The Pen Project
The Pen Project
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 2
Copyright © 2018 PTCoE
All rights reserved. With the exception of brief passages PRINCE2® is a registered trade mark of AXELOS Limited.
and quotes for reviewing or commenting purposes, no part The Swirl logo™ is a trade mark of AXELOS Limited.
of this publication may be reproduced or transmitted in any
form or by any means without prior consent of PTCoE
(Professional Training Center of Excellence)
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 3
About the authors
Frank Turley has been a Project Manager for more than 15 years and a PRINCE2® Practitioner. He is also a PRINCE2,
Scrum and Project Management trainer and coach and has written a number of PRINCE2® and Project Management
related books. Frank is best known in the PRINCE2 world for his work in creating the most popular PRINCE2 Self Study
training including:
• The PRINCE2 Foundation Training Manual and video course
• The PRINCE2 Practitioner Training Manual
• The Scrum Master Training Manual
Website:
LinkedIn Profile: http://linkedin.com/in/frankturley
Nader K. Rad is a project management consultant, author, and trainer at Management Plaza. His career started in 1997
and he has been involved in many projects in different industries. He has designed a number of project management
courses, prepared a number of e-learning materials, and written more than 40 books and plenty of practical articles on
project management concepts and standards, planning software, scheduling, etc.
He is certified as PMP®, PRINCE2® Practitioner, PRINCE2 Agile™ Practitioner, MoP Practitioner, MSP Foundation,
M_o_R Foundation, MoV Foundation, P3O Foundation, AgilePM Practitioner, ITIL Foundation, CSM, PSM I, PSPO I,
Agile Scrum Foundation, Advanced in Structured and Critical Thinking, Integrator in Agile Service Projects, etc.
Website: http://nader.pm/
LinkedIn Profile: https://www.linkedin.com/in/naderkrad/
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 4
Who is this sample PRINCE2 project for?
Document: Who is this sample PRINCE2 project for?
1) PRINCE2 Foundation Students
• Browse over the main PRINCE2 documents, this will help your understanding of PRINCE2.
• Look at: 1) Project mandate, 2) Project Brief, 3) Initiation Stage Plan, 4) Product Description, 5) PID, 6) Register Files, 7) Log files
2) PRINCE2 Practitioner Students
• You need to be familar with all PRINCE2 management documents and their structure (typical contents)
• It is therefore best to become familar with the scenario used in this sample project and then become familar with each PRINCE2
management document
• This is perhaps the best way to prepare for the Practitioner Exam as the exam uses a given project scenario and you are expected
to know how to apply PRINCE2.
3) Gaining PRINCE2 experience
• Many people never get a chance to work in a PRINCE2 environment and don’t understand how to apply PRINCE2.
• We suggest to re-create this sample project based on another scenario (e.g. a project you have done)
• This is perhaps the best way to practice PRINCE2 (We at MPLAZA will be happy to give you feedback if you do this)
4) Implementing a PMO
• Many companies are now considering implementing a PMO but are not sure where to start
• We suggest that you identify a standard project from your organization and document it like this sample project
• Start of as simple as possible so you can deliver a first internal sample project (a reference project)
• The PMO can then gradually update this reference sample project to introduce new techniques and lessons
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 5
Who is this sample PRINCE2 project for?
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 6
Who is this Sample PRINCE2 project for?
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 7
The
Project Scenario
We have created an easy to understand project scenario as the focus
is on how to use the PRINCE2 management documents
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 8
Project Scenario
The Sales Manager chaired a meeting and the outcome of the meeting was as follows:
• We will give a quality pen/pencil to all clients to help reduce client turnover and improve relationship
• The majority of pens will be given out by the sales people
• The pen must be of good quality so people will be happy to use it (not be embarrassed to use it)
• Budget: €6 to €8 each
• Presentation of pen is important
• Company logo must appear on pen
Project Scope
• Define quality requirements
• Choose & test Pens/Pencils
• Order Pens with logo
• Choose clients to give pen to
Out of Scope
• Giving out the pens is not part of the project
• Designing the logo (will be supplied my marketing person)
• Original list of clients (will be supplied by accounts)
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 9
Pre-Project
Starting up a Project
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 10
Project mandate
Pre-Project Stage 1 (initiation) Stage 2 Stage 3 (Final)
Processes
Management Products
Other documents will be gradually added to this diagram. They will be presented in one of the
following colors:
Blue: Created once in the project
Green: Created once in every stage
Orange: Created/updated multiple times in every stage
Dark Red: Created/updated for each Work Package
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 11
Project mandate
2. Reasons
Build better relationships with clients and reduce the loss in the renewal of
maintenance contracts by 50%.
The project mandate does not have to
• CopyWorld365 has 4,200 maintenance contracts
contain much information
• Profit of €200 per contract = €840k
• 5% loss each year costs €42,000 Normally just the reasons and the name of
the Executive.
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 12
Lessons Log
Pre-Project Stage 1 (initiation) Stage 2 Stage 3 (Final)
Processes
Management Products
Project
mandate
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 13
Lessons Log
Document: Lessons Log Project: Pen Project Author: Project Manager Date:
The PM will facilitate the gathering of lessons. Lessons can come from users, Team
Managers, past project Lessons Reports, consultants, … Lesson seen
before?
Seen Date Logged
ID +- Recommendations Priority Stage
before Logged by
1 We used the business gift company “BizGifts” last year and they offered a Yes 12/1 PM 3 2
good service
2 The time to deliver gifts always seems to take longer than agreed by most Yes 12/1 PM 2 1
companies (so add time buffer)
3 The business gift company “Gifts4All” provided a poor service for our No 13/1 PM 2 2
neighboring company.
4 There is a ISO standard for pens: ISO 12757-2 No 13/1 PM 2 SU
5
…
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 14
Daily Log
Document: Daily Log Project: Pen Project Author: Project Manager Date:
When we were preparing the list of potential suppliers, I realized that one of I believe I’m capable of evaluating the suppliers honestly.
01 06-17 them is owned by an old friend of mine (conflict of interest) Project Manager 06-17 I’ve also informed the project board about this conflict of
interest.
A sales man from one of the potential suppliers came to our office today to I returned the gift and put the supplier in the company’s
02 06-18 meet me, while I was in a meeting. He left me a gift and left the building Project Manager 06-18 black list.
before I could meet him. This can be considered a bribery.
Daniel Ross, who’s responsible for the logo, is asked to prepare its vector He’s replaced by Julie Gates, who’s more expert on graphic
03 06-22 version, but he doesn’t seem to know how. Project Manager 06-23 design. We’ve lost two days, but the activity has a lot of float
and we won’t get into any problems.
The communication between Julie Gates and the supplier needed for the Julie Gates is asked to meet with the responsible person in
04 06-25 design of the logo is not effective enough. It takes a lot of time for each Project Manager 06-25 the supplier company to discuss the requirements of the
version to be reviewed and the new version is released. logo and to prepare it together.
The Daily Log is used to capture issues and risks in the Starting up a Project process
After that, it is used as a (private) daily journal by the Project Manager
Note: the content of this sample Daily Log belongs to next stages of the project
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 15
Project Product Description (part of Project Brief)
Pre-Project Stage 1 (initiation) Stage 2 Stage 3 (Final)
Processes
Management Products
Project
mandate
Project Brief
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 16
Project Product Description (Workshop)
The Project Manager hosted a workshop to create the Project Product Description. The main workshop goals:
1. Get buy-in from the necessary stakeholders
2. Identify the most important requirements for the pen and prioritize them
3. Complete the Project Product Description during the workshop
Requirements Exercise
• The PM gave each person post-its and reminded them about the project goals
• The PM asked each person to list 10 pen requirements
• After this exercise, the PM categorized each requirement and identified the top requirements
• The requirements are listed below using the MoSCoW technique
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 17
Project Product Description (part of Project Brief)
This is a good example of the Project Product Description (Main product description). It does
not have to be a large document..
Document: Project Product Description Project: Pen Project Author: Project Manager Date:
1. Purpose
3. Derivation
The purpose of the pens will be to provide a constant reminder of our company
1. Business Gift Catalogs
to most of our clients and reduce the loss of maintenance contracts renewals
2. Client list
by 50% in the next 12 months.
4. Development skills required
2. Composition
Purchasing skills
1. Pens to evaluate 3. Reviewed client list
Account (Client) management
2. Chosen Pen 4. Distributed Pens
This example has outlined four main requirements and defined the quality level for each requirement. See
Quality the next slide for more information.
Quality Expectation Quality looking pen Priority M Quality Expectation Logo display correctly on pen Priority M
Acceptance Criteria 1: Looks like it cost > €10 Acceptance Criteria 1: Correct size on pen
2: Look like a professional pen 2: Logo will not erase in 5 years of normal use
Tolerance None Tolerance 1: Size ± 10%, 2) Logo erase: + 100%
1: Confirm that 8 of 10 see value > €10 Acceptance method 1: Measure logo on pen with ruler
Acceptance method
2: Logo: Ask for Logo guarantee
2: Confirm that 9 of 10 see pen as professional
1: Susan Kelly, AC2: Susan Kelly
Responsibilities 1: Susan Kelly, 2: Susan Kelly Responsibilities
Quality Expectation 5 year guarantee Priority M Quality Expectation Pen easy to write with Priority M
Acceptance Criteria 1: 5 year guarantee from supplier Acceptance Criteria 1: 9 of 10 people find pen easy to write with
Tolerance 1: ± 10% Tolerance 1: ± 10%
1: Guarantee certification Acceptance method 1: Provide survey report
Acceptance method
Responsibilities 1: Susan Kelly
Responsibilities 1: Sales Manager will accept guarantee
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 18
Introduction to the quality information
This slide provides information about the quality data required in the Project Product Description
Most Project Managers find it very difficult to understand this from the official PRINCE2 Manual
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 19
Project Management Team Structure (part of Project Brief)
Processes
Management Products
Project
mandate
Project Brief
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 20
Project Management Team Structure (part of Project Brief)
Document: Project Management Team Structure Project: Pen Project Author: Project Manager Date:
Corp..
Corporate or Programme Management
These are their normal job functions
Direction
Senior User Executive Senior Supplier
CopyWorld365 Employees & Job titles Susan Kelly John King Terry Clinton
John King: CEO
Susan Kelly: Sales Manager Project Assurance Change Authority
Delivery Management
Terry Clinton: Purchasing & Accounts
Rose Carr: Client Project Manager
Project Manager
Rose Carr Project Support
Rose Carr
Tailoring comments for the PMT These are the PMT roles for the project
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 21
outline Business Case (part of Project Brief)
Pre-Project Stage 1 (initiation) Stage 2 Stage 3 (Final)
Processes
Management Products
Project
mandate
Project Brief
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 22
Outline Business Case (part of Project Brief)
Document: Outline Business Case Project: Pen Project Author: Executive Date:
2. Expected Benefits
• Reduce loss of maintenance contracts by 50% : value €42,000/year
• Increase new machine orders by 5%±1%: 16,000/year
The outline Business Case does not have to contain much data
3. Expected dis-benefits This information will be expanded later into the Business Case document in
None the Initiation stage.
It is written by the Executive with normally some assistance from the Project
4. Timescale Manager
12 weeks (3 months)
5. Costs
• Pen costs: €9 by 400 pens = €3,600
• Other project costs: €600
6. Investment appraisal
See Business Case (Initiation stage)
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 23
Project Brief
Pre-Project Stage 1 (initiation) Stage 2 Stage 3 (Final)
Processes
Management Products
Project
mandate
Project Brief
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 24
Project Brief
Document: Project Brief Project: Pen Project Author: Project Manager Date:
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 25
Initiation Stage Plan
Pre-Project Stage 1 (initiation) Stage 2 Stage 3 (Final)
Processes
Management Products
Project
mandate
Daily Log, Lessons Log
Project Brief
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 26
Initiation Stage Plan
Document: Initiation Stage Plan Project: Pen Project Author: Project Manager Date:
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 27
The pre-project activities are now complete and the Project Board may give
permission for the Initiation Stage to begin
Stage 1
Initiation (Planning)
Approx. 80% of the work in this stage is focused on planning (product breakdown, requirements,
product descriptions, estimating, scheduling)
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 28
Communication Management Approach (part of PID)
Pre-Project Stage 1 (initiation) Stage 2 Stage 3 (Final)
Processes
Management Products
Project
mandate
Risk Register, Quality Register, Issue Register
Daily Log, Lessons Log
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 29
Communication Management Approach (part of PID)
Document: Communication Management Approach Project: Pen Project Author: Project Manager Date:
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 30
Risk Management Approach (part of PID)
Document: Risk Management Approach Project: Pen Project Author: Project Manager Date:
1. Introduction 7. Scales
This document describes how risk management will be done during the The following scale will be used:
project: It is based on the standard approach document. Very low < €50
Low < €100
2. Risk Management Procedure
Medium < €250
The procedure should cover activities such as: Identify, Assess, Plan, Implement High < €500
and Communicate. The PM will be responsible for carrying out this risk Very high > €500
management procedure and for keeping the risk documents up to date and
will take corporate policy into account. 8. Roles & Responsibilities
Project Board Inform about new and existing risks
3. Tools and techniques
Project Manager Gather risk information for the project
• The PM will use the standard risk register to track all risks and this risk Risk management procedure
register is based on the corporate layout. Executive Communicate with clients
• The PM will also communicate high level risks in the business case and the
highlight report to the project board. 9. Risk response categories
Threat: Avoid, reduce, transfer, share, accept, contingent plans
4. Records Opportunity: Exploit, enhance, transfer, share, accept, contingent plans
The following documents will be used for risk management:
- Risk register, business case, highlight report 10. Risk Tolerances
5. Timing of risk management activities Risks should be escalated if any risk put more than 30% of the expected
benefits of the project in question.
The PM will spend about 1 to 2 hours each week on risk management
The executive must review risks for each stage decision and highlight report. 11. Risk Budget: A risk budget will be established
6. Risk Categories Used: PESTLE 12. Proximity: Not used
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 31
Product Breakdown Structure (part of the next Stage Plan)
Processes
Management Products
Project
mandate
Risk Register, Quality Register, Issue Register
Daily Log, Lessons Log
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 32
Product Breakdown Structure (part of the next Stage Plan)
Document: PBS for Stage 2 (hierarchy chart) Project: Pen Project Author: Project Manager Date:
Internal
Supplier Evaluation Pens Distribution Final Pens
Evaluation
List of potential
Catalog of pens List of evaluators List of clients requirements
suppliers
Purchase order for Evaluation and Sales people Purchase order for
Selected supplier
evaluation pens filled in forms delivered the finalized pen
Legend:
Group of
External products Products products
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 33
Product Breakdown Structure (part of the next Stage Plan)
Document: PBS for Stage 2 (Mindmap) Project: Pen Project Author: Project Manager Date:
3
Legend
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 34
Product Description(s) (part of PID)
Pre-Project Stage 1 (initiation) Stage 2 Stage 3 (Final)
Processes
Management Products
Project
mandate
Risk Register, Quality Register, Issue Register
Daily Log, Lessons Log
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 35
Product Description: Client List
Document: Product Description: List of Clients Project: Pen Project Author: Project Manager Date:
1. Identifier: PEN03.2
This is an example of a Product Description and the objective is to
2. Title: Client List describe the expected delivered product.
3. Purpose
List of all existing clients that will receive a pen
4. Composition
• Contact person and company names
• Current contract value for each company Identify the components that make up the product
• Contact person at CopyWorld365
5. Derivation (Source)
• Existing client list What is used to create this product (source)?
• Client contract
6. Development skills required
Customer knowledge
7. Quality Criteria
1. Contract value must be the current contract value The Product Description also includes the quality criteria, how the
2. Contact name must be the decision maker or main influencer product will be tested (method), tolerance, skills for tester and
quality reviewer.
Criteria Method Tolerance Skills Required
1 Review None Contract knowledge
2 Review None Contract knowledge
Producer: Reviewer Approver
Gerry Malone CFO Sales Manager
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 36
Risk Register
Pre-Project Stage 1 (initiation) Stage 2 Stage 3 (Final)
Processes
Management Products
Project
mandate Risk Register, Quality Register, Issue Register
Daily Log, Lessons Log
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 37
Risk Register
Document: Risk Register Project: Pen Project Author: Project Manager Date:
Project Name Pen Project Risk / Impact Amounts are related to the value of the expected
Project No 008 High Risk > € 7,500 benefits (See the Benefits Management Approach)
Project Manager Rose Carr Medium > € 1000 The expected gain is: €58,400
Project Executive John King Low Risk < € 1000
Users may not like the pens and therefore not keep
2 S. Kelly 7/3/13 Product using them which result in 90% - 100% reduction in € 8,760 Year 1 Reduce Active S. Kelly R Clark
benefits
Some sales people may not distribute the pens as
3 S. Kelly 9/3/13 Product intended, therefore the benefits will not be realized € 5,600 Year 1 Reduce Active S. Kelly S. Kelly
for these users
Example: How to calculate Probability * Impact The response text is not included in this example
The likelihood that majority of users will not like pen: 15%
New risks will continue to be identified as we plan
The Impact if almost all users don’t like pen: €58,400
The Probability * Impact = 20% * €58,400 = €8,760 and execute the project
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 38
Benefits Management Approach
Pre-Project Stage 1 (initiation) Stage 2 Stage 3 (Final)
Processes
Management Products
Project
mandate
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 39
Benefits Management Approach
Document: Benefits Management Approach Project: Pen Project Author: Project Manager Date:
4. Accountable for Benefits The PM will ask the Senior User (Susan Kelly)
Accountable Benefit 1. What are the expected benefits?
1. Susan Kelly: Reduce loss of maintenance contracts by 50% 2. When do you expect to get these benefits?
2. Susan Kelly: Increase new machine orders by 5% 3. How to measure these benefits?
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 40
Project Controls (part of PID)
Pre-Project Stage 1 (initiation) Stage 2 Stage 3 (Final)
Processes
Management Products
Project
mandate Risk Register, Quality Register, Issue Register
Daily Log, Lessons Log
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 41
Project Controls (part of PID)
Document: Project Controls Project: Pen Project Author: Project Manager Date:
1. Management Stages
The project will be managed in three stages: 4. Assessments
• Stage 1 – Initiating the project (Planning) Cost is assessed for the whole project and each stage.
• Stage 2 – Preparing everything to start evaluating sample pens, including Cost = Planned Cost v Forecasted cost. This cost parameter will be compared to
preparing requirements, selecting the supplier, selecting and buying sample the tolerances set for the whole project or a stage.
pens, preparing evaluation forms, and selecting evaluators Time is assessed for the whole project and each stage: Time = Forecasted
• Stage 3 – Preparing the final pens, including the evaluation of sample pens, duration / Planned duration. This time parameter will be compared to the
selecting, buying, receiving from supplier, and preparing the list of the sales tolerances for the whole project or a stage.
people to distribute them, and clients who are supposed to receive them.
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 42
Project Plan (part of PID)
Processes
Management Products
Project
mandate Risk Register, Quality Register, Issue Register
Daily Log, Lessons Log
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 43
Project Plan (part of PID)
Document: Project Plan (Part 1) Project: Pen Project Author: Project Manager Date:
5. Budgets
Project budget: €3,840 (internal people time is not charged)
Risk Budget: €0, 0 days | Change Budget: €480. This is only a high-level PBS in the Project Plan, there
Time Budget: 45 days (duration) will be more detail in the Stage Plans.
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 44
Project Plan (part of PID)
Document: Project Plan (part 2) Schedule Project: Pen Project Author: Project Manager Date:
We can also prepare a list of the resources needed for the plan. It’s best to prepare it as a time phased
table, extracted from the schedule.
2. Resources
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 45
Business Case (part of PID)
Processes
Management Products
Project
mandate Risk Register, Quality Register, Issue Register
Daily Log, Lessons Log
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 46
Business Case (part of PID)
Document: Business Case Project: Pen Project Author: Project Manager Date:
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 47
Tailoring of PRINCE2 (part of PID)
Pre-Project Stage 1 (initiation) Stage 2 Stage 3 (Final)
Processes
Management Products
Project
mandate Risk Register, Quality Register, Issue Register
Daily Log, Lessons Log
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 48
Tailoring of PRINCE2 (part of PID)
Document: Tailoring of PRINCE2 Project: Pen Project Author: Project Manager Date:
4. Adapting the Management Products A small project like this would usually be tailored
The management products will be kept separated (each in a single document). differently, it would contain about 80% less of the
We would not use formal and documented Work Packages. documentation shown.
Checkpoint Reports will be verbal (not written).
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 49
Project Initiation Documentation (PID)
Processes
Management Products
Project
mandate Risk Register, Quality Register, Issue Register
Daily Log, Lessons Log
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 50
Project Initiation Documentation (PID)
Document: Project Initiation Documentation Project: Pen Project Author: Project Manager Date:
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 51
Stage Boundary
This is the Stage Boundary process and it starts towards the end of
the current stage.
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 52
Dependencies Diagram (part of the next Stage Plan)
Pre-Project Stage 1 (initiation) Stage 2 Stage 3 (Final)
Processes
Management Products
Project
mandate Risk Register, Quality Register, Issue Register
Daily Log, Lessons Log
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 53
Dependencies Diagram (part of the next Stage Plan)
Document: Dependencies Diagram Project: Pen Project Author: Project Manager Date:
1. Dependencies Diagram
Requirements Logo
Legend:
Selected Supplier
Stage 1 Stage 2
List of potential Short list of qualified Catalog of pens
suppliers suppliers
Purchase order of
pens to be evaluated Purchase order of
Received pens
the finalized pen
Evaluation form
Sales people
delivered
List of clients
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 54
Schedule (part of the next Stage Plan)
Processes
Management Products
Project
mandate Risk Register, Quality Register, Issue Register
Daily Log, Lessons Log
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 55
Schedule (part of the next Stage Plan)
Document: Schedule for Stage 2 Plan Project: Pen Project Author: Project Manager Date:
1. Product Schedule
Note: durations shown for the groups of products are based on a rollup of products on all stages, rather than this specific stage.
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 56
Next Stage Plan
Processes
Management Products
Project
mandate
Risk Register, Quality Register, Issue Register
Daily Log, Lessons Log
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 57
Next Stage Plan
Document: Plan for Stage 2 (description) Project: Pen Project Author: Project Manager Date:
5. Budgets
Stage budget: €640 (internal people’s time is not charged) Time: 10 days
Risk Budget: €0, 0 days | Change Budget: €80
The End Stage Report and the Lessons Report can also be
Budgets (time and money) and tolerances of each stage are determined
submitted with the next Stage Plan
separately; however, they should always be consistent with the budget and
tolerances of the whole project (Project Plan).
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 58
The first stage the Initiating Stage (main focus is on
planning). In this project, project execution starts from
the second stage continues to the third (last) stage.
Stage 2
From now on, we’ll execute the project, monitor and
control it, revise the plans, and prepare new plans in
the stage boundaries.
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 59
Work Package
Pre-Project Stage 1 (initiation) Stage 2 Stage 3 (Final)
Processes
Management Products
Project
mandate Risk Register, Quality Register, Issue Register
Daily Log, Lessons Log
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 60
Work Package (WP)
Document: Work Package #1 Project: Pen Project Author: Project Manager Date:
1. Date 6. Tolerances
2016-06-29 Time: 0% | Cost: 0% | Scope: 0% |
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 61
Issue Register
Pre-Project Stage 1 (initiation) Stage 2 Stage 3 (Final)
Processes
Management Products
Project
mandate Risk Register, Quality Register, Issue Register
Daily Log, Lessons Log
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 62
Issue Register
Document: Issue Register Project: Pen Project Author: Project Manager Date:
Selected supplier sent the new catalog three Problem/co Jun 29, Rose Open
01 Rose Carr High Level 2 (last updated Jun
days later than expected ncern 2016 Carr 30, 2016)
We have only one issue up to now. During the project, new issues We should always try to close any open issues
will arise, be closed, escalated, …. as soon as possible and if possible.
Less important issue will be documented in the Daily Log
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 63
Issue Report
Processes
Management Products
Project
mandate Risk Register, Quality Register, Issue Register
Daily Log, Lessons Log
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 64
Issue Report
Document: Issue Report for ID-01 Project: Pen Project Author: Project Manager Date:
1. Recommendation
Two future activities for preparing the evaluation forms and preparing the list 1. Closure date
of evaluators can be done by using more resources. Jul 1, 2016
The best option for extra resources is the IT Department; they are capable of
helping us executing these two activities faster. This instance of the Issue Report shows the issue after its
closure. The Issue Report might have been initially created
as soon as the issue is captured.
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 65
Issue Register
Pre-Project Stage 1 (initiation) Stage 2 Stage 3 (Final)
Processes
Management Products
Project
mandate Risk Register, Quality Register, Issue Register
Daily Log, Lessons Log
Project Brief Project Initiation Documentation Issue Report All registers, including the Issue Register, are maintained
Four Approach Docs Tailoring continuously. It is created during the initiation stage.
Project Product Description
Product Descriptions(s) Project Plan
Project Management Team
Project Controls Business Case
Structure
Outline Business Case Benefits Management Approach
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 66
Issue Register
Document: Issue Register Project: Pen Project Author: Project Manager Date:
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 67
Highlight Report
Pre-Project Stage 1 (initiation) Stage 2 Stage 3 (Final)
Processes
Management Products
Project
mandate
Risk Register, Quality Register, Issue Register
Daily Log, Lessons Log
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 68
Highlight Report
Document: Highlight report # 4 Project: Pen Project Author: Project Manager Date:
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 69
Stage 2
Stage Boundary
Towards the end of a stage (after most of the work
has been done), the Project Manager can start
thinking about the next stage
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 70
Product Breakdown Structure (part of the next Stage Plan)
Processes
Management Products
Project
mandate
Risk Register, Quality Register, Issue Register
Daily Log, Lessons Log
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 71
Product Breakdown Structure (part of the next Stage Plan)
Document: PBS for Stage 2 (Mindmap) Project: Pen Project Author: Project Manager Date:
Legend
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 72
Dependencies Diagram (part of the next Stage Plan)
Document: Dependencies Diagram Project: Pen Project Author: Project Manager Date:
1. Dependencies Diagram
Requirements Logo
Legend:
Selected Supplier
Stage 1 Stage 2
List of potential Short list of qualified Catalog of pens
suppliers suppliers
List of clients
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 73
Schedule (part of the next Stage Plan)
Pre-Project Stage 1 (initiation) Stage 2 Stage 3 (Final)
Processes
Management Products
Project
mandate Risk Register, Quality Register, Issue Register
Daily Log, Lessons Log
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 74
Schedule (part of the next Stage Plan)
Document: Schedule for Stage 3 Plan Project: Pen Project Author: Project Manager Date:
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 75
Next Stage Plan
Processes
Management Products
Project
mandate Risk Register, Quality Register, Issue Register
Daily Log, Lessons Log
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 76
Next Stage Plan
Document: Next Stage Plan (for Stage 3) Project: Pen Project Author: Project Manager Date:
3. Lessons incorporated
Allow buffer time for delivery of pens
Investigate the ISO standard for pens: ISO 12757-2
5. Budgets
Stage budget: €3,200 (internal people time is not charged), 25 days
Risk Budget: €0, 0 days | Change Budget: €400, 3 days
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 77
Configuration Management
Processes
Management Products
Configuration Management
Project
mandate Risk Register, Quality Register, Issue Register
Daily Log, Lessons Log
Project Brief Project Initiation Documentation Issue Report Configuration Management is used
Four Approach Docs Tailoring throughout the project to track
Project Product Description Highlight Report Next Stage Plan
Product Descriptions(s) Project Plan
changes and states of all products and
PBS Schedule
Project Management Team documents. Many PMs do not have a
Project Controls Business Case Dependencies
Structure system or a process for configuration
Outline Business Case
management. Tip: use a spreadsheet.
Benefits Management Approach
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 78
Configuration Management
Product ID
Document: Configuration Management Project: Pen Project Author: Project Manager Date:
Date: 2016-07-20
ID Product Title/Name Current Date of last Mgmt Product Group Status Source Owner Succe- Issues Risks
Version update Stage ssors
02 Short list of qualified suppliers v1 2016-06-21 2 Supplier Approved Int. Purchasing dep. 03
03 Selected supplier v1 2016-06-25 2 Supplier Approved Int. Purchasing dep. 04
04 Catalog of pens v1 2016-06-28 2 Supplier Received Ext. Purchasing dep. 05 01
05 Short list of pens to be evaluated v1 2016-06-29 2 Evaluation pens Approved Int. Purchasing dep. 06
06 Purchase order of pens to be evaluated v1 2016-06-29 2 Evaluation pens Approved Int. Purchasing dep. 09
09 Evaluation results v1 2016-07-19 3 Internal Evaluation Approved Int. Purchasing dep. 10 02, 03
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 79
Configuration Item Record
Processes
Management Products
Configuration Management
Project
mandate Risk Register, Quality Register, Issue Register
Daily Log, Lessons Log
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 80
Configuration Item Record
Document: Configuration Item Record #14 Project: Pen Project Author: Project Manager Date:
Date: 2016-07-20
Item ID 14
Item Name Logo Look at the Logo data in the last slide “Configuration Management”
This is the same information but presented in this format.
Current version 4
Some other examples of Configuration Item Records are the MP3
Date of last update 2012-06-27 Tags in your SmartPhone or a library index card that provides book
Management stage 2 information.
Item Type Marketing For bigger projects, it can take a lot of effort to keep this data up to
date and the PM will need need time or assistance.
Status Approved (ready for use)
Source Internal (Marketing Department)
Owner Purchasing Department
Users All (Public)
Location Marketing Pack
Marketing Guidelines Doc (MKT045)
Related
Marketing Pack
Cross Reference NA
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 81
End Stage Report and Lessons Report
Processes
Management Products
Configuration Management
Project
mandate Risk Register, Quality Register, Issue Register
Daily Log, Lessons Log
Towards the end of the SB
Project Brief Project Initiation Documentation Issue Report End Stage Report process, the End Stage Report is
Four Approach Docs Tailoring Highlight Report Next Stage Plan created. It provides the Project
Project Product Description
Product Descriptions(s) Project Plan PBS Schedule
Board with a summary of the
Configuration
Project Management Team performance of the stage and
Project Controls Business Case Item Record Dependencies
Structure overall project status.
Outline Business Case Benefits Management Approach Lessons Report
We will also add a Lessons Report
Initiation Stage Plan End Stage Report Work Package
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 82
End Stage Report
Document: End Stage Report #2 Project: Pen Project Author: Project Manager Date:
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 83
Lessons Report (part of End Stage Report)
Document: Lessons report #2 Project: Pen Project Author: Project Manager Date:
1. Executive summary
We had a successful stage and learned a lesson, which helps us avoid problems
in future.
What we’ve learned through the stage.
2. Scope of the report
The lesson from the second stage of the project
3. Lessons
What went well:
• We could easily choose the supplier, because the team provided us with
needed information in time and had good communications.
• We could easily choose the evaluators.
• The help of IT Department was really useful, and we couldn’t recover the
delay without their help.
What didn’t went well:
• There were delays in receiving catalogs and this delayed all its depending
activities. In retrospective, we realized that we could have asked them for
the catalogs sooner. We will increase our buffer time when ordering from
suppliers in the future.
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 84
This is the last stage of the project.
This stage can proceed once the Project Board have
reviewed the End Stage Report (from Stage 2) and the
next Stage Plan for Stage 3
Stage 3
Final Stage
The Closing a Project process at the end of this stage.
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 85
Quality Register
Processes
Management Products
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 86
Quality Register
Production date
Target Approval
Actual Approval
Quality Method
Actual Quality
Review Date
Product Name
Target Quality
Quality ID
Product ID(s)
Review Date
Approver
Reviewer
Producer
Records
Quality
Result
Date
Date
01 01 List of potential suppliers Inspection John Bob Frank 6-21 6-20 6-21 6-20 6-21 Pass Link
02 02 Short list of qualified suppliers Inspection John Bob Frank 6-21 6-21 6-21 6-21 6-21 Pass Link
03 03 Selected supplier Inspection John Bob Frank 6-25 6-25 6-26 6-25 6-27 Fail Link
04 05 Short list of pens to be evaluated Inspection John Bob Frank 6-29 6-30 6-30 6-30 7-1 Pass Link
05 06 Purchase order of pens to be evaluated Inspection Robin Stephan Frank 6-29 6-30 6-30 6-30 7-2 Pass Link
06 07, 08, 09, Evaluation of pens Inspection Robert Stephan Frank 7-28 7-29
10
07 11, 12 List of clients and sales people Inspection Mary Bob Frank 7-30 7-30
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 87
Product Status Account
Pre-Project Stage 1 (initiation) Stage 2 Stage 3 (Final)
Processes
Management Products
Configuration Management
Project
mandate Risk Register, Quality Register, Issue Register
Daily Log, Lessons Log
Project Brief Project Initiation Documentation Issue Report End Stage Report Product Status
Four Approach Docs Tailoring Account
Project Product Description Highlight Report Next Stage Plan
Product Descriptions(s) Project Plan Configuration PBS Schedule
Project Management Team Item Record
Project Controls Business Case Dependencies
Structure
Outline Business Case Benefits Management Approach Lessons Report A Product Status Account should be
called a Product Status Report as it is
Initiation Stage Plan End Stage Report Work Package
a report about one or more products
Next Stage Plan
Note: this diagram only contains the
PBS Schedule
sample documents of this training course,
Dependencies rather than all the necessary documents in
each stage.
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 88
Product Status Account
Document: Product Status Account #6 Project: Pen Project Author: Project Manager Date:
ID Product Name (Title) Current Date of last Mgmt Product Group Status Source Owner Succe- Issues Risks
Version update Stage ssors
09 Evaluation results 1 2016-07-19 3 Internal Evaluation Approved Int. Purchasing dep. 10 02, 03
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 89
End Project Report and Lessons Report
Processes
Management Products
Project Brief Project Initiation Documentation Issue Report End Stage Report Product Status End Project Report
Four Approach Docs Tailoring Account Lessons Report
Project Product Description Highlight Report Next Stage Plan
Product Descriptions(s) Project Plan Configuration PBS Schedule
Project Management Team Note: this
Project Controls Business Case Item Record Dependencies
Structure diagram only
contains the
Outline Business Case Benefits Management Approach Lessons Report sample
documents of
Work Package
Initiation Stage Plan End Stage Report this training
course, rather
Next Stage Plan We should prepare a End Project Report at the end of the than all the
PBS Schedule project to review how the project performed against the necessary
initial PID. This may also include a Lessons Report, which documents in
Dependencies each stage.
reviews all the lessons learned through the project.
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 90
Lessons Report (part of End Project Report)
Document: Lessons Report - Final Project: Pen Project Author: Project Manager Date:
3. Lessons
What went well?
• It was easy to choose the supplier, because the team provided us with
needed information in time and we had good communication. We should A Lessons Report normally covers:
always take help from such people in our projects. - What we’ve learned through this project.
• It was also easy to choose the evaluators due to the support of the Sales - Tips that would be useful for future projects.
Manager.
• The help of IT Department was really helpful and helped us to recover the
delay.
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 91
End Project Report
Document: End Project Report Project: Pen Project Author: Project Manager Date:
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 92
Summary
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 93
Summary
What we practiced in this sample project:
• Pre-Project • Stage 2
• Project mandate • Work Package
• Daily Log • Issue Register
• Lessons Log • Issue Report
• Project Brief
• Lessons Report
• Project Product Description
• Project Management Team Structure
• Highlight Report
• Outline Business Case • Configuration Management
• Initiation Stage Plan • Configuration Item Record
• Next Stage Plan
• Stage 1 • End Stage Report
• Benefits Management Approach
• Risk Register • Stage 3
• Project Initiation Documentation • Product Status Account
• Communication Management Approach • Lessons Report
• Product Description(s) • End Project Report
• Project Controls
• Tailoring of PRINCE2
• Business Case
• Project Plan
• Next Stage Plan
• End Stage Report
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 94
Summary
Processes
Management Products
Configuration Management
Project
mandate Risk Register, Quality Register, Issue, Register
Project Brief Project Initiation Documentation Issue Report End Stage Report Product Status End Project Report
Four Approach Docs Tailoring Account Lessons Report
Project Product Description Highlight Report Next Stage Plan
Product Descriptions(s) Project Plan Configuration PBS Schedule
Project Management Team Item Record
Project Controls Business Case Dependencies
Structure
Outline Business Case Benefits Management Approach Lessons Report
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 95
Summary
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 96
Notes Page
Notes
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 97
Notes Page
Notes
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 98
Notes Page
Notes
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 99
Notes Page
Notes
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 100
Notes Page
Notes
PRINCE2® is a Registered Trade Mark of the AXELOS. The Swirl logo™ is a Trade Mark of the AXELOS. P2P-SampleProject-EN Version V01 – Premium Edition 101