SSDM Version 31697176750
SSDM Version 31697176750
PREPARED BY
CHIEF ENGINEER (SUBSTATION DESIGN) NTDC, WAPDA HOUSE LAHORE
Table of Content:
CHAPTER 1 INTRODUCTION TO SUBSTATION DESIGN STANDARD .............................................................. 1
REFERENCES: .................................................................................................................................................. 84
ANNEXURE-A: ................................................................................................................................................. 86
Substation Design Manual
1.2 Scope
This manual shall:
i. cover primary transmission and sub-transmission class substations within voltage range of
132kV ~ 500kV.
ii. deal with basic design philosophy and design practices adopted by NTDC over the past many
years.
iii. provide basic environmental consideration viz. temperature, altitude, humidity, wind speed etc.
iv. provide basic system parameters and their tolerance limits viz. frequency, voltage etc.
v. indicate equipment rating, standardized and used in NTDC network
vi. gather the maximum information at one place and makes the life of the design engineer easy
vii. not replace any international or national standard
viii. not specify the material standard specification for various material/ equipment which are
covered separately by NTDC specifications.
ix. assume that all material and equipment used in the substation is in accordance with the NTDC
specifications.
Note:
At the time of development of this document, Ultra High Voltage, 765kV has been proposed for the
evacuation of power from Dasu, hydropower projects. Therefore, only some basic parameters relating to
system has been mentioned in this document and detailed practices regarding design and material /
equipment has not been discussed.
1|Chapter1
Substation Design Manual
2|Chapter1
Substation Design Manual
3|Chapter2
Substation Design Manual
insulated Substations. The switching schemes shall generally be adopted at different voltage levels in
AIS depending on the importance of the installation.
2.3.2 Gas Insulated Substation
A gas insulated substation (GIS) is a high voltage substation in which the major structures are contained
in a sealed environment with sulfur hexafluoride gas as the insulating medium. The clearance required
for phase to phase and phase to ground for all equipment is much lower than that required in an air
insulated substation.
Gas insulated substations offer other advantages in addition to the reduced space requirements. Because
the substation is enclosed in a building, a GIS is less sensitive to pollution, as well as salt, sand or large
amounts of snow. Although the initial cost of building a GIS is higher than building an air insulated
substation, the operation and maintenance costs of a GIS are less.
2.3.3 Hybrid Substation
Beside the two basic (conventional) designs, there are also compact solutions available that can be
realized with air-insulated and/or gas insulated components. Here is HV substation portion is installed in
air on platforms instead of building.
4|Chapter2
Substation Design Manual
5|Chapter2
Substation Design Manual
3
Not used in new substation, some old substation has this switching scheme.
6|Chapter2
Substation Design Manual
7|Chapter2
Substation Design Manual
8|Chapter2
Substation Design Manual
Altitude
Suitable for outdoor installation Up to 1000 meters above sea level
Wind Load
122kg/m2 (corresponding to wind speed of
Suitable for withstanding maximum wind load
44.2 m/s
Seismic Conditions
Richter-scale up to 7 (horizontal acceleration
Suitable to withstand the seismic stress / magnitude
up to 4 m/s2 (0.4g)
Soil Bearing Capacity 0.5 to 1 kg/cm2
Enclosure Protection Class
Out Door IP 55
In Door IP 51
Metal-clad switch-gear IP 51 CH
9|Chapter2
Substation Design Manual
These limits are provided strictly for voltage regulation purposes. These limits are not to be construed as
connection system voltages.
2.8.3 Short Circuit Levels
Table 2-5: Short Circuit Level and Duration
Nominal System System Highest Three phase Symmetrical Short Circuit Current
Sr. #
Voltage (kV) Voltage (kV) Short Circuit Current (kA) Duration(sec)
1 11 12 25 3
2 33 36 25 3
3 66 72.5 31.5 1
4 132 145 40 1
5 220 245 40/50/63 1
6 500 550 50/63 1
7 765 800 63 1
10 | C h a p t e r 2
Substation Design Manual
Basic lightning impulse insulation levels (BIL) are specified with respect to a standard 1.2/50 µs wave
shape and the basic switching impulse insulation level (BSL) is specified for 250/2500 µs impulse with
tolerances specified by IEC/IEEE.
Insulation level for low voltage less than 1kV (AC & DC) shall be 2/3kV Power frequency withstand
voltage for one minute.
2.8.7 Creepage Distance
2.8.7.1 Switchyard / Substations
i. All outdoor bushings/insulators for switchyard/substations shall have a minimum creepage /
leakage distance of 31mm/kV, system highest voltage, line to line.
4
Highest value of phase-to-phase voltage (r.m.s value) for which equipment is designed in respect of its insulation as well as other
characteristics which relates to this voltage in relevant equipment standard.
5
Insulation configuration having two phase terminals and one earth terminal. The phase terminal belongs to the same phase of a three-phase
system temporarily separated in to two independently energized parts (e.g. open switch devices)
6
ratio to phase-to-earth peak value
11 | C h a p t e r 2
Substation Design Manual
ii. All air insulated bushing / insulators mounted inside cable box/ cabinet of equipment installed
outdoors shall have minimum creepage / leakage distance of 25mm/kV, nominal voltage, line
to line.
2.8.7.2 Indoor installation
The minimum creepage/leakage distances for indoor installations shall be as under:
Table 2-9: Minimum Creepage for Indoor Installations
12mm/kV For enclosed insulators such as those installed inside a metal-clad switchgear or
cabinet which are type tested for impulse level and routine tested for power
frequency withstand test.
25mm/kV For exposed insulators such as wall mounted bushings
12 | C h a p t e r 2
Substation Design Manual
It shall be kept in consideration that breaker number is mentioned in single digit, while isolator/earthing
switch is mentioned in double digit where second digit represents bus to whom it is connected. For line
and transformer Isolators first digit represents bus number while second digit is always zero e.g D1Q10.
Also, it may be noted that the bay/dia numbering is done from left to right in increasing order.
Table 2-10: Designated Letter for different Voltage Level
Voltage Level Designation
132kV E
220kV D
500kV B
The transformer is designated as T or ATB (Auto-transformer Bank) and their numbering is done from
left to right in increasing order.
7
Applicable for tertiary winding only. The rated MVA of tertiary shall be min 1/3 of HV or LV winding capacity of auto-transformer.
8
OFAF cooling shall only be used when approved by NTDC.
9
Auto-Transformer Bank
13 | C h a p t e r 2
Substation Design Manual
14 | C h a p t e r 2
Substation Design Manual
15 | C h a p t e r 3
Substation Design Manual
drawing shall be indicated by the letter of the row and number of the column. These indications
shall be preceded by the sheet number, the drawing identification number or item identification
number.
ix. North point (reference to grid, true, or magnetic north) shall be marked on upper left corner of
the drawing.
x. Scales and lettering sizes shall be chosen appropriate for the type of drawing. All major drawings
shall be prepared on A0 paper size.
xi. All acronyms shall be expanded in the legend and notes of the drawing. Legends, notes, symbols
shall be carefully reviewed for correctness and completeness.
16 | C h a p t e r 3
Substation Design Manual
v. Neutral and Ground Connections shall be shown for all equipment or components in power
system, which have such connection.
vi. Winding connection or vector connection and associated abbreviations for transformers (power,
grounding or others), generators, reactors, capacitor banks, VTs etc., shall be shown.
vii. Ratings such as MVA/kVA capacity, ampere capacity, voltage, frequency, impedance,
interrupting capacity, transformation ratio, No. of cores, accuracy class, short time withstand
rating, inductance, resistance, capacitance, number of phases etc., shall be marked for all
equipment as applicable. The additional functions of any equipment not intended for normal use
shall be identified under “Notes & Legend” of the drawing.
viii. Busbars shall be identified with the number of phases, material/size of the conductor(s) and rated
quantities of voltage, normal current, short time withstand current and duration of short circuit.
ix. The transmission lines shall be identified with the material, size and number of the
conductor/cable and the far-end substation name.
x. Minimum information for the CTs shall be ratio (including all taps for multi-ratio CTs), accuracy
class, burden, short circuit current etc., as applicable.
xi. Minimum information for VTs shall be ratio (including extended tap, if any), accuracy class,
burden etc., as applicable.
xii. Current Transformer (CT) shall be installed towards bus bar in both Line and Transformer bay
in case no bus bar differential protection is used at the substation i.e. DISCOs Substation.
xiii. Current Transformer (CT) shall be installed towards Line/before circuit breaker in Line bay and
towards Transformer/after circuit breaker in Transformer bay when bus bar differential
protection used at the substation.
xiv. Following No. of 11kV outgoing feeders shall be shown on single line diagram with respect to
132/11.5kV Power transformer:
Table 3-1: Proposed 11kV Outgoing Feeders
Max No of Proposed 11kV Outgoing
Rating of Power Transformer (MVA)
Feeders
10/13 4
20/26 6
31.5/40 8
xv. Future expansion of the bus-bar system at least in a near future may also be considered.
3.4.2 Relaying and Metering Single Line Diagram
This will have the following requirements in addition to switching single line diagram requirements.
i. The operating source, current and/or voltage, shall be shown for instruments, meters, relays and
associated switches by connecting lines together with any transformations at all levels as
applicable. All equipment shall be shown in the diagram.
ii. Functions of relays shall be shown by the use of appropriate device numbers as per IEEE C37.2.
iii. Supplementary information (like prefix, arrow mark etc., as required) shall be added to a device
whenever needed for clarity. Graphic symbols for electrical and electronic devices that form part
of the diagram shall be in accordance with IEEE Std 315 or IEC 60617. All secondary devices
such as meters, transducers, relay operating coils etc., shall be of same size as far as possible.
iv. The number of instrument transformers and their ratios shall be shown. The connected ratio shall
be indicated for multi-ratio current transformers. Unused current transformer shall be shown as
shorted secondary. Polarity marking shall be shown for all instrument transformers.
17 | C h a p t e r 3
Substation Design Manual
v. Detailed equipment information and conductor material/size shall not be shown on Relaying and
Metering single line diagram.
vi. Appropriate numbering scheme for major electrical equipment shall be applied as specified in
Chapter No. 2.
vii. Legend and Notes of the drawing shall contain the following information:
a. Each and every relay device number and its functional designation.
b. Tripping and lockout relay function, if energization of trip coils cannot be shown in the drawing
part.
c. Each and every meter, transducer shall be identified.
3.5 General Layout Diagram
General Layout plan shows a detailed layout of proposed site and work with respect to the boundary and
vicinity. GLO is a plan which indicates what is existing, what is proposed and what is to be dismantled
as per scope of work.
For a new substation, a general layout plan shall indicate natural, geographic and humanoid neighborhood
of substation to be constructed as mentioned in submitted site/contour map. Moreover, arrangement of
switchyard, control house building, residential colony and other auxiliary structures shall be clearly
displayed with exact dimensions on the GLO plan.
For extension work in an already existing substation, the GLO plan already prepared shall incorporate all
the proposed extension work as well as indicate the structures to be dismantled through cross-hatching.
The General Layout Diagram shall be prepared as follows:
i. General Layout plan shall be drawn on a scale of 1:500 or 1:1000 as per site area.
ii. All dimensions shall be in millimeters. Dimension are measured from center to center.
iii. Legends shall be marked on the drawings with reference to the symbols used in the drawing.
iv. Physical dimensions of plot allocated for construction of G/S shall be mentioned on General
Layout Plan.
v. Temporary Benchmark (T.B.M) shall be marked on the drawing.
vi. Location of main road/highway to the plot, water bodies/Drain near or inside the plot (if located),
Location of building or any other structures such as residential colony, graveyard, bridge etc.
located adjacent to plot shall be shown on the General Layout Plan.
vii. Location of Entry gate shall be shown at a suitable place on the boundary for providing access to
the substation from approach road.
viii. Watchtower shall be shown on the boundary wall. Security guard cabin along with attached
washroom shall be shown near the main gate inside the boundary.
ix. Residential colony shall be proposed and located at a suitable place as per site keeping in mind
the best utilization of the available land and have a separate access road. Residential colony shall
not affect future extension of the switchyard.
18 | C h a p t e r 3
Substation Design Manual
10
It should be kept in consideration that standard drawings are being proposed/designed for different areas as per soil, weather conditions and
seismic and non-seismic zones as well as type of masonry/RCC for 132kV switchyard. The list of standard foundation drawing is attached as
Annex-A. All these standard drawings have been designed for bearing capacity from 0.5kg/cm² to 1.0 kg/cm². In case the soil bearing capacity
is less than 0.5kg/cm2, the standard foundation drawings are modified by the civil department as per requirements.
19 | C h a p t e r 3
Substation Design Manual
vi. The detailed information regarding civil parameters and dimension shall be mentioned on
foundation drawing of each equipment.
20 | C h a p t e r 3
Substation Design Manual
21 | C h a p t e r 4
Substation Design Manual
Figure 4-1: Classes and Shapes of Over-Voltages, Standard Voltage Shapes and Standard Withstand
Voltage Tests
22 | C h a p t e r 4
Substation Design Manual
23 | C h a p t e r 4
Substation Design Manual
CHAPTER 5 Clearances
5.1 Introduction
The definition of the required electrical clearances in air is fundamental to the design of the AIS
substation. (It should be noted that at altitudes in excess of 1000 m, the reduced air pressure results in the
need for larger clearances). The clearances are required as it is not practical to test the entire AIS
substation installation with test voltages to confirm the required insulation level.
These clearances ensure that the substation design minimizes the risk of a breakdown of insulation and
that the substation can be operated reliably. In addition, IEC 61936-1 gives some guidelines on
appropriate values which may be considered.
The design of the substation must restrict access to danger zones, taking into account the need for
operational and maintenance access.
External fences, or walls, are required particularly for AIS substations. Where safety distances cannot be
maintained, permanent protective facilities are required.
24 | C h a p t e r 5
Substation Design Manual
Range II:
The phase-to-earth air clearances for is determined from Table 5-2 for the rated switching impulse
withstand voltage.
Table 5-2: Minimum Phase to Earth Clearance for Range II
Rated Switching
Highest Rated Lightning Minimum Phase to Earth
Nominal Impulse Withstand
Voltage of Impulse Clearance
Voltage Voltage
Equipment Withstand mm
Un kV
Um Voltage
(kV) Rod-Structure Conductor-
(kV r.m.s) kV Phase to Earth
N structure
500 550 1550 1175 4100 3100
Rated Switching
Impulse Withstand Minimum Phase to Phase
Highest
Nominal Rated Lightning Voltage Clearance
Voltage of
Voltage Impulse kV mm
Equipment
Un Withstand Voltage
Um
(kV) kV Conductor-
(kV r.m.s) Rod -
Phase to Phase Conductor
Conductor
parallel
500 550 1550 1760 5000 4200
25 | C h a p t e r 5
Substation Design Manual
26 | C h a p t e r 5
Substation Design Manual
27 | C h a p t e r 5
Substation Design Manual
Where
N minimum clearance
H’ Minimum clearance of live parts above accessible surface at the external fence
a If this distance to live parts is less than H, protection by barriers or obstacles shall be provided
b If this distance is smaller than 2 250 mm, protection by barriers or obstacles shall be provided
Figure 5-3: Boundary distances and minimum height at the external fence/wall
28 | C h a p t e r 5
Substation Design Manual
29 | C h a p t e r 5
Substation Design Manual
30 | C h a p t e r 6
Substation Design Manual
indefinitely, maintaining maximum flexibility throughout each stage of expansion will ensure the least
costly and most efficient use of the facilities during the service period.
To facilitate future expansion, arrange the initial design to accommodate all requirements of a current
long-range system forecast. The site should be as large as practical to allow for future development. Large
areas readily allow for changes in the basic substation configuration and switching scheme should future
conditions so dictate. Leave at least one and preferably both ends of all major buses open for future
expansion. When a basic initial arrangement is planned, placement of equipment should take into account
future expansion of the substation into a more complex, reliable, and flexible configuration. Frequently,
additional bus supports are installed initially to facilitate future expansion.
6.2.4 Substation Profile
The profile of substation structures and equipment has become an increasingly important aspect to
consider in substation layout. In the past, large lattice and box-type structures supporting overhead strain
buses were commonly used. Most substations currently being designed and constructed use low-profile
structures and rigid bus-work. Low-profile construction generally uses lower structures with a minimum
number of members for support.
6.2.5 Equipment Removal
Substation arrangements have to include adequate space for the installation and possible removal of large
pieces of equipment such as power transformers and power circuit breakers. Buses, particularly in low
profile arrangements, even when at acceptable operating elevations, can block the removal of equipment.
Consequently, it is important to consider equipment removal routes during the structure layout. Often the
most desirable arrangement has the main buses at higher elevations than the buses and equipment in the
substation bays. In this way, the main buses will not block the removal of equipment located in the
substation interior.
Removable bus sections can also be provided to permit movement of large equipment. This, however,
requires bus de-energization during the procedure.
31 | C h a p t e r 6
Substation Design Manual
Line and transformer bays sequence should, if possible, be fixed minimizing the possibility of
overloading bus bars and or connection conductors.
It is necessary to consider in the layout design, the possibility of extension of the substation. This topic
is more important in the case of substations with ring scheme bus bars. A particular design allows for an
easy transformation from a ring scheme to a double bus bar with one and half breaker scheme.
Lightning protection is necessary to protect the substation from lightning strokes .This protection can be
arranged in either overhead earth wires. Special protection has to be paid to the elimination of the risk of
the earth wire fall down on the switchgear.
6.3.2 Secondary Circuit
In order to minimize the electromagnetic interference between primary circuit and control equipment and
for economic reasons (especially when cables are employed), an alternative is to decentralize the control,
protection and automation equipment. Following this way kiosks containing secondary equipment should
be installed as near as possible to the switching equipment. However, In hard climate conditions (very
cold/ hot), this solution may not be economic.
6.3.3 Criteria for the choice between Rigid or Flexible Conductor
At present, the substation design with voltage level up to 500kV, rigid conductors are preferred as it is
simpler and more economic. In this case aluminum alloy tubes are employed. For higher voltage levels,
it can cause more difficulty to set up tube bundle conductors with equivalent diameter suitable to contain
corona effect to an acceptable limit.
Of course, the choice of best solution is influenced by the availability of materials that’s changes from
country to country, and by different company experiences.
In the following table advantages and disadvantages of both solutions are illustrated:
Table 6-1 : Rigid Conductors Solution vs. Flexible Conductors Solution
Rigid Conductors Solution Flexible Conductors Solution
Advantages
Simplicity, easy reading of operation Use of the same material employed for overhead
configuration lines lines
Plant disposition with only two levels Bundle multiple conductors with appropriate
Easy access to the transformers or to the diameter to reduce corona effect in ultra-high
switchyard for maintenance voltage substations are easily fulfilled.
Easy use of pantograph or semi pantograph
disconnectors
Easy substation extension
Easy verification of electrodynamics forces effect
Short erection time
Lower grounding area for plant installation
Disadvantages
Uneasy temporary bypass of circuit breakers on Complex layout for simplex schemes
both sides of bus bars Difficult verification of withstand to
Possibility of mechanical resonance between the electrodynamics forces
tube structure and the wind gust frequency, can be Bus bars over passes are to be provided
prevented by suitable damping devices. Considerable environmental impact consequent
Difficulty for availability of tubes and support to three levels of conductors in the substation
material in some countries. Considerable construction cost
Difficulty in employing pantograph or semi
pantograph disconnectors
Difficulty in substation extension
32 | C h a p t e r 6
Substation Design Manual
33 | C h a p t e r 6
Substation Design Manual
34 | C h a p t e r 6
Substation Design Manual
35 | C h a p t e r 7
Substation Design Manual
36 | C h a p t e r 7
Substation Design Manual
37 | C h a p t e r 7
Substation Design Manual
38 | C h a p t e r 7
Substation Design Manual
related material and gradation requirements for the base and surface course material. Application of the
wearing courses should be made in accordance with highway standard.
7.6.5 Roadways in the Substation Yard
Many substations do not have any specific drives or roads within the fenced yard. The entire yard is
considered as drivable by light traffic.
If it is desirable to have specific drives within the fenced yard for access to transformer banks or as a
perimeter drive, the wearing surface can be the same as for the access road. The width may be reduced
to 500 cm (197”) or even less. Inside radii for interior drives may be 750 cm (295”) or less as space
allows. Culverts and cable trenches should also be designed for anticipated heavy equipment loads.
39 | C h a p t e r 7
Substation Design Manual
In addition, where structural component is exposed to a different extent on opposite faces, consideration
shall be given to the thermal effects caused by resulting temperature gradient across the structural section.
In absence of other data, a temperature difference of 15 °C shall be considered.
The table of mean temperature above may not necessarily give maximum surface temperature conditions
and reference should be made to shade temperature. Consideration shall also be given to degree to degree
of exposure during construction.
Allowance shall be made for the stresses induced in any structure due to difference in temperature
between the surface of a member or between parts of structure.
The temperature of a concrete and steel surface exposed to sunshine may be taken as 70°C maximum.
e) Seismic Loads
As per Pakistan Building Code 2007, foundations shall be designed corresponding to seismic zone
probability.
40 | C h a p t e r 7
Substation Design Manual
Figure 7-4: Seismic zoning map of Pakistan according to Building Code of Pakistan (BCP 2007).
f) Crane Loads
All crane ways shall have their design load increase for the impact as follows:
a) A vertical force equal to 25% of the maximum wheel load.
b) The lateral force 20% of the weight of the trolley and lifted load only, applied one half at top of
each rail.
c) The longitudinal force of 10% of the maximum wheel loads of the crane applied at the top of
the rail.
g) Construction loads
Consideration shall be given to construction sequence to ensure that a structure is able to carry the design
loads which act before completion of the structure and, also that exceptional loads resulting from
construction sequence are catered for. This consideration shall include dead, wind and thermal loads
together with suitable imposed loads, as appropriate.
41 | C h a p t e r 7
Substation Design Manual
Combination of Loads
All parts of structure shall be designed for the worst combination of dead, imposed and equipment loads
with temperature, wind, seismic and other effects. The following load combinations shall be considered:
D.L. + I.L
D.L. + W.L.
D.L. + I.L. + W.L.
D.L. + S.L.
D.L. + I.L. + S.L.
Where,
D.L. = Dead Load
I. L. = Imposed Load
W.L. = Wind Load
S.L. = Seismic Load
The imposed load shall include for dynamic effects where appropriate. The imposed and wind loads shall
be combined with dead load and which each other in such a way to give the worst possible stresses at any
location. In addition, thermal effects shall be considered, where significant, acting in conjunction with
the combined load cases. Load cases need not be combined arbitrarily without regard of practical
possibilities.
Foundations shall be designed by using reactions imposed by the structures they support.
7.8.1.3 Safety Factors
The factor of safety applied to the foundation design shall be greater than the factor of safety applied to
the structure design. The overall factor of safety shall not be less than 3.0 against the maximum
anticipated pressure applied to soil.
Foundation design shall be based on allowable bearing capacity of soil if working load are to
be considered.
The factor of safety against sliding shall not be less than 1.5. For overturning during construction or
erection and other non-recurring load element and for all other conditions, the factor of safety shall not
be less than 2.0 based on working loads. Passive earth pressure from backfill shall be considered in
computing these factors of safety. Unless specified otherwise in detailed soil investigation the coefficient
of friction use in computing the safety factor against for cast -in-place foundation shall be 4.0.
For shallow foundation against uplift, factor of safety shall not be less than 1.5.
Unless otherwise established by soil investigation report or actual pile load test, minimum safety factor,
against long-term operating load shall not be less than 3.0 for compression and 2.0 for uplift.
The factor of safety for bearing pressure for dead loads against soil bearing capacity shall be at least 3.0
and for combined dead and live loads, the factor of safety shall be at least 2.0.
42 | C h a p t e r 7
Substation Design Manual
43 | C h a p t e r 7
Substation Design Manual
For deep foundations such as drilled piers, the ultimate bearing capacity in cohesive and cohesion-less
soils shall be analyzed and computed.
7.8.2.4 Ground Water Table
Ground water table level is essential in foundation design because excavation below it requires
dewatering which increases the cost. It has a significant effect on the bearing capacity of shallow
foundations. The submergence of soil causes loss of all apparent cohesion and at the same time the unit
weight of submerged soil will be reduced to one half the weight of the same soil above water table. Thus,
bearing capacity shall be analyzed using the highest possible groundwater level derived from the Geo
technical Investigation report.
7.8.2.5 Differential Settlement
Clay, silt and silty sand are usually problematic soils. Weak strata of soil under a thin layer of dense or
good soil shall be carefully examined and taken in to account. To determine differential settlement
between foundations that would cause damage to support equipment, settlement shall be investigated and
reports submitted to NTDC for approval. Foundation shall be sized so that settlement under dead load
will not exceed 6m. Differential settlements of foundations for interconnected machinery is not
acceptable. Foundations for buildings shall be designed so that differential settlement will not produce
excessive stresses in structural members or cause crack in walls.
7.8.2.6 Chemical Tests
Soils may impact foundations and other buried systems as a result of chemical attack on concrete,
corrosion of steel, and other detrimental weathering. Consult a corrosion specialist or engineer familiar
with these chemical tests to determine the appropriate cement type based on prevailing solvable sulfate
and chloride ion concentrations within the soil or groundwater. Resistivity of the soil, pH, sulfides, Redox
readings, and nitrates may also have detrimental effects on concrete, steel, or grounded structures. These
conditions require localized testing and design.
7.8.2.7 Ground Improvement
Any measure taken to improve ground conditions shall be subject to approval of NTDC and in- situ test
shall be conducted to verify improvement ad results submitted for review.
7.8.3 Type of Foundations
The types of foundations mostly used for substation building structures and equipment support structure
can be summarized as following:
7.8.3.1 Drilled Piers
Drilled Piers used to support light equipment and structures having primarily horizontal and uplift loads
such as bus support and gantry structures.
7.8.3.2 Spread /isolated Footings and Mat Foundations
Spread/Isolated and Mat Foundations are usually preferred for foundation of control bu ilding and large
electrical equipment.
7.8.3.3 Pad Foundations
Pad foundations are sometimes recommended as foundations for miscellaneous equipment, and power
transformer.
44 | C h a p t e r 7
Substation Design Manual
45 | C h a p t e r 7
Substation Design Manual
7.9.2 Manholes
A companion item to some underground raceway systems is the manhole. Generally used in conjunction
with below-grade duct banks, a manhole serves as a pulling and splicing point for cable runs, as a point
to turn a duct line, and as a place to provide contraction and expansion of power conductors.
7.9.3 Hand-holes
Unlike manholes, hand-holes have a definite place in substation design. A hand-hole is essentially a
miniature manhole installed approximately 61 cm (24”) below grade and measuring about 3700
centimeter square (573.5 inch square). It serves as a pulling point for cables in a direct-burial conduit
system. To prevent floating, no bottom or floor is provided. This feature also allows easy conduit entry.
A split metal cover or a lightweight concrete cover with knockouts is used.
46 | C h a p t e r 7
Substation Design Manual
47 | C h a p t e r 7
Substation Design Manual
48 | C h a p t e r 7
Substation Design Manual
49 | C h a p t e r 7
Substation Design Manual
Windows can be provided, if desired, in office and lavatory areas. Battery rooms and control and metering
areas do not need windows.
Consider adequate methods for building insulation. These methods include use of insulated wall panels,
ceiling insulation, storm doors, and windows, and weather-stripping around all openings.
Masonry buildings may be left unpainted or may be painted with portland cement or latex paint. Tint all
prime coats to match the finished coat.
7.10.5 Control House Building Layout
The size of substation building shall provide adequate working space, height and electrical clearances for
all indoor equipment. Wherever possible, similar equipment shall be located to adjacent. Future
expansion shall be considered while allocating space to various equipment. Normally the layout plan of
two storey control house is as under:
i. Ground Floor Plan
Store, Toilet, Workshop, Battery Room, Relay Room, 5witchgear Room, Communication Room
ii. First Floor Plan
Control Room, Relay Testing Lab, Staff Room, Offices, Toilet
In a 132kV substation, single storey building is used and Relay and control panels are housed in a single
room.
iii. Equipment Arrangement
a) Relay and Control Panels
For 220kV and above substation, relay panels shall be installed in relay room while control panels shall
be installed in control room while for 132kV substations, both shall be installed in same room. A
minimum clearance of 1800 mm shall be provided between rows of panels and from wall/ columns face
which is nearest to panel. Panels associated with one feeder or transformer shall preferably be grouped
together.
b) Metal-clad Switchgear
All section of Metal-clad switchgear shall be housed in one room. The dimensions of metal-clad
switchgear cubicle and space required for removal of a circuit breaker shall vary depending of design and
rating of metal-clad switchgear or as per recommendation of manufacturer.
c) Station Battery
A separate battery room shall be provided and additional room for communication battery shall be
allocated. The battery room shall be sized according to number of battery banks, size of battery bank,
layout of racks and as to provide a clearance at least 150 cm between any battery and eye and skin wash
equipment.
The battery room shall be provided with a trapped and vented floor drain to serve eye and skin wash
facilities and wash down of electrolyte spills. The floor drain shall be connected to neutralizing pit before
connecting to drainage system.
d) Battery Charger
Battery charger is normally installed in control room while communication battery charger is installed in
communication room. Working space for battery charger shall not be less than 100 cm in any case.
50 | C h a p t e r 7
Substation Design Manual
e) Auxiliary Panels
Auxiliary AC/DC panels shall be installed in control room and 15 cm space shall be maintained between
panels to facilitate conduit connection. DC distribution panel for the communication system shall be
installed in communication room. Working space for battery charger shall not be less than 1 m in any
case.
f) Communication Equipment
A separate communication room shall be provided to accommodate communication equipment, fiber
optic terminal and carrier equipment. Cabinets and racks for communication equipment shall be of
following types:
1. Swinging-Rack Cabinet
This type can be located with its back directly against the building wall or placed side by side and still
provide convenient access to the rear of the chassis mounted on the rack. Typical dimensions of this type
of cabinets are: H 220 cm , L = 85 cm and width 65 cm.
2. Fixed Equipment Rack
This type of equipment racks shall be floor mounted and installed side by side. Back access may be
needed depending on equipment design. Typical H 220 cm
g) SCADA Equipment
SCADA equipment shall be installed in control room and manufacturer's dimensional data shall be used
for installation shall be used.
h) HVAC
Please refer to chapter No. 10
i) Fire Suppression and Detection Equipment
Please refer to chapter No. 10
51 | C h a p t e r 7
Substation Design Manual
52 | C h a p t e r 8
Substation Design Manual
The calculations involved and explanation of these factors are mentioned in the design procedure of
grounding system.
8.1.4 Components of Grounding System
A grounding system of a substation consists of the following components:
8.1.4.1 Grounding Grid /Mesh
The grounding grid/mesh is a combination of network of interconnected horizontally buried conductors
laid as far as possible at uniform spacing which is buried at a depth of 0.8m ~ 1.0 m below final ground
level (excluding the gravel) and shall encompass all of the area within the fence, and shall extend at least
l.0 meters outside the substation fence on all sides (if space permits), including all gates in any position
(open or closed) to enclose as much ground as practicable and to avoid current concentration and hence
high gradients at the grid periphery. A perimeter grid conductor shall also surround the substation
buildings, at a distance of 0.5-1.5 meters. All conductors shall be bonded at points of crossover by
thermoweld process. Following conductor size is used in NTDC network.
Table 8-1: Voltage Level and Diameter of Conductor
Voltage level (kV) Minimum Diameter of Horizontal
conductor (mm2)
132 95
220 120
500 185
8.1.4.2 Gravel
The entire area (except for roads, transformer ways etc.) inside the fence, and including a minimum of
l.0 meters outside the fence (if space permits), is surfaced with gravel of layer 200mm. For NTDC
grounding grid design, soil resistivity of gravel of 5000Ω-m shall be considered.
8.1.4.3 Grounding Rods
Grounding rods are used in a grounding system are used at the corner to avoid concentration of current
and high voltage gradient at the corners. Also, for two layer and multi-layer soil models, where the upper
layer has high soil resistivity, deep driven rods are considered so that the rod is in contact with low
resistivity lower soil layer. Other than corners they are particularly installed at following location in a
Substation:
i. For neutral grounding of a transformer
ii. Additional earthing rod near power and auto-transformer is provided for safety grounding
iii. Surge arresters are also provided with earth rods to provide low impedance path to the surges
In NTDC normally l6mm ɸx 3.0m rods are used, however length of the rod may increase depending upon
the requirement. Ground rods are installed with their top, 0.8 to 1.0 m minimum below grade and bonded
to the grounding grid by thermoweld process.
8.1.4.4 Connections
The required connections of the mesh are made through cross type connection where straight conductor
run along the perimeter.
Pigtails/risers are left at appropriate locations for grounding connections to structures or equipment. The
pigtails/risers are then readily accessible after backfilling for the above grade connections.
53 | C h a p t e r 8
Substation Design Manual
54 | C h a p t e r 8
Substation Design Manual
55 | C h a p t e r 8
Substation Design Manual
.
= ....... Eq. 8-1
where:
IB = rms magnitude of tolerable shock current through the body in Amperes.
ts = Duration of the current exposure in sec. (Shock duration).
( ) .
= ....... Eq. 8-2
( . ) .
= ....... Eq. 8-3
Where;
1000=Resistance of a human body in ohms from hand-to-both feet, from hand-to-hand, and from one foot
to the other foot.
Cs=Reduction factor for derating the nominal value of surface layer resistivity. It is 1 for no protective
surface layer (Protective layer resistivity equal to soil resistivity).
For protective surface layer of resistivity higher than soil resistivity, the value of Cs is < 1. The actual
value shall be determined by the following formula:
Where;
hs=Thickness of the soil protective surface layer in meter
Ρ=Soil resistivity in ohms-meter
ρs=Resistivity of the surfacing material in ohms-meter
For all grounding design calculations, the value of Cs can also be obtained from Figure-2 given below:
Where
To ensure safety, the actual step voltage, touch voltage, metal-to-metal touch voltage, or transferred
voltage must be less than the tolerable limits.
56 | C h a p t e r 8
Substation Design Manual
Figure 8-2: Surface Layer Derating Factor (Cs) Versus Thickness of Surface Material (hs)
Where
IG=Maximum grid current in Amperes.
Df=Decrement factor for the entire duration of fault (tf) in seconds. This accounts for the asymmetry of
the fault current, i.e. the effect of DC current offset. Df depends on system X/R ratio and fault duration.
For NTDC system with minimum shock duration of 1sec.
Ig =R.M.S symmetrical grid current in Amperes. It represents the portion of the symmetrical ground fault
current that flows between the grounding grid and surrounding ground. It can be expressed as follows:
= ⋅ ....... Eq. 8-7
Where
Sf=Current division factor relating the magnitude of fault current to that of its portion flowing between
the grounding grid and surrounding ground. This factor is normally computed as per IEEE 80. However,
for NTDC application, the minimum value of this factor shall be taken as 0.7 unless otherwise specified.
If=Breaker short circuit rating.
Taking the above definition into account maximum grid current IG shall be:
= . ⋅ ....... Eq. 8-8
4. Calculation of Grid Potential Rise (GPR)
Grid potential rise (GPR), which is given by the following formula:
= . ....... Eq. 8-9
Where:
IG = Maximum Grid Current in Amperes
Rg = Grid resistance in ohms
57 | C h a p t e r 8
Substation Design Manual
GPR shall be restricted to around 5000 V as far as possible to safe guard microprocessor based equipment
and communication equipment.
5. Calculation of Mesh Voltage (Em)
Mesh voltage Em is represented by the equation:
Where
Ρ=Soil resistivity in ohm-meter
Km=Spacing factor for mesh voltage
Ki=Corrective factor accounting for grid geometry=0.644 +0.148 x n
LM=LC + LR for grids with no ground rods, or grids with only a few rods scattered throughout the
grid but none located in the corner or along the perimeter of the grid.
Or
For grids with ground rods in the corner as well as along the perimeter and throughout the grid.
Where:
LM = Effective buried length
LC = Total length of grid conductors in meter
LR = Total length of ground rods in meter.
Lx = Maximum length of the grid in x direction in meter
Ly = Maximum length of the grid in y direction in meter
Lr = Length of each ground rod in meter
Where
Kii = Corrective weighting factor that adjusts the effect of inner conductors on the corner mesh= 1 for
grids with ground rods along the perimeter,
Or for grids with ground rods in the grid corners, as well as both along the perimeter and throughout
the grid area
1
=
(2 )
For grids with no ground rods or grids with only a few ground rods, none located in the corners or on the
perimeter
Kh = Corrective weighting factor that emphasizes the effects of grid depth
ℎ
= 1+
ℎ
58 | C h a p t e r 8
Substation Design Manual
Otherwise;
=
4. √
.
.
=
=
+
Where:
Dm= Maximum distance between any two points on the grid
A = Area of the grid in square meter
Lr = Length of each ground rod in meter
Lp = Peripheral length of the grid in meter
Where
Ls = Effective buried conductor length in meter = 0.75 LC + 0.85 LR for grids with or without ground
rods
For simplification, the maximum step voltage is assumed to occur at a distance equal to the grid depth
(h) just outside the perimeter conductor. For the usual burial depth of 0.25m < h <2.5m,
59 | C h a p t e r 8
Substation Design Manual
The following equation shall be used to evaluate the minimum conductor size (in mm²) as a function of
conductor current:
where:
If = Symmetrical ground fault current in kA. (For NTDC system this value shall be breaker rated short
circuit current)
A = Conductor cross section in mm²
Tm = Fusing temperature in °C
Ta = Ambient temperature in °C
αr = Thermal coefficient of resistivity of conductor material at reference temperature Tr
ρr = Resistivity of the ground conductor at referenced temperature Tr in microohms cm
tc = Maximum possible clearing time. This shall be taken as 1.0 (one) second.
TCAP = Thermal capacity factor from Table 10-1 in J/cm³.°C
1 1
= = −
α α
Where,
Tr =reference temperature for material constants in °C
αr = thermal coefficient of resistivity of conductor material at 0°C in 1/ ºC
Note that αr and ρr are both to be found for the same reference temperature. Table 8-2 provides the material
constants for copper wire at 20°C.
Table 8-2: Material Constants for Copper wire at 20ºC
Description Material αr factor K0 at Fusing ρr 20ºC TCAP
Conductivity at 20ºC 0ºC Temperature (μΩ-cm) thermal
(%) (1/ºC) Tm (ºC) capacity
J/(cm3.°C)
Commercial, Hard
97 0.00381 242 1084 1.78 3.42
drawn copper
Annealed Soft
100 0.00393 234 1083 1.72 3.42
drawn copper
The final choice of conductor after calculation shall be from the nearest higher sizes shown in Table 8-2.
Where
Rg = Substation ground resistance in ohm
ρ = Average ground resistivity in ohm-m
A = The area occupied by the ground grid in m²
60 | C h a p t e r 8
Substation Design Manual
LT = The total buried length of conductors in m. (In case of grid rod combination LT shall be combined
length of earthing conductor and ground rods).
h = Depth of grid in meters excluding gravel covering. This value is used for calculations even in case
the grid is partly embedded under the control building.
For 220 & 500kV substations, the ground resistance shall be equivalent to 1 ohm or less and for 132kV
substations, the ground resistance shall be equivalent to 2 ohm or less.
61 | C h a p t e r 8
Substation Design Manual
62 | C h a p t e r 8
Substation Design Manual
63 | C h a p t e r 8
Substation Design Manual
64 | C h a p t e r 9
Substation Design Manual
Act as the stabilizing winding and provide a path for zero sequence currents. Thus, the third
harmonic voltages are eliminated by circulation of third harmonic current in the short circuit
path of the delta winding.
In substation applications, to supply auxiliary loads.
The tertiary winding shall be designed to be strong enough mechanically to have requisite thermal
capacity and to have sufficient impedance with respect to two main windings to be able to withstand the
electromagnetic effects of short circuit across main windings.
Normally size of the tertiary winding is one third of the main winding. Tertiary winding is brought out
using four terminals i.e. (open delta) in case of three phase unit and delta connection is completed and
one side is grounded using following arrangements. In case of the three single phase units, the delta is
completed externally and one side is grounded as per following:
65 | C h a p t e r 9
Substation Design Manual
Based upon above analogy of system, various type of cooling methods are ‘ONAN’, ‘ONAF’, ‘OFAF’,
and ‘ONWF’ etc.
In NTDC ONAN and ONAF system is usually used and ONAF system is used in two stages i.e. ONAF1
& ONAF2 which can be controlled automatically.
For triple rated power transformers, the third rating corresponds to second stage of cooling. In order to
maintain the operational reliability of forced cooling system, 25% redundancy in forced cooling capacity
is required.
66 | C h a p t e r 9
Substation Design Manual
67 | C h a p t e r 9
Substation Design Manual
68 | C h a p t e r 9
Substation Design Manual
comprise “Minimum Oil” and “Bulk Oil” whereas oil-less comprise “Air Blast”, “Vacuum” and “SF6
Gas” circuit breakers.
Breakers are also classified as three-pole, single-throw, and independent pole operation. Three-pole
single-throw breakers utilize one mechanical device to trip all three poles with a linkage to gang the
operation together.
The operating mechanism of a circuit breaker has to be designed to ensure positive or definite opening
of the circuit breaker, and circuit interruption has to occur whether the tripping or opening signal is
received with the circuit breaker fully closed or in any partially closed position. The operating mechanism
should also be capable of closing, reclosing and latching closed the circuit breaker when applied to the
short circuit current.
9.3.3 Application of Power Circuit Breakers
The oil breakers are no more utilized in NTDC network while Air-blast circuit breakers are also not
proposed due to stringent air quality.
There NTDC has only specifications for Vacuum type and SF6 type circuit breakers.
9.3.3.1 Vacuum Circuit Breakers
The application of VCBs in NTDC/DISCO system is limited to the Metal-clad switchgear up-to voltage
level of 36kV.
Vacuum circuit breakers are generally manufactured up-to 69kV, continuous current ratings up-to 4000A,
and cover almost all standard interrupting ratings up-to 50kA. The pressure in interrupting chamber is
10-11 bar.
9.3.3.2 SF6 Gas Circuit Breakers
The application of SF6 is from 36kV to 800kV voltage level and NTDC/DISCO system utilizes this
breakers for 132kV, 220kV and 500kV voltage level.
SF6 circuit breakers are generally manufactured up-to 800kV, continuous current ratings up-to 4000A,
and cover almost all standard interrupting ratings up-to 63kA. The pressure in interrupting chamber is 6
bar.
69 | C h a p t e r 9
Substation Design Manual
these devices are not designed to interrupt the load current. At transmission voltages it is usual for
disconnectors to be power operated. Earthing switches maybe power or manually operated.
Fault current in excess of specified rating may cause disconnectors to blow open by magnetic forces of
short circuit current. High pressure contacts are used to prevent this opening. NTDC requires silver plated
contacts. High contact pressures ensure self-cleaning action – a characteristic of utmost importance in the
high pollution areas.
9.4.2 Types of Disconnectors
There are four types of disconnectors in common use
1. Center Break (Rotary)
2. Horizontal Double Break
3. Pantograph (Vertical)
4. Vertical Break
The way in which these types of disconnector operate has an important effect on the design of the
substation. Three insulation conditions must be considered while selecting disconnectors
1. Phase to earth insulation level
2. Phase to phase insulation level
3. Insulation level across the open contacts of one phase
The insulation level across particular contact is important in areas where surge over voltages can occur
across the disconnector.
9.4.3 Applications of Disconnectors
The application of Disconnector/Isolator is from 33kV to 500kV voltage level and NTDC/DISCO system
utilizes Disconnector/Isolator for 132kV, 220kV and 500kV voltage level.
Disconnector/Isolator are generally manufactured up-to 550kV, continuous current ratings up-to 3150 A,
and rated short circuit duration up to 3 secs.
70 | C h a p t e r 9
Substation Design Manual
The zinc oxide surge arrester very simple in construction. It is gap-less and consists of a stack of zinc
oxide block. Its characteristics can be set very precisely and unless temporary over voltages are relatively
high (such as in case of a non-effectively earthed system) then it is usually possible to obtain lower
protective levels compared with the gapped type of arresters.
9.5.3 Application of Surge Arresters
The application of surge arrestor is from 11.5kV to 500kV voltage level and NTDC/DISCO system
utilizes surge arrestors for 132kV, 220kV and 500kV voltage level. Surge arrestors are generally
manufactured up-to 500kV with discharge current ratings up-to 20 kA and short circuit withstand current
up to 63 kA.
71 | C h a p t e r 9
Substation Design Manual
resistive divider as a voltage sensor) with analogue to digital signal conversion. Digital optical instrument
transformers can be combined with HV equipment ( e.g Circuit breakers)
9.7.2 Voltage Transformer (VT)
Voltage transformers are either of the capacitor (CVT) or electromagnetic type. CVTs are used singly for
metering/Synchronizing purposes or in three phase sets for protection.
Electromagnetic VTs are used when a higher degree of accuracy than can be provided by a CVT, is
required. For example, for the purpose of high accuracy metering or when no other means of discharging
an overhead line or cable is available.
9.7.3 Current Transformer (CT)
Current transformers are specified by their primary rated current and their accuracy class which are
selected according to their service requirement
The rated current of the current transformers should be selected from the IEC series. Rated current and
ratios should be selected according to the requirements of continuous current rating, accuracy and
protection. Current rating can also be extended (120%, 150% or 200%). Current transformers can
continuously be overloaded by 20%.
When the characteristics of a network are liable to evolve, multi-ratio CTs are necessary to allow
flexibility in future development and an increase in circuit loading. They not only require an adequate
nominal current rating to allow for future requirements but also the ability to operate protection relays
when prospective short- circuit current levels are at minimum. Usually a number of secondary windings
are housed within a single primary housing
The application of accuracy classes is as follow
0.1, 0.2,0.2s, 0.5 for measurement and metering
and 5 & 10.0 for protection
Measuring and metering functions require a different secondary winding (core) from the protection
functions (which have different accuracy, secondary power rating and rated overcurrent factor).
9.7.4 Combined Current Voltage
In some cases current and voltage transformers are combined in one primary housing. The main
advantage of these transformers is that only one structure/foundation is required in the switchyard.
9.7.5 Applications of Instrument transformers
Instrument transformers are generally manufactured for 500kV, 220kV and 132kV systems with
maximum symmetrical short circuit current ratings up-to 50 kA and maximum fault duration of 3 seconds.
9.8 Cables
9.8.1 General
A cable is an assembly of one or more wires running side by side or bundled, which is used to carry
current. This chapter highlights cable classification, selection, and sizing and installment practices in
NTDC system.
9.8.2 Cable Classification
Cables used in a substation are classified into following categories:
72 | C h a p t e r 9
Substation Design Manual
73 | C h a p t e r 9
Substation Design Manual
9.8.4.1 Ampacity
Conductor sizing based on ampacity is made by calculating the current required to serve the connected
load. The cable should be capable of carrying normal and emergency load currents. Since the type of
installation of cable plays an important part in ampacity rating therefore, when cables are routed through
several types of installation conditions, conductor size shall be selected based on the most severe site and
environmental conditions.
9.8.4.2 Voltage Drop
When a circuit supplies power to a load, it experiences a drop in voltage and a dissipation of energy in
the form of heat. The allowable voltage drop shall be limited to 5 % of the system nominal voltage
throughout, from the supply sources to the load ends. Voltage drop restriction will require an increase in
conductor size.
9.8.4.3 Short Circuit Capability
Short circuit current will require an increase in conductor size selected if it is not sufficient to dissipate
the heat generated under fault conditions. In substation LV cable systems, conductor short circuit
capability shall not be considered. However, cable from station transformer to main distribution board
should be checked for short circuit capability. Short circuit capability of the cable size selected for station
transformer to main distribution Board shall be checked with the formula derived on the basis of IEC
60724.
.
= ∗ (For copper conductor PVC insulated)
√
.
= ∗ (For copper conductor XLPE insulated)
√
Where,
Isc = Short circuit current in kilo amperes
t = Duration of short circuit current in seconds
A = Cross sectional area of conductor in mm²
74 | C h a p t e r 9
Substation Design Manual
75 | C h a p t e r 1 0
Substation Design Manual
Characteristics Ratings
System Highest Voltage 12 kV
Frequency 50 Hz
Maximum Symmetrical short Circuit 12.5 kA or 25 kA
current
Vector Group Dyn11
76 | C h a p t e r 1 0
Substation Design Manual
77 | C h a p t e r 1 0
Substation Design Manual
10.4.3.1Batteries
A substation dc system consists of a battery of suitable voltage (number of cells) and suitable size
(ampere-hour capacity) connected in parallel with a control bus together with properly selected voltage
regulated charging equipment (battery charger). Two of the most important components of a substation
dc system are the main battery and charger. These components should be sized correctly. Under sizing
could possibly mean a circuit breaker reclose failure and undue service interruption. Oversizing, while
not damaging, is expensive. However, the cost of the supply is a fraction of total substation cost, and the
economics should be balanced with reliability. At a minimum, the main battery should be sized to allow
normal substation operation for 10 hours. In NTDC network there are two batteries with their separate
battery chargers. Generally, lead acid batteries are preferred but Ni Cad batteries can also be used.
Table 10-4: Standard Rating Table for Battery Bank
Ratings Type A Type B
System Nominal Voltage 110 volts 220 Volts
Normal voltage of cell 2 volts 2 volts
Open circuit voltage of cell 2.055 volts 2.055 volts
at full charge
Number of cell in battery 55 110
The ampere capacity of the charger can be determined using Equation 10.1
= +( . )/ ....... Eq. 10-1
Where:
A = Charge capacity (amperes)
L = Continuous load (amperes)
C = Discharge (amperes hours)
H = Recharge time (hours)
10.4.5 Telecom Batteries
In NTDC network 48 Volts batteries along with their separate battery chargers are required for
telecommunication purposes.
78 | C h a p t e r 1 0
Substation Design Manual
79 | C h a p t e r 1 1
Substation Design Manual
80 | C h a p t e r 1 1
Substation Design Manual
81 | C h a p t e r 1 1
Substation Design Manual
82 | C h a p t e r 1 2
Substation Design Manual
relevant IEC Standards and NTDC specifications, but not less than +/- 0.2%. Revenue class metering
shall have the following characteristics:
i. Three elements, four-wire configuration with accuracy class of 0.2s.
ii. Meters shall be capable of measuring and recording at 30 minutes intervals for a period of 180
days with intervals programmable from 5 minutes to 30 minutes.
iii. The meter must have the capability of recording active and reactive power and energy and
maximum load demand for the entire billing period. The meter billing period may be
programmable and capable of being programmed to automatically store the accumulated value
and reset the counter for next billing period.
iv. Multiplier corresponding to the combination of CT and PT ratios may be programmable in the
meter.
v. Meters shall have internal time clock for time and date sampling of data. Time clock must have
high accuracy and synchronize to GPS time signals.
vi. Meters shall have capability for remote meter reading by telemetering or by SCADA.
Communication ports should be provided with optical and serial data communication with
industry / NTDC standard protocol support.
vii. Meter should have self-diagnostic capability and include an alarm to indicate failure and/or
tampering.
83 | C h a p t e r 1 2
Substation Design Manual
References:
RUS Bulletin 1724E-300 “Design Guide for Rural Substation”, 2001
Saudi Electricity Company (SEC), Transmission Standards and Specification “Substation Design
Standards” series
Tasmanian Networks - R590634 v1.0, “Substation Civil Design and Construction Standard”, 2018
Cigre-161 Joint Working Group 23.03 “General Guidelines for The Design of Ac Substations” ,2000
Electra-179 CIGRE Joint Working Group 36.01/06 “A Summary of Standards for Human Exposure to
Electric and Magnetic Fields at Power Frequencies”
Martin J. Heathcote, “The J&P Transformer Book – A Practical Technology Of The Power Transformer”,
12th Edition, 1998
IEC 60076, “Power Transformers”
IEC 60071-1, “Insulation Coordination, Part 1: Definitions, Principles and Rules”
IEC 60071-2, “Insulation Coordination, Part 2: Application Guide”
IEC 61869, “Standard for Instrument Transformers”
IEC 62271-1, “High-voltage switchgear and control-gear - Part 1: Common specifications for alternating
current switchgear and control-gear”
IEC 62271-100, “High-voltage switchgear and control-gear - Part 100: Alternating-current circuit-
breakers”,
IEC 62271-102, “High-voltage switchgear and control-gear - Part 102: Alternating current disconnectors
and earthing switches”
IEC 62271-104, “High-voltage switchgear and control-gear - Part 104: Alternating current switches for
rated voltages higher than 52 kV”
IEEE 80, “IEEE Guide for Safety in Substation Grounding”
IEEE 81, “IEEE Recommended Guide for Measuring Earth Resistivity, Ground Impedance and Earth
Surface Potentials of a Ground System”
IEEE 998, “IEEE Guide for Direct Lightning Stroke Shielding of Substations”
P-46-2008, “Power Transformers”
P-169-2009, “Auto-Transformers”
P-41-81, “Three Phase Pad Mounted Transformers”
P-171-2008, “220 kV Alternating Current Circuit Breakers”
P-193-2010, “SF6 Circuit Breakers 145 kV ,72.5 kV and 36 kV”
P-173-1983, “220 kV Disconnectors”
P-128-2011, “145 kV ,72.5 kV and 36 kV AC Bus and line Disconnectors (Isolators)”
P-174-2008, “220 kV and 500 kV Current Transformers”
P-90-2012, “Current Transformers (145 kV ,72.5 kV and 36 kV)”
84 |
Substation Design Manual
85 |
Substation Design Manual
Annexure-A:
86 |
LEGEND
500kV LINE
SYMBOL NOMENCLATURE VOLTAGE SPECIFICATION
444 kV
500 kV 550 kV, 4000A, 50kA
500kV CCVT
( R & Y - phase) LINE TRAP
CA 220 kV 245 kV, 2000A, 40kA
HV/ BCT 2
3x250 MVA
1
SEE DETAIL 'A' ATB 525/231/23
YNa0d 1
kV
500 kV
525/231/23kV, 3x250 MVA, YNa0d1, 7.5%
IMPEDANCE AT ONAN MVA BASE
TER/BCT T-1 7.5% @ ONAN RATING
AUTO TRANSFORMER
Taps - 17
OUT OF CT 220/132/11kV, 250 MVA, YNa0d1, 10%
N/BCT
1 220 kV
3000:1500/1 30VA IMPEDANCE AT ONAN MVA BASE
LV/BCT
M
SHUNT REACTOR BANK 500kV, 3x37MVAR
D-1 D-2 D2Q10 220kV BUSBAR - I
D1Q11 D2Q11
M M
4000A,40kA
D1Q1 245kV D2Q1 245kV
3150A 3150A
P1 40kA P1 40kA
1 1
TABLE-3 TABLE-1
2 2
DETAILS OF BUSHING CTs VA BURDEN (AT LOWEST TAP) & CLASS DETAILS OF YARD CTs
CT-1 3 CT-1 3
4 4 525/231/23kV, 3x250 MVA ATB
500kV 220kV 132kV 132kV METERING
5 5
RATIO VA ACC. CLASS
P2 P2 ACC. ACC. ACC. ACC.
220kV 220kV CORE # BURDEN CLASS BURDEN CLASS BURDEN CLASS BURDEN CLASS
D1Q12 M CVT Y - PHASE CVT Y - PHASE M D2Q12 CORE #
HV 3000:2500:2000:1200/1A 30 5P20
1,2,3
1 15 VA 0.2 15 VA 0.2 15 VA 0.5 15 VA 0.2S
D1Q31 M M
D2Q31 CORE # 30
LV 3000:2500:2000:1200/1A 5P20 2 30 VA 5P20, TPS 30 VA 5P20, TPS 30 VA 10P20
P2 P2 1,2,3
5 5 TV 5P20
CORE # 1,2 4500:3000/1A 30 3 30 VA 5P20, TPS 30 VA 5P20, TPS 30 VA 10P20
4 4
N CORE # 1,2 3000:2500:2000:1200/1A 30 5P20 4 30 VA 5P20, TPS 30 VA 5P20, TPS 30 VA 10P20
CT-3 3 CT-3 3
2 2 5 30 VA 5P20, TPS 30 VA 5P20, TPS
220/132/11kV, 250 MVA AUTO T/F
1 1
P1 245kV P1 245kV
3150A 3150A
D1Q3 40kA D2Q3 40kA RATIO VA ACC. CLASS TABLE-2
220kV 220kV
CVT Y - PHASE M D1Q32 CVT R & Y - PHASE M D2Q32 CORE #
3000:2400:1500:1200/1A 30 5P20 VA BURDEN (AT LOWEST TAP) & CLASS DETAILS OF YARD CCVTs/CVTs/PTs
HV
1,2,3,4
M D1Q21 M D2Q21 CCVT/CVTs 500kV & 220kV 132kV PTs 132kV METERING
P2 P2 LV CORE # 30
2400:2000:1500:1200/1A 5P20
5 5 1,2,3,4 ACC. ACC. ACC.
CORE # BURDEN BURDEN BURDEN
CLASS CLASS CLASS
4 4 CVT-2 TV CORE # 1,2 3000:1500/1A 30 5P20
CT-2 3 CT-2 3 220kV CVT CORE # 1 1 200 VA 0.2 75 VA 0.5 50 VA 0.2
1200:600/1A 30 5P20
2 2 Y-PHASE N
CORE # 2 2400:2000:1500:1200/1A 30 5P20 3P (500kV) 200 VA 6P
1 1 2 200 VA
P1 P1 6P (220kV)
245kV 245kV
D1Q2 3150A D2Q2 3150A
40kA 40kA 500kV 3x37MVAR SHUNT REACTOR BANK
M D1Q22 M D2Q22 220kV BUSBAR - II ACC. CLASS
RATIO VA
TERTIARY GROUNDING ARRANGEMENT
D2Q20
D1Q10 D1Q20 M 4000A,40kA HV
CORE #
1000:500:250/1A 30 5P20
D1E10 M M D1E20 M M 1,2,3
198 kV CORE # ( DETAIL OF 'B' ) ( DETAIL OF 'A' )
4 LN 1000:500/1A 30 5P20
1,2
LINE TRAP
LINE TRAP LINE TRAP
LINE TRAP 3
kV
31
2
18
250 MVA
220kV CVT
( B - phase)
220kV CVT
( B - phase) SEE DETAIL 'B'
1 ATB 220/132/11 kV
kV
YNa0d 1
V
T-2
k
TER/BCT
31
18
10% @ ONAN
220kV CCVT 220kV CCVT Taps - 27
( R & Y - phase) ( R & Y - phase) OUT OF CT 1
LV/BCT
3000:1500/1 30VA
CA CA 2
3
V
kV
N/BCT
k
198 kV 198 kV
31
18
4
120 kV
MPT
P1
220kV LINE-I 220kV LINE-II MCT
P2
P2
4
3
2
1
P1 145kV 132kV PT-2
132kV PT-1
2000A (3-Phase)
E3Q1 40kA (3-Phase)
B3 M M
132kV BUS BAR-I
3150A,40kA B1 B2 E3Q11 M M E3Q12 B4 B5 B6 B7
132kV BUS BAR-II E1Q12 M M E1Q11 E2Q12 M M E2Q11 E5Q12 M M E5Q11 E6Q12 M M E6Q11 E7Q12 M M E7Q11
3150A,40kA
E4Q12 M M E4Q11
E1Q1 E2Q1 P2 P2 E5Q1 E6Q1 E7Q1
P1 P1 1 4 P1 P1 P1
1 1 2 3 1 1 1
2 2 3 2 2 2 2
3 3 4 1 3 3 3
4 4 P1 P1 4 4 4
P2 P2 P2 P2 P2
E1Q10 E2Q10 E4Q1 E5Q10 E6Q10
M M M M
BUS COUPLER 120 kV
E1E10 M E2E10 M E5E10 M E6E10 M 10/13 MVA
132/11.5 kV
120 kV 120 kV T-3 Dyn II
9% @ ONAN
120 kV 120 kV 11 kV
PT PT
PAKISTAN DESIGN
DEPARTMENT
NATIONAL TRANSMISSION & DESPATCH COMPANY (NTDCL)
MIAN
DRAWN BY IJAZ MAHMOOD
CHECKED
500/220/132kV MODEL
ASSTT.
UMAR AZIZ
SUB STATION
MANAGER
DEPUTY
SINGLE LINE DIAGRAM
MANAGER
CHIEF
ENGINEER MAZHAR ALI DWG NO. PDW/TE -
a
40.0m 40.0m
i a a a a
30.75m 30.75m
b b b
a
20.0m 20.0m
a
4000
a 16.9m
5500
C C C d g 13.8m
d
10.m k
13000
9000
220kV FUTURE EXT.
7000
ROAD
ROAD
5500
ROAD
PATH PATH PATH G
SA PI/ CCVT/CVT LT/PI ISO GT/PI ISO CB SA SR GT PI-H PI-A PI-A ISO CB CT ISO GT/PI/CVT ISO CT CB ISO GT/PI/CVT ISO CT CB ISO PI-A CVT/PI-A PI-H GT/PI ISO S-A A T B Trans. S-A 200kV ISO GT CT CT CT GT CT CT CT GT GANTRY ISO LA Trans. 250MVA LA M.PT M.CT CT CB PI-A PI-H PI ISO ISO PI-A PI-H CB CT ISO PT LA
TOWER
10000 5500 4000 6000 10000 6500 44300 11200 8000 8000 8000 9000 11000 8500 7000 6500 6500 7000 8500 10500 6500 6500 7000 8500 11000 9000 8000 8000 8000 7500 7500 8500 5500 10000 4000 12500 5500 4000 4000 4000 4000 8000 4000 32000 7000 5500 7500 6500 4500 5000 4000 4000 4500 2500 4000 6000 4000 2500 5500 3500 3500 5000 5000 16000
38000 42000 18000 4000 3000 2500 2500 3000 3000
47000 33000
› 80000 55500 66000 39000 66000 29000 132kV TOWER
1000 1000
500kV TOWER
SECTION - A-A SECTION - A-A SECTION - A-A SECTION - A-A
500kV SIDE 220kV SIDE 220kV T / LINE 220kV SIDE 132kV SIDE 16.9m
13.8m
7000
11KV ST. TRANS. LA CB CT PI-A PI-A PI ISO ISO PI-A PI-A PI-A GANTRY
GANTRY
3500 3000 4000 3000 4500 2500 4000 6000 4000 2500 4500
2500 1000 2500 2500
B
17000 33000
16000 16000
SECTION - D-D
27000 5000 8000 8000 8000 8000 4000 4000 4000 4000 4000 4000 4000 4000
132kV 10/13MVA T/F
B
R
SECTION - G-G
6000
6000
500kV SIDE (SHUNT REACTOR )
9000
Porch Level
+0.200
Tread=300
Riser=150
ENTERANCE
V1 W4 W2 V2 W2 W2 W2 W2 W2 W2 W2
LINE TRAP
EF
EF 2825x1500
WC WC
D6
TOILET W3
CCVT &
DW1 4775x4370 4775x4370 4685x4370 4685x4370 4685x4370
D6 D6 2625x4370 4975x4370 4600x4375 ROOM ROOM WORKSHOP+STORE OFFICE OFFICE
CVT
CVT
KITCHEN D4
2810x4370 ROOM 3850x2650 R.E OFFICE ENGINEER ENGINEER ELECTRICAL
V2 TEA/ ROOM OPERATION MECHANICAL/ MECHANICAL/
TOILET STAFF F.F.L
STENO
+0.800
4775x4600
D4 D4 D4 D4 D4 LOBBY D4 D4 D4 D4 D4
UP.
ENTRANCE
D2
D2
CORRIDOR 2500mm WIDE UP.
D4 D3 D2
38550
Ex.Fan
11855x13770 D4
W1
W1
AC/DC ROOM
11 9685x13770
11
BUS BAR-II
13000
W1
W1 11kV
SWITCH ROOM D1
AA
D4
Ex.Fan
2800 8000 2700 8000
220kV
AA
Ex.Fan
D1
CVT
W2 W2 W2 W2 W2 W2 W2 W2 W2
2500
AA
UP
HP
HP PI
PI
P.M.T P.M.T AA
5000 8000
5226 5226
6000
4.5-m R.C.C TRANS. WAY
1170
10 10
7000
R
3500 2500
Y
3500
6000
6000
R
PI
2500 2500
2500 2500
12000
7000
5500
17001700
5500
D D
S1
S1
6000
PI
2500
6000 3500
BUS BAR-I BUS BAR-II
B
7000
9 9
132kV T / LINE
2.5 - m R.C.C SERVICE ROAD
4500
AUTO-T/ F
R
Y
B
3000
6000
6000
3×250MVA
3000
PI
7500
12000
6000
5500
6000 Y
7500
525/231/23kV
G C
CVT
CVT
6000
6000
PI
B
4500
5000
5000
6000
6000
8' 8'
14000
14000
6000
4500
8000 16000
6000
6000
R
PI
7500
PI PI
12000
6000
6000
8000
8000
8000
5000
6000 Y
7500
R
5450
6000
CVT
158500
PI
PI
5000
5000
5000
4500
6000
6000
6500
7 7
3-m R.C.C Service Rd.
6000
BK
10650
4500
4500
8000
8000
8000
4500
220kV FUTURE EXT.
6550
6000
6000
BUS COUPLER
32000
7500
12000
2500
2500
CVT CT CT
16000
16000
1700
6000
6500
F F
6000
13000
13000
7500
7500
CVT
3250
MK
Y AT - 1
6000
6000
6' 6'
6550
CB CB
Y
8000
S3
250MVA
S3
4500
10650
TACC
6000
6 A 6
6000
6500
4500
4500
16000
16000
500kV T / LINE
R
B 2.5 - m R.C.C SERVICE ROAD
121360
6000
5450
R
PI
7500
12000
6000
8000
8000
8000
8000
4.0 - m R.C.C SERVICE ROAD B CT CT
Y
3500
3 - m R.C.C SERVICE ROAD
5500
6000
3250
7500
6000
6000
3500
PI
05' 05 E
05 05'
TACC
4500
6000
132kV T / LINE
6000
14000
6000
4500
7000
04 04
CVT CVT
PI
7500
12000
6000
PI
6000
6000
5000
ROOM
7500
METERING
SPARE
6000
5000
500kV SWITCH YARD
4500
4500 5000
6000
03 A 03
5500
6000
4500
6000
7500
6000
7000
7000
6000
2.5 - m R.C.C SERVICE ROAD
7500
6000
6000
3500
3500
S2
6000
S2
02' 02'
5500
ISO ISO
02 02
PT PT
41950
BUS BAR-I
AA
G
220kV
2800 8000 2700 8000 2700
2600 2600
AA
CVT
10300 8000 8000
AA
HP
AA
5000 8000 5300
7000
497500 B
(WITH EARTHING SWITCH)
TERMINAL TOWER 500kV
SURGE ARRESTER
CIRCUIT BREAKER
CIRCUIT BREAKER
CIRCUIT BREAKER
CIRCUIT BREAKER
CURRENT TRANS:
CURRENT TRANS:
CURRENT TRANS:
POST INSULATOR
POST INSULATOR
POST INSULATOR
POST INSULATOR
POST INSULATOR
POST INSULATOR
POST INSULATOR
POST INSULATOR
GANTRY (TYPE-6)
SHUNT REACTOR
GANTRY (TYPE-2)
GANTRY (TYPE-2)
GANTRY (TYPE-5)
GANTRY (TYPE-3)
ISOLATOR (DS)
ISOLATOR (DS)
ISOLATOR (DS)
ISOLATOR (DS)
ISOLATOR (DS)
ISOLATOR (DS)
ISOLATOR (DS)
ISOLATOR (DS)
TRANSFORMER
LINE ISOLATOR
PT / ISO / POST
PT / ISO / POST
PT / ISO / POST
PT / ISO / POST
PT / ISO / POST
PT / ISO / POST
A T B TRANS:
TRANS. WAY
R & Y Phase /
TRANS. WAY
CCVT / CVT
C V T / PI /
C V T / PI /
LINE TRAP
S-A 200kV
GANTRY
GANTRY
GANTRY
GANTRY
GANTRY
TRANS.
CVT /
M. C T
ROAD
PATH
CVT
ISO
ISO
ISO
ISO
ISO
ISO
ISO
CB
CB
CT
CT
PT
LA
LA
LA
0
10000 5500 4000 6000 10000 6500 6500 11000 8500 7000 8300 11200 8000 8000 8000 9000 11000 8500 7000 6500 6500 7000 8500 10500 6500 6500 7000 8500 11000 9000 8000 8000 8000 7500 7500 14000 10000 4000 12500 5500 8000 16000 8000 32000 7000 5500 7500 6500 3750 6250 4000 3000 4500 2500 6500 6000 4000 2500 2500 4500 4000 3500 3500 3000 5000 5000 16000
3000 2500 1000
29000 1000
80000 55500 66000 39000 66000 61000 16000 16000 32000 47000 33000 40000
A A' B C D E F G H I J K
40.0m
Notes:
ROAD
ROAD
9000
2. This drawing does not give civil data. However, it forms the mandatory basis for the final PAKISTAN
7000
4
4
4
4
4
CHIEF ENGINEER
4 4 4
constructional design.
4 4 4
4 4 4
4 4 4
±0.00
SA CVT DS GT PI-H PI-H PI-H DS CB CT DS GT/PI DS DS DS GT/CB CT DS GT/PI DS CT CB DS PI-H PI-H PI-H MAST GT DS DS DS 4500 GT PT ISO GT
3000 2500 3500 2500 2500 3500
ISO ISO ISO GT
3500 2500 2500 3500
ISO ISO ISO GT GT PI PI-A PI-A ISO CT CB CT ISO PI-A PI-A PI-A GT
3. Electrical filling compound and electrical jointing compound shall be used for all NATIONAL TRANSMISSION AND DESPATCH COMPANY ( NTDCL )
4000 5500 4000 6000 6000 5500 7000 5500 6000 5250 4000 4000 5250 7000 5500 6000 6000 5500 7000 5500 6000 6000 7000 8000 8000 8000 8000 4500 2500 2400 2200 2400 2500 4500
electrical connections and shall be applied to connector groove dead end bodies / MIAN
3500 3500 3500 3500 SECTION - E-E 2500 2400 2200 2400 2500 DRAWN
SECTION - C -C SECTION - F-F assemblies and on conductors prior to assemblies. IJAZ MAHMOOD
SECTION - B-B 500kV SIDE
132kV SIDE
132kV SIDE (Bus Culper) 4. Special care shall be exercised in handling all tubing cables and fittings to prevent 500/220/132kV MODEL
CHECKED
scratches on their surface
220kV SIDE
5. After mounting Aluminium tube, a 10mm dia hole to be drilled in lowest point of each ASSTT
SUB STATION
UMAR AZIZ
tube for dewatering. MANAGER
6. Location of 132kV Surge Arrestors may be adjusted as per site requirement according to DEPUTY
SWITCH YARD LAYOUT
MANAGER
LV Bushings of 220/132kV Auto-Transformers
MANAGER SCALE :- 1 : 750 DATE :- 10 - 09 - 2020
CHIEF
ENGINEER
MAZHAR ALI DWG NO. PDW/TS -