Prestige Skytech Schedule: S. No. Description Quantity Unit Start Date Ceiling Works

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 21

PRESTIG

S. No. DESCRIPTION QUANTITY UNIT START DATE


CEILING WORKS

1 GYPSUM FRAME WORK 227 SQM 10/5/2022

2 GYPSUM BOARDING 227.00 SQM 10/19/2022


3 PAINTING WORK UP TO ONE COAT 227 SQM 10/25/2022
FLOORING WORKS

4 MARBLE FLOORING 321.00 SQM 10/14/2022

CLADDING WORKS

5 ALUMINIUM FRAMING ON WALL 421 SQM 10/5/2022

6 PLY/CEMENT BOARD FIXING ON WALL 421 SQM 10/21/2022

7 MARBLE CLADDING 324.00 SQM 10/22/2022

8 LACQUERED GLASS FIXING 97.00 SQM 11/5/2022

9 PAINTING FINAL COAT 227 SQM 11/5/2022


10 MARBLE POLISHING 645 SQM 11/1/2022
LOOSE FURNITURE
1 Reception Table of 4000mm (L) 1 NOS
2 Waiting Lounge Seating-1 seater 4 NOS
3 Waiting Lounge Seating-2 seater 2 NOS
4 Waiting Lounge Centre Table 2 NOS 12/1/2022
5 Reception Chairs 2 NOS
12/1/2022

6 Planters-600mm dia , 750mm high FRP planters. 5 NOS

Trap Door
1 2600mm x 1500mm 1 NOS
2 150mm x 150mm 1 NOS 10/25/2022

S. No. DESCRIPTION QUANTITY UNIT START DATE


CEILING WORKS
1 GYPSUM FRAME WORK 133 SQM 10/15/2022
2 GYPSUM BOARDING 133.00 SQM 10/18/2022
3 PAINTING WORK UP TO ONE COAT 133 SQM 10/20/2022
FLOORING WORKS

4 MARBLE FLOORING 151.00 SQM 10/20/2022

CLADDING WORKS
5 ALUMINIUM FRAMING ON WALL 203.00 SQM 10/10/2022

6 PLY/CEMENT BOARD FIXING ON WALL 203.00 SQM 10/20/2022

7 MARBLE CLADDING 141.00 SQM 10/25/2022

8 LACQUERED GLASS FIXING 62.00 SQM 11/10/2022


9 PAINTING FINAL COAT 133 SQM 11/5/2022
10 MARBLE POLISHING 292 SQM 11/1/2022
LOOSE FURNITURE
10 Reception table 1 Nos
11 Waiting Lounge Seating 2 Nos
12 Waiting Lounge Centre Table 1 Nos 12/1/2022
13 Reception Chairs 2 Nos
14 Planters-600mm dia , 750mm high FRP planters. 2 Nos
TRAP DOORS
15 2300mm x 1500mm 1 Nos
10/27/2022
16 150mm x 150mm 1 Nos

WING A STILT
S. No. DESCRIPTION QUANTITY UNIT START DATE
CEILING WORKS
1 GYPSUM FRAME WORK 121 SQM 10/15/2022
2 GYPSUM BOARDING 121.00 SQM 10/18/2022
3 PAINTING WORK UP TO ONE COAT 121 SQM 10/23/2022
FLOORING WORKS
4 MARBLE FLOORING 168.00 SQM 10/22/2022

MARBLE POLISHING 339 SQM 11/5/2022


CLADDING WORKS
5 ALUMINIUM FRAMING ON WALL 255 SQM 10/10/2022
6 PLY/CEMENT BOARD FIXING ON WALL 255 SQM 10/20/2022
7 MARBLE CLADDING 171.00 SQM 10/28/2022
8 LACQUERED/BRONZ GLASS FIXING 84.00 SQM 11/10/2022
9 PAINTING FINAL COAT 121 SQM 11/5/2022
TRAP DOOR
10 450mm x450mm 8 Nos 10/27/2022
SKIRTING
11 SS Skirting 39 Rmts 11/5/2022
12 SS Strips 73 Rmts 11/5/2022

W
S. No. DESCRIPTION QUANTITY UNIT START DATE
1 SCREEDING WORK IN FLOORING 663.37 SQM 12:10:22

2 POP/PUNNING ON CURVED WALL 160.2 SQM 10/20/2022

CEILING WORKS

3 GYPSUM FRAME WORK 562 SQM 20:10:22

5 GYPSUM BOARDING 562.00 SQM 10/25/2022


6 PAINTING WORK UP TO ONE COAT 562 SQM 10/30/2022
7 BAFFLE CEILING 132.05 SQM 12/25/2022
FLOORING WORKS
8 MARBLE FLOORING 700 SQM 10/25/2022
9 MARBLE POLISHING 700 SQM 11/20/2022
CLADDING WORKS
10 ALUMINIUM FRAMING 668.00 SQM 10/15/2022

11 PLY/CEMENT BOARD FIXING 668 SQM 10/30/2022

12 MARBLE CLADDING 603 SQM 11/5/2022

13 LACQUERED GLASS FIXING 65.00 SQM 11/20/2022

14 PAINTING FINAL COAT 562 SQM 11/25/2022


15 METAL FIXING 160.2 SQM 12/25/2022
16 CARPET/RUG
17 Carpet/RUG- 3000mmx4500mm 2 Nos
18
19 LOOSE FURNITURE
Reception Table 1 NOS
Waiting Lounge Seating - Single seater type 1 4 NOS
Waiting Lounge Seating - Single seater type 2 4 NOS
12/10/2022
Reception Chairs 2 NOS
Waiting Lounge Center Table Rectangular Shape 2 NOS
Waiting Lounge Center Table 600mm Dia 4 NOS

W
S. No. DESCRIPTION QUANTITY UNIT START DATE
CEILING WORKS

1 GYPSUM FRAME WORK 2352.5 SQM 10/20/2022

2 GYPSUM BOARDING 2352.5 SQM 10/25/2022


3 PAINTING WORK UP TO ONE COAT 2352.5 SQM 10/30/2022
FLOORING WORKS
4 QUARZ FLOORING 2053.5 SQM 10/20/2022
CLADDING WORKS
5 ALUMINIUM FRAMING 4820.5 SQM 10/25/2022
6 PLY/CEMENT BOARD FIXING 4820.5 SQM 10/30/2022
7 QUARZ CLADDING 2570.5 SQM 11/5/2022
8 LACQUERED GLASS FIXING 2250 SQM 11/5/2022
9 PAINTING FINAL COAT 2352.5 SQM 11/15/2022
TRAP DOORS
10 450mm x450mm
SKIRTING
11 SS Skirting 999 RMT 11/10/2022
12 SS Strips 2216 RMT 11/5/2022

W
S. No. DESCRIPTION QUANTITY UNIT START DATE

CEILING WORKS

1 GYPSUM FRAME WORK 2352.5 SQM 10/20/2022


2 GYPSUM BOARDING 2352.5 SQM 10/25/2022
3 PAINTING WORK UP TO ONE COAT 2352.5 SQM 10/30/2022
FLOORING WORKS
4 QUARZ FLOORING 2053.5 SQM 10/20/2022
CLADDING WORKS
5 ALUMINIUM FRAMING 4820.5 SQM 10/25/2022
6 PLY/CEMENT BOARD FIXING 4820.5 SQM 10/30/2022
7 QUARZ CLADDING 2570.5 SQM 11/5/2022
8 LACQUERED GLASS FIXING 2250 SQM 11/5/2022
9 PAINTING FINAL COAT 2352.5 SQM 11/15/2022
TRAP DOORS
10 450mm x450mm
SKIRTING
11 SS Skirting 999 RMT 11/10/2022
12 SS Strips 2216 RMT 11/5/2022

WING A
S. No. DESCRIPTION QUANTITY UNIT START DATE
CEILING WORKS
1 GYPSUM FRAME WORK 2352.5 SQM 10/20/2022
2 GYPSUM BOARDING 2352.5 SQM 10/25/2022
3 PAINTING WORK UP TO ONE COAT 2352.5 SQM 10/30/2022
FLOORING WORKS
4 QUARZ FLOORING 2053.5 SQM 10/20/2022
CLADDING WORKS
5 ALUMINIUM FRAMING 4820.5 SQM 10/25/2022
6 PLY/CEMENT BOARD FIXING 4820.5 SQM 10/30/2022
7 QUARZ CLADDING 2570.5 SQM 11/5/2022
8 LACQUERED GLASS FIXING 2250 SQM 11/5/2022
9 PAINTING FINAL COAT 2352.5 SQM 11/15/2022
TRAP DOORS
10 450mm x450mm
SKIRTING
11 SS Skirting 999 RMT 11/10/2022
12 SS Strips 2216 RMT 11/5/2022

W
S. No. DESCRIPTION QUANTITY UNIT START DATE
CEILING WORKS
1 GYPSUM FRAME WORK 2352.5 SQM 10/20/2022
2 GYPSUM BOARDING 2352.5 SQM 10/25/2022
3 PAINTING WORK UP TO ONE COAT 2352.5 SQM 10/30/2022
FLOORING WORKS
4 QUARZ FLOORING 2053.5 SQM 10/20/2022
CLADDING WORKS
5 ALUMINIUM FRAMING 4820.5 SQM 10/25/2022
6 PLY/CEMENT BOARD FIXING 4820.5 SQM 10/30/2022
7 QUARZ CLADDING 2570.5 SQM 11/5/2022
8 LACQUERED GLASS FIXING 2250 SQM 11/5/2022
9 PAINTING FINAL COAT 2352.5 SQM 11/15/2022
TRAP DOORS
10 450mm x450mm
SKIRTING
11 SS Skirting 999 RMT 11/10/2022
12 SS Strips 2216 RMT 11/5/2022

S. No. DESCRIPTION QUANTITY UNIT START DATE


CEILING WORKS
1 GYPSUM FRAME WORK 2352.5 SQM 10/20/2022
2 GYPSUM BOARDING 2352.5 SQM 10/25/2022
3 PAINTING WORK UP TO ONE COAT 2352.5 SQM 10/30/2022
FLOORING WORKS

4 QUARZ FLOORING 2053.5 SQM 10/20/2022

CLADDING WORKS
5 ALUMINIUM FRAMING 4820.5 SQM 10/25/2022

6 PLY/CEMENT BOARD FIXING 4820.5 SQM 10/30/2022

7 QUARZ CLADDING 2570.5 SQM 11/5/2022


8 LACQUERED GLASS FIXING 2250 SQM 11/5/2022
9 PAINTING FINAL COAT 2352.5 SQM 11/15/2022
TRAP DOORS
10 450mm x450mm
SKIRTING
11 SS Skirting 999 RMT 11/10/2022
12 SS Strips 2216 RMT 11/5/2022

WING
S. No. DESCRIPTION QUANTITY UNIT START DATE
CEILING WORKS
1 Grid ceiling marking 10/25/2022
3 Gypsum ceiling framing 667 SQM 11/1/2022
4 Gypsum board fixing 667 SQM 11/5/2022
5 Painting 667 SQM 11/20/2022
CLADDING WORKS
6 Washbasin counter 1009 RMT 11/15/2022
7 Mirror panelling 661 SQM 11/15/2022
DOORS
Wooden doors
Single Leaf Laminated wooden Door (Size:1000x
8 2400mm) 292 Nos 11/25/2022
Single Leaf Flush Door with Undercut (Size:800x
9 2400mm) 9 Nos
Single Leaf Flush Door with louvers & Grab Bar
10 (Size:1200x 2400mm) 146 Nos
11 Single Leaf Flush Door (Size: 1000x 2400mm) 146 Nos
Glass doors
SINGLE LEAF GLASS DOOR (1000mm x 2400mm)
12 2 Nos 11/20/2022
PRESTIGE SKYTECH SCHEDULE

WING A STILT-01 VISITOR LOBBY


TARGET DATE PLANNED % ACHIEVED % MANPOWER DEPLOYED

10/15/2022 100% 90%

10/25/2022 100% 0%
10/30/2022 N/A

10/22/2022 100% 37%

Marble--12 nos
Carpenter - 05 nos
Gypsum Ceiling - 05nos
10/15/2022 100% 90% Painter-04 nos
House keeping - 02 nos

Total -28
10/25/2022 100% 21%

11/5/2022 100% 19%

11/15/2022 100% 0%

11/15/2022 100% 0%
11/15/2022 100% 0%

100% 0%
100% 0%
100% 0%
12/7/2022 100% 0%
100% 0%
12/7/2022

100% 0%

100% 0%
10/30/2022 100% 0%

WING A STILT-01 EMPLOYEE LOBBY


TARGET DATE PLANNED % ACHIEVED % MANPOWER DEPLOYED

10/25/2022 100% 0%
10/23/2022 100% 0%
1/25/2022 N/A

10/25/2022 100% 30% Marble--06 nos


Carpenter - 04 nos
Gypsum Ceiling - 04nos
Painting--04 nos
10/15/2022 100% 90% House keeping - 02 nos
10/25/2022 100% 0% Total - 20

11/10/2022 100% 0%

11/15/2022 100% 0%
11/10/2022 100% 0%
11/15/2022 100% 0%

100% 0%
100% 0%
12/7/2022 100% 0%
100% 0%
100% 0%

100% 0%
10/30/2022
100% 0%

WING A STILT-01 PASSENGER LOBBY - HIGH ZONE & LOW ZONE


TARGET DATE PLANNED % ACHIEVED % MANPOWER DEPLOYED

10/25/2022 100% 0%
10/28/2022 100% 0%
10/30/2022

Marble--06 nos
Carpenter - 04 nos
Gypsum Ceiling - 04nos
Painter--03 nos
House keeping - 02 nos
10/30/2022 100% 100% Marble--06 nos
Carpenter - 04 nos
11/15/2022 100% 0% Gypsum Ceiling - 04nos
Painter--03 nos
House keeping - 02 nos
10/15/2022 100% 90% Total - 19
10/25/2022 100% 0%
11/15/2022 100% 0%
11/15/2022 100% 0%
11/10/2022 100%

10/30/2022 100% 0%

11/15/2022 100% 0%
11/15/2022 100% 0%

WING A -L-01 VISITOR ENTRANCE LOBBY


TARGET DATE PLANNED % ACHIEVED % MANPOWER DEPLOYED
14:10:22 100% 100%

10/30/2022 100% 100%

10/30/2022 100% 0%

11/5/2022 100% 0%
11/10/2022 - -
12/30/2022 - -

11/10/2022 100% 0%
12/30/2022 - -
Marble 15nos
Carpenter - 05nos
10/25/2022 100% 20% Gypsum ceiling - 05 nos
Painter - 03nos
11/10/2022 100% 0% Housekeeping - 02nos

11/20/2022 100% 0% Total - 29

11/30/2022 100% -

11/30/2022 100% -
12/30/2022 100% -
12/30/2022 100% 0%

100% 0%
100% 0%
100% 0%
12/20/2022
100% 0%
100% 0%
100% 0%

WING A TYPICAL FLOOR -L-01 Lift Lobby


TARGET DATE PLANNED % ACHIEVED % MANPOWER DEPLOYED

11/15/2022 100% 70%

11/20/2022 100% -
11/25/2022 - -

11/25/2022 100% 30% Stone works - 20nos


Gypsum - 10nos
12/15/2022 100% 60% Carpenter- 10nos
Painter - 10
12/20/2022 100% 0% Housekeeping-05nos
12/25/2022 100% 0%
12/25/2022 100% 0% Total - 55
12/30/2022 - -

12/30/2022 100% 0%
12/25/2022 100% 0%

WING A TYPICAL FLOOR -L-02 Lift Lobby


TARGET DATE PLANNED % ACHIEVED % MANPOWER DEPLOYED

11/15/2022 100% 0%
11/20/2022 100% -
11/25/2022 - -

11/25/2022 100% 0%
Stone works - 20nos
Gypsum - 10nos
Carpenter- 10nos
Painter - 10
Housekeeping-05nos
Stone works - 20nos
Gypsum - 10nos
12/15/2022 100% 30% Carpenter- 10nos
12/20/2022 100% 0% Painter - 10
12/25/2022 100% 0% Housekeeping-05nos
12/25/2022 100% 0% Total - 55
12/30/2022 - -

12/30/2022 100% 0%
12/25/2022 100% 0%

WING A TYPICAL FLOOR -L-03 Lift Lobby (Mock-up)


TARGET DATE PLANNED % ACHIEVED % MANPOWER DEPLOYED

11/15/2022 100% 100%


11/20/2022 100% 100%
11/25/2022 - -

11/25/2022 100% 70%


Stone works - 20nos
Gypsum - 10nos
12/15/2022 100% 30% Carpenter- 10nos
12/20/2022 100% 100% Painter - 10
12/25/2022 100% 70% Housekeeping-05nos
12/25/2022 100% 70% Total - 55
12/30/2022 - -

12/30/2022 100% 70%


12/25/2022 100% 70%

WING A TYPICAL FLOOR -L-04 Lift Lobby


TARGET DATE PLANNED % ACHIEVED % MANPOWER DEPLOYED

11/15/2022 100% 100%


11/20/2022 100% 0%
11/25/2022 - -

11/25/2022 100% 0%
Stone works - 20nos
Gypsum - 10nos
12/15/2022 100% 0% Carpenter- 10nos
12/20/2022 100% 0% Painter - 10
12/25/2022 100% 0% Housekeeping-05nos

Total - 55
Stone works - 20nos
Gypsum - 10nos
Carpenter- 10nos
Painter - 10
Housekeeping-05nos
12/25/2022 100% 0% Total - 55
12/30/2022 - -

12/30/2022 100% 0%
12/25/2022 100% 0%

WING A TYPICAL FLOOR - L-05


TARGET DATE PLANNED % ACHIEVED % MANPOWER DEPLOYED

11/15/2022 100% 0%
11/20/2022 100% 0%
11/25/2022 - -

11/25/2022 100% 0%
Stone works - 20nos
Gypsum - 10nos
12/15/2022 100% 0% Carpenter- 10nos
Painter - 10
12/20/2022 100% 0% Housekeeping-05nos
12/25/2022 100% 0% Total - 55
12/25/2022 100% 0%
12/30/2022 -

100% 0%

12/30/2022 100% -
12/25/2022 100% -

WING A TYPICAL FLOOR -L-01 TO L-5 - TOILETS


TARGET DATE PLANNED % ACHIEVED % MANPOWER DEPLOYED

11/10/2022 100% 0%
11/20/2022 100% 0%
11/30/2022 100% 0%
12/10/2022 100% 0%

Stone works - 05nos


Gypsum - 06nos
12/15/2022 100% 0%
12/15/2022 100% 0%
Stone works - 05nos
Gypsum - 06nos
Carpenter- 05nos
Painter - 05nos
12/20/2022 100% 0% Housekeeping-03nos

Total - 524
100% 0%

100% 0%
100% 0%

11/30/2022 100% 0%
DEPENDENCY FROM JMC/Prestige REMARKS

Existing framing work done by JMC.Need Need clearance on Existing ceiling framing.Either
MEP clearance to continue the work. continue or remove and rework by soundarya.

Clearance from MEP services

Electrical conduit fixing work pending in 02 days work delayed due to Generator
Visitor entry&Employee entry. problem&Machinery hold by JMC.

Need clearance on Existing wall Alluminium


Existing Framing done by JMC.Need MEP
framing.Either continue or remove and rework by
clearance to continue further
soundarya.

Existing Framing done by JMC.Need MEP Need clearance on Existing ply panelling .Either
clearance to continue further continue or remove and rework by soundarya.

Existing cladding done by JMC.Need MEP Need clearance on Existing cladding .Either
clearance to continue further continue or remove and rework by soundarya.

Existing cladding done by JMC.Need MEP Need clearance on Existing cladding .Either
clearance to continue further continue or remove and rework by soundarya.

- -
- -

Starts after completion of Civil works


Starts after completion of Civil works

Yet to fix -
Yet to fix -

DEPENDENCY FROM JMC/Prestige REMARK

Electrical conduiting pending


MEP/Fire clearance required

Need clearance on existing flooring either to be


Existing marble flooring done by JMC. removed or continued.

Existing framing done by JMC. Electrical clearance required


MEP clearance required before Ply or
board fixing
MEP clearance required before Ply or
board fixing
MEP clearance required
MEP clearance required
MEP clearance required

starts after completion of civil works

yet to fix
yet to fix

DEPENDENCY FROM JMC/Prestige REMARK

MEP services clearance required


Clearance from MEP services
EXISTING FLOORING REMOVAL OR RETAIN DECISION TO
Existing flooring done by JMC. BE GIVEN
EXISTING FLOORING REMOVAL OR RETAIN DECISION TO
BE GIVEN

EXISTING FRAMING REMOVAL OR RETAIN DECISION TO


Existing framing done by JMC. BE GIVEN
MEP clearance required
MEP clearance required
MEP clearance required

yet to fix

-
-

DEPENDENCY FROM OTHER VENDORS REMARK


COMPLETED

Note:- Curved area finish in wall paper (WF14-Wall


Primer finishing done paper D'Décor- Classic meatllics II DWP0246 Brown
on wall finished with water baser primer)

MEP services has to be completed before AC ducting and sprinkler piping work to be
the initiation of Gypsum frame works completed before frame work

Clearance from MEP services befor this all support to be taken for sandlier

MEP clearance required


-

MEP clearance required


MEP clearance required before Ply or
board fixing
MEP clearance required before Ply or
board fixing
MEP clearance required before Ply or
board fixing
-
-
-

-
-
-
starts after completion of civil works
-
-
-

DEPENDENCY FROM OTHER VENDORS REMARK

MEP services clearance pending in High


zone
MEP services clearance pending
-

MEP clearance required


MEP clearance required
-
-
-

-
-

DEPENDENCY FROM OTHER VENDORS REMARK

MEP services clearance pending


MEP services clearance pending
-

MEP services clearance pending


MEP clearance required
MEP clearance required
-
-
-

-
-

DEPENDENCY FROM JMC/Prestige REMARK

completed
completed
-

MEP clearance required


MEP clearance required
-
-
-

-
-

DEPENDENCY FROM JMC/Prestige REMARK

completed
MEP clearance required
-

MEP clearance required

MEP clearance required


MEP clearance required
-
-
-

-
-

DEPENDENCY FROM JMC/Prestige REMARK

MEP services clearance pending


MEP services clearance pending

Electrical clearance before flooring works


initiations

MEP clearance required


MEP clearance required before Ply or
board fixing
-
-
-

yet to fix

-
-

DEPENDENCY FROM JMC/Prestige REMARK

MEP clearance required


MEP clearance required
MEP clearance required
-
-
-