YAWEI Laser Installation Instructions
YAWEI Laser Installation Instructions
YAWEI Laser Installation Instructions
Dear users:
Thanks for choosing Yawei laser cutting machine.To finish the installation & commission on time,and ensure the good running of your machine during the
long using.Please read below instructions,and prepare the below things before the machine’s arriving.
I. Facility environment
1.Environment temperature:0℃-40℃,relative humidity:15%-75%.Proper temperature and humidity are very important for stable running of laser cutting machine.
When the temperature and humidity are over the limits,it may affect the normal running of machine.If the humidity is over the limit,the laser resource need to be
preheated for 30min before normal running.If the conditions permit,we suggest customer to add an air conditional for laser resource.
2.The air from equipment installation location and air compressor must be without aromatic hydrocarbon material(e.g. solvent and hydrocarbon).These material will
led to the “air barrier”,so that laser beam can not get through and cause damage to the equipments.
3.Equipment must be keeped away from atmospheric medium(e.g. rain,hail,snow,fog,etc),and can only run in cleaning indoor enviroment.It is prohibited to run the
machine in explosive and dusty enviroment.
4.Machine needs to be fixed with anchoring(supplied by Yawei),so the floor need to be as flat as possible.The surface irregularities(the altitude intercept between
highest and lowest point) must be controlled within 10mm.The thickness of ferroconcrete must be over 150mm.
1)To avoid the affection of vibration,there should be no punching,bending,shear machine aside.If this requirement can not be fulfilled,please dig a damping ditch or
install additional damping device.
2)Requirements for damping ditch:Width≥100mm,Depth≥the thickness of ferroconcrete,the range must cover all the machine.Inside the ditch must fill the sands or
other buffering material.
The weight of the main machine is around 10-15 ton. Machine needs to be lifted by a crane during the installation.When a crane is not available,please rent a lifting
device and prepare the necessary lifting appliance(e.g. wirerope,soft liting tape,etc)
Please prepare hand type hammer drill,Φ17*150 drill,hydraulic jack of 10 ton(The minimum lifting gap <50mm), and socket with enough wiring.