ESTIMATES
ESTIMATES
BY: MLOK
A. EARTHWORKS
EXCAVATION
DEPTH: 1 METER
@ 24 UNITS
1.5 M
1.5 M
1.5 M
1.5 M
1
0.9 m
0.1 m
1. 0 m
= (1.5 x 1.5 x 1) – (1.35 x 1.35 x 0.20) - (0.3 x 0.3 x 0.9) – (1.5 x 1.5 x 0.1)
= 19 cu. m
B. CONCRETE WORKS
FOOTING (@24 units)
1.5 m
1.5 m
2
0.9 m
0.1 m
1. 0 m
COST:
WALL FOOTING
TOTAL LENGTH = 89.6 m
THICKNESS = 0.20 m
WIDTH = 0. 30 m
COST:
3
SUB TOTAL: 13,500 + 2,100 + 5,400 + 350 + 650 = 22,000 pesos
FLOOR SLAB
o GROUND FLOOR
COST:
SECOND FLOOR
FLOOR AREA = 137.2 sq. m
THICKNESS = 0.15 m
COST:
CONCRETE COLUMN
21 columns = h1
3 columns = h2
4
HEIGHT1 = 3.95 + 2.7 = 6.65 m for 21 columns
0.3 m
0.3 m
COST:
CONCRETE BEAM
TOTAL LENGTH 1 = 128.8 m (for ground floor tie beam)
TOTAL LENGTH 2 = 116.8 m (for second floor beam)
TOTAL LENGTH 3 = 107.8 m (for roof beam)
0.3 m
0.4 m
5
VOLUME = 0.3 x 0.4 x 353.4 = 42.408 = 43 cu. m
COST:
CONCRETE STAIRS
C. STEELWORKS
6
SECOND FLOOR LINE
COST: COST:
10mm steel bar = 140 pesos 10mm steel bar = 140 pesos
pesos
TOTAL = 25,430 + 23,433 = 48,863
= 140 x 171 pcs = 23,940 pesos = 140 x 157 pcs = 21,980 pesos
#16 G.I. tie wire = 75 pesos per kg #16 G.I. tie wire = 75 pesos per kg
= 6.528 x 75 = 489.6 = 490 pesos = 6.027 x 75 = 452.025 = 453 pesos
LABOR = 350 pesos per day LABOR = 350 pesos per day
COLUMN REINFORCEMENT (16 mm steel bar)
FOREMAN = 650 pesos per day FOREMAN = 650 pesos per day
24 columns (ground floor)
+ 21
SUB TOTAL: 23,940 + 490 + 350 650columns (for second
= 25,430 pesos floor) SUB TOTAL: 21,980 + 453 + 350 + 650 = 23,433 pesos
8 steel bar for every column
COST:
@ 16 mm = 330 pesos each
SECOND FLOOR COLUMN @21 columns 168 x 330 = 55,440 pesos
LABOR = 350
FOREMAN = 650
BEAM REINFORCEMENT
SLAB REINFORCEMENT
STAIRS
D. MASONRY WORKS
NUMBER OF CHB
SECOND FLOOR LINE
GROUND FLOOR
Height = 2.6 + 0.25 = 2.85 m
8
Total length = 105.4 m
Total Area = Awall – Awindow – Adoor
Awall = 300.39 sq. m
Adoor1 @3 units = 2.10 x 0.9 = 1.89 x 3 = 5.67 sq. m
Adoor2 @5 units = 2.10 x 0.8 = 1.68 x 5 = 8.4 sq. m
Aw1 @1 units = 1.83 x 1.83 = 3.35 x 1 = 3.35 sq. m
Aw2 @5 units = 1.30 x 1.53 c= 1.99 x 5 = 9.95 sq. m
Aw3 @1 units = 0.5 x 0.5 = 0.25 x 1 = 0.25 sq. m
TOTAL AREA = 272.77 sq. m
CHB = (by area method) = 1 sq. m = 12.5 pcs of CHB
= 272.77 x 12.5 = 3,409.625 = 3,410 pieces
COST
1 CHB = 15 pesos
3,410 x 15 = 51,150 pesos
Labor = 350 pesos per day
Foreman = 650 per day
TOTAL COST = 51,150 + 350 + 650 = 52,150 pesos
SECOND FLOOR
Height = 2.7 m
Total length = 110.42 m
TOTAL AREA = Awall – Awindow – Adoor
Awall = 298.134 sq. m
Adoor1 @1 units = 2.10 x 0.9 = 1.89 x 1 = 1.89 sq. m
Adoor2 @6 units = 2.10 x 0.8 = 1.68 x 6 = 10.08 sq. m
Adoor3 @3 units = 2.10 x 0.70 = 1.47 x 3 = 4.41 sq. m
Aw1 @9 units = 1.83 x 1.83 = 3.35 x 9 = 30.15 sq. m
Aw3 @2 units = 0.5 x 0.5 = 0.25 x 2 = 0.50 sq. m
TOTAL AREA = 251.104 sq. m
CHB = (by area method) = 1 sq. m = 12.5 pcs of CHB
= 251.104 x 12.5 = 3,138.8 = 3,139 pieces
COST
1 CHB = 15 pesos
3,139 x 15 = 47,085 pesos
Labor = 350 pesos per day
Foreman = 650 per day
TOTAL COST = 47,085 + 350 + 650 = 48,085 pesos
9
GROUND FLOOR
SECOND FLOOR
GROUND FLOOR
10
Fine Sand = 700 pesos per cu. m
= 700 x 9 = 6,300 pesos
LABOR = 350 per day
FOREMAN = 650 per day
TOTAL COST = 26,250 + 6,300 + 350 + 650 = 33,550 pesos
SECOND FLOOR
E. FORMWORKS
COLUMN (0.30 x 0.30)
@6mm marine plywood formworks
o P = 2(a + b) + 0.20 =
I. EARTHWORKS
16,000 Excavation
22,600 Gravel Bedding
34,600 Final Backfilling
18,000 Gravel Bedding (Slab filling)
11
91,200 + 9,120 = 100,320
TOTAL = 100,320
32,850 Footing
183,650 Floor Slab
53,850 Concrete Column
151,850 Concrete Beam
- Concrete Stairs
- SUB TOTAL
TOTAL =
48,863 Footing
120,800 Column Reinforcement
Beam Reinforcement
Slab Reinforcement
Stairs Reinforcement
- SUB TOTAL
TOTAL =
12
TOTAL = 276,634
13