EVM
EVM
Earned Value takes these three data sources and can compare the budgeted value of
work scheduled with the “earned value of physical work completed” and the actual
Some terms
Planned Value (PV): Planned value is the authorized budget that is assigned to
Earned Value (EV): Earned value is the measure of actual work performed
Actual Cost (AC): Actual cost is the actual expenditure incurred for the work
EV – PV.
Cost Performance Index (CPI): The cost performance index is the measure of
calculated as, CPI= EV/AC; CPI > 1 indicates the project is under budget and CPI
measure the efficiency of the project schedule. The schedule performance index is
calculated as, SPI= EV/PV; SPI > 1 indicates the project is ahead of schedule and
Estimate at Cost: (EAC): Estimate at cost is the prediction of how much the
project will cost upon completion. Estimate at cost is calculated as, EAC= Budget
at completion (BAC)/CPI.
complete the remaining work. The estimate to complete is calculated as, ETC=
EAC-AC.
Item Questions
What’s reported
Forecasted
Estimate At Completion (EAC) Original Budget / CPI New total budget
Completion Date Estimate (CDE) Original Schedule / SPI New total time needed