1) Summary of Requirements
1) Summary of Requirements
1) Summary of Requirements
Cement Content : Minimum = 250 kg/m3 [Project & ERA's Technical Specification]
: Maximum = 550kg/m3 [Project & ERA's Technical Specification]
(A) ~ Target Average Compressive Strength (f cr) When Suffiicient Historical Data's are not available [From Table 4.2, ACI 214R-02]:-
'
(B) ~ Target Average Compressive Strength (f 'cr) When Suffiicient Historical Data's are available [From Table 4.1,Table 4.3,Eq.4-2b and ACI 214R-02]
~ Standard Deviation of the Test Record for this Concrete Class[S,ACI 214R-02] : 3.58 Mpa
Modification Factor For the Calculated Standard Deviation [Table 4.1 below] : 1
Probability of Meeting the Specified Strength Z,Values of Z for Various Percentages of Tests Falling Between the mean +ZS
and the mean –ZS [Table 4.3 below] :
2.1 Cement : Portland Pozzolan Cement (PPC) Produced and Supplied by Derba Cement
2.2 Coarse Aggregate : Crushed Aggregate Produced at km 49+700 a Nominal Size of 20mm
2.3 Fine Aggregate: Blended Sand (50% - crushed sand from 54+600, 50% - natural sand from Areka)
17072013
4) Input Data's
CA
Parameters Water Cement Sand/FA
"02" "01"
Sp. Gravity 1 2.98 2.59 2.57
Absorbition (%) … … 2.40 2.24
Natural Moisture Content (%) … … 1.21 0.89
Fineness Modulus … … 3 … …
Dry Rodded Unit Weight (Kg/m 3) … … … 1655
Loose Unit Weight (Kg/m 3) … … 1580 1517 1497
5)Water-Cement Ratio
Nom.max size of aggregate= 20 mm
Target Avg Compr. Strength= 22 Mpa
~w/c= 0.66 For a nom. Max size of aggr.of 20mm…[Table A1.5.3.4 (a) and (b) of ACI 211.1 - 91]
if (w/c >= 0.5), take water-cement ratio to
0.66 [as amended by the Project Technical Specification Sub-clause 8400 ]
be =
Estimated Qty.
Adjusted Qty. (Kg per cu.m of
Constituent Materials (Kg per cu.m of Absorption (%) NMC (%) Free Water (%) Free Water (kg)
concrete)
concrete)
10) Composition of Laboratory Trial Batch, scale the masses down to produce 0.027m3 of concrete
Therefore the mass of each component to get 0.027 m3 of concrete is :
Cement= 7425 gm
Water= 5528 gm
Coarse Aggregate(wet)= 27023 gm
Sand (wet)= 22648 gm
Total= 62624 gm 2319 kg/m3
The batch as mixed shows the follwing properties :
Measured Slump= 43 mm
Workability = O.K.
Additional Water= 150 gm
Water (Net Mixing)= 5044 gm
Unit Weight of Fresh Concrete= 2432 kg/m3
Yield of Trial Batch= 0.03 m3
New (w/c) Ratio= 0.66 < 0.5 [Project & ERA's Technical Specification]
>>> The volume of ingredients other than air in the original trial batch was :
Vc= 0.002 m3
Vw= 0.006 m3
Vca= 0.011 m3
Vs= 0.009 m3
Total= 0.028 m3
Since the Yield was= 0.026 m3
Amount of air which was detectable within the precision of
the unit mass test and significant figures of the 0.002 m3
calculations=
787.36 Kg (Dry)
>>> Sand/fine aggregate content per 1 Cu.m of concrete is
0.304 m3………….
=
796.89 Kg (Wet)
17072013
Compr.
Max.load at Average
Cast Date Age in days Slump (mm) Weight (g) Density (kg/m3) Strength
Failure (KN) (Cylindrical)
Cube (Mpa.)
7 0 0.00
7 0 0.00 0.0
7 0 0.00
13
44
20
28 0 0.00
2/
28 0 0.00 0.0
/1
16
28 0 0.00
Target Average Compressive Strength (f'cr) =21.9Mpa
☻Box sizes (50cm Length * 40cm Width * X cm Height) & Recommended Volume of Water Per Bag of Cement will be :-
Volume of Water Per Bag of Cement = 33 Liters
Coarse Agg. Per Bag of Cement,19mm= Two box each 2*(19.5 cm height)
Coarse Agg. Per Bag of Cement,9.5mm= One box each 1*(19 cm height)
Fine agg.(Sand) Per Bag of Cement= Two box each 2*(21.5 cm height)
Remark:-