S.K. Nirmani - FGS:MBA:2021:196
S.K. Nirmani - FGS:MBA:2021:196
S.K. Nirmani - FGS:MBA:2021:196
1
Table of Contents
Introduction .......................................................................................................................... 4
Conclusion .......................................................................................................................... 21
References ........................................................................................................................... 22
2
List of Figures
List of Tables
3
Introduction
Project Feasibility
Implementing the Customer Relationship Management (CRM) system in this organisation requires
an in-depth feasibility study due to the number of evolving parts. For the success of this project
number of factors such as, financial, legal, operational and time related constraints must be taken
into account.
This project's technological viability is supported by the availability of high-quality CRM software
solutions that can be tailored to meet the requirements of the organization. The software is adapted
to the retail firm's specific requirements in terms of customer and inventory management. The
CRM can also be expanded as needed to meet the company's evolving requirements.
Financial gains might be expected from the implementation of a CRM system. Increasing sales is
a natural result of enhancing customer service and reduce the delay of production by streamline
the process. The CRM system is meant to boost corporate output by decreasing the amount of time
spent on mundane tasks and improving the quality of customer data for use in strategic decision
making. The company should see a profit after expenses are cut and sales are boosted.
The privacy regulations and General Data Protection Regulation (GDPR) must be carefully
adhered to the CRM system. In order to achieve that the company needs the advice of legal experts
and data protection specialists to store, handle, and disseminate data in accordance with such
applicable laws. The company's cash and good name is safe if legal measures are taken.
4
Operational Feasibility of the Project
By syncing the CRM with the rest of the system, we can minimise disruptions to productivity. After
the link is made, employees have quick and easy access to customer information and be able to
make full use of the CRM system's functionalities. The company also provide training so that
workers can make good use of the CRM system.
Within four months, the organisation should have the CRM system up and running and reaping its
benefits. The project schedule will account for the time needed to choose software, modify it,
migrate data, train staff, and maintain the system. This schedule guarantees the project's successful
conclusion without sacrificing quality or efficiency.
The Statement of Work (SOW) and Work Breakdown Structure (WBS) define the project's scope,
deliverables, timetable, and achievable tasks.
Objective: The principal aim is to deploy a Customer Relationship Management (CRM) system
that efficiently oversees customer engagements, simplifies procedures, and amplifies profitability
for the retail enterprise of moderate size.
The process of choosing a customer relationship management (CRM) software that is tailored to
the unique requirements of an organisation.
5
Customization to match the organization's business processes, data migration from existing
systems to the new CRM system, employee training, and system maintenance and support are all
crucial steps in CRM system implementation.
6
4.4 Provide ongoing support and 5 1 4.2
resources
5 System maintenance 15 3
5.1 Implement monitoring tools 5 1 4.4
5.2 Schedule routine maintenance 5 1 5.1
5.3 Address system issues and updates 5 1 5.2
6 Project closure 15 3
6.1 Evaluate project performance 5 1 5.3
6.2 Document lessons learned 5 1 5.3
6.3 Celebrate project success 5 1 6.2
Network Diagram
The Network Diagram shows project operations while the Responsibility Matrix allocates team
members to tasks.
The following table shows the EST, LST, EFT, and ST for each activity in the Work Breakdown
Structure (WBS) needed to create a Network Diagram.
7
Table 2: Network Diagram Calculations
Task No. Task Description Duration Predecessors EST EFT LST LFT Slack = Slack =
(weeks) LFT- EFT LST -
EST
1 Project initiation 3
1.1 Develop project charter 1 0 1 0 1 0 0
1.2 Identify stakeholders 1 1.1 1 2 1 2 0 0
1.3 Establish project team 1 1.2 2 3 2 3 0 0
2 CRM selection and 4
customization
2.1 Assess software options 1 1.3 3 4 3 4 0 0
2.2 Select CRM software 1 2.1 4 5 4 5 0 0
2.3 Customize software to 2 2.2 5 7 5 7 0 0
meet organizational needs
3 Data migration 3
3.1 Evaluate existing data 1 2.3 7 8 7 8 0 0
3.2 Develop data migration 1 3.1 8 9 8 9 0 0
plan
3.3 Migrate data to the new 1 3.2 9 10 9 10 0 0
CRM system
4 Employee training 4
8
4.1 Develop training 1 3.3 10 11 10 11 0 0
materials
4.2 Schedule training sessions 1 3.3 10 11 10 11 0 0
4.3 Conduct training sessions 1 4.2 11 12 11 12 0 0
4.4 Provide ongoing support 1 4.2 11 12 11 12 0 0
and resources
5 System maintenance 3
5.1 Implement monitoring 1 4.4 12 13 12 13 0 0
tools
5.2 Schedule routine 1 5.1 13 14 13 14 0 0
maintenance
5.3 Address system issues and 1 5.2 14 15 14 15 0 0
updates
6 Project closure 3 0 0
6.1 Evaluate project 1 5.3 15 16 15 16 0 0
performance
6.2 Document lessons learned 1 5.3 15 16 15 16 0 0
6.3 Celebrate project success 1 6.2 16 17 16 17 0 0
• EST is the earliest a task can start. It's based on its predecessor(s)' EFT. A task's EST is its predecessors' maximum EFT. Any task without a
predecessor has an EST of 0.
o EST + task duration = EFT. It indicates the earliest possible work completion.
9
• LST: The latest time a task can start without delaying the project. Subtract the task's duration from its Late Finish Time (LFT). LST = EST for
the last task or any task without a successor.
• LFT: The latest time a task can be done without delaying the project. Its successor(s)' Late Start Time (LST) determines it. A task's LFT is the
least LST of its successors. LFT = EFT for the last task or any task without a successor.
• Slack (or Float): How long the project team may delay a task without delaying the project. EST minus LST (or EFT minus LFT) yields it. Critical
route tasks have zero slack.
10
Figure 1: Project Network Diagram
The Network Diagram would show task sequence, critical path, and potential bottlenecks.
11
Project Critical Path
The critical path is the longest path from the start to the finish of the project with zero slack. The duration of this path is 17 weeks, which indicates the
minimum time required to complete the project.
12
Project Gannt Chart
13
Figure 6: Project Gantt Chart Part 04
Responsibility Matrix
The Responsibility Matrix assigns tasks to appropriate team members, encouraging responsibility
and project efficiency.
A complete SOW, WBS, Network Diagram, and Responsibility Matrix can help the project team
plan and implement the CRM system. This method will allow the team to execute all tasks within
the project's scope and deadline.
The project's Responsibility Matrix shows who handles which team responsibility.
14
2.3 Customize X X
software to meet
needs
2.4 Test CRM X X
software
customization
2.5 Review and X X
approve
customization
3.1 Evaluate X
existing data
3.2 Develop data X
migration plan
3.3 Clean and X
prepare data for
migration
3.4 Migrate data to X X X
new CRM
system
3.5 Verify data X X
migration
4.1 Develop training X
materials
4.2 Schedule X X
training sessions
4.3 Conduct training X
sessions
4.4 Evaluate training X X
effectiveness
4.5 Provide ongoing X X X
support and
resources
5.1 Implement X X
monitoring tools
5.2 Schedule routine X X
maintenance
15
5.3 Address system X X
issues and
updates
6.1 Evaluate project X
performance
6.2 Document X
lessons learned
6.3 Conduct project X X X X X
review meeting
6.4 Prepare project X
closure report
6.5 Celebrate project X X X X X
success
The matrix assigns team members to tasks, encouraging responsibility and ensuring adequate
resource allocation.
The project budget estimates software licencing, modification, training, and maintenance costs.
Cost distribution entails funding project stages.
Below is the CRM implementation budget and cost breakdown. Software licencing, modification,
training, and maintenance are budgeted. Cost distribution entails funding project stages.
16
Cost Distribution Plan:
The budget and cost distribution plan details CRM project costs. The project team can optimise
resource use and financial planning by implementing a fund management system to allocate and
manage financial resources across stages.
Quality management for CRM deployment is detailed below. The proposed plan ensures the CRM
system meets the company's demands. Tables show quality objectives, assurance, and control.
Quality Objectives:
17
Quality Assurance:
Quality Control:
This quality management plan ensures the CRM system meets the company's requirements. This
plan helps the project team monitor the CRM system's quality throughout its existence.
Below is the CRM installation risk management plan. The proposed technique involves risk
identification, impact assessment, and mitigation. Tables clarify risk and mitigation techniques.
18
Risk Identification:
Risk Assessment:
19
Risk management can assist identify, assess, and manage CRM implementation project risks. This
method helps the project team manage risks and increase project success.
Below is a detailed CRM deployment project communications strategy. The proposed plan outlines
how project stakeholders will get updates, progress, and difficulties. Tables clarify communication
objectives, methodologies, and stakeholder identification.
Communication Objectives:
Objective Description
Information Keep stakeholders informed about project status, progress, and issues
Engagement Engage stakeholders in decision-making, problem-solving, and feedback
processes
Documentation Maintain a record of project communication for reference, tracking, and
future projects
Communication Methods:
20
Project Team Execution of project tasks Regular Meetings, Email Bi-weekly, As
Updates needed
Employees CRM system users, Email Updates, Progress As needed,
training Reports Monthly
Vendors CRM software and Email Updates, Regular As needed, Bi-
services Meetings weekly
This CRM deployment communication plan informs and involves stakeholders. This technique
ensures clear and efficient communication, improving teamwork and project success.
Conclusion
21
References
Chen, I. J., & Popovich, K. (2003). Understanding customer relationship management (CRM):
People, process and technology. Business Process Management Journal, 9(5), 672-688.
https://doi.org/10.1108/14637150310496758
Dyche, J. (2002). The CRM Handbook: A Business Guide to Customer Relationship Management.
Addison-Wesley.
Peppers, D., & Rogers, M. (2016). Managing Customer Experience and Relationships: A Strategic
Framework. John Wiley & Sons.
Vukšić, V. B., Bach, M. P., & Popovič, A. (2013). Supporting performance management with
business process management and business intelligence: A case analysis of integration and
orchestration. International Journal of Information Management, 33(4), 613-619.
https://doi.org/10.1016/j.ijinfomgt.2013.03.003
22