Pert
Pert
This is the duration that is given with some experience in related activity
fields with normal conditions and known productivity rate of
resource.
The Mean & Variance of durations
The Mean Duration/Time (te) is derived from the equation
te = (to+ 4 tm+ tp)/6 ------ (1)
o m p o m p o m p
Durations
Class Ex-1
Activity to tm tp te te
(to+ 4 tm+ tp)/6
1–2 3 5 7 (3+ 4 x 5 + 7)/6
2–3 4 8 12 (4 + 4 x 8 + 12)/6
3–4 6 8 14 (6 + 4 x 8 + 12)/6
4–5 2 4 7 (2 + 4 x 4 + 7)/6
Beta Distributions of durations
Probability
o m p 3 55 7 o m p
Durations
Ex:2
Activity Optimistic Most likely Pessimist Mean Variance Standard
to tm ic Time (σ2) = (tp – to Deviation
tp te = )2/36 (σ)
(to+ 4 tm+ tp)/6
1-2 1 1 7
1-3 1 4 7
1-4 2 2 8
2-5 1 1 1
3-5 2 5 14
4-6 2 5 8
5-6 3 6 15
Ex:3
Activity Optimistic Most likely Pessimist Mean Variance Standard
to tm ic Time (σ2) = (tp – Deviation
tp te = (σ)
(to+ 4 tm+ tp)/6 to )2/36
1-2 3 5 7
1-3 1 2 3
2-5 6 8 12
3-4 8 12 17
4-5 0 0 0
4-6 6 9 12
4-7 3 6 8
5-8 5 7 9
6-9 1 2 3
8-9 3 6 8
7-10 8 15 20
9-10 2 4 6
Probability of completion time for a project
• Used under projects with uncertain durations
• Finds out the probability of completing a project with in
the scheduled completion time.
• This is done by 3 assumptions:
1. Assume that the mean critical path turns out to be the
longest path through the project (µ)
If x1, x2, x3 … etc are mean durations on critical path, then
40 50 60
Probability of completion time for a project
The characteristics of a normal distribution are…
Duration
Probability of completion time for a project
Now, once a normal distribution curve is drawn, the
target is to find out the probability of completing the
project in a given time.
X can be μ or μ
Probability of completion time for a project
For a STANDARD normal distribution (SND) the mean is 0, and variance is 1
μ μ
σ σ
X X
Probability of completion time for a project
Ex:2
Activity Optimistic Most Pessimistic Mean Time Variance
to likely tp te = (σ2) = (tp – to
tm (to+ 4 tm+ )2/36
tp)/6
1-2 1 1 7 2 1
1-3 1 4 7 4 1
1-4 2 2 8 3 1
2-5 1 1 1 1 0
3-5 2 5 14 6 4
4-6 2 5 8 5 1
5-6 3 6 15 7 4
Questions
• What is the probability of completing the project in
17 days
• What is the probability of completing project in 15
days
• What is the probability of completing the project in
18 days
Ex:3
Activity Optimistic Most likely Pessimistic Mean Time Variance
to tm tp te = (σ2) = (tp – to
(to+ 4 tm+ tp)/6 )2/36
1-2 3 5 7 5 0.44
1-3 1 2 3 2 0.11
2-5 6 8 12 8.33 1.0
3-4 8 12 17 12.17 2.25
4-5 0 0 0 0 0
4-6 6 9 12 9 1.0
4-7 3 6 8 5.83 0.694
5-8 5 7 9 7 0.444
6-9 1 2 3 2 0.11
8-9 3 6 8 5.83 0.694
7-10 8 15 20 14.67 4.0
9-10 2 4 6 4 0.44
Questions
• What is the probability of completing the project in
34.67 days
• What is the probability of completing project in 36
days
• What is the probability of completing the project in
31 days
• What is the probability that the project will be
completed only after 36 days