Annexure – 2 30V DC System shifting methodology
Project : Construction of Upgrading 132/33kV Thumrait Grid Station From 2x30 MVA to 2x63MVA
Client : Oman Electricity Transmission Company S.A.O.C. (OETC)
Client Consultant : Dawood Engineering Consultancy L.L.C. (DEC)
Contractor : United Engineering Projects Company L.L.C. (UEP)
Required
S. No. Activity Description Start Time End Time Required Manpower Remarks
Duration
1 PTW Receiving 15 Mins 08:00 AM 08:15 AM DISC CEP-1
DISC CEP-1
DCRP Testing Engineer-1
2 Setup temporary DC supply Source kit 15 Mins 08:15 AM 08:30 AM
Electrical Supervisor-1
Electrical Technication-2
Switch OFF the following,
DISC CEP-1
1. 30V DC Charger-1 & 2 MCB in LVAC Panel.
DCRP Testing Engineer-1
3 2. 30V DC Fuse box-1 & 2. 15 Mins 08:30 AM 08:45 AM
Electrical Supervisor-1
3. 30V DCDB Outgoing MCB's
Electrical Technication-2
Check and confirm no voltage
Dis-connect DC Supply incoming / outgoing cables
from
DISC CEP-1
1. 11kV Switchgear Bus-A & Bus-B.
DCRP Testing Engineer-1
4 2. 20MVA Tx. RTCC-1 & 2. 15 Mins 08:45 AM 09:00 AM
Electrical Supervisor-1
3. 30V DC Fuse box-1 & 2 (Charger cable only).
Electrical Technication-5
4. 30V DC Charger-1 & 2.
5. 30V DC DB.
CEP-1
Cable Glanding & Termination of new cables in
Testing Engineer-1
5 1. 11kV Switchgear Bus-A & Bus-B. 15 Mins 09:00 AM 09:15 AM
Electrical Supervisor-1
2. 20MVA Tx. RTCC-1 & 2.
Electrical Technication-5
Contractor: Client Consultant:
United Engineering Projects Company L.L.C. Dawood Engineering Consultancy L.L.C.
Page 1 of 2
Required
S. No. Activity Description Start Time End Time Required Manpower Remarks
Duration
CEP-1
Providing 30V DC supply from temporary DC supply Testing Engineer-1
6 15 Mins 09:15 AM 09:30 AM
Source kit Electrical Supervisor-1
Electrical Technication-5
DISC CEP-1
DCRP Testing Engineer-1
7 Shifting 30V DC Charger & DCDB 120 Mins 09:30 AM 11:30 AM Electrical Supervisor-1
Electrical Technication-5
Fabricator-2
CEP-1
Cable Glanding & Termination in 30V DC Charger & Testing Engineer-1
8 45 Mins 11:30 AM 12:15 PM
DCDB (LV AC/DC Supply & Interpanel cables) Electrical Supervisor-1
Electrical Technication-5
Shifting of following DC supply cables from DISC CEP-1
Temporary DC source kit to 30V DCDB, DCRP Testing Engineer-1
9 45 Mins 12:15 PM 01:00 PM
1. 11kV Switchgear Bus-A & Bus-B. Electrical Supervisor-1
2. 20MVA Tx. RTCC-1 & 2. Electrical Technication-5
10 Cancel PTW 15 Mins 01:00 PM 01:15 PM DISC CEP-1
Contractor: Client Consultant:
United Engineering Projects Company L.L.C. Dawood Engineering Consultancy L.L.C.
Page 2 of 2