Bistro Estimate
Bistro Estimate
BILL OF MATERIALS
I. FOUNDATION
Quantity Unit Price Total Grand Total
1 Ground Floor Concrete Slab
a. Portland Portland Cement (Class AA) 130 Bags ₱ 240.00 ₱ 31,200.00
b. Sand 6 Cu. M ₱ 1,100.00 ₱ 6,600.00
c. Gravel 11 Cu. M ₱ 1,500.00 ₱ 16,500.00
₱ 54,300.00
1 1.00 m x 1.00 m x 0.35 m Footing
a. Portland Cement (Class AA) 13 Bags ₱ 240.00 ₱ 3,120.00
b. Sand 1 Cu. M ₱ 1,100.00 ₱ 1,100.00
c. Gravel 1 Cu. M ₱ 1,500.00 ₱ 1,500.00
₱ 5,720.00
2 1.20 m x 1.20 m x 0.35 m Footing
a. Portland Cement (Class AA) 18 Bags ₱ 240.00 ₱ 4,320.00
b. Sand 8 Cu. M ₱ 1,100.00 ₱ 8,800.00
c. Gravel 7 Cu. M ₱ 1,500.00 ₱ 10,500.00
₱ 23,620.00
3 Steel Works
a. 16 mm Diameter Reinforced Bars (Grade 280) 15 Pcs. ₱ 526.00 ₱ 7,890.00
b. Galvanized Iron Wire #16 6 Kg ₱ 70.00 ₱ 420.00
₱ 8,310.00
₱ 91,950.00
II. WALL FOOTING (Concrete Works & Steel Works)
1 Exterior Walls (Concrete Hollow Blocks) Quantity Unit Price Total Grand Total
a. Firewall
i. (CHB 4") 803 Pcs. ₱ 12.00 ₱ 9,636.00
b. Ground Floor Walls (CHB 4")
i. Front 200 Pcs. ₱ 12.00 ₱ 2,400.00
ii. Rear 237 Pcs. ₱ 12.00 ₱ 2,844.00
iii. Left Side 170 Pcs. ₱ 12.00 ₱ 2,040.00
c. Second Floor Walls (CHB 4")
i. Front 129 Pcs. ₱ 12.00 ₱ 1,548.00
ii. Rear 202 Pcs. ₱ 12.00 ₱ 2,424.00
iv. Left Side 128 Pcs. ₱ 12.00 ₱ 1,536.00
₱ 22,428.00
Interior Walls (CHB 4")
2 a. Ground Floor
i. Kitchen 80 Pcs. ₱ 12.00 ₱ 960.00
ii. Toilet Room 63 Pcs. ₱ 12.00 ₱ 756.00