Schedule
Schedule
Schedule
INTAKE
Start: 01/06/2022
Finished: 30/09/2022
Stocking soil
area
Start: 27/09/2022
Finished: 06/12/2022
Start: 06/12/2022
Finished: 14/02/2023
Start: 16/06/2022
Start:25/08/2022 Start: 16/07/2022 Finished: 21/09/2022
Finished: 17/06/2023 Finished: 18/11/2022
Start: 16/06/2022
Start:05/08/2022 Finished: 18/09/2022
Finished: 01/03/2023
Start: 21/07/2022
Finished: 10/11/2022
Start: 31/07/2022
Finished: 27/12/2022
Start: 10/08/2022
Finished: 06/02/2023
Start: 30/08/2022
Start: 20/08/2022 Finished: 04/05/2022
Finished: 20/03/2023
Start: 09/09/2022
Finished: 11/06/2023
Sheet pile Backfill to the sea Guide Sheet pile Excavation and structure work
9m drilling 16m 16m shoring And backfilling
Thank you