Complete Technical Document
Complete Technical Document
1.0 ABBREVIATIONS…………………………………………………………………………………….3
3.0 INTRODUCTION……………………………………………………………………………………...5
AC Alternating Current
GCU Generator Control Unit (also referred to as Generator Control System in this
document)
PI Polarization Index
Figure 1: Block diagram showing the existing Power system architecture at RIVTAF Golf Estate
Figure 2: Block diagram showing the proposed Power system architecture at RIVTAF Golf Estate
Figure 3: Single Line Diagram for Modified Power System Network at Rivtaf Golf Estate
Figure 1: Block diagram showing the existing Power system architecture at RIVTAF Golf Estate
(Each of the substations is equipped with RMUs, step-down transformers, change-over units and distribution boards)
Figure 4 below shows a single line diagram of the electrical network after introducing the proposed
synchronization system to the existing power system in the estate.
Figure 3: Single Line Diagram for Modified Power System Network at RIVTAF Golf Estate
1. A Power Management System (PMS), for the overall control of the six (6) generator sets and the
power transfer system.
2. The Generator Control Unit (GCU) for each generator set, controlling the engine, generator and
auxiliary equipment.
3. The Automatic Transfer System (ATS) for automatic power transfer between PHCN supply and
stepped-up synchronized generator supply.
4. The control system, consisting the GCUs, PMS and ATS, is supplied by a 230V UPS
2.2.1
Below is the list of information that will be made available for visualization:
2. SYSTEM SAFETY:
In the case of an emergency, ease in system isolation is vital. The Power Management system
provides such function. All generator breakers will be opened and generator units will be shutdown
in cases of emergency
5. DATA LOGGING:
The proposed PMS makes it possible for incorporating of technologies for capturing and storing of
data that can be analyzed and can help for future planning of power generation and distribution in
the estate.
A brief explanation on the tenth (10th) function. The system will be designed with Load dependent
Start/Stop capabilities. This means that not all generators will be running at the same time over a long
period of time except the load demands it. The proposed Generator Control Unit will be designed such that
generators can be arranged in order of priority based on their availability. For example, a generator unit that
is 90% fit for operation can be given higher operational preference by the system while a generator that
requires maintenance will be given a lower preference.
LEGEND
All available generator units will be started, synchronized sequentially in the order of their priorities and
the load that is demanded will be shared accordingly. At least five out of the six generators should be
available at any given time. This is to ensure that the generated power meets the estimated peak electrical
load of 2MW that is consumed by the estate. If after all the generator have been synchronized, the load
demand is less than the 2MVA, the Generator Control system will reduce the generated power to match the
demanded power by stopping generating sets (starting from the least in the priority list).
The Generator Control System will add or drop generating units to the network based on increase or
decrease in the load demanded.
2. SCENERIO 2:
When Mains is restored, the Automatic Transfer System (ATS) ensures a safe and open transition from
generator supply to Mains supply by closing opening the 11kV generator incoming breaker and closing the
11kV Mains incoming breaker
After the transition to Mains, the Generator Control Units automatically open the Air Circuit breakers and
shuts down the generating units.
Automatic Mode can be selected by pressing the button on the DSE8610 modules that are mounted
on the GCU panels and the DSE 8610 module that is mounted on the ATS panel. In this mode, the following
actions are carried out;
1. Automatic Transition of Power supply from Mains to Generator and Vis versa when Mains is
present and absent respectively.
2. Automatic synchronization of generators
3. Automatic Load-sharing of load demand among synchronized generators
4. Automatic starting and stopping of generator sets based on load demand
5. Safe shutdown of system during emergency.
2. MANUAL MODE
Manual Mode can be selected by pressing the button on the DSE8610 modules that are mounted on
the GCU panels and the DSE 8610 module that is mounted on the ATS panel. In this mode, the following
actions can be carried out;
1. Manual starting and stopping of generator sets
2. Manual closing and opening of Air Circuit Breakers
3. Manual closing and opening of 11kV rated incoming breakers from Mains and generator.
4. Safe shutdown of system during emergency.
The manual operation of the system should only be used for test purposes during maintenance.
The following checks will be carried out on the existing generator sets to verify the integrity of the units:
1. Carry out IR & continuity tests on all cables before & after cable installation.
2. Excavate cable trench as per project drawings (standard specs: 1.0m for HV cables & 0.6m for
LV cables.)
3. Prior to cable installation, ensure the trenches are debris free.
4. Carry out cable installation between & back fill up to 300mm using sharp sand. Install cable slabs
& backfill completely.
5. Carry out cable termination & hook-up using appropriate cable glands & lugs.
6. Cable Risers, Ladders & Trays would be used as points of hook-up & termination, if need arises.
Carry out integrity tests & checks on existing Earthing installations, if result is less than 1ohm, Earthing
improvement would be recommended. All new Earthing installations would be bonded or tied to the
existing Earthing