Ref N° 1 - DESIGN PHILOSOPHY
Ref N° 1 - DESIGN PHILOSOPHY
Ref N° 1 - DESIGN PHILOSOPHY
&
CONSTRUCTION
DESIGN PHILOSOPHY
CONTENTS
1. INTRODUCTION 4
1.1. Foreword 4
1.2. Objectives 4
1.3. Scope 4
2. ABBREVIATIONS & DEFINITIONS 5
2.1. Abbreviations 5
2.2. Definitions 9
3. APPLICABLE STANDARDS 14
4. KEY OPERATIONAL REQUIREMENTS 15
4.1. Functionality 15
4.2. Maintainability 15
4.3. Health, Safety and Environmental 15
4.4. Layout 15
4.5. Robustness 15
4.6. Redundancy 16
4.7. Flexibility 16
4.8. Reliability 16
4.9. Control & Monitoring 16
4.10. Turndown 16
4.11. Documentation 17
5. DESIGN CONSIDERATIONS 18
5.1. General 18
5.2. Capacity 18
5.3. Configuration 19
5.4. Staged Development 19
5.5. Environment Considerations 19
5.6. Operations Input 20
6. REVIEW AND VERIFICATION OF CONCEPTUAL DESIGN 21
7. DESIGN AND ENGINEERING 22
7.1. General 22
7.2. Process 23
7.3. Mechanical 24
7.4. Piping and Layout 25
7.5. Electrical 26
7.6. Control and Instrumentation 28
7.7. Telecommunications 30
7.8. Health, Safety and Environmental 30
7.9. Civil/Structural 31
7.10. Architectural 32
8. PROJECT ORGANISATION 33
9. VENDOR SELECTION 33
10. TAGGING AND LABELLING 33
11. DOCUMENTATION 34
11.1. General 34
11.2. Process Flow Diagrams 35
11.3. P&IDs 35
11.4. Safety Device Register 36
11.5. Safeguarding Diagrams 36
11.6. Alarm and Trip Schedule 36
DESIGN PHILOSOPHY Page 2
11.7. Controller Tuning Parameters Register 36
11.8. Cause and Effect Charts 36
11.9. Vessel Level Co-ordination Diagrams 37
11.10. Hazardous Area Drawings 37
11.11. Instrument Layout Drawings 37
11.12. Valve Registers 37
11.13. Data Sheets 37
11.14. Special Piping Items Databook 38
11.15. Vendor Documentation 38
11.16. Fiscal Metering Dossier 38
1.1. Foreword
1.2. Objectives
1.3. Scope
2.1. Abbreviations
General
Can Can requirements are conditional and indicates a
possibility open to the user of the philosophy.
Technical
Criticality Criticality is a relative measure of the consequence of a
particular failure mode and its frequency of occurrence.
The criticality value is used to rank failure modes when
performing an FMEA
FMEA – Failure Stands for Failure Mode and Effects Analysis. A FMEA
Mode and is an inductive, bottoms-up method of analysing system
Effects Analysis design and performance. The core of the analysis is the
determination of the effects of various types of failures on
a system.
FMECA - Failure Stands for Failure Mode, Effects, and Criticality Analysis.
Mode, Effects, A FMEA is an inductive bottoms-up method of analysing
and Criticality system design and performance. The core f the analysis
Analysis is the determination of the effects of various types of
failures on a system. A criticality factor, assigned to each
failure mode, allows ranking the most severe failure
modes and the ones most likely to occur. The analyst
may then target these failure modes in order to reduce
their probability of occurrence.
MTBF – Mean Mean Time Between Failures is the mean time expected
Time Between between failures and is measured in hours. It is a
Failures statistical value and is meant to be the mean over a long
period of time and large number of units. For constant
failure rate systems, MTBF is the inverse of the failure
rate. (Technically MTBF should be used only in reference
to repairable items, while MTTF should be used for non-
repairable items, but MTBF is commonly used for both
repairable and non-repairable items).
MTTF – Mean Mean Time to Failure is the mean time expected to the
Time to Failure first failure of a piece of equipment. It is a statistical
value and is meant to be the mean over a long period of
time and large number of units. For constant failure rate
systems, MTTF is the inverse of the failure rate.
(Technically MTBF should be used only in reference to
repairable items, while MTT should be used for non-
repairable items, but MTBF is commonly used for both
repairable and non-repairable items.)
Operational Time The period of time during which an active item performs
its intended function, i.e. the accumulated time in service
during the period of the event data surveillance.
Note: On the data forms the operational time is specified
as the accumulated time in active operation for all items
in the population of interest.
DESIGN PHILOSOPHY Page 11
PI+D Derivative action on change of PV, not on error.
System Integrity The ability of the system to perform the required safety
function under all operating conditions and within the
required time scale.
Any equipment or systems installed shall comply with the relevant Standards,
Specifications, Industry Codes, Algerian Laws and Sonatrach Standards:
Algerian Legislation
Sonatrach Standards
4.1. Functionality
4.2. Maintainability
4.2.1 All equipment shall be designed and facilities provided such that
maintenance can be carried out safely, quickly and easily with
minimum disruption to production.
4.3.1 All installed facilities shall comply with SH’s HSE requirements.
4.3.2 The design shall take into consideration risks to personnel during
routine and non-routine operations and maintenance activities.
4.3.3 The design shall document the methodology for shutting down,
depressuring, draining, purging and isolating all items of equipment. A
nitrogen connection shall be provided to pressure test the equipment
once isolated.
4.4. Layout
4.4.1 Equipment layout shall ensure safe access for routine operation,
equipment monitoring and maintenance activities. It shall be designed
to minimise hazards to personnel and other equipment in emergency
situations, as well as providing some shelter from direct sunlight during
routine operation.
4.5. Robustness
4.6. Redundancy
4.6.2 The design and selection of equipment shall enable the minimum
number, type and variety of spare parts to be held on site. Equipment
and spares shall be selected to minimise life cycle costs.
4.7. Flexibility
4.7.2 The total capacity of the storage tanks should be between three and
seven days of full production, to be determined during detailed design
based on export requirements.
4.8. Reliability
4.8.1 Equipment selection and design shall ensure high availability and
reliability. Proven design and technology shall be selected for the duty
and location.
4.8.2 Remote location of the facility in the Algerian desert shall be taken into
consideration when selecting equipment. Maintenance costs can be
excessive due to the logistics associated with obtaining spares and
vendor support. Life cycle costs shall be used to select equipment not
just capital cost.
4.10. Turndown
4.11. Documentation
5.1. General
5.1.3 The facility components shall be of proven design for the intended duty.
5.2. Capacity
5.2.1 In the design and sizing of the facility a complete set of data on the
predicted variations in the inlet/wellstream quantities, composition and
characteristics shall be considered. Simulation data should be
available to cover all known operating cases over the lifetime of the
field. From the simulation results, sizing cases shall be tabulated for
each equipment item.
5.2.2 The design case (maximum and minimum) shall be determined for all
processes and equipment. In selecting the sizing of all equipment and
pipework the following shall be addressed:
Design capacity.
Design margin over and above the required design capacity.
Additional capacity to rerun of off-spec fluids at the required rate.
Additional capacity to make up for plant unavailability.
5.2.4 Control valves should be designed such that the maximum flowrate is
achievable. However for start-up and early production, undersized
control valves maybe required. The undersized control valve should be
fitted for start-up. Where ever practical it should be possible to fit larger
internals in a control valve to meet the maximum duty. If this turndown
is too great for one size of body then two valves should be installed.
5.3. Configuration
5.5.4 Adequate shielding and shelter from the sun shall be provided for all
electronic equipment and equipment sensitive to high temperature.
Exposed field equipment could be subjected to high levels of direct
sunlight with high surface and equipment operating temperatures (circa
95 Deg C).
5.5.5 Adequate shielding and shelter from the sun shall be provided for
personnel required to work for long periods outside.
5.6.1 Operations input and review shall be sought throughout the project life
cycle from Design through to Commissioning. Operations should be
involved in the project as early as possible.
5.6.2 Operations input and review shall be sought for the following as a
minimum before finalising:
6.1 Prior to commencing detailed design a full review and verification of the
conceptual design shall be carried out. The engineer shall familiarise
himself with any existing facilities, site details, Operational
Philosophies, Conceptual Design and Basis of Design. Any
inconsistencies shall be clarified and any additional information
obtained. A Conceptual Design Verification Report shall be prepared.
6.2 The conceptual design documents are not an absolute reference but
are to be used with caution and intelligence. Optimisation of the
concept with respect to the key operational requirements should be
considered and any changes approved by SH.
7.1. General
7.1.3 All design calculations, specifications, drawings and all other related
documents shall be performed using SI units.
7.2. Process
7.2.1 The process engineering scope for the design shall include but not be
limited to the following:
7.3.1 The mechanical engineering scope for the design shall include but not
be limited to the following:
7.4.1 The piping and layout scope for the design shall include but not be
limited to the following:
The unit plot plan should be drawn so that North reads in the
same direction on the paper as the main plant reference
drawings.
Establish specific control points such as main columns and
locate these by coordinates, and then dimension all equipment in
the group from these columns.
Each plan must clearly indicate its top and bottom elevation
limitations.
All plans should be labelled in a similar manner for clarity and
uniformity.
7.5. Electrical
7.5.1 The electrical engineering scope for the design shall include but not be
limited to the following:
7.6.1 The control and instrumentation scope for the design shall include but
not be limited to the following:
7.7.1 The telecommunications scope for the design shall include but not be
limited to the following:
7.8.1 The safety and loss control engineering work shall include, but not be
limited to, the following:
7.8.4 The Contractor shall collate all deliverables associated with HSE
engineering into an HSE Engineering Book.
7.9. Civil/Structural
8.1 A detailed project organisation chart shall be available from the start of
the design stage. The organogram should be added to, modified and
regular updates issued as the project progresses from Design to
Engineering, Procurement, Construction and Commissioning.
8.2 The organogram should show name, role and contact details (email,
telephone and fax number as a minimum).
9. VENDOR SELECTION
9.1 All vendors will have to be on the Approved Vendor List supplied by
SH. Vendors not on this list will have to be approved by SH.
9.2 Vendor selection shall take into consideration, but not be limited to, the
following requirements:
10.1 One standard tagging and labelling system shall be employed for the
whole facility. This should be consistently used and be logical for the
operation and maintenance personnel, and be included in the SH
system.
10.2 All equipment shall be individually tagged such that they are easily
identifiable in the field, and an aid to fault finding.
10.3 Pipelines and flowlines shall be colour coded and easily identifiable
from the air.
10.4 Large equipment such as vessels and tanks shall have clearly visible
tag numbers. All vessel name plates will be stamped with an Algerian
Government stamp after testing.
10.5 The format for ferruling of cabling and terminals should be agreed with
SH prior to commencement of detailed design. Ferruling shall be
consistent and standard across all the plant, including vendor
packages.
11.1. General
11.1.4 Document numbering shall follow a logical format and conform to the
project document numbering standard.
Tag number
Purchase Order Number
Supplier
System
P&IDs
Safeguarding Diagrams
Cause and Effects
Hazardous Area Classification
Line List
Data sheets (Design and Supplier)
Supplier drawings
Piping isometric and general arrangements
Layouts
Instrument layout and hook-up
Cable numbers
Alarm and Trip Schedule
Safety Device Register
Calculations
HAZOP studies
11.2.1 These shall show the system in schematic form and cover any
modifications to the process design throughout field life.
11.2.3 Heat and Material Balance tables shall be produced for each of the
system design cases.
11.3. P&IDs
11.3.2 A Legend sheet shall be produced. This can include typical details
such as shutdown valve instrumentation and sampling skids.
11.3.5 All valves shall be identified with a unique tag number. If this leads
to over-crowding, then a separate drawing with irrelevant items
removed shall be produced.
11.3.6 Flow direction shall generally be from left to right. Main process
streams and vessel outlines shall have heavier line weights than
secondary/utility lines, and instrument signal lines should be lighter
again.
11.3.7 Continuation flags shall include the continuation drawing number and
appropriate description.
11.3.13 P&IDs to be titled consistently throughout the plant. Pro forma title
block shall be agreed with SH prior to commencement of detailed
design.
11.4. Safety Device Register
Relief valves
Trip settings
Control valve trim sizes (for gas blowby relief cases)
Fire proofing insulation
Pump impeller size (may impact discharge pipe rating)
11.5.2 These diagrams are based on the system PFD(s) and show the
location of safeguarding devices such as relief devices, blowdown
devices, shutdown valves.
11.7.1 This is a controlled document that records the tuning parameters for
plant controllers, including set points and controller actions, and
provides background information/references. It is envisaged that this
will be completed during plant commissioning. The register shall
include controller set points
11.8.2 These should be formatted such that any one input device and any
one output device only appears once.
11.9.2 These diagrams shall show the relationship between level instrument
ranges, level bridle lengths, vessel nozzles and actual vessel
elevations.
11.12.3 Valves that have a special status (e.g. locked open) or form part of
an interlock system shall be clearly shown to have that function.
11.13.2 Design data sheets shall clearly state the design basis for the
presented data.
11.13.4 Supplier data sheets for process heat exchangers shall include
system volumes to assist blowdown calculations.
11.14.1 This databook shall include a register of Special Piping items as well
as relevant design and supplier documentation.
11.16.1 Each fiscal metering system shall have a dossier. Each dossier shall
contain:
Inspection certificates.
Calibration certificates.