0% found this document useful (0 votes)
426 views13 pages

ESTIMATES

The document provides a cost estimate for earthworks, concrete works, and steelworks for a construction project. It includes estimates for excavation, gravel bedding, backfilling, footing, walls, slabs, columns, beams, and steel reinforcement. The total estimate for concrete works is PHP 183,650. Separate cost estimates are provided for excavation works totaling PHP 76,600, and steel reinforcement totaling PHP unknown.

Uploaded by

Raff
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
426 views13 pages

ESTIMATES

The document provides a cost estimate for earthworks, concrete works, and steelworks for a construction project. It includes estimates for excavation, gravel bedding, backfilling, footing, walls, slabs, columns, beams, and steel reinforcement. The total estimate for concrete works is PHP 183,650. Separate cost estimates are provided for excavation works totaling PHP 76,600, and steel reinforcement totaling PHP unknown.

Uploaded by

Raff
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 13

ESTIMATES

BY: MLOK

A. EARTHWORKS
 EXCAVATION
 DEPTH: 1 METER
 @ 24 UNITS
1.5 M

1.5 M

VOLUME: 1.5x1.5x1 = 2.25 cu. m

VOLUME TOTAL: 2.25 x 24 = 54 cu. m

EQUIPMENT: 1 Unit Backhoe with Operator = 15,000 per day

LABOR COST: 350 pesos per day

FOREMAN: 650 pesos per day

SUB TOTAL: 350 +15,000 + 650 = 16,000 pesos

 GRAVEL BEDDING ( For footing)


 @24 units

1.5 M

1.5 M

0.1 M GRAVEL BEDDING

VOLUME: 1.5x1.5x0.1 = 0.225 = 1 cu. m

VOLUME TOTAL: 1x24 = 24 cu. m

MATERIALS: 1 washed gravel (PASSING 3/4'”)

= 900 pesos per unit

= 900 x 24 = 21,600 PESOS

LABOR COST: 350 pesos per day

FOREMAN: 650 pesos per day

SUB TOTAL: 21,600+350+650 = 22,600 pesos

 FINAL BACKFILLING (24 units excavated)

1
0.9 m

0.1 m

1. 0 m

VOLUME = V excavated – V footing - V column – V gravel bedding

= (1.5 x 1.5 x 1) – (1.35 x 1.35 x 0.20) - (0.3 x 0.3 x 0.9) – (1.5 x 1.5 x 0.1)

= 1.5795 cu. m = 2.0 cu. m

= 2.0 x 24 units = 48 cu. m

MATERIAL: Item 200 = 700 pesos per unit

= 700 x 48 = 33,600 pesos

LABOR = 350 per day

FOREMAN = 650 per day

SUB TOTAL: 33,600 + 350 + 650 = 34,600 pesos

 GRAVEL BEDDING (For slab filling)


 DEPTH = 0.1 m
 FLOOR AREA = 184 sq. m

VOLUME = 184 x 0.1 = 18.4 cu. m

= 19 cu. m

MATERIALS = 1 washed gravel (PASSING 3/4'”)

= 900 pesos per unit

= 900 x 19 = 17,100 pesos

LABOR = 350 pesos per day

FOREMAN = 650 Pesos per day

SUB TOTAL: 17,100 + 350 + 650 = 18,100 pesos

B. CONCRETE WORKS
 FOOTING (@24 units)

1.5 m

1.5 m

2
0.9 m

0.1 m

1. 0 m

VOLUME = 1.35 x 1.35 x 0.20 = 0.3645


VOLUME TOTAL = 0.3645 x 24 = 8.748 cu. m
= 9 cu. m

CLASS A CONCRETE MIX (1:2:4)


 Cement (40 kg per Bags) = 9 x 9.0 = 81 Bags
 Sand (cubic meter) = 9 x 0.50 = 4.5 = 5 cu. m
 Gravel (cubic meter) = 9 x 1 = 9 cu. m

COST:

 Cement = 250 pesos per bag


= 250 x 81 bags = 20,250 pesos LABOR COST = 350 pesos per day
 Fine Sand = 700 pesos per cubic meter FOREMAN = 650 pesos per day
= 700 x 5 = 3,500 pesos
 Gravel = 900 pesos per cu. m
= 900 x 8 = 8,100 pesos

SUB TOTAL: 20,250 + 3,500 + 8,100 + 350 + 650 = 32,850 pesos

 WALL FOOTING
 TOTAL LENGTH = 89.6 m
 THICKNESS = 0.20 m
 WIDTH = 0. 30 m

VOLUME = 89.6 x 0.20 x 0.30 = 5.376 cu. m = 6 cu. m

CLASS A CONCRETE MIX (1:2:4)


 Cement (40 kg per Bags) = 6 x 9.0 = 54 Bags LABOR = 350 pesos per day
 Sand (cubic meter) = 6 x 0.50 = 3 cu. m FOREMAN = 650 Pesos per day
 Gravel (cubic meter) = 6 x 1 = 6 cu. m

COST:

 Cement = 250 pesos per bag


= 250 x 54 bags = 13,500 pesos
 Fine Sand = 700 pesos per cubic meter
= 700 x 3 = 2,100 pesos
 Gravel = 900 pesos per cu. m
= 900 x 6 = 5,400 pesos

3
SUB TOTAL: 13,500 + 2,100 + 5,400 + 350 + 650 = 22,000 pesos

 FLOOR SLAB
o GROUND FLOOR

 TOTAL FLOOR AREA = 184 sq. m


 THICKNESS = 0.15 m

VOLUME = 184 x 0.15 = 27.6 cu. m = 28 cu. m

CLASS A CONCRETE MIX (1:2:4)


 Cement (40 kg per Bags) = 28 x 9.0 = 252 Bags LABOR = 350 pesos per day
 Sand (cubic meter) = 28 x 0.50 = 14 cu. m FOREMAN = 650 Pesos per day
 Gravel (cubic meter) = 28 x 1 = 28 cu. m

COST:

 Cement = 250 pesos per bag


= 250 x 252 bags = 63,000 pesos
 Fine Sand = 700 pesos per cubic meter
= 700 x 28 = 19,600 pesos
 Gravel = 900 pesos per cu. m
= 900 x 28 = 25,200 pesos

SUB TOTAL: 63,000 + 19,600 + 25,200 + 350 + 650 = 108,800


pesos

 SECOND FLOOR
 FLOOR AREA = 137.2 sq. m
 THICKNESS = 0.15 m

VOLUME = 137.2 x 0.15 = 20.58 cu. m = 21 cu. m

CLASS A CONCRETE MIX (1:2:4)


 Cement (40 kg per Bags) = 21 x 9.0 = 189 Bags LABOR = 350 pesos per day
 Sand (cubic meter) = 21 x 0.50 = 10.5 cu. m = 11 cu. m FOREMAN = 650 Pesos per day
 Gravel (cubic meter) = 21 x 1 = 21 cu. m

COST:

 Cement = 250 pesos per bag


= 250 x 189 bags = 47,250 pesos
 Fine Sand = 700 pesos per cubic meter
= 700 x 11 = 7,700 pesos
 Gravel = 900 pesos per cu. m
= 900 x 21 = 18,900 pesos

SUB TOTAL: 47,250 + 7,700 + 18,900 + 350 + 650 = 74,850 pesos

TOTAL = 108,800 + 74,850 = 183,650 pesos

 CONCRETE COLUMN
 21 columns = h1
 3 columns = h2

4
HEIGHT1 = 3.95 + 2.7 = 6.65 m for 21 columns

HEIGHT2 = 3.95 m for 3 column

0.3 m

0.3 m

VOLUME1 = (0.3 x 0.3) x 6.65 x 21 = 12.57= 13 cu. m

VOLUME2 = (0.3 x 0.3) x 3.95 x 3 = 1.07 = 2 cu. m

TOTAL VOLUME = 13 + 2 = 15 cu. m

CLASS A CONCRETE MIX (1:2:4)


 Cement (40 kg per Bags) = 15 x 9.0 = 135 Bags LABOR = 350 pesos per day
 Sand (cubic meter) = 15 x 0.50 = 7.5 = 8 cu. m FOREMAN = 650 Pesos per day
 Gravel (cubic meter) = 15 x 1 = 15 cu. m

COST:

 Cement = 250 pesos per bag


= 250 x 135 bags = 33,750 pesos
 Fine Sand = 700 pesos per cubic meter
= 700 x 8 = 5,600 pesos
 Gravel = 900 pesos per cu. m
= 900 x 15 = 13,500 pesos

SUB TOTAL: 33,750 + 5,600 + 13,500 + 350 + 650 = 53,850 pesos

 CONCRETE BEAM
 TOTAL LENGTH 1 = 128.8 m (for ground floor tie beam)
 TOTAL LENGTH 2 = 116.8 m (for second floor beam)
 TOTAL LENGTH 3 = 107.8 m (for roof beam)

TOTAL LENGTH = 128.8 + 116.8 + 107.8 = 353.4 m

0.3 m

0.4 m

5
VOLUME = 0.3 x 0.4 x 353.4 = 42.408 = 43 cu. m

CLASS A CONCRETE MIX (1:2:4)


 Cement (40 kg per Bags) = 43 x 9.0 = 387 Bags LABOR = 350 pesos per day
 Sand (cubic meter) = 43 x 0.50 = 21.5 = 22 cu. m FOREMAN = 650 Pesos per day
 Gravel (cubic meter) = 43 x 1 = 43 cu. m

COST:

 Cement = 250 pesos per bag


= 250 x 387 bags = 96,750 pesos
 Fine Sand = 700 pesos per cubic meter
= 700 x 22 = 15,400 pesos
 Gravel = 900 pesos per cu. m
= 900 x 43 = 38,700 pesos

SUB TOTAL: 96,750 + 15,400 + 38,700 + 350 + 650 = 151,850


pesos

 CONCRETE STAIRS

C. STEELWORKS

 TOTAL LENGTH = 1.5 – 2(0.075) = 1.35


 FOOTING (24 units, @12mm)  CUT BARS = 10 pcs
1.5 m
= 10 x 2 = 20 pcs cuts of 12mm at every footing
 TOTAL NO. OF CUTS = 20 x 24 = 480 pcs
 @6m L steel bar
1.5 m =6m/1.35 = 4.44 = 4 pcs
= 480/4 = 120 pcs steel bar
TIE WIRES:
 @10 Cut bars = 10 x 10 = 100 intersections of steel bars to be tied per footing
COST: = 100 x 24 = 2,400 ties
 @ 30 cm long tie wire = 2,400 x 0.30 = 720 m G.I tie wires
 12mm steel bar = 195 pesos  @ 1 kg = 53 m long = 720/53 = 13.58 = 14 kg G.I tie wire
= 195 x 120 pcs = 23,400 pesos
 #16 G.I. tie wire = 75 pesos per kg
 = 14 x 75 = 1,050 pesos
 LABOR = 350 pesos per day
 FOREMAN = 650 pesos per day

SUB TOTAL: 23,400 + 1,050 + 350 + 650 = 24,450 pesos

 REINFORCING BAR FOR CHB = 10mm

6
SECOND FLOOR LINE

FINISH FLOOR LINE

FOR GROUND FLOOR FOR SECOND FLOOR

 TOTAL LENGTH = 105.4 m  TOTAL LENGTH = 110.42 m


 HEIGHT = 2.60 + 0.25 = 2.85 m  HEIGHT = 2.70 m
 TOTAL AREA = Awall – Awindow – Adoor  TOTAL AREA = Awall – Awindow – Adoor
 Awall = 300.39 sq. m  Awall = 298.134 sq. m
 Adoor1 @3 units = 2.10 x 0.9 = 1.89 x 3 = 5.67 sq. m  Adoor1 @1 units = 2.10 x 0.9 = 1.89 x 1 = 1.89 sq. m
 Adoor2 @5 units = 2.10 x 0.8 = 1.68 x 5 = 8.4 sq. m  Adoor2 @6 units = 2.10 x 0.8 = 1.68 x 6 = 10.08 sq. m
 Aw1 @1 units = 1.83 x 1.83 = 3.35 x 1 = 3.35 sq. m  Adoor3 @3 units = 2.10 x 0.70 = 1.47 x 3 = 4.41 sq. m
 Aw2 @5 units = 1.30 x 1.53 c= 1.99 x 5 = 9.95 sq. m  Aw1 @9 units = 1.83 x 1.83 = 3.35 x 9 = 30.15 sq. m
 Aw3 @1 units = 0.5 x 0.5 = 0.25 x 1 = 0.25 sq. m  Aw3 @2 units = 0.5 x 0.5 = 0.25 x 2 = 0.50 sq. m
 TOTAL AREA = 272.77 sq. m  TOTAL AREA = 251.104 sq. m
 @0.80 m vertical spacing = 1.60 sq. m (Table 3-5)  @0.80 m vertical spacing = 1.60 sq. m (Table 3-5)
= 272.77 x 1.60 = 436.432 m = 251.104 x 1.60 = 401.77 m
 @horizontal bars at 3 every layers = 2.15 sq. m (table 3-5)  @horizontal bars at 3 every layers = 2.15 sq. m (table 3-5)
= 272.77 x 2.15 = 586.46 m = 251.104 x 2.15 = 539.87 m
 TOTAL STEEL BAR = 436.432 + 586.46 = 1,022.89 m  TOTAL STEEL BAR = 401.77 + 539.87 = 941.64 m
= 1,022.89 /6.00 = 170.48 = 171 pcs. @10mm x 6m long = 941.64 /6.00 = 156.94= 157 pcs. @10mm x 6m long

TIE WIRES: TIE WIRES:


 AREA OF WALL = 272.77 sq. m  AREA OF WALL = 251.104 sq. m
 @80 vertical spacing and 3 layers horizontal spacing at 30 cm long  @80 vertical spacing and 3 layers horizontal spacing at 30 cm long
tie wire = 0.024 tie wire tie wire = 0.024 tie wire
= 272.77 x 0.024 = 6.528 kgs. #16 G.I. wire = 251.104 x 0.024 = 6.027 kgs. #16 G.I. wire

COST: COST:
 10mm steel bar = 140 pesos 10mm steel bar = 140 pesos
 pesos
TOTAL = 25,430 + 23,433 = 48,863
= 140 x 171 pcs = 23,940 pesos = 140 x 157 pcs = 21,980 pesos
 #16 G.I. tie wire = 75 pesos per kg  #16 G.I. tie wire = 75 pesos per kg
= 6.528 x 75 = 489.6 = 490 pesos = 6.027 x 75 = 452.025 = 453 pesos
 LABOR = 350 pesos per day  LABOR = 350 pesos per day

 COLUMN REINFORCEMENT (16 mm steel bar)
FOREMAN = 650 pesos per day  FOREMAN = 650 pesos per day
 24 columns (ground floor)
 + 21
SUB TOTAL: 23,940 + 490 + 350 650columns (for second
= 25,430 pesos floor) SUB TOTAL: 21,980 + 453 + 350 + 650 = 23,433 pesos
 8 steel bar for every column

0.4 m Dowel for 2nd floor 0.30 m


0.15 Concrete slab
0.30 m
0.4 m BEAM
TOTAL HEIGHT 1 = 0.4 + 0.4 + 2.85 + 1.0 + 0.20 = 4.85 m
 @8 steel bar for every column = 8 x 24 = 192 pcs
7
2.85 m COST:
 @ 16 mm = 330 pesos each
 192 x 330 = 63,360 pesos
 LABOR = 350
GROUND FLOOR LINE  FOREMAN = 650

1.0 m TOTAL HEIGHT 2 = 0.4 + 0.4 + 2.70 = 3.5 m


 @8 steel bar for every column = 8 x 21 = 168 pcs
0.20 m

COST:
 @ 16 mm = 330 pesos each
SECOND FLOOR COLUMN @21 columns  168 x 330 = 55,440 pesos
 LABOR = 350
 FOREMAN = 650

TOTAL COST = 63,360 + 55,440 + 350(2) + 650(2) = 120,800 pesos

 BEAM REINFORCEMENT
 SLAB REINFORCEMENT
 STAIRS

D. MASONRY WORKS

 NUMBER OF CHB
SECOND FLOOR LINE

FINISH FLOOR LINE

 GROUND FLOOR
 Height = 2.6 + 0.25 = 2.85 m

8
 Total length = 105.4 m
 Total Area = Awall – Awindow – Adoor
 Awall = 300.39 sq. m
 Adoor1 @3 units = 2.10 x 0.9 = 1.89 x 3 = 5.67 sq. m
 Adoor2 @5 units = 2.10 x 0.8 = 1.68 x 5 = 8.4 sq. m
 Aw1 @1 units = 1.83 x 1.83 = 3.35 x 1 = 3.35 sq. m
 Aw2 @5 units = 1.30 x 1.53 c= 1.99 x 5 = 9.95 sq. m
 Aw3 @1 units = 0.5 x 0.5 = 0.25 x 1 = 0.25 sq. m
 TOTAL AREA = 272.77 sq. m
 CHB = (by area method) = 1 sq. m = 12.5 pcs of CHB
= 272.77 x 12.5 = 3,409.625 = 3,410 pieces
 COST
 1 CHB = 15 pesos
 3,410 x 15 = 51,150 pesos
 Labor = 350 pesos per day
 Foreman = 650 per day
 TOTAL COST = 51,150 + 350 + 650 = 52,150 pesos

 SECOND FLOOR
 Height = 2.7 m
 Total length = 110.42 m
 TOTAL AREA = Awall – Awindow – Adoor
 Awall = 298.134 sq. m
 Adoor1 @1 units = 2.10 x 0.9 = 1.89 x 1 = 1.89 sq. m
 Adoor2 @6 units = 2.10 x 0.8 = 1.68 x 6 = 10.08 sq. m
 Adoor3 @3 units = 2.10 x 0.70 = 1.47 x 3 = 4.41 sq. m
 Aw1 @9 units = 1.83 x 1.83 = 3.35 x 9 = 30.15 sq. m
 Aw3 @2 units = 0.5 x 0.5 = 0.25 x 2 = 0.50 sq. m
 TOTAL AREA = 251.104 sq. m
 CHB = (by area method) = 1 sq. m = 12.5 pcs of CHB
= 251.104 x 12.5 = 3,138.8 = 3,139 pieces
 COST
 1 CHB = 15 pesos
 3,139 x 15 = 47,085 pesos
 Labor = 350 pesos per day
 Foreman = 650 per day
 TOTAL COST = 47,085 + 350 + 650 = 48,085 pesos

TOTAL = 52,150 + 48,085 = 100,235 PESOS

 MORTAR (by area method)

9
 GROUND FLOOR

 Area of the wall = 272.77 sq. m


 For class B mixture: (10cmx20cmx40cm CHB)
 CEMENT (0.522sq.m) = 272.77 x 0.522 = 142.38594 = 143 bags
 SAND (0.0435sq.m) = 272.77 x 0.0435 = 11.87 = 12 cu. m
 Cost
 Cement = 250 pesos per bag
= 250 x 143 = 35,750 pesos
 Fine Sand = 700 pesos per cu. m
= 700 x 12 = 8,400 pesos
 LABOR = 350 per day
 FOREMAN = 650 per day
 TOTAL COST = 35,750 + 8,400 + 350 + 650 = 45,150 pesos

 SECOND FLOOR

 Area of the wall = 251.104 sq. m


 For class B mixture: (10cmx20cmx40cm CHB)
 CEMENT (0.522sq.m) = 251.104 x 0.522 = 131.076 = 132 bags
 SAND (0.0435sq.m) = 251.104 x 0.0435 = 10.92 = 11 cu. m
 Cost
 Cement = 250 pesos per bag
= 250 x 132 = 33,000 pesos
 Fine Sand = 700 pesos per cu. m
= 700 x 11 = 7,700 pesos
 LABOR = 350 per day
 FOREMAN = 650 per day
 TOTAL COST = 33,000 + 7,700 + 350 + 650 = 41,700 pesos

TOTAL = 45,150 + 41,700 = 86,850 PESOS


 PLASTERING (16 mm thickness)
 By area method

 GROUND FLOOR

 Area of the wall = 272.77 sq. m


= 272.77 x 2(sides) = 545.54 sq. m
 For class B mixture:
 CEMENT (0.192) = 545.54 x 0.192 = 104.744 = 105 bags
 SAND (0.016) = 545.54 x 0.016 = 8.729 = 9 cu. m
 Cost
 Cement = 250 pesos per bag
= 250 x 105 = 26,250 pesos

10
 Fine Sand = 700 pesos per cu. m
= 700 x 9 = 6,300 pesos
 LABOR = 350 per day
 FOREMAN = 650 per day
 TOTAL COST = 26,250 + 6,300 + 350 + 650 = 33,550 pesos

 SECOND FLOOR

 Area of the wall = 251.104 sq. m


= 251.104 x 2(sides) = 502.208 sq. m
 For class B mixture:
 CEMENT (0.192) = 502.208 x 0.192 = 96.4239 = 97 bags
 SAND (0.016) = 502.208 x 0.016 = 8.035= 8 cu. m
 Cost
 Cement = 250 pesos per bag
= 250 x 97 = 24,250 pesos
 Fine Sand = 700 pesos per cu. m
= 700 x 8 = 5,600 pesos
 LABOR = 350 per day
 FOREMAN = 650 per day
 TOTAL COST = 24,250 + 5,600 + 350 + 650 = 30,850 pesos

TOTAL = 33,550 + 30,850 = 64,400 PESOS

E. FORMWORKS
 COLUMN (0.30 x 0.30)
@6mm marine plywood formworks
o P = 2(a + b) + 0.20 =

TOTAL COST FOR EVERY WORKS

I. EARTHWORKS

16,000 Excavation
22,600 Gravel Bedding
34,600 Final Backfilling
18,000 Gravel Bedding (Slab filling)

91,200 SUB TOTAL

10% Overhead, Contingencies, Miscellaneous


91,200 x 0.10 = 9,120

11
91,200 + 9,120 = 100,320

TOTAL = 100,320

II. CONCRETE WORKS

32,850 Footing
183,650 Floor Slab
53,850 Concrete Column
151,850 Concrete Beam
- Concrete Stairs

- SUB TOTAL

10% Overhead, Contingencies, Miscellaneous


- x 0.10 = -

TOTAL =

III. STEEL WORKS

48,863 Footing
120,800 Column Reinforcement
Beam Reinforcement
Slab Reinforcement
Stairs Reinforcement

- SUB TOTAL

10% Overhead, Contingencies, Miscellaneous


- x 0.10 = -

TOTAL =

IV. MASONRY WORKS

100,235 CHB Wall


86,850 Mortar
64,400 Plastering

251,485 SUB TOTAL

10% Overhead, Contingencies, Miscellaneous


251,485 x 0.10 = 25,148.5 = 25,149 pesos
251,485 + 25,149 = 276,634 pesos

12
TOTAL = 276,634

13

You might also like