.2.1 Expansion Joint 0%


2.2.2 Construction Joint 0%
2.2.3 Water Stop 0%
2.2.4 Rubber Concrete 0%
2.2.5 Provision of Lintel Beam 0%
2.2.6 Concrete topping to roof 0%
2.2.7 CHB Walls 0%
2.2.8 Plastering walls 0%
2.2.9 Painting 0%
2.2.10 Nosing

4 CLOSE OUT
4.1 Audit 0%
4.2 Hand over Docs 0%

You might also like