DPR_Behu_ Camp Construction-Ch.

212+200 DPR Date: 21-08-2023

Camp construction upto:-15 Oct 2023 Overall responsibility: Mr.Manoj Uniyal


Target date to Balance/
Sr. Item Description Units Scope Executed Responsible Person Remarks
complete Status
1 Land identification for camp 9-Jun-23 Acre 33 33 -
2 Land lease 20-Jun-23 Acre 33 33 -
3 Boundary wall 31-Aug-23 Rmt 2,200 800 1,400

4 Development of Pathway/Drainage 15-Sep-23 Rmt -


Mr.S.N Mishra

5 Bore well for water 31-Aug-23 Nos 3 1 2

6 Electric connection (500 KW) 10-Sep-23 Nos 1 1

Blocks
Civil work status

Truss
Target to complete in Foundation Flooring Electrical & Responsible
Sr. Item Description Excavation PCC Floor PCC RCC Column Panel Erection Erection+Sheet False ceiling Finishing work Remarks
all aspect (Brick Work/RCC) /Tiling Plumbing Person
fixing
1 Security cabin 31-Aug-23 Completed Completed Completed Completed Completed Completed Completed
2 Admin Office 25-Sep-23 Completed Completed Completed
3 Laboratory 15-Sep-23
4 Mess 20-Sep-23
5 Store 20-Sep-23
6 Workshop 15-Oct-23
7 Guest House 15-Oct-23 Completed Completed Completed
8 Manager Block 10-Sep-23 Completed Completed Completed Completed
9 Engineer Block-1 5-Sep-23 Completed Completed Completed Completed Completed Completed Completed Plumbing WIP
10 Engineer Block-2 10-Sep-23 Completed Completed Completed
11 Supervisor Block-1 5-Sep-23 Completed Completed Completed Completed Completed Completed Completed Mr.Arvind
12 Supervisor Block-2 5-Sep-23 Completed Completed Completed Completed WIP WIP Kumar Sinha
13 Supervisor Block-3 5-Sep-23 Completed Completed Completed Completed
14 Supervisor Block-4 10-Sep-23 Completed Completed Completed Completed
15 Supervisor Block-5 15-Sep-23 Completed Completed Completed
16 Supervisor Block-6 15-Sep-23 Completed Completed Completed
17 Toilet Block 5-Sep-23 Completed Completed Completed Plumbing WIP
18 STP 4-Sep-23 Completed Completed Completed Completed Completed Slab work completed
19 Labor Blocks-1 15-Sep-23
19 Labor Toilet block 14-Sep-23

19 Parking yard 31-Aug-23

Plant Foundation Construction and Erection


Civil work Mobilization and Erection

Target to complete in Excavation & RCC Foundation Plant Mobilization Status for Plant Status for Plant
Sr. Item Description Apply of CTE Apply of CTO Responsible Person Remarks
all aspect Foundation PCC Construction status Erection Commissioning

1 RMC -30 CPH 15-Sep-23 Reached site


2 WMM- 200 TPH 30-Sep-23 Mr.S.N Mishra
3 Hot Mix Plant -200 TPH 15-Oct-23 As per availability of Plant

Yard Foundation Construction and Erection


Civil work status Shed erection

Target to complete in Mobilization of Machinery Responsible


Sr. Item Description Foundation PCC RCC Foundation Beam Flooring Mobilization Status Sheet fixing Electric work Remarks
all aspect M/c commissioning Person

1 Diesel pump 15-Oct-23 -

2 High mast (2 Nos.) 30-Sep-23 -


3 Over head tank (5 Nos.) 15-Sep-23 -

4 Weigh Bridge-1 2-Sep-23 Completed Completed Reached site Mr.S.N Mishra

5 Weigh Bridge-2 15-Oct-23

Area developement for misc etc & stacking of


6 30-Sep-23 -
materials

Note:- Target date for one time updation only

21-08-2023 Manpower engaged (Nos.) 64