Technical Rider Prometheus'22
Technical Rider Prometheus'22
Technical Rider Prometheus'22
Show: "Prometheus`22"
COMPANY
1. Theatre’s name: Hungarian Theatre of Cluj
2. Address: Str. Emil Isac nr.26-28 Cluj-Napoca, Romania
3. Director:Gábor Tompa
4. Contact person: Zoltán Csép tel: 0040-742-557857
E-mail:[email protected] [email protected]
5. Technical manager: Levente Borsos tel: 0040-744-392673
E-mail: [email protected]
INFORMATION ABOUT THE SHOW
1. Title: Prometheus`22
Required dimensions:
Stage opening 10mx6m
Stage’s dimension 18mx16m
Height of grid: 12m min.
Fly line drift 11m
Batten lenght 12m
Batten capacity 150kg min.
Stage:
General remarks:
• The stage and the fly bars will be entirely clear before the coming of the technical crew.
• Allow a ramp or a fork lift for loading/unloading.
• Unless verbal agreement between both venues, the schedule of the technical rider must be respected.
• Black, even floor (a 1% rake is accepted)
• Cleaning the stage is necessary before rehearsals and performances
• The use of the auditorium is necessary, a middle corridor is necessary
• There will be water on stage
• As the production uses smoke effects the venue smoke detectors should be isolated prior to the show
• We must screw the set elements to the floor
• 10 chairs on stage, behind the set
• An adequate place with table, chair in the lobby for our promotional materials
• There are scenes in which the actors are smoking
• Please provide a Genie lift (Genie aerial work platform AWP20-S) will be used by actors as part of the set
Equipment required:
Quantity Equipment Description
1 Genie AWP-20S Needed as part of the set
1 Set of black backdrop, legs, suffites
2 Ladder(s) Height of work: 8 m
3 Automatic screwdriver
4 Props table(s) 1mx1m
5 Dressing room(s) minimum With mirrors, table, towels, drinking water, shower
1 Washing machine
1 Dryer
2 Iron and iron board
2 Hair dryer
1 Electric shaver
1 Hair-curler
Props:
To provide for each rehearsal and performance (will be discussed separately):
Quantity Equipment Description
Light:
General remarks:
• All spotlights will be provided with clamps, safety cables, colour frames, iris and all necessary accessories.
The equipment will be supplied with the necessary cables.
- All the devices of the company have a Schucko connector, 220V, 50Hz in case of differences please
provide adequate adaptors for them
Sound:
Equipment required:
Quantity Equipment Description
1 Main Mixing board 16 in, 8 buses
FOH Nexo Ps15-series or similar (LRC plus Ls500 subs)
4 Active speaker Stage monitoring, behind the set
Wireless lavalier mics, bodypack transmitters,
4 Sennheiser ew500 series
receivers
3 Sennheiser ew500 series Wireless handheld microphone, receiver
4 Intercom Light booth, sound booth, stage manager, fly man
2 Intercom Stage, wireless!
- All the devices of the company have a Schucko connector, 220V, 50Hz in case of differences please
provide transformers, adequate adaptors for them
Video:
Equipment required:
7000Ansi min. with different lenses (choosing the
2 Video projector right one depends on the position of the projector for
the subtitles and the projected film during the show)
It will be hanged on a fly bar above the audience area
2 Hanging system for the projector
or from FOH
1 Video camera For stage monitoring
2 Tv set Min 37cm for stage monitoring (behind the set)
The necessary cables for video
Subtitles – ( performance in Hungarian, Romanian, Slovenian and English with Hungarian, Romanian and
Slovenian subtitles)
Equipment required:
1 Laptop For ppt files with Resolume
2 TV-set On stand stage left and right
1 Video projector For subtitles
1 Video screen Above the stage (front) for subtitles
Dressing rooms:
General remarks:
• All dressing rooms fitted with toilet, shower, table, mirror, make up light, keys.
• Space for 7 actors, 9 actress
• Separate room for the technical crew (9 persons)
• Still water and towels will be provided.
Schedule:
Chiefectrician
Maintenance/
cleaning man
Technician
Electrician
chief/Tech
Required technicians.
Prop man
Date Timetable Description
Dresser
Flyman
Sound
Crew
9h– 10h Unloading,get in 1 6 1 1 1 1 1
Day 1 10h – 13h Set up, lights set up also 1 4 1 1 1 2 1 1
14h – 18h Set up goes on 1 4 1 1 1 2 1 1
Set up goes on, focusing,
19h – 22h 1 1 1 1 1 2 1 1
cuing
Day 2
10h – 11h Technical rehearsal 1 1 1 1 1 2 1 1 3
11h – 16h Rehearsal 1 1 1 1 1 2 1 1
16h – 17h Corrections 1 1 1 1 1 2 1 1 3
18.30h Doors opening
19h – Performance 1 1 1 1 1 2 1 1 3