PMP Revision GKK - 2 - 3 - Oct 2021

Download as pdf or txt
Download as pdf or txt
You are on page 1of 88
At a glance
Powered by AI
The document talks about project cost management processes like planning cost management, estimating costs, determining budget and controlling costs.

The main inputs are Project Charter, Project Management Plan, Project Documents, Agreements, Enterprise Environmental Factors and Organizational Process Assets. The tools & techniques include Expert Judgment, Data Gathering, Data Analysis, Decision Making and Meetings. The output is Stakeholder Engagement Plan.

The main inputs are Project Management Plan, Project Documents, Enterprise Environmental Factors and Organizational Process Assets. The tools & techniques include Expert Judgment, Communication Skills, Interpersonal and Team Skills and Meetings. The outputs are Change Requests, Project Management Plan Updates and Project Documents Updates.

DAY 2

PROJECT MANAGEMENT BODY OF KNOWLEDGE


(PMBOK ® GUIDE 6 TH EDITION) EXAMINATION
GKK 2 ND & 3 RD OCT 2021REVISION CLASS

VETRI SIVAM, PMP,PRINCE2,PRINCE2 AGILE


ITIL V4, LSSGB,LSSBB, ASM, MoR, BIG DATA(UTM), COLOR BRAIN
SPECIALIST

GKK_SIVAM_2&3RD OCT 2021


1
MODULE 7 COST MANAGEMENT
7.1 Plan Cost 7.2 Estimate Costs 7.3 Determine Budget 7.4 Control Costs
Management
• Inputs • Inputs • Inputs • Inputs
• Project Charter • Project Management • Project Management • Project Management
• Project Management Plan Plan Plan
Plan • Project Documents • Project Documents • Project Documents
• Enterprise • Enterprise • Business Documents • Project Funding
Environmental Factors Environmental Factors • Agreements Requirements
• Organizational Process • Organizational Process • Enterprise • Work Performance
Assets Assets Environmental Factors Data
• Tools & Techniques • Tools & Techniques • Organizational Process • Organizational Process
• Expert Judgment • Expert Judgment Assets Assets
• Data Analysis • Analogous Estimating • Tools & Techniques • Tools & Techniques
• Meetings • Parametric Estimating • Expert Judgment • Expert Judgment
• Outputs • Bottom-Up Estimating • Cost Aggregation • Data Analysis
• Cost Management Plan • Three-Point Estimating • Data Analysis • To-Complete
• Data Analysis • Historical Information Performance Index
• Project Management Review • Project Management
Information System • Funding Limit Information System
• Decision Making Reconciliation • Outputs
• Outputs • Financing • Work Performance
• Cost Estimates • Outputs Information
• Basis of Estimates • Cost Baseline • Cost Forecasts
• Project Documents • Project Funding • Change Requests
Updates Requirements • Project Management
• Project Documents Plan Updates
Updates • Project Documents
Updates
2
MODULE 7: COST MANAGEMENT
Project Cost Management establishes the procedures in planning cost management, project cost estimates
for performing all the project activities, including costs of quality management activities, followed by
project budgeting where risk management costs are added as a project cost contingency reserve, and
finally provide the monitoring and controlling mechanism for project cost control
Life-cycle costing for the project capital investment including costs during its useful lifespan
Planning the project scope with an appreciation of Value Engineering i.e. finds alternatives in production
and material with specific economic or production objectives
Percent rule: 0/100, 100/0, 50/50, 25/75, etc. - left number (upfront) followed by right number
(balance at completion of work)
Project Selection is finding out the financial attractiveness of a project investment over others
 Benefit Cost Ratio (BCR) = Benefit/Cost, a.k.a. Return-On-Investment (ROI) = Return/Investment
 Payback Period – how long does it take in time to recover the invested amount and what happens
after this time is unimportant (the shorter the period, the more attractive is the project)
 Discounted Cash Flow using Present Value (PV) where present value accounts for the real value of
future value of money as if at hand today
 PV=FV/ ((1+r)^n) where FV is Future Value; r is interest a.k.a. discount rate, cost of capital, hurdle
rate, or inflation rate, and n is the time periods in the future.
 Net Present Value (NPV) is the cumulative total of PVs over a certain period of time
 Internal Rate of Return (IRR) is the discount rate r, of which the NPV is made zero, and the IRR is
determined by trial and error to make NPV to zero or close to zero as possible (assuming returns are
plowed back as investment)
3
LIFE CYCLE COSTING

4
DEFINITION
Variable Cost cost that is dynamic with the amount of production or work
 Direct Cost (related to the project in question), e.g. salaries, allowances, travel costs
 Indirect or Overhead Cost (not only related to the project in question), e.g. taxes, utility costs
Fixed Cost cost that is static with production or work
 Direct Cost (related to the project in question), e.g. setting up costs, training costs
 Indirect or Overhead Cost (not only related to the project in question), e.g. rentals, security, insurance,
operating permits
Sunk Cost – written-off cost which can never be recovered or considered in a revived project’s budget
(Rough) Order of Magnitude Estimate in the range of -25 to +75% of actual, usually made during
Initiating; Budget(ary) Estimate in the range of -10 to +25% of actual, usually made during early and mid
Planning; and Definitive Estimate in the range of -5 to +10% of actual, usually made during later in
Planning and is based on detailed information
Net Working Capital = Current Assets − Current Liabilities (indicating an organization’s financial health)
Economic Value Added is value produced by the project above the costs of financing the project
Opportunity Cost is the cost of the opportunity one would obtain for an opportunity while neglecting all
other opportunities – adding all the other neglected opportunities is the opportunity cost
Law of Diminishing Returns – in the real world, doing double effort does not mean halving the time taken to
accomplish an activity due to overhead loss or inefficiency
Depreciation is a decrease in the value of an asset over time
1. Straight line depreciation
2. Accelerated depreciation - depreciates much faster than straight line depreciation, e.g. Sum of Years'
Digits, and Double Declining Balances
5
7.1 PLAN COST MANAGEMENT
Cost Management Plan describes how costs will be estimated, budgeted, managed, monitored, and
controlled
Normally, the project financial performance analysis is performed outside the project, or before getting
the project go-ahead (before issuance of the project charter)

INPUTS TOOLS & TECHNIQUES OUTPUTS


The Project Charter, Project Expert Judgment Cost Management Plan containing
Management Plan (e.g. schedule accuracy and precision levels, units
Data Analysis,
management plan, and risk of measure, organizational
management plan) and Meetings procedures links between each
Enterprise Environment Factors (e.g. WBS control account to the
marketplace economic terms and performing organization's
conditions, use of commercial accounting system, control
databases to help estimate costs thresholds, rules of performance
more accurately), and measurement (earned value
Organizational Process Assets like management), reporting formats,
cost estimating policies and and cost management process
templates, historical cost descriptions
information and relevant project
files such as lessons learned from
previous projects

6
7.2 ESTIMATE COSTS
Estimating the amount of monetary resources needed to compete the project activities - resources for cost
estimating are Human Resources, Materials, Equipment, Facilities, Services, Misc., etc., and when estimating
costs, cost trade-offs and cost-related risks must also be considered

INPUTS TOOLS & TECHNIQUES OUTPUTS


Project Management Plan (e.g. cost Expert Judgment, Analogous Cost Estimates, including the Basis
management plan, quality Estimating, Parametric Of Estimates which are supporting
management plan, and scope Estimating, Bottom-Up documents to substantiate how the
baseline), Project Documents (e.g. Estimating and Three-Point cost estimate is obtained, and
lessons learned register, project Estimates Project Documents Updates (e.g.
schedule, resource requirements, and assumption log, lessons learned
risk register), Enterprise Data Analysis (e.g. alternatives register, and risk register)
Environmental Factors (e.g. market analysis, reserve analysis, and
conditions, published commercial cost of quality)
information, and exchange rates Decision Making
and inflation), and Organizational
Process Assets

7
RESERVE ANALYSIS USING MONTE CARLO
SIMULATION & TORNADO DIAGRAM

8
UNDERSTANDING COST RESERVE ANALYSIS
We have understood that we can utilize any of these tools and techniques to produce the cost reserve:

1. Quantitative Cost Risk Analysis (basing on probability of occurrence and cost impact) – this analysis is
mentioned in the 11.4 Quantitative Risk Analysis section

2. Three Point Estimating (uses optimistic best case, most likely and pessimistic worst case costs for use in
Triangular or PERT distribution calculation)

3. Monte Carlo Simulation (simulating many possible and random cost durations bounded by optimistic best
case, most likely and pessimistic worst case costs to find the project cost probability distribution

The cost reserve calculation can either be obtained from [1] when optimistic best case and pessimistic worst case
are not known, [2] for better reserve analysis, or [3] for the best reserve analysis

9
7.3 DETERMINE BUDGET
Aggregating the costs estimated at every activity or work packages, and are then added with the
summation of the activities’ contingency reserves to become the project cost baseline
The project budget is the project cost baseline (from the summation of work package costs and
contingency reserves) provided that the management reserve is not included

INPUTS TOOLS & TECHNIQUES OUTPUTS


Project Management Plan (e.g. cost Cost Aggregation Cost Baseline
management plan, resource
management plan, and scope Funding Limit Reconciliation Known as S-Curve Chart shows the
baseline), Project Documents (e.g. A regulatory function where large project’s accumulated cost
basis of estimates, cost estimates, variation in project expenditure is expenditure pattern over time - this
project schedule, and risk register)
undesirable because of the large chart includes all the necessary
fund disbursements which may cause reserves, where the Project Budget
Business Document (e.g. business difficulties in managing cash flows – = Work Package Cost Estimates +
case, and business management the funding requirement needs to be
smoothened, probably by setting
Contingency Reserves
plan)
date constraints for work, staggering Project Funding Requirements
Agreements (especially the cost- payment schedules, or spreading out
related information), Enterprise procurements over a longer period of Project Documents Updates
Environmental Factors, and time
Organizational Process Assets Expert Judgment, Data Analysis,
Historical Information Review,
and Financing

10
COST BASELINE & PROJECT BUDGETING
Management
Reserve (when
expected to be utilized Read this way
for unknown-unknown
risks
(Multiple)
Contingency
PROJECT Control Activity
Reserve (for
BUDGET Accounts Contingency
known risks)
(this is known Reserve
Cost Baseline as the Project
Budget if Sum of Activities
Management (Multiple)
or Work
Reserve is Activity Cost
Package Cost
excluded) Estimates
Estimates

EARNED VALUE
CHART

11
EARNED VALUE MANAGEMENT FORMULAE
Description of Measurement Description Acronym Formula

How much work should be done? Planned Value PV


How much work is done? Earned Value EV
How much did the “is done” work actually cost? Actual Cost AC

What is the schedule variance now? Schedule Variance SV EV-PV

What is the cost variance now? Cost Variance CV EV-AC

What is the performance index for schedule now? Schedule Performance Index SPI EV/PV

What is the performance index for cost now? Cost Performance Index CPI EV/AC

What do we now expect the project duration to be at completion? Schedule At Completion SAC (Planned Project Duration)/SPI

What was the total job supposed to cost at completion? Budget At Completion BAC

EAC forecast for ETC work


performed at the present CPI
EAC=BAC/CPI or
EAC=AC+ETC
EAC forecast for ETC work
What do we now expect the total job to cost at completion? Estimate At Completion EAC performed at the budgeted
rate EAC=AC+(BAC-EV)
EAC forecast for ETC work
considering both SPI and CPI
EAC=AC+[(BAC–
EV)/(CPI×SPI)]

What do we now expect the remaining cost to be until completion? Estimate To Complete ETC EAC-AC

What do we now expect the cost variance to be at completion? Variance At Completion VAC BAC-EAC

Remaining Work/Remaining
What do we now expect the cost performance index to be until To Complete Performance TCPI Funds: (BAC-EV)/(BAC-AC) or
completion to ensure meeting the cost performance baseline? Index (BAC-EV)/(EAC-AC) when
AC>BAC} 12
7.4 CONTROL COSTS
Causes to inflated expenditures need to be detected promptly and through cost variance analysis – by
comparing the actual expenditures against the planned cost expenditures in the cost performance baseline
or S-cost curve)
Variations need to be kept to a minimum, with an approved cost variation tolerance band called control
thresholds in the cost management plan

INPUTS TOOLS & TECHNIQUES OUTPUTS


Project Management Plan (e.g. cost Expert Judgment, Data Analysis Work Performance Information,
management plan, cost baseline, and (e.g. Earned Value Analysis Cost Forecasts, Change Requests,
performance measurement (EVA), variance analysis, trend Project Management Plan Updates
baselines), Project Documents, analysis using charts and (e.g. cost management plan, cost
Project Funding Requirements, Work forecasts, and reserve analysis)baseline, and performance
Performance Data, and measurement baseline), Project
Organizational Process Assets To-Complete Performance Index Documents Updates, (e.g.
(TCPI) is a measure of the cost assumption log, basis of estimates,
performance that is required to cost estimates, lessons learned
be achieved with the remaining register, and risk register)
resources where TCPI = work
remaining / remaining funds
Project Management
Information System (to capture
planned value PV, earned value
EV, and actual cost AC statistics)
13
7.4 CONTROL COSTS
An oil pipeline 280kms long is to be assembled in a project taking 280 days to complete at a project cost of $28
million.

Assuming the project progresses linearly, we can assume the following:


 280 days → 280kms would mean 1km/day planned productivity rate
 280 days → $28 million would mean $100K/day planned cost expenditure rate
 Where 1km distance costs $100K to assemble or $100K/km

Supposing at Day 5, the engineer on-site announces 7kms had been assembled and the cost accountant says that it
costs $800,000 to perform the work of the engineer
1. PV@Day5 = 5 days x 1km/day x $100K/km = $500K
2. EV@Day5 = 7kms x $100K/km = $700K
3. AC@Day5 = $800K
4. Therefore, SV@Day5 = EV@Day5 - PV@Day5 = $700K - $500K = $200K (worth of work ahead of schedule), and
SPI@Day5 = EV@Day5 / PV@Day5 = 1.4 (the schedule is ahead by 40%)
5. CV@Day5 = EV@Day5 - AC@Day5 = $700K - $800K = -$100K (more spending for the work done) , and CPI@Day5 =
EV@Day5 / AC@Day5 = 0.875 (overspending by 12.5%)
6. If the SPI and CPI are maintained throughout the project until project completion, it is expected that the SAC =
280days/SPI = 200 days, and EAC = $28million/CPI = $32 million
7. Because the project had overspent in the 5 days, it has to “catch up” to ensure that the planned value PV is
maintained until project completion → future CPI value must be TCPI = Remaining Work/Remaining Funds where
(BAC-EV) / (BAC-AC) = ($28million - $700K) / ($28million - $800K) = 1.0037
14
EARNED VALUE CHART

15
QUANTITATIVE RISK ANALYSIS EXAMPLE
A project manager is assigned to a project to build a massive data center complex in a secured
industrial park. The part the manager is involved in is worth $2.6 million. The project plan
requires work to be done to install and setup the server hardware and networking equipment,
test and validate the performance, and install building access security.

A vendor has informed that several key servers may be late to arrive, causing a delay that has
to be overcome by accelerating the installation and testing works. It is predicted that there is a
80% chance the servers will be late by 30 days. To bring the work up to speed will require an
additional cost of $320,000 in overtime payments and other expedition costs. Also, a new
security feature costing $100,000 is included in the security system that can lower the
unauthorized assess risk to the building to 2% where the security breach can cost a goodwill
damage of $500,000.

A bonus worth $50,000 will be awarded when the project can be delivered on time and on
specification,. The project manager estimates a 50% chance of getting the bonus should the
delays be resolved by then.

What is the expected project cost, the best case and its worst-case costs?

Note: Expected Monetary Value (EMV) is positive for opportunities and negative for threats, and the
new Project Cost = project cost – (ΣEMV)
16
MODULE 8 QUALITY
MANAGEMENT
8.1 Plan Quality Management 8.2 Manage Quality 8.3 Control Quality

• Inputs • Inputs • Inputs


• Project Charter • Project Management Plan • Project Management Plan
• Project Management Plan • Project Documents • Project Documents
• Project Documents • Organizational Process Assets • Approved Change Requests
• Enterprise Environmental Factors • Tools & Techniques • Deliverables
• Organizational Process Assets • Data Gathering • Work Performance Data
• Tools & Techniques • Data Analysis • Enterprise Environmental Factors
• Expert Judgment • Decision Making • Organizational Process Assets
• Data Gathering • Data Representation • Tools & Techniques
• Data Analysis • Audits • Data Gathering
• Decision Making • Design for X • Data Analysis
• Data Representation • Problem Solving • Inspection
• Test and Inspection Planning • Quality Improvement Methods • Testing/Product Evaluations
• Meetings • Outputs • Data Representation
• Outputs • Quality Reports • Meetings
• Quality Management Plan • Test and Evaluation Documents • Outputs
• Quality Metrics • Change Requests • Quality Control Measurements
• Project Management Plan • Project Management Plan • Verified Deliverables
Updates Updates • Work Performance Information
• Project Documents Updates • Project Documents Updates • Change Requests
• Project Management Plan
Updates
• Project Documents Updates
17
DEFINITION
Quality is the degree to which a set of inherent characteristics fulfills requirements (e.g. a candidate
wanting to “pass” the exam and not about getting excellent grades)
Grade is a category or rank used to distinguish items that have the same functional use but do not share
the same requirements for quality (e.g. choice of different PC processors, different grades of engine oil,
etc.)
Precision is the level of consistency of repeated measurements or exactness, whereas accuracy is the
assessment of “correctness” of the measured value to a certain measure standard
Prevention Over Inspection – when quality is built into or having good quality assurance, there should be
little reason for non-conformance to happen!
Outliers (assignable causes are mentioned in [ ], special cause in red)
[overfill due to machine restart] [overfill due to jammed bottle] Common Causes are also known as
randomly occuring causes in a process
UCL – they are normal process variations
48.5 Special Causes are where assignable
causes reveal as unusual events which
occur in a process and these are not
LCL normal process variations
35.3
Control Limits are observed data points
within the tolerances bounded by the
upper control limit (UCL) and the lower
control limit (LCL) are known to be “in-
control”, and those outside are “out-of-
control” or outliers 18
DEFINITION
Cost of Quality (COQ) is the total price of all efforts to achieve product or service quality, and this includes all
work to build a product or service that conforms to the requirements as well as all work resulting from
nonconformance to the requirements
COQ should be incorporated into the project cost estimate, and it includes:
Cost of conformance: Cost of non-conformance:
 Planning ◦ Scrap
 Training and indoctrination ◦ Rework
 Process control ◦ Expediting
 Field testing ◦ Additional material or inventory
 Product design validation ◦ Warranty repairs or service
 Process validation ◦ Complaint handling
 Test and evaluation ◦ Liability judgments
 Quality audits ◦ Product recalls
 Maintenance and calibration ◦ Product corrective actions
Tolerance is a range of acceptable results within upper and lower limits
Standard Deviation (or Sigma) is the distance from the mean value
+/- 6 sigma: 99.99%; +/- 3 sigma: 99.73%;
+/- 2 sigma: 95.46%; +/- 1 sigma: 68.26%

19
DEFINITION
Internal failures are found in the project, and external failures are found by the customer
Marginal Analysis shows that there is an optimal quality cost for projects, where investing in additional
prevention/appraisal costs is neither beneficial nor effective
Prevention – Avoiding quality non-conformance (quality assurance)
Inspection – Appraising if quality is being met (purposely seeking non-compliance)
Attribute Sampling – Numerical count of conformance or non-conformance in a sample (countable non-
conformance like number of faulty light bulbs)
Variables Sampling – Continuous-scale measurement of a certain measure in a sample (like appraising
the actual volume of liquids, weights, lengths to target KPIs)
Customer Satisfaction – project customer is satisfied when the project
deliverables or results conform to their quality expectations and
needs
Prevention Over Inspection – when quality is built into or having good
quality assurance, there should be little reason for non-conformance
to happen!
Plan-Do-Check-Act (PDCA) - an iterative four-step management
method for the control and continual improvement of processes and
products; also known as the Shewhart-Deming cycle

20
8.1 PLAN QUALITY MANAGEMENT
Quality planning is conducted simultaneously with other project planning processes and it determines
which quality standard to comply, how compliance is satisfied, and accommodate the performing
organization’s quality policy and project customer quality validation format
According to Deming and Juran, most of the quality problems that exist are due to a defect or failure in
processes that are controlled by the quality policy defined according to the performing organization’s top
management and their lack of leadership in this area
Deming supports the practice of ceasing mass inspections and ending awards based on price

INPUTS TOOLS & TECHNIQUES OUTPUTS


Project Charter, Project Data Gathering (e.g. Quality Management Plan, Quality
Management Plan (e.g. benchmarking, brainstorming, Metrics, Project Management Plan
requirements management plan, risk and interviews) Updates (e.g. risk management
management plan, stakeholder plan, and scope baseline), and
Data Analysis (e.g. cost-benefit Project Documents Updates (lessons
engagement plan, and scope
analysis, and cost of quality) learned register, requirements
baseline)
Decision Making (e.g. flowcharts, traceability matrix, risk register, and
Project Documents (e.g. assumption logical data model, matrix stakeholder register)
log, requirements documentation, diagrams, and mind mapping)
requirements traceability matrix, risk
register and stakeholder register), Data Representation, Expert
Enterprise Environment Factors, and Judgment, Test and Inspection
Organizational Process Assets Planning, and Meetings
21
8.2 MANAGE QUALITY
The process is conducted throughout the project life cycle but is more intense during Executing phase, and it
translates the quality management plan into executable quality activities
The process uses quality control measurements which are data and results from 8.3 Control Quality
process to bring quality assurance while in a broader sense also have concern with the product design
aspects, design guidelines, and process improvements
This process is where project managers have greatest influence over quality, or impact on the quality of
the project during this process
In agile projects, quality management is performed by all team members throughout the project, but in
traditional projects, quality management is often the responsibility of specific team members

INPUTS TOOLS & TECHNIQUES OUTPUTS


Project Management Plan, Project Data Gathering, Data Analysis, Quality Reports, Test and
Documents (e.g. lessons learned Decision Making, Data Evaluation Documents, Change
register, quality control Representation, scheduled or Requests (e.g. corrective and
measurements, quality metrics, and random quality Audits preventive changes), Project
risk report), and Organizational Design for X is a set of technical Management Plan Updates and
Process Assets guidelines for the design and Project Documents Updates Note: In
optimization of a product agile, retrospectives are considered
Problem Solving, and Quality as lessons learned within the context
Improvement Methods (e.g. of “Manage Quality” process
PDCA and Six Sigma)
22
FLOWCHARTING

SCATTER DIAGRAM
(OR SCATTER PLOT)
Used to determine
the relationship
Variable A

between two or CAUSE & EFFECT


more pieces of DIAGRAM
corresponding data Analyzes the Input to a
The data are process to identify the
plotted on an "X-Y" causes of errors to an
chart to determine observed effect
correlation

CAUSE
& EFFECT
Variable B
DIAGRAM
23
8.3 CONTROL QUALITY
Controlling quality is a reactive initiative, that is to identify, recommend, correct, repair, or fix non-
conformance after the non-conformance has been detected through stakeholder inspection or complaints
It requires project deliverables to be verified (for completeness, compliance, and fitness for use) by the
project team to meet stakeholders’ requirements, and for final acceptance
Control Quality process is performed throughout the project life cycle, but more intensely during
Monitoring and Controlling phase
In agile projects, the Control Quality activities may be performed by all team members throughout the
project life cycle but in waterfall model-based projects, the quality control activities are performed at
specific times, toward the end of the project or phase, by specified team members

INPUTS TOOLS & TECHNIQUES OUTPUTS


Project Management Plan, Project Data Gathering (e.g. checklists, Quality Control Measurements are
Documents (e.g. lessons learned check sheets, statistical sampling, the results obtained from quality
register, quality metrics, and test and and questionnaires and surveys), control initiatives passed back to
evaluation documents), Approved Data Analysis (e.g. performance manage quality process
Change Requests, Deliverables, reviews, and root cause analysis), Verified Deliverables, Work
Work Performance Data, Enterprise Inspection, and Testing/Product Performance Information, Change
Environmental Factors, and Evaluations Requests, Project Management Plan
Organizational Process Assets Data Representation, Meetings Updates, Project Documents
Updates

24
SEVEN BASIC QUALITY TOOLS
1. Cause-And-Effect Diagram (a.k.a. Ishikawa diagram or fishbone diagram) shows the causes
relating to an anticipated or observed effect
2. Flowcharts
3. Checksheet organizes facts to reveal certain traits or patterns
4. Pareto Diagram is a ranked frequency histogram detailing the attributes or causes of non-
compliance/defects (also known as 80/20 rule where 80% of defects are contributed by a lesser
few 20%)
5. Histogram is a bar chart which shows statistical distributions from the frequency of occurrence
6. Control Chart plots process variations bounded by two sets of limits

Process-determined Upper (UCL) and Lower (LCL)


Control Limits which are moving averages based on a
certain standard deviation or sigma (e.g. ±3s)
May have project customer-specified Upper (USL) and
Lower (LSL) Specification Limits
Out-Of-Control (a.k.a. outliers) points are either
process data points beyond the UCL/LCL limits, or
rule-of-seven (or Run) data points grouped suspiciously
above or below the mean because they show non-
random behavior

7. Scatter Diagram (a.k.a. Scatterplot) shows if there is any relationship or correlation between two
factors or variables
25
CHECKSHEET & PARETO DIAGRAM

PARETO DIAGRAM
• Ranks defects in order of frequency of occurrence to
depict 100% of the defects (displayed as a histogram)
• Defects with most frequent occurrence should be
targeted for corrective action.
• 80-20 rule: 80% of problems are found in 20% of the
work.
• It does not account for severity of the defects

26
27
Unusual behavior - Rule of Seven:
CONTROL CHART out of control (outliers) here is known as a “run”

RUN CHART
Apart from the normally understood out-of-control points
or outliers, we use the rule of seven data points in a row
and this is also called a Run: A series of consecutive
points on the same side of the average and is considered
abnormal if 7 consecutive points data points are above
or below the process mean because of suspicious non-
randomness and requires investigation

A Run Chart is a chart useful to observe shifts and trends


– a series of consecutive points which reflect a steadily
increasing or decreasing pattern
28
MODULE 9 RESOURCE MANAGEMENT
9.1 Plan Resource 9.2 Estimate Activity 9.3 Acquire Resources 9.4 Develop Team 9.5 Manage Team 9.6 Control Resources
Management Resources
• Inputs • Inputs • Inputs • Inputs • Inputs • Inputs
•Project Charter •Project Management •Project Management •Project Management •Project Management •Project Management
•Project Management Plan Plan Plan Plan Plan
Plan •Project Documents •Project Documents •Project Documents •Project Documents •Project Documents
•Project Documents •Enterprise •Enterprise •Enterprise •Work Performance •Work Performance
•Enterprise Environmental Factors Environmental Factors Environmental Factors Reports Data
Environmental Factors •Organizational •Organizational •Organizational •Team Performance •Agreements
•Organizational Process Assets Process Assets Process Assets Assessments •Organizational
Process Assets • Tools & Techniques • Tools & Techniques • Tools & Techniques •Enterprise Process Assets
• Tools & Techniques •Expert Judgment •Decision Making •Colocation Environmental Factors • Tools & Techniques
•Expert Judgment •Bottom-Up Estimating •Interpersonal and •Virtual Teams •Organizational •Data Analysis
•Data Representation •Analogous Estimating Team Skills •Communication Process Assets •Problem Solving
•Organizational •Parametric Estimating •Pre-Assignment Technology • Tools & Techniques •Interpersonal and
Theory •Data Analysis •Virtual Teams •Interpersonal and •Interpersonal and Team Skills
•Meetings •Project Management • Outputs Team Skills Team Skills •Project Management
• Outputs Information System •Physical Resource •Recognition and •Project Management Information System
•Resource Management •Meetings Assignments Rewards Information System • Outputs
Plan • Outputs •Project Team •Training • Outputs •Work Performance
•Team Charter •Resource Requirements Assignment •Individual and Team •Change Requests Information
•Project Documents •Basis of Estimates •Resource Calendars Assessments •Project Management •Change Requests
Updates •Change Requests •Meetings Plan Updates •Project Management
•Resource Breakdown •Project Documents
Structure •Project Management • Outputs Plan Updates
Plan Updates •Team Performance Updates •Project Documents
•Project Documents •Enterprise
Updates •Project Documents Assessments Updates
Updates •Change Requests Environmental Factors •Enterprise
•Enterprise •Project Management Updates Environmental Factors
Environmental Factors Plan Updates Updates
Updates •Project Documents
•Organizational Updates
Process Assets •Enterprise
Updates Environmental Factors
Updates
•Organizational
Process Assets
Updates

29
ORGANIZATIONAL CONSIDERATIONS FOR PROJECT
AGILITY
Organizational process assets (OPAs) and enterprise environmental factors (EEFs) can influence both the
direction and the outcome of any project

Organizational change management covers the skills and techniques for influencing changes that
support agility

Two key factors that motivate the use of change management in an agile context are:
1. Changes associated with accelerated delivery: early and often - unfortunately, the customer organization
many not be ready to accept the delivery at this increased pace and this requires alignment between
customer acceptance and project outputs pace

2. Changes associated with agile approaches – organizations just beginning to embrace agile approaches see
high degrees of change, thus requiring transitioning to more frequent hand-offs between teams, departments,
or vendors

Barriers to change happen when work is decomposed into departmental silos instead of building cross-
functional collaboration, short-term pricing strategies instead of long-term, failing to look at the big
picture delivery, lack of incentives to hone and diversify skills, and overwhelming many projects at once

When details of a deliverable are not sufficiently known, a planning package should be used, where
the details of the deliverables defined within planning packages can be considered known unknowns,
or risks
TRENDS AND EMERGING PRACTICES
 Resource management methods - due to the scarce nature of critical resources, concepts in lean
management, just-in-time (JIT), Kaizen, total productive maintenance (TPM), theory of constraints (TOC),
and other methods are used
 Emotional intelligence (EI) - the project manager should invest in personal EI by improving inbound (e.g.
self-management and self-awareness) and outbound (e.g. relationship management) competencies
 Self-organizing teams - the increase in using agile approaches requires team functions to operate
without centralized control, and the project manager provides the environment and support needed and
trusts the team to get the job done. The team continuously adapt to the changing environment and
embrace constructive feedback
Virtual teams/distributed teams – the globalization of projects has need for virtual teams and they are not
co-located at the same site. The availability of communication technology has made virtual teams
feasible. The challenges of managing virtual teams are mainly in the communication domain, including a
possible feeling of isolation, gaps in sharing knowledge and experience between team members, and
difficulties in tracking progress and productivity, possible time zone difference and cultural differences

Parkinson's law states that “work expands so as to fill the time available for its completion”
 If something must be done in a year, it will be done in a year ; if something must be done tomorrow, it
will be done tomorrow
Student syndrome refers to planned procrastination
 A student will only start to apply themselves to an assignment at the last possible moment before its
deadline, and this eliminates any potential safety margins and puts the person under stress and
pressure
31
ORGANIZATIONAL CULTURE
Every project has its own aspirations complete with culture and
requirements of where emphasis is placed within the business
environment
Awareness of the organizational priorities must be communicated, and
priorities are recorded between two extremes like:
 Exploration - Execution
 Speed - Stability
 Quantity - Quality, and
 Flexibility – Predictability

Every organization has tradeoffs, and the best balance is required to


establish the right priorities for an agile implementation
ORGANIZATIONAL STRUCTURE
The structure of an organization strongly influences through:
 Geographically distributed and dispersed project organizations may find several challenges
impeding their work on any project
 Projects with highly functionalized structures may find general resistance to collaboration across its
organization
 Reducing the size of a project deliverable will motivate more frequent handoffs across departments,
and thus more frequent interactions and a faster flow of value across the organization.
 Allocation of people to projects
 Some organizations choose to implement projects primarily through vendors and through agile
techniques such as retrospectives and follow up on possible improvement areas when the vendor is
still engaged can help mitigate loss of product knowledge
When addressing an individual challenge area or implementing a new hybrid or agile
approach, it is recommended to undertake the work incrementally
A common practice is to treat the change process as an agile project with its own backlog
of changes that could be introduced and prioritized by the team, based on perceived
value or other considerations
AGILE PMO
Agile creates cultural change and the PMO helps to shepherd the
business value creation across the organization
The PMO needs to be conversant in several competencies such as:
 Developing and implementing standards
 Developing personnel through training and mentoring
 Multiproject management
 Facilitating organizational learning
 Managing stakeholders
 Recruiting, selecting, and evaluating team leaders
 Executing specialized tasks for projects
MANAGEMENT & LEADERSHIP
In agile/adaptive environments, the projects will have high variability and can benefit from team
structures that maximize focus and collaboration, such as self organizing teams with generalizing
specialists, and therefore planning for physical and human resources is much less predictable in projects
with high variability
Management involves using positional power to produce results and control
Leadership involves:
 Visionary - setting long-term direction and aligning people through relational power
 Innovative, challenges status quo, motivating, and inspiring trust
 Communicating, building and preserving relationships
 Facilitating ethical conduct, negotiating, and leading change
Responsibility and accountability
 Project manager is ultimately responsible (accountable) for the entire project and the team
 Project manager gives responsibility and authority to the team by delegating, and expects reliability
and accountability from the team in return

35
FORMS OF POWER
The ability of one person to influence the behavior of another
1. Positional also called formal, authoritative, legitimate (e.g. formal position granted in the
organization or team)
2. Informational (e.g. control of gathering or distribution)
3. Referent (e.g. respect or admiration others hold for the individual, credibility gained)
4. Situational (e.g. gained due to unique situation such as a specific crisis)
5. Personal or charismatic (e.g. charm, attraction)
6. Relational - preferable power (e.g. participates in networking, connections, and alliances)
7. Expert – preferable power (e.g. skill, information possessed; experience, training, education,
certification)
8. Reward-oriented – preferable power (e.g. ability to give praise, monetary or other desired
items)
9. Punitive or coercive – least preferable power (e.g. ability to invoke discipline or negative
consequences)
10. Ingratiating (e.g. application of flattery or other common ground to win favor or cooperation)
11. Pressure-based (e.g. limit freedom of choice or movement for the purpose of gaining compliance
to desired action)
12. Guilt-based (e.g. imposition of obligation or sense of duty)
13. Persuasive (e.g. ability to provide arguments that move people to a desired course of action)
14. Avoiding (e.g. refusing to participate)
36
LEADERSHIP STYLES
Many ways of leading the team depending on the leader, team member, organization and
environmental characteristics, such as:
1. Laissez-faire (e.g. allowing the team to make their own decisions and establish their own
goals, also referred to as taking a hands-off style)
2. Transactional - most typically used (e.g. focus on goals, feedback, and accomplishment to
determine rewards; management by exception)
3. Servant leader (e.g. demonstrates commitment to serve and put other people first by
focussing on other people’s growth, learning, development, autonomy, and well-being;
concentrates on relationships, community and collaboration; leadership is secondary and
emerges after service)
4. Transformational (e.g. empowering followers through idealized attributes and behaviors,
inspirational motivation, encouragement for innovation and creativity, and individual
consideration)
5. Charismatic (e.g. able to inspire; is high-energy, enthusiastic, self-confident; holds strong
convictions)
6. Interactional – most preferred (e.g. a combination of transactional, transformational, and
charismatic)

37
HERSEY AND BLANCHARD SITUATIONAL
LEADERSHIP STYLES & BRUCE TUCKMAN TEAM
DEVELOPMENT PHASES
Hersey and Blanchard characterized leadership
styles into four behavior types, which they
named S1 to S4:
 S1: Directing (or Telling) - is characterized by one-
Encouraging Steering way communication in which the leader defines the
roles of the individual or group and provides the
what, how, why, when and where to do the task
 S2: Coaching (or Selling) - while the leader is still
providing the direction, he/she is now using two-way
communication and providing the socio-emotional
support that will allow the individual or group being
influenced to buy into the process and build
teamwork
Entrusting Tasking  S3: Supporting (or Participating) - this is how shared
Low Directive High Directive decision making about aspects of how the task is
and Low Supportive and Low Supportive accomplished and the leader is providing less task
Behavior Behavior
behaviors while maintaining high relationship
behavior
 S4: Delegating - the leader is still involved in
decisions; however, the process and responsibility has
been passed to the individual or group. The leader
stays involved to monitor progress
Adjourning Performing Norming Storming Forming
Effective leaders need to be flexible, and must
adapt themselves according to the situation
38
CONFLICT RESOLUTION TECHNIQUES
1. Collaborate/ Work together and diffuse head-on conflicts, or find solutions to the root cause
Problem Solve of the conflict. Most preferable technique because of its “win-win” approach.

Finding solutions that are majority acceptable to the affected parties.


2. Compromise/
Regarded as second preferable a “lose some-lose some” solution when all
Reconcile
parties give something up to meet in the “middle” and reach a consensus.

Retreating from the conflict, or deferring it to be resolved at a later date or


3. Withdraw/
get it resolved by others. Perhaps conducted because of other pressing issues
Avoid
to consider. Does not provide a solution to the conflict.

Focusing on what has been agreed upon rather than the differences of
4. Smooth/ opinion, in order to minimize disagreements by making differences seem less
Accommodate important. May involve willing to give up someone’s interest to the needs of
others to achieve harmony. Does not provide a solution to the conflict.

Imposing own opinion or viewpoint (solution) on others (using his/her superior


power position) and eliminating the other parties’ opinions. Least preferable
5. Force/Direct
technique, and is a “I win, you lose” solution and may result in increased
conflict later. Perhaps conducted because of an urgent or emergency situation.
39
THEORIES OF MOTIVATION
Maslow's Hierarchy Of Needs Theory
The lower-level needs must be satisfied first before the higher
needs can be addressed - individuals have five levels of needs in
which motivational tension develops and is directed towards
satisfying the next level of unmet need
The person advances to the next level of needs after the lower
level need is at least satisfied

Level 5: Self-actualization
Level 4: Self-esteem, recognition
Level 3: Socialization, acceptance, love
Level 2: Security and safety
Level 1: Food, shelter and clothing

40
THEORIES OF MOTIVATION Contingency Theory
There is “no one best way to manage people” – it is all too
dependent on the person himself and the situation the
person is in
Frederick Herzberg's Motivation-Hygiene Theory
Consists of satisfiers (motivators) and the
dissatisfiers (hygiene factors) using the term hygiene Vroom’s Expectancy Theory
in the sense that they are considered maintenance Creating an expectancy in a person, the expectancy may
factors that are necessary to avoid dissatisfaction indeed become a fact through motivating by altering the
person's effort-to-performance expectancy, performance-
If individuals are satisfied, they can thus be
to-reward expectancy, and the reward valence (the value
motivated because it is the job content or job
an individual places on the rewards of an outcome)
passion that motivates individuals

These are Hygiene Factors These will make McGregor's Theory X and Theory Y
or “must haves”, otherwise people more Theory X says that people inherently dislike work, prefer to
people will be dissatisfied satisfied be directed, and that they must be coerced or controlled to
do work to achieve objectives
Theory Y says that people view work as being as natural as
play and rest, and they will exercise self-direction and
control towards achieving objectives they are committed to,
and they learn to accept and seek responsibility

Theory Z
The belief that management's high levels of trust,
confidence and commitment to workers leads to high levels
of motivation and productivity on the part of workers
41
THEORIES OF MOTIVATION
McClelland's Three Needs Theory (also known as Achievement Motivation Theory) proposed that an
individual’s specific needs are acquired over time and are shaped by one’s life experiences
A person’s motivation and effectiveness in certain role functions are influenced by three needs
1. Achievement need - people with a high need for achievement loves to seek challenges to achieve
and excel
2. Affiliation need - the need to feel accepted by other people, living and working harmoniously, and
delights in personal interactions
3. Power need - a person's need for power can be one of two types - personal and institutional
 Those who need personal power want to direct others
 Persons who need institutional power (also known as social power) want to organize the efforts of
others to further the goals of the organization
 Managers with a high need for institutional power tend to be more effective than those with a high
need for personal power

McClelland says that people with different needs are motivated differently
 High need for achievement (Ach) - high achievers should be given challenging projects with
reachable goals
 High need for affiliation (Aff) - employees with a high affiliation need perform best in a cooperative
environment
 High need for power (Pow) - management should provide power seekers the opportunity to manage
others
42
9.1 PLAN RESOURCE MANAGEMENT
Project resources include team members, supplies, materials, equipment, services and facilities - physical
resources are acquired from the performing organization’s internal assets or procured from outside, and
team resources are recruited into project roles, developing the team and administering their competency
development
Resource availability and the country’s governing laws need to be considered – planning for the team
resources is done by the project manager and the human resource manager
Collective action refers to action taken together by a group of people whose goal is to enhance their
status and achieve a common objective, and it is enacted by a representative of the group

INPUTS TOOLS & TECHNIQUES OUTPUTS


Project Management Plan, and Expert Judgment Resource Management Plan
Project Documents Data Representation Identification of resources, acquiring
resources, roles, authority,
Enterprise Environmental Factors Assignment matrix shows the competence, and responsibilities
engagement with worker’s union via project resources assigned to
Collective Bargaining Agreements, Contains project organization charts,
each work package – one project team resource management,
and existing economic conditions) example of a responsibility training, team development, resource
Organizational Process Assets assignment matrix is a RACI control, and recognition plan
(Responsible, Accountable, (recognition and rewards)
Consult, and Inform) chart
Organizational Theory and Team Charter and Project
Meetings Documents Updates
43
RACI CHART

RACI Person Person Person Person Person Person


Activity 1 2 3 4 5 6

Obtain user requirements A R C I C C

Produce technical
R R I C I A
specifications

Produce design schematics R C R A I C

Conduct alternatives study C I R R I A

44
9.2 ESTIMATE ACTIVITY RESOURCES
This process estimates the team resources, and the type and quantities of materials, equipment, and
supplies necessary to perform project work
This process is closely coordinated with other processes such as the 7.2 Estimate Costs process

INPUTS TOOLS & TECHNIQUES OUTPUTS


Project Management Plan (e.g. Expert Judgment, Bottom-Up Resource Requirements, Basis of
resource management plan, and Estimating, Analogous Estimates, Resource Breakdown
scope baseline), Project Documents Estimating, Parametric Structure which is a hierarchical
(e.g. activity list, activity attributes, Estimating, Data Analysis, structure of resource types (e.g.
assumption log, cost estimates, Project Management human resource, equipment,
resource calendars, and risk Information System, and material, facility, and others), and
register), Enterprise Environmental Meetings Project Documents Updates (e.g.
Factors, and Organizational activity attributes, assumption log,
Process Assets and lessons learned register)

45
9.3 ACQUIRE RESOURCES
This process obtains team members, facilities, equipment, materials, supplies, and other resources
necessary to complete project work, and this can happen anytime throughout the project

INPUTS TOOLS & TECHNIQUES OUTPUTS


Project Management Plan, (e.g. Decision Making (multi-criteria Physical Resource Assignments, and
resource management plan, decision analysis to make Project Team Assignments
procurement management plan selections based on availability, Knowing when resources are
obtained from 12.1 Plan cost, ability, experience, available using Resource
Procurement Management process, knowledge, skills, attitude, and Calendars, and making Change
and cost baseline) international factors) Requests
Project Documents (e.g. project Interpersonal and Team Skills Project Management Plan Updates
schedule, resource calendars, (negotiating for resources with
resource requirement, and functional managers, other Project Documents Updates
stakeholder register) teams, external organization Enterprise Environmental Factors
Enterprise Environmental Factors, and suppliers) Updates, and Organizational
and Organizational Process Assets Pre-Assignment (where team Process Assets Updates
members are already given)
Using Virtual Teams where the
team members are separated
by great distances

46
9.4 DEVELOP TEAM
Developing the team (including the project manager) to have high team performance throughout the
project life cycle - the cost of developing the team comes from the project budget

INPUTS TOOLS & TECHNIQUES OUTPUTS


Project Management Plan, Project Colocation (e.g. war room or Team Performance Assessment of
Documents (e.g. lessons learned tight matrix is where a team can developmental activities and team
register, project schedule, project sit together and get closer effectiveness, Change Requests,
team assignments, resource communication and Project Management Plan Updates
calendars, and team charter), and teamworking), Virtual Teams, (e.g. lessons learned register, project
Enterprise Environmental Factors using Communication schedule, project team assignments,
Technology (e.g. shared portal resource calendars, and team
or repository, video charter), Enterprise Environmental
conferencing, audio Factors Updates , and
conferencing, and email/chat), Organizational Process Assets
Interpersonal and Team Skills Updates
(e.g. conflict management,
influencing, motivation,
negotiation, and team building),
Recognition and Rewards,
Training, Individual and Team
Assessments, and Meetings

47
9.5 MANAGE TEAM
Managing team members performance, optimizing performance, observing behavior, manages conflicts,
and resolves issues

INPUTS TOOLS & TECHNIQUES OUTPUTS


Project Management Plan, Project Interpersonal and Team Skills Change Requests to correct any
Documents (e.g. issue log, lessons (e.g. conflict management by shortcomings or enhancements,
learned register, project team intervening early and apply Project Management Plan Updates
assignments, and team charter), conflict resolution techniques, (e.g. Resource management plan,
Work Performance Reports (from decision making, emotional schedule baseline, and cost baseline),
4.5 Monitor and Control Project intelligence, influencing, and Project Documents Updates (e.g.
Work), Team Performance leadership), and Project Issue log, lessons learned register,
Assessments, Enterprise Management Information and project team assignments), and
Environmental Factors, and System Enterprise Environmental Factors
Organizational Process Assets Note: HR performance appraisals
Note: Reward items like perquisites may use 360-deg feedback
(perks) are at management’s
discretion (different from
employment benefits)

48
9.6 CONTROL RESOURCES
Controlling physical resources assignments and allocation as per plan, monitoring the planned and actual
utilization of resources, taking actions

INPUTS TOOLS & TECHNIQUES OUTPUTS


Project Management Plan, Project Data Analysis (e.g. alternatives Work Performance Information,
Documents (e.g. issue log, lessons analysis, cost-benefits analysis, Change Requests, Project
learned register, physical resource performance reviews, and trend Management Plan Updates (e.g.
assignments, project schedule, analysis), Problem Solving, resource management plan, schedule
resource breakdown structure, Interpersonal and Team Skills baseline, and cost baseline), Project
resource requirements, and risk (e.g. negotiation and Documents Updates (e.g.
register), Work Performance Data, influencing), and Project assumption log, issue log, lessons
Agreements, and Organizational Management Information learned register, physical resource
Process Assets Systems assignments, resource breakdown,
and risk register)

49
MODULE 10 COMMUNICATIONS
MANAGEMENT
10.1 Plan Communications 10.2 Manage Communications 10.3 Monitor Communications
Management
• Inputs • Inputs • Inputs
• Project Charter • Project Management Plan • Project Management Plan
• Project Management Plan • Project Documents • Project Documents
• Project Documents • Work Performance Reports • Work Performance Data
• Enterprise Environmental Factors • Enterprise Environmental Factors • Enterprise Environmental Factors
• Organizational Process Assets • Organizational Process Assets • Organizational Process Assets
• Tools & Techniques • Tools & Techniques • Tools & Techniques
• Expert Judgment • Communication Technology • Expert Judgment
• Communication Requirements • Communication Methods • Project Management Information
Analysis • Communication Skills System
• Communication Technology • Project Management Information • Data Representation
• Communication Models System • Interpersonal and Team Skills
• Communication Methods • Project Reporting • Meetings
• Interpersonal and Team Skills • Interpersonal And Team Skills • Outputs
• Data Representation • Meetings • Work Performance Information
• Meetings • Outputs • Change Requests
• Outputs • Project Communications • Project Management Plan
• Communications Management • Project Management Plan Updates
Plan Updates • Project Documents Updates
• Project Management Plan • Project Documents Updates
Updates • Organizational Process Assets
• Project Documents Updates Updates
50
MODULE 10: COMMUNICATIONS MANAGEMENT

It is found that 80%-90% of a project manager’s time is spent on


communicating the project, making communication a key requirement
and processes are required for the collection and consolidation of data,
creation, release and storage of the kinds of information to be
communicated with selected stakeholders at the right time and place
There are two parts to successful communication:
1. Developing an appropriate communication strategy based on both the
needs of the project and the project’s stakeholders
2. From that strategy, a communications management plan is developed to
ensure that the appropriate messages are communicated to stakeholders
in various formats and various means as defined by the communication
strategy
Communication has to be adaptive to the stakeholders because of the
different cultures, competency backgrounds, expertise levels,
understanding and influence
51
COMMUNICATION THEORY – JOHARI WINDOW
The Johari window has four quadrants representing
Open Area, Blind Spot, Hidden Area, and Unknown
Area
 Arena or Open Area - represents public information about
the person, known by each individual and others
 Blind Spot or Blind Area - refers to the characteristics of the
person unknown to the individual themselves, but known to
others
 Facade or Hidden Area: - represents the secret side of the
person, or what the person knows, and others do not know,
the individual keeping such information concealed
deliberately or otherwise
 Unknown Area - represents the characteristics innate in a
person, but which neither the person nor anyone else comes  The purpose of the Johari window concept
to realise is to expand the open area of an
The ultimate need is to enlarge the open self individual through self-disclosure and
quadrant with the intent to establish a fruitful feedback
relationship with the self as well with others such that  Self disclose by the person expands the
the work can be performed efficiently when working open area horizontally by contracting the
as a team facade or hidden area
 Feedback from others expands the open
area vertically by contracting the unknown
area
52
Communication Dimensions
Written
Verbal Visual
Printed words, figures, drawings, graphs,
Listening and talking Video, demonstrations
schematics

Verbal Nonverbal, Indirect (a.k.a. paralingual)


Vocalized message Volume, pitch, rhythm, body language (e.g. gestures)

Internal External
In-project communication needs Press release, media statement
Vertical Horizontal
Superiors and subordinates Peers
Formal
Informal
Reports, briefings, presentations,
Sketches, paper notes, casual discussions, company and personal emails
newsletters, company letters

Communication Methods
Between two or more parties performing a multidirectional exchange of information
Interactive
in real time. It employs communications artifacts such as meetings, phone calls, instant
Communication
messaging, some forms of social media, and videoconferencing.

Sent or distributed directly to specific recipients who need to receive the information.
This ensures that the information is distributed but does not ensure that it actually
Push Communication
reached or was understood by the intended audience. Push communications artifacts
include letters, memos, reports, emails, faxes, voice mails, blogs, and press releases.
Used for large complex information sets, or for large audiences, and requires the
recipients to access content at their own discretion subject to security procedures.
Pull Communication
These methods include web portals, intranet sites, e-learning, lessons learned
databases, or knowledge repositories.
53
Steps For Effective Communication

1. Prepare your message, intent


A. Sender and purpose beforehand
encode
message 2. Encode the message into a
format and language the
recipient can understand
accurately

Communication 3. Time the message transmission


D. Recipient
may Noise B. Sender and choose a suitable
acknowledge; transmit
Values, culture, message via transmission medium to allow for
feedback or taboos, beliefs, suitable
respond to maximum recipient's attention or
message distance, out-of- medium
context urgency

4. Ensure the recipient understood


(acknowledge) the message

C. 5. Recipient understands the


Recipient message carefully and
decode accurately or check facts first
message before feedback or responding
to sender

54
10.1 PLAN COMMUNICATIONS MANAGEMENT
This process is about finding out the kinds of information and other communication needs of the project
stakeholders – who needs it, when should the information be released, what information to release, who
prepares the information, how is the information released

INPUTS TOOLS & TECHNIQUES OUTPUTS


Project Charter, Project Expert Judgment, and Communications Management Plan,
Management Plan (e.g. resource Communication Requirement Project Management Plan Updates,
management plan, and stakeholder Analysis and Project Documents Updates
engagement plan), Project (e.g. project schedule, and
Total number of
Documents (e.g. requirement stakeholder register)
communication channels is
documentation, and stakeholder
n(n-1)/2, where n is the number
register), Enterprise Environmental
of stakeholders
Factors, and Organizational
Process Assets Communication Technology
Communication Models
Communication Methods
Interpersonal and Team Skills,
Data Representation, and
Meetings

55
10.2 MANAGE COMMUNICATIONS
This process ensures relevant and timely distribution to the right project stakeholders and allows them to
participate for further information requests, making clarifications, and engage in discussions

INPUTS TOOLS & TECHNIQUES OUTPUTS


Project Management Plan (e.g. Communication Technology, Project Communication, Project
resource management plan, Communication Methods, Management Plan Updates (e.g.
communications management plan, Communication Skills (e.g. Communications management plan,
and stakeholder engagement plan), communication competence, and stakeholder engagement plan),
Project Documents (e.g. change log, feedback, nonverbal, and and Project Documents Updates
issue log, lessons learned register, presentations), Project (e.g. issue log, lessons learned
quality report, risk report, and Management Information register, project schedule, risk
stakeholder register), Work System, Project Reporting, and register, and stakeholder register)
Performance Reports (from 4.5 Interpersonal and Team Skills
Monitor and Control Project Work), (e.g. active listening, conflict
Enterprise Environmental Factors, management, cultural awareness,
and Organizational Process Assets meeting management,
networking, and political
awareness), and Meetings

56
10.3 MONITOR COMMUNICATIONS
This process ensures the information needs of the project and its stakeholders are met, making sure the key
benefit of this process is the optimal information flow

INPUTS TOOLS & TECHNIQUES OUTPUTS


Project Management Plan (e.g. Expert Judgment, Project Work Performance Information,
resource management plan, Management Information Change Requests, Project
communication management plan, System, Data Representation, Management Plan Updates (e.g.
and stakeholder engagement plan) Interpersonal and Team Skills, communications management plan,
Project Documents (e.g. issue log, and Meetings and stakeholder engagement plan),
lessons learned register, and project Project Documents Updates (e.g.
communications), Work Performance issue log, lessons learned register,
Data, Enterprise Environmental and stakeholder register)
Factors, and Organizational
Process Assets

57
MODULE 11 RISK
11.3 Perform 11.4 Perform
MANAGEMENT
11.1 Plan Risk 11.2 Identify Risks Qualitative Risk Quantitative Risk 11.5 Plan Risk 11.6 Implement 11.7 Monitor Risks
Management Analysis Analysis Responses Risk Responses

• Inputs • Inputs • Inputs • Inputs • Inputs • Inputs • Inputs


•Project Charter •Project •Project •Project •Project •Project •Project
•Project Management Plan Management Plan Management Plan Management Plan Management Plan Management Plan
Management Plan •Project Documents •Project Documents •Project Documents •Project Documents •Project Documents •Project Documents
•Project Documents •Agreements •Enterprise •Enterprise •Enterprise •Organizational •Work
•Enterprise •Procurement Environmental Environmental Environmental Process Assets Performance Data
Environmental Documents Factors Factors Factors • Tools & •Work
Factors •Enterprise •Organizational •Organizational •Organizational Techniques Performance
•Organizational Environmental Process Assets Process Assets Process Assets •Expert Judgment Reports
Process Assets Factors • Tools & • Tools & • Tools & •Interpersonal and • Tools &
• Tools & •Organizational Techniques Techniques Techniques Team Skills Techniques
Techniques Process Assets •Expert Judgment •Expert Judgment •Expert Judgment •Project •Data Analysis
•Expert Judgment • Tools & •Data Gathering •Data Gathering •Data Gathering Management •Audits
•Data Analysis Techniques •Data Analysis •Data Analysis •Data Analysis Information •Meetings
•Meetings •Expert Judgment •Interpersonal and •Interpersonal and •Interpersonal and System • Outputs
• Outputs •Data Gathering Team Skills Team Skills Team Skills • Outputs •Work
•Risk Management •Data Analysis •Risk •Representation of •Strategies for •Change Requests Performance
Plan •Interpersonal and Categorization Uncertainty Threats •Project Documents Information
Team Skills •Data • Outputs •Strategies for Updates •Change Requests
•Prompt Lists Representation •Project Documents Opportunities •Project
•Meetings •Meetings Updates •Contingent Management Plan
• Outputs • Outputs Response Updates
•Risk Register •Project Documents Strategies •Project Documents
•Risk Report Updates •Strategies for Updates
Overall Project •Organizational
•Project Documents Risk Process Assets
Updates •Decision Making Updates
• Outputs
•Change Requests
•Project
Management Plan
Updates
•Project Documents
Updates

58
DEFINITIONS

Risk Management is an on-going activity throughout the life cycle and its purpose is to
identify risks, assess the risks ranked in order of probability and impact, determine the
risk threshold, and develop risk responses to these risks – in order to maximize
opportunities and minimize threats

Risk Threshold is the level of a specific risk a stakeholder is willing to take; below the
risk threshold risk is accepted, but above it risk is not accepted (e.g. we can accept
some shipment delay but no more than 4 days)

Risk Trigger is the point when the risk happens (e.g. hitting 4 days)

Risk Tolerance is *the degree, amount, or volume of risk that an organization or


individual will withstand (the overall risk in a project)

Risk Factors are determined by the risk event’s probability (or frequency) of occurrence
and impact (or consequence)

Risk Conditions like project and business environment which poses risks to the project
(e.g. recession, flood, high staff turnover, etc.)

59
11.1 PLAN RISK MANAGEMENT
A risk management plan is required to document the requirements and objectives of risk management
such as the risk tolerances of the project stakeholders, including managing of “new” risks and removal of
“old” risks during the course of the project life cycle, making ad-hoc risk response decisions; identifying,
analyzing the risks and planning for risk responses
As the project progresses, the overall project risk reduces when remaining unknowns are translated to
knowns - unknowns are eventually zero when the project has been successfully completed

INPUTS TOOLS & TECHNIQUES OUTPUTS


Project Charter, Project Expert Judgment, Data Analysis, Produce the Risk Management Plan
Management Plan, Project and Meetings with project
Documents, Enterprise Environmental stakeholders to brainstorm and
Factors (understanding risk attitudes analyze risk information, needs
of people and risk tolerence of the and expectations, and develop
organization), and Organizational risk-related initiatives to
Process Assets (observing risk- manage risks according to the
related compliance and risk management plan
procedures, etc.)

60
11.2 IDENTIFY RISKS
Project stakeholders are involved to provide risk information inputs and their risk tolerances during
identifying risks
Identify risks individually as well as overall project risk is an iterative process or on-going throughout the
project life cycle because new risks may emerge anytime in the project, and earlier identified risks may
disappear or at a level of different risk intensity

INPUTS TOOLS & TECHNIQUES OUTPUTS


Project Management Plan Expert Judgment, Data Risk Register is a document that
Project Documents Gathering (e.g. brainstorming, captures:
checklists, interviews), Data List of identified risks
Agreements Analysis (e.g. root cause
analysis, assumption and Probability and impact
Procurement Documents (from 12.1
Plan Procurement Management constraint analysis, SWOT Risk triggers
process) analysis, document analysis),
Interpersonal and Team Skills, Potential risk owners
Enterprise Environmental Factors, Prompt Lists, and Meetings List of potential risk responses
and Organizational Process Assets
Risk Report, and Project Documents
Updates

61
11.3 PERFORM QUALITATIVE RISK ANALYSIS
A rapid, cost-effective and subjective analysis of ranking and prioritizing risks (may use narratives,
scoring, weightages, guessimates)

INPUTS TOOLS & TECHNIQUES OUTPUTS


Project Management Plan, Project Expert Judgment, Data Project Documents Updates
Documents (e.g. assumption log, risk Gathering, Data Analysis (e.g. Risk report and issue log
register, and stakeholder register), risk data quality assessment, risk
Enterprise Environmental Factors, probability and impact Risk register updates (such as
and Organizational Process Assets assessment, and assessment of revision of risk rankings, “flagging”
other risk parameter like of certain risk areas, risk-related
urgency, strategic impact, etc. issues requiring different levels of
Probability attention and response, risks
/ Low Medium High Interpersonal and Team Skills, requiring additional analysis, watch
Impact
Risk Categorization, Data lists, risk trends, etc.) –
Representation (e.g. probability
Low A6 A7
and impact matrix, and Assumption log updates to
hierarchical charts), and accomodate new risk assumptions
Medium A4 A3
Meetings when new information is made
available
High A1 A2, A5
Low risks need to be added into
Conventional probability-impact matrix table, where each identified risk is watch lists for monitoring
mapped against the probability of risk occuring and the severity of impact
62
11.4 PERFORM QUANTITATIVE RISK ANALYSIS
Quantitative Risk Analysis process uses a numerical approach to risk analysis and this is more preferable,
accurate and objective (but is more time-consuming to undertake) compared to Qualitative Risk Analysis
Statistical backing either by frequency of observations, or probability distribution by Monte-Carlo
simulation; and Decision-Tree which can numerically justify the probability of occurrence, and this is
primarily used for decision making purposes

INPUTS TOOLS & TECHNIQUES OUTPUTS


Project Management Plan (e.g. risk Expert Judgment, Data Project Documents Updates
management plan, scope baseline, Gathering, Interpersonal and Assessment of overall project risk
schedule baseline, and cost baseline), Team Skills, Representations of exposure
Project Documents (e.g. assumption Uncertainty like using
log, basis of estimates, cost probability distributions, Data Detailed probabilistic analysis of the
estimates, cost forecasts, duration Analysis (e.g. simulation like project
estimates, milestone list, resource Monte Carlo, sensitivity analysis Prioritized list of individual project
requirements, risk register, risk for determining which risks have risks
report, and schedule forecasts) the most influence Tornado Trends in quantitative risk analysis
Diagram, decision tree analysis, results
Enterprise Environmental Factors,
and influence diagrams)
and Organizational Process Assets Recommended risk responses

63
11.5 PLAN RISK RESPONSES
Responding to risks to increase opportunities and reduce threats to the project
Often used with a modifier (e.g. management reserve, contingency reserve) to provide details on what
types of risk are meant to be mitigated; the funds and resources will be reduced and adjusted over time

INPUTS TOOLS & TECHNIQUES OUTPUTS


Project Management Plan (e.g. Expert Judgment, Data Change Requests, Project
resource management plan, risk Gathering, and Interpersonal Management Plan Updates (e.g.
management plan, and cost and Team Skills schedule management plan, cost
baseline), Project Documents (e.g. management plan, quality
Strategies For Negative Risks
lessons learned register, project management plan, resource
Or Threats
schedule, project team assignments, management plan, procurement
resource calendars, risk register, risk Strategies For Positive Risks Or management plan, scope baseline,
report, and stakeholder register), Opportunities schedule baseline, and cost baseline),
Enterprise Environmental Factors, Contingent Response Strategies and Project Documents Updates
and Organizational Process Assets (e.g. assumption log, cost forecasts,
Strategies For Overall Project lessons learned register, project
Risk schedule, risk register, and risk
Data Analysis, and Decision report)
Making

64
DEFINITIONS
Risk Categories
Grouping risks by common root causes can help us to develop effective risk
responses like technical, external, organizational, environmental, business, etc.
Helps to determine the areas of the project most exposed to the effects of
uncertainty

Risk Responsibilities
Project Manager is fully responsible to initiate, integrate and lead risk
management across all knowledge areas and processes
Functional Manager manages functional risks affected by, or affecting the project
Project Team requires a working knowledge of risk management tools and
techniques, and be the “ears and eyes” for the project manager

Risk Types
Unknown unknowns (unplanned) - having no information about the risk; cannot be
proactively planned to respond as it has to be a reactive response called a
workaround and is financed by the management reserve
Known unknowns - having partial information about the risk and known knowns -
having complete information about the risk; these risks are proactively planned
are financed by the contingency reserve

65
RESIDUAL, SECONDARY RISKS AND RISK
RESPONSE STRATEGIES
Residual risk is the leftover/minor risks that remain after a risk response
Secondary risk is a risk arising as a direct outcome of implementing a risk response
A workaround is an unplanned risk response (does not appear in the risk response plan) but only be
determined and executed when an unknown-unknown risk happens
Strategies For Negative Risks Or Threats
1. Escalate when the threat is outside the scope of the project, or the proposed response would exceed
the project manager’s authority and is no further monitored by the team
2. Avoid or eliminate the adverse risk (or cause), or taking an alternative course of action; usually this is
considered during initiating or planning where the level of influence is high and the cost of change is
low, otherwise reducing the impact of a risk event by reducing the possibility of its occurrence
3. Transfer or deflect the risk and risk ownership to a third party; e.g. contracting, retention, warranties,
guarantees, bonds and insurance
4. Mitigate the risk's probability and impact to an acceptable threshold (e.g. prototyping, simulating
and modeling)
5. Accept the consequence of a risk occurring, perhaps because it is not cost-effective to respond -
active risk acceptance is to execute alternatives or fallback (contingency) plan; and passive risk
acceptance is to accept the risk and do nothing
66
RESIDUAL, SECONDARY RISKS AND RISK
RESPONSE STRATEGIES
Strategies For Positive Risks Or Opportunities
1. Escalate when the opportunity is outside the scope of the project, or the proposed response would
exceed the project manager’s authority and is no further monitored by the team
2. Exploit or pursue the opportunity
3. Enhance an existing opportunity
4. Share the opportunity with strategic partners (e.g. joint-ventures, alliances and partnerships) to
increase the value of collaboration energies instead of doing it on its own
5. Accept the opportunity as it comes along (not actively pursuing it)
Strategies For Overall Project Risk
 Avoid, Exploit, Transfer/share, Mitigate/enhance, and Accept
Contingent Response Strategies
These are developed in advance and designed to be used only under predefined conditions if there is
advanced and sufficient warning to implement this plan (such as missed milestones, missed deliverables, etc.)
e.g. if you are having an outdoor barbeque and it seems it is going to rain, move the cooking under a
shelter and have guests moved inside the house
Note: Can be a contingency plan (or alternative backup plan), or a fallback plan (return to previous
workable solution) developed in advance of a risk event occurring and is designed to be used when the
primary risk response proves not to be effective
67
11.6 IMPLEMENT RISK RESPONSES
This is process of implementing the risk response plans when the risks are triggered

INPUTS TOOLS & TECHNIQUES OUTPUTS


Project Management Plan, (e.g. Expert Judgment, Interpersonal Change Requests, and Project
lessons learned register , risk and Team Skills, and Project Documents Updates (e.g. issue log,
register, and risk report), and Management Information lessons learned register, project team
Organizational Process Assets System assignments, risk register, and risk
report)

68
11.7 MONITOR RISKS
This is a continuing process of tracking new risks and those on the watch list, reanalyzing existing risks,
monitoring threshold trigger conditions for risk responses and contingency plans, monitoring residual (or
secondary) risks, reviewing the execution of risk responses, and monitoring contingency reserve

INPUTS TOOLS & TECHNIQUES OUTPUTS


Project Management Plan, Project Data Analysis (e.g. technical Work Performance Information,
Documents (e.g. issue log, lessons performance analysis, and Change Requests, Project
learned register, risk register, and Management Plan Updates, Project
reserve analysis to find out if the
risk report), Work Performance contingency reserve is sufficient Documents Updates (e.g.
Data, and Work Performance to last until project closeout assumption log, issue log, lessons
Reports (from 4.5 Monitor and learned register, risk register, and
Audits to check the risk response
Control Project Work) risk report), and Organizational
effectiveness and how well the
Process Assets
risk management methodology
is being practiced
Meetings like conducting risk
reassessment on identified risks,
including residual or secondary
risks left behind from executed
risk responses, and new risks

69
MODULE 12 PROCUREMENT MANAGEMENT
12.1 Plan Procurement 12.2 Conduct Procurements 12.3 Control Procurements
Management
• Inputs • Inputs • Inputs
• Project Charter • Procurement Management Plan • Project Management Plan
• Business Documents • Procurement Documents • Project Documents
• Project Management Plan • Procurement Documentation • Agreements
• Project Documents • Seller Proposals • Procurement Documentation
• Enterprise Environmental Factors • Enterprise Environmental Factors • Approved Change Requests
• Organizational Process Assets • Organizational Process Assets • Work Performance Data
• Tools & Techniques • Tools & Techniques • Enterprise Environmental Factors
• Expert Judgment • Expert Judgment • Organizational Process Assets
• Data Gathering • Advertising • Tools & Techniques
• Data Analysis • Bidder Conferences • Expert Judgment
• Source Selection Analysis • Data Analysis • Claims Administration
• Meetings • Interpersonal and Team Skills • Data Analysis
• Outputs • Outputs • Inspection
• Procurement Management Plan • Selected Sellers • Audits
• Procurement Strategy • Agreements • Outputs
• Bid Documents • Change Requests • Closed Procurements
• Procurement Statement of Work • Project Management Plan • Work Performance Information
• Source Selection Criteria Updates • Procurement Documentation
• Make-or-Buy Decisions • Project Documents Updates Updates
• Independent Cost Estimates • Organizational Process Assets • Change Requests
• Change Requests Updates • Project Management Plan
• Project Documents Updates Updates
• Organizational Process Assets • Project Documents Updates
Updates • Organizational Process Assets
Updates
70
Project Procurement Management covers the essentials of procurement decisions, contract administration
and closure principles

Procurement is buying resources from outside the project organization for use in the project to produce
the required deliverables, results, products or services

The term Buyer is used to refer to the party buying things from a Seller who provides them

Procurement management process is seller-centric - e.g. managing seller’s performance, payments to


seller, agreements with seller, etc.

A contract is in place if there is an offer and acceptance - a bilateral contract has both the Buyer and
Seller sign-offs; whereas a unilateral contract is for a unit price purchase by the Buyer is also known as
a purchase order for a straight-forward procurement

Constructive changes are unauthorized contract changes that are performed but are not from a change
document going through the CCB to have the CCB approval - they are frequent cause of disputes and
claim

A Buyer/Seller share ratio means (Buyer’s commitment)/(Seller’s commitment), e.g. 20/80 ratio means
20% buyer–80% seller (BSR = 0.2)

71
PROCUREMENT AND CONTRACTS
A collaborative win-win approach is required in procurements and contracts
 Emphasizing multi-tiered structure in contracting relationships using several agreements
rather than lumped into one agreement
 Promote value-driven deliverables instead of phase gates and milestones
 Scope according to fixed-priced micro-deliverables (i.e., as per user stories) presented
in fixed-price increments
 Limit the overall budget to a fixed amount, so that any new inclusions to the scope will
be a decision of replacing original work with new work
 Implement a shared financial risk approach whereby the seller will be rewarded for
early delivery, or penalized for lateness
 Provide an exit clause whereby the customer can exercise control over contractual
obligations to the seller or agile supplier
 The customer may adjust or vary the project scope, or adjust features to fit the capacity
 Embedding the agile supplier’s services directly into the customer’s organization
 Favoring full-service agile suppliers that provide wholesome full value, rather than
piecemeal work
12.1 PLAN PROCUREMENT MANAGEMENT
Making procurement decisions: finding out what to buy, what to make (make-or-buy), from whom, when
and how
The types of contract to enter in must be appropriate to the kind of purchases to be made and need to
be favorable to the buyer although we aim to achieve a win-win resolution
Ignorance of purchasing law is not an excuse to exempt from legal implications – the project manager is
to provide purchasing advice to the procurement office to execute the procurement
Procurement office will dominate the procurement process in compliance to the project organization
process assets – who signs off the procurement documents is the person who can make amendments

INPUTS TOOLS & TECHNIQUES OUTPUTS


Project Charter, Business Expert Judgment, Data Procurement Management Plan,
Documents,(e.g. business case and Gathering, Data Analysis, Data Procurement Strategy, Bid
benefits management plan), Project Analysis, Source Selection Documents, Procurement Statements
Management Plan Analysis (e.g. least cost or Of Work, Source Selection Criteria,
Enterprise Environmental Factors, qualifications only, quality- Make-Or-Buy Decisions,
and Organizational Process Assets based/highest technical proposal Independent Cost Estimates,
score, quality and cost-based, Change Requests, Project
sole source, and fixed budget Documents Updates, and
decisions), and Meetings Organizational Process Assets
Updates

73
PROCUREMENT DOCUMENTS
Procurement Management Plan
• The document that describes how procurement processes from developing procurement documentation
through contract closure will be managed.
• Contains information on what to make or buy, the pre-qualified vendor list, make an independent
estimate of expected project costs, develop the seller’s screening, seller’s evaluation criteria and
weighting system, the types of contracts to use, and how the procurement will be executed
Procurement Strategy (e.g. delivery methods, contract payment types, and procurement phases)
• Fixed-price contracts are suitable when work is predictable and its requirements are well defined and
not likely to change; cost-plus contracts are suitable when work is evolving, likely to change, or not well
defined; time and material contracts are suitable when the work is uncertain, amounting in time for
effort and material to use
Bid Documents (e.g. request for information, request for quotation, and request for proposal when there is
a problem in the project and the solution is not easy to determine)
Procurement Statements Of Work
• Is derived from the WBS whose work or procurement item requires to be fulfilled by sellers, including
performance criteria required of sellers
• The procurement statement of work must be clear, complete and as concise as possible and it should
also describe the work and activities that the seller is required to complete, including meetings, reports
and communications
The procurement documentation consists of bid documents, procurement statement of work, independent
cost estimates, and source selection criteria
74
CONTRACT TYPES
Fixed-Price (or Lump-Sum) Contracts
Fixed-price contracts are suitable when work is predictable and its requirements are well defined and not
likely to change

FFP Firm Fixed Price (most commonly used, FPEPA Fixed Price Economic Price Adjustment
a.k.a. lump sum: least buyer risk, highest seller contract allows for price adjustment based on
risk) some predetermined price index if the contract is
Seller sells item at $100K and buyer accepts and for many years, affected by inflation/deflation,
pays $100K or susceptible to volatile prices
If the item gets more expensive, the seller must Seller sells item at $100K and buyer accepts and
keep his promise to sell at $100K pays $100K
If the item gets more expensive, the seller must
FPIF Fixed Price Incentive Fee given for fixed keep his promise to sell at $100K
price contracts as a way to motivate the seller to However, if the item gets more expensive over a
meet or exceed the predetermined project cost, certain price, the seller can negotiate with the
schedule or technical performance metrics buyer for a new selling price
Seller sells item at $100K and buyer accepts and
pays $100K with an additional incentive fee if the
seller can meet some predetermined conditions
If the item gets more expensive, the seller must
keep his promise to sell at $100K, and the
incentive fee offer is still valid
75
CONTRACT TYPES
Cost-Plus also known as Cost-Reimbursable Contracts
Payment (reimbursement) to the seller for seller's actual costs, plus a fee typically representing seller profit
Cost-plus contracts are suitable when work is evolving, likely to change, or not well defined

CPFF Cost Plus Fixed Fee is commonly used CPIF Cost Plus Incentive Fee is the fairest
where a fixed fee (profit) has already been contract to buyer and seller as there is an
agreed to the seller, although the reimbursable additional incentive to seller based on lower cost
cost can vary differential (on top of his agreed upon fixed
Seller sells item at target selling price $100K with fee) to obtain the best cost advantage to buyer;
a certain fixed fee, and buyer accepts and pays however, if vice-versa, the seller has to absorb
$100K plus the fixed fee the excess cost
If the item gets more expensive, the buyer will pay Seller sells item at a target selling price $100K
at the new higher selling price plus the fixed fee with a certain fixed fee, and buyer accepts and
If the item gets cheaper, the buyer will pay at the pays $100K plus the fixed fee
new cheaper selling price plus the fixed fee If the item gets more expensive, the buyer will pay
at the new higher selling price plus the fixed fee
If the item gets cheaper, the buyer will pay at the
new cheaper selling price plus the fixed fee with
an additional pre-agreed incentive amount
calculated from the difference of the target selling
price and the cheaper selling price
76
CONTRACT TYPES
CPAF Cost Plus Award Fee is used when a Time and Material Contracts
majority of fee is only earned based on the The full value of the agreement and the exact
satisfaction (discretion) by the buyer of the seller quantity of items to be delivered are not
according to certain subjective performance defined by the buyer at the time of the contract
criteria defined and incorporated in the contract award, and this is usually used when the project
Seller sells item at a target selling price $100K scope is unable to be defined (e.g. legal costs)
with a certain award fee, and buyer accepts and
Time and material contracts are suitable when the
pays $100K plus the award fee provided that the
work is uncertain, amounting in time for effort
seller is able to meet certain obligation
and material to use
If the item gets more expensive, the buyer will pay
at the new higher selling price plus the award fee These contracts can be a combination of cost-
If the item gets cheaper, the buyer will pay at the reimbursable and fixed-price
new cheaper selling price plus the award fee

Note: There is a Cost Plus Percentage of Costs (CPPC) contract but is removed from the PMBoK 6th
Edition. The CPPC works when the buyer agrees to give the seller a certain percentage of the final cost as
a fee – this may be exploited by the seller to charge a high cost to command a high seller’s fee. The buyer
has to audit to ensure that the final cost is not being manipulated.

77
12.2 CONDUCT PROCUREMENTS
Procurements are conducted to solicit seller responses, appraise sellers through the bid , shortlisting,
negotiating, and finally awarding a written contract to the seller
It is important that purchasing, contracting, and legal requirements are observed, and advised by
experts in these areas

INPUTS TOOLS & TECHNIQUES OUTPUTS


Project Management Plan, Project Expert Judgment, Advertising, Selected Sellers, Agreements (or
Documents (e.g. lessons learned Bidder Conferences are contracts) for the procurement with
register, project schedule, conducted between the buyer sellers, Change Requests, Project
requirements documentation, risk and sellers to acquaint the Management Plan Updates, Project
register, and stakeholder register) sellers with the procurement Documents Updates (e.g. lessons
needs, Data Analysis, and learned register, requirements
Procurement Documentation (e.g.
Interpersonal and Team Skills documentation, requirements
bid documents, procurement
with seller on the terms and traceability matrix, resource
statement of work, independent cost
conditions of the purchase in a calendars on the availability of the
estimates, and source selection
contract, governing law, seller sellers, risk register, and stakeholder
criteria)
performance, schedules, register), and Organizational
Seller Proposals, Enterprise payments, warranty, etc. Process Assets Updates
Environmental Factors, and
Organizational Process Assets

78
12.3 CONTROL PROCUREMENTS
Procurement contracts which had been signed with sellers need to be administered to ensure sellers
perform to contractual obligations and paid accordingly

INPUTS TOOLS & TECHNIQUES OUTPUTS


Project Management Plan (e.g. Expert Judgment, Claims Closed Procurements when the
requirements management plan, risk Administration such as disputes buyer formally provides a written
management plan, procurement or contested claims, or appeals, notice to the seller to formally
management plan, change Data Analysis (e.g. performance discharge from the contract, or
management plan, and schedule reviews, earned value analysis, informally the buyer pays the seller
baseline) and trend analysis), Inspection, the final payment, Work
and Audits of seller’s Performance Information,
Project Documents (e.g. assumption Procurement Documentation
performance
log, lessons learned register, Updates, Change Requests, Project
milestone list, quality reports, Management Plan Updates, Project
requirements documentation, Documents Updates, and
requirements traceability matrix, and Organizational Process Assets
stakeholder register), Agreements, Updates (e.g. payment schedules
Procurement Documents, Approved and requests, seller performance
Change Requests, Work evaluation documentation,
Performance Data, Enterprise prequalified seller lists updates,
Environmental Factors, and lessons learned repository, and
Organizational Process Assets procurement file)
79
TERMINATING DISPUTED PROCUREMENT
CONTRACT
Terminated work has to be mutually agreed by buyer and seller, and has to be validated by the buyer
(or valuation) before payment for work done so far is given to the seller
Disputes are preferred to be settled by, by order:
1. Mediation (negotiation)
2. Adjudication (statutory procedure and legally binding provided by a third party adjudicator
selected by the parties in dispute)
3. Arbitration (by a third party arbitrator or arbitration panel, selected by the parties in dispute,
having a court process, providing testimony and give evidence similar to a trial but it is usually less
formal and legally binding)
4. Litigation (going to court with lawyers and a lengthy process) when all else fails and this is least
desirable

Adjudication/Arbitration and Mediation are the two major forms of Alternative Dispute Resolution (ADR)
refers to any means of settling disputes other than Litigation

80
MODULE 13 STAKEHOLDER
MANAGEMENT
13.1 Identify Stakeholders 13.2 Plan Stakeholder 13.3 Manage Stakeholder 13.4 Monitor Stakeholder
Management Engagement Engagement
• Inputs • Inputs • Inputs • Inputs
• Project Charter • Project Charter • Project Management Plan • Project Management Plan
• Business Documents • Project Management Plan • Project Documents • Project Documents
• Project Management Plan • Project Documents • Enterprise Environmental • Work Performance Data
• Project Documents • Agreements • Factors • Enterprise Environmental
• Agreements • Enterprise Environmental • Organizational Process • Factors
• Enterprise Environmental Factors Assets • Organizational Process
• Factors • Organizational Process • Tools & Techniques Assets
• Organizational Process Assets • Expert Judgment • Tools & Techniques
Assets • Tools & Techniques • Communication Skills • Data Analysis
• Tools & Techniques • Expert Judgment • Interpersonal And Team • Decision Making
• Expert Judgment • Data Gathering Skills • Data Representation
• Data Gathering • Data Analysis • Ground Rules • Communication Skills
• Data Analysis • Decision Making • Meetings • Interpersonal And Team
• Data Representation • Data Representation • Outputs • Skills
• Meetings • Meetings • Change Requests • Meetings
• Outputs • Outputs • Project Management Plan • Outputs
• Stakeholder Register • Stakeholder Management Updates • Work Performance
• Project Management Plan Plan • Project Documents Information
Updates Updates • Change Requests
• Project Documents • Project Management Plan
Updates Updates
• Project Documents
Updates

81
Project Stakeholder Management identifies
people, groups or organizations having a vested
interest in the project, with the aim of engaging
stakeholders using strategies, and ensuring
stakeholders needs and expectations are met
Stakeholders come and go, and it is important
for the project manager to be “on top of things”,
and tailor each project stakeholder management
considering stakeholder diversity, relationship
complexity, and communication technology used
Project managers in reality behave like
salespersons, always “reading” the stakeholders
mind, finding appropriate stakeholder
management strategies to actively pursue good
rapport with key stakeholders and always
engaging the stakeholders with the motive of
increasing project success
Image credit:
In agile/adaptive environments, aggressive https://www.mindtools.com/media/Diagrams/Figure2_Forcefield
transparency using direct and active engagement _Analysis_v3.png
with stakeholders is encouraged, bypassing
layers of bureaucracy in order to ensure timely Kurt Levin created the Force Field Analysis to help
and productive discussion and decision making make a decision by analysing the forces for and
against a change, and it helps you communicate the
reasoning behind your decision

82
13.1 IDENTIFY STAKEHOLDERS
Project stakeholders are people, groups and organizations who have positive or negative interests and
impacts in a project

INPUTS TOOLS & TECHNIQUES OUTPUTS


Project Charter Expert Judgment, Data Stakeholder Register is a project
Business Documents (e.g. business Gathering (e.g. questionnaires document about project
case, and benefits management and surveys, and brainstorming) stakeholders:
plan) Identification information
Data Analysis (mapping
Project Management Plan (e.g. stakeholders) Assessment information
communications management plan Stakeholder classification
and stakeholder engagement plan Stakeholders can be classified
just as these plans are via Data Representation and Project Management Plan Updates
progressively elaborated) Meetings (e.g. requirements management plan,
communications management plan,
Project Documents (e.g. change log, risk management plan, and
issue log, and requirements stakeholder engagement plan)
documentation)
Project Documents Updates (e.g.
Agreements, Enterprise assumption log, issue log, and risk
Environmental Factors, and register)
Organizational Process Assets

83
STAKEHOLDER MAPPING
Images are sourced from:
clockwise from top left
High power, interested
people: these are the people
1. www.mindtools.com
you must fully engage and 2. www.justpmblog.com
make the greatest efforts to 3. www.projectexperts.com
satisfy. Best channels:
Issues, Change Logs, Status
4. www.bawiki.com
Meetings

High power, less interested


people: put enough work in
with these people to keep
them satisfied, but not so
much that they become
bored with your message.
Steering Committee, Board Stakeholder Cube
Meeting Updates by Lucid Consulting
Low power, interested
people: keep these people
adequately informed, and
talk to them to ensure that
no major issues are arising.
These people can often be
very helpful with the detail
of your project. In-Person,
Video, Email Updates

Low power, less interested


people: again, monitor
these people, but do not
bore them with excessive
communication. Send Email,
Status Reports

84
STAKEHOLDER MAPPING
http://www.gpmfirst.com/books/stakeholder-relationship-management/mapping-stakeholders

Salience Model (Mitchell, Agle and Wood, 1997)


https://www.slideshare.net/archanabinoy143/salience-modelsupply-chain-management

Power: Coercion (based on force or threat), utilitarian (based on

Dimension
resource control or incentives offered), or normative (based on symbolic
influences such as moral authority)
Legitimacy: Factors such as who is funding the effort, who is impacted
by the effort, and who has control of specific assets needed to execute
the project are common factors of legitimacy
Image sources from top to bottom

Urgency: The degree to which stakeholder claims call for immediate


attention
Latent Stakeholders
1. Dormant: They have the power to cause problems for the project,
and need to be carefully managed
2. Discretionary (Weak Stakeholder): Their needs and issues should
be heard and understood by the project team, but incorporating
those needs is likely to be discretionary based on the needs of
other stakeholders with greater power or urgency
Direction of influence 3. Demanding: These are most likely to be project detractors if their
Category demands are not incorporated
Expectant Stakeholders
4. Dominant: Their power and legitimacy make them important for
project success, but their low urgency means they may not have to
be part of the core project effort
5. Dangerous: Their power and urgency can make them threats to
project success, and they are often drivers of scope expansion or
other changes that do not fall within the legitimate needs of the
project
6. Dependent: Their lack of power makes them dependent on the
project team to ensure their needs are heard and fully considered
7.  Core or Definitive: These are stakeholders who always take top
priority and evaluated as having power, legitimacy, and urgency
85
13.2 PLAN STAKEHOLDER ENGAGEMENT
Developing approaches to involve stakeholders based on their needs, expectations, interests, and
potential impact on the project
INPUTS TOOLS & TECHNIQUES OUTPUTS
Project Charter, Project Expert Judgment , Data Stakeholder Engagement Plan
Management Plan (e.g. resource Gathering, Data Analysis (e.g. A subsidiary plan of the project
management plan, communications assumption and constraint management plan that identifies
management plan, and risk analysis, and root cause the strategies and actions required
management plan), Project analysis), Decision Making, Data to promote productive involvement
Documents (e.g. assumption log, Representation (e.g. mind of stakeholders in decision making
change log, issue log, project mapping, stakeholder and execution
schedule, risk register, and engagement assessment matrix),
stakeholder register), Agreements, and conduct Meetings
Enterprise Environmental Factors,
and Organizational Process Assets
Stakeholder Unaware Resistant Neutral Supportive Leading
Current Desired
Stakeholder Engagement Assessment Stakeholder 1
engagement engagement
Matrix identifies the current Desired
engagement level of a specific Stakeholder 2
engagement
Current
stakeholder and the desired engagement
engagement level Current Desired
Stakeholder 3
engagement engagement

86
13.3 MANAGE STAKEHOLDER ENGAGEMENT
This is a process of regularly communicating and working with stakeholders throughout the project life
cycle to increase project success

INPUTS TOOLS & TECHNIQUES OUTPUTS


Project Management Plan (e.g. Expert Judgment, Change Requests, Project
communications management plan, Communication Skills, Management Plan Updates (e.g.
risk management plan, stakeholder Interpersonal and Team Skills communications management plan
engagement plan, and change (e.g. conflict management, and stakeholder engagement plan),
management plan), Project cultural awareness, negotiation, Project Documents Updates, (e.g.
Documents (e.g. change log, issue observation/conversation, and change log, issue log, lessons
log, lessons learned register, and political awareness), Ground learned regster, and stakeholder
stakeholder register), Enterprise Rules, and Meetings register)
Environmental Factors, and
Organizational Process Assets

87
13.4 MONITOR STAKEHOLDER ENGAGEMENT
This is a process of monitoring stakeholder relationships, tailoring strategies and plans for engaging
stakeholders, and conduct the necessary changes to enhance interactions in managing stakeholders

INPUTS TOOLS & TECHNIQUES OUTPUTS


Project Management Plan (e.g. Data Analysis (e.g. alternatives Work Performance Information,
resource management plan, analysis, root cause analysis, and Change Requests, Project
communications management plan, stakeholder analysis), Decision Management Plan Updates (e.g.
and stakeholder engagement plan), Making (e.g. multicriteria resource management plan,
Project Documents (e.g. issue log, decision analysis and voting), communications management plan,
lessons learned register, project Data Representation, and stakeholder engagement plan),
communications, risk register, and Communication Skills (e.g. Project Documents Updates (e.g.
stakeholder register), Work feedback and presentations), issue log, lessons learned register,
Performance Data, Enterprise Interpersonal and Team Skills risk register, and stakeholder
Environmental Factors, and (e.g. active listening, cultural register)
Organizational Process Assets awareness, leadership,
networking, and political
awareness), and Meetings

88

You might also like