API 653 Round-2023
API 653 Round-2023
Close Open
d Book
Code Part from Code
Book
St is the maximum allowable hydrostatic test stress in pound force per square inch
(lbf/in.2); use the smaller of 0.88Y or 0.472T for bottom and second courses; use
the smaller of 0.9Y or 0.519T for all other courses. use the smaller of 0.9Y or
0.519T for all other courses.
4.3.5 Distortions Ok
4.3.5.1 Shell distortions include out-of-roundness, buckled areas, flat spots, dents,
and peaking and banding at welded joints.
4.3.8.2 Excessive weld reinforcement does not require rework if the tank has a Ok
satisfactory history of service. If the reinforcement will interfere with floating roof
seal operation, it shall be ground as required.
4.4.5.4 Unless a stress analysis is performed, the minimum bottom plate thickness Ok
in the critical zone of the tank bottom defined in 9.10.1.2 shall be the smaller
of one-half the original bottom plate thickness (not including the original
corrosion allowance) or 50 % of tmin of the lower shell course per 4.3.3.1 but not
less than 0.1 in. Isolated pitting will not appreciably affect the strength of the plate.
4.4.5.7 The thickness of the projection of the bottom plate beyond the shell as Ok O
measured at the toe of the outside bottom-to-shell fillet weld shall not be less than
0.1 in. The projection of the bottom plate beyond the outside toe of the
shell-to-bottom weld shell shall be at least 3/8 in.
Ok
Ok Ok
6.4.2.1.1
10.4.2.7 Tack welds used in the assembly of vertical joints of tank shells shall be Ok
removed and shall not remain in the finished joint when the joints are welded
manually. When such joints are welded by the submerged-arc process,the tack
welds shall be thoroughly cleaned of all welding slag but need not be removed
provided that they are sound and are thoroughly fused into the subsequently
applied weld beads. Tack welds shall be made using a fillet-weld or butt-weld
procedure qualified in accordance with Section IX of the ASME Code. Tack welds
to be left in place shall bemade by qualified welders.
10.4.2.10 Low-hydrogen electrodes shall be used for welding temporary and Ok
new permanent attachments to shells of API 650 Group IV, IVA, V, or VI
materials. The welding procedure selected shall not cause underbead cracking;
also, the need for preheat of thick plates and the effect of low ambient temperature
during welding shall be considered.
Section 12—Examination and Testing very importance Ok Ok
13.1.2.2 If information required to complete the nameplate as required by the as- Ok
built standard is available and traceable to the tank, a new Replacement
Nameplate, similar to that shown in Figure 10.1 in API 650, may be
attached under the direction of the Authorized inspector.
B.2.2.2 Rigid body tilting of a tank Ok
B.3.4 Edge Settlement Ok
B.3.4.1 Maximum allowable settlement Bew is shown in Figure B.11 for settled
areas that include bottom lap welds essentially parallel to the shell (±20°).
Ok
API 4.5.4 Ok
650 3- Drip ring shall extend at least 3”
Given tank Dia 100 ft , type cone roof and ask about slope of frangible joint ? Ok
ASM MT Ok
T-761.1 Magnetizing Equipment.
Ev (a) Frequency. Magnetizing equipment with an ammeter shall be calibrated at least
once a year, or whenever the equipment has been subjected to major electric
repair, periodic overhaul, or damage. If equipment has not been in use for a year
or more, calibration shall be done prior to first use.
(c) Tolerance. The unit ’ s meter reading shall not deviate by more than ±10% of
full scale, relative to the actual current value as shown by the test meter.
Ok
PT
T-651 TECHNIQUES
Either a color contrast (visible) penetrant or a fluorescent penetrant shall be used
with one of the following three penetrant techniques:
(a) water washable
(b) post-emulsifying
(c) solvent removable
T-652 TECHNIQUES FOR STANDARD TEMPERATURES Ok
As a standard technique, the temperature of the penetrant and the surface of the
part to be processed shall not be below 40°F (5°C) nor above 125°F (52°C)
UT Ok
T-462.6 Temperature.
For contact examination, the temperature differential between the calibration block
and examination surfaces shall be within 25°F (14°C). For immersion examination,
T-262 DENSITOMETER AND STEP WEDGE COMPARISON FILM Ok
T-262.1 Densitometers. Densitometers shall be calibrated at least every 3 month.
(d) The densitometer is acceptable if the density readings do not vary by more than Ok
±0.05 density units from the actual density stated on the national standard step
tablet or step wedge calibration film.
571 Ok