Mos Silt Fence
Mos Silt Fence
Mos Silt Fence
Silt Fence
1.0 INTRODUCTION
A silt fence is a temporary sediment barriers consisting of filter fabric stretched across and attached to
supporting posts, entrenched and depending upon the strength of the fabric used, backed by a wire
fence for support. Silt fence can be considered an on-site control as it caters to small overland sheet
flow. It is most effective in securing site perimeter, protecting topsoil stock pile and intercepting sheet
flow along slope contours. Silt fence requires regular inspection and maintenance as it is easily
damaged. Sediment built-up behind fence should be regularly removed.
2.0 REQUIREMENT
PARAMETER REQUIREMENT
Design Storm First 50mm of rainfall over the contribution (equivalent impervious)
catchment
Installation of a silt fence will typically involve a procedure of digging a trench and securing the barrier
into position. Standard silt fencing will feature an overall height of three feet (3') to accommodate
various sediment build up and water flows. One of most commonly used approaches for installing silt
fence is Static slicing method.
a) Static sling machine pulls a narrow blade through the ground to create a silt 12” deep, and
inserts the silt fence fabric into the slit behind the blade.
b) The blade is designed to slightly disrupt soil upward nest to the slit minimize horizontal
compaction thereby creating an optimum condition for compacting the soil vertically on
both side of the fabric.
c) To compact the soil to achieve nearly the same or greater compaction as the original
undisturbed soil is by rolling a tractor wheel 2 to 4 times.
d) The compaction is to reduce air spaces between soil particle to avoid infiltration saturate
the soil so that water will not find a pathway under the fence.
e) When the silt fence is holding back several tons of accumulated water and sediment, it
needs to be supported by posts that are driven 2 ft into well-compacted soil.
f) The installation of silt fence is complete after the posts are driving in and the fabric is
attaching to the post.
4.0 MAINTENANCE
1. Use J-hooks (Figure 3) along silt fences, berms, and other structures to break up long flow paths,
reduce flow velocities, and trap sediment before it reaches down gradient locations.
3. Repair or replace silt fence found to be non-functional, due to severe weather conditions, age,
extended use, damage, or other causes.
4. Use rock berms along dips and in low corners of silt fences if blowouts and bypasses occur frequently
in these locations.
5. Where repeated failures occur, install additional upgradient erosion prevention and/or sediment
control practices or redundant BMPs to eliminate the problem.
6. Repair or replace ineffective fabric and fiber rolls due to collapse, tearing, decomposition, etc. within
24 hours of discovery.
5.0 INSPECTION
1. During installation, make sure support posts are on the downhill side of the fabric.
2. Inspect silt fences at least once a week and after each rainfall, as required by permits, and make
required repairs immediately.
4. After installation, tug on the top of the fabric between posts to ensure that it is embedded tightly.
5. Make sure fabric is securely attached to the posts, without excessive sagging.
8. After a rain, check silt fences for bypasses below or around the ends of each silt fence section.
9. Note and record blowouts, sections where the fence is down, etc.
10. Note the condition of support posts along each section of silt fence.
11. Observe and record the amount of sediment deposited on the upslope side of the silt fence.