Lecturenote - 923618598chapter 4
Lecturenote - 923618598chapter 4
According to Ministry of Mines and Energy, in 1990 the energy total requirement in Ethiopia was estimated
at 177.6 TWh per year of which 76.1% from wood, 16.1% agricultural by-product, 5.3% from fuel oil and
1.1% from electricity, 0.8% from charcoal and 0.6% through others. The energy is used in the sectors of
domestic in the town and rural areas, industry, service, agriculture and transport.
The 1.1% contribution of electrical energy of the total energy requirement is derived mainly from
hydropower. This is used mainly for domestic use in the towns, industries and services. Ethiopia has got
substantial hydropower potential from which less than 2% has been utilized, and the remaining should be
developed at small to large scale so that source of energy for various uses can be replaced by this more
environmentally friendly alternative source.
The above equation neglects the difference in kinetic energy term. In low land rivers, with large magnitude
of discharge and low head as in the runoff plants, neglecting the energy from this term may mean neglecting
significant energy term.
From the above relationship:
Pp= γ.Q.H (KW) = 9.81 Q.H (KW)
Since
1 hp = 736 Watts
Pp= 13.33 Q.H (hp)
If the river course is divided in to a number of n stretches, the total power can be described by:
n
P (Q H )
1
From the available stream flow data, one can obtain flow duration curve of the stream for a given site by
plotting the discharge against the percentage duration of the time for which it is available. Similarly, power
duration curve can be plotted since power is directly proportional to the discharge and available head.
Potential power resources can be characterized by values according to the discharge taken as a basis of
computation. The conventional discharges are Q100, Q95, Q50, Qm. Thus we have,
i) Minimum potential power designated Pp100, computed from the minimum flow that is available for 100% of
the time (365 days or 8760 hrs.)
ii) Small potential power computed from the flow available for 95% of the time. This represented by Pp 95
iii) Median potential power is computed from the flow available for 50% of time. This is represented by Pp 50.
iv) Mean potential power is computed from the average of mean yearly flows for a period of 10 to 30 years.
This is designated as Ppm and is also known as gross power potential.
KIOT 2
HYDRAULIC STRUCTURE I (CENG3161)
Figure4.1: Flow\Power duration curve (Power scale multiplying factor = 9.81 η.H)
KIOT 3
HYDRAULIC STRUCTURE I (CENG3161)
Thus in a grid system, a power station may be distinguished as a base load plant or peak load plant.
Hydropower plants are best suited as peak load plants, because hydropower plants can start relatively quickly
and can thus accept load quickly.
Hydropower
Load (MW)
Nuclear
Thermal
Time (months)
Figure 4.2: Place of hydropower in a power system.
KIOT 4
HYDRAULIC STRUCTURE I (CENG3161)
a) Block power plant b) Twin block plant c)Island plant d) pier head plant e)
Submersible plant
Figure 4.3: Run-off-River Plant Arrangement
KIOT 5
HYDRAULIC STRUCTURE I (CENG3161)
KIOT 6
HYDRAULIC STRUCTURE I (CENG3161)
A weir or barrage is built across a river & the low head created is used to generate power. It also acts as a
controlled spilling device.
The power house is normally in the main course of the river
Preferred in perennial rivers with moderate to high discharge, flat slope, little sediment and stable reach of a
river.
Water enters the power house through an intake structure incorporating some or all of the following.
1.- Entrance flume separated by piers and walls for each machine unit.
2.- Turbine chamber: scroll case with turbine
3.- Concrete or steel draft tube
4.- Power house building
Additional structures are
- deflector or skimmer walls
- forebay
- service bridge
- river training walls
- sediment trap and flushing sluices, where necessary
i) The flatter slopes of power canal and the absence of meander, by reducing length, helps in providing head.
KIOT 7
HYDRAULIC STRUCTURE I (CENG3161)
ii) If the river has a natural fall, diverting the water from u/s side of the fall & locating the power house at the
d/s side of the fall provide the required head.
iii) In inter-basin diversion, water may be diverted from a higher level river to a lower river through a diversion
canal to the power house located at the lower river.
Main structures of the diversion canal plant:
1) Diversion weir with its appurtenant structures.
2) Diversion canal intake with its ancillary works such as sills, trash racks, skimmer wall, sluice, settling basin,
disiltting basin, disilting canal, silt exclusion arrangement is needed in some sediment laden streams.
3) Bridges and culverts of the canal.
4) Forebay & its appurtenant structures.
High head diversion plants
High head is developed by:
i) Diverting the river water through systems of canals and tunnels to a downstream point of the same river.
ii) Diverting the water through canals and tunnels to a point on another river which is at much lower level.
The main feature here is complicated conveyance system & relatively high head compared to the diversion
type.
There may be two situation concerning storage situation
a) A diversion weir to create pondage ( and no storage). Here like run-off-plant the power production is
governed by the natural flow in the river.
b) Storage may be provided on the main river at the point of diversion. (This second situation is advantageous
since the fluctuation in reservoir level does not materially affect the head and the power output can be adjusted
by the controlled flow release from the reservoir. Eg. Fincha & Melka Wakana power plants)
KIOT 8
HYDRAULIC STRUCTURE I (CENG3161)
The most important basis of pumped storage plant is the relative arrangements of turbines and pumps
- four units -pump, motor, generator, turbine
- three units- pump, generator, turbine
- two units-generator, turbine>reversible pump-turbine installation
4.3 Storage and Pondage
Storage is providing to balance seasonal fluctuation by building reservoir dams. Pondage is provided through
balancing reservoir or forebay for short term fluctuations (daily or hourly)
KIOT 9
HYDRAULIC STRUCTURE I (CENG3161)
Dead storage
This is a storage capacity of the reservoir provided to accommodate the deposition of silt in the reservoir. It is
expected that the dead storage space will eventually fill up with sediment at which time one says the dam has
served its full purpose.The life of a reservoir is dependent on the silting capacity of the reservoir. Provisions for
flushing out silt through deep seated bottom outlets/sluices is made in most dams. However this has a limited
effectiveness.
Evaporation Loss
Provision should be made for evaporation since it is an important loss item actual evaporation rate depends
upon location & meteorological factors. In arid and semi-arid regions at least 2 to 2.5m of depth should be
added as a rule of thumb.
Sometimes it may be required to carry over some of the live storage to the next year as a safety measure. This
carry over storage is determined by analyzing the storage requirement for a sequence of two or three
consecutive dry years.
2) Pondage Capacity
KIOT 10
HYDRAULIC STRUCTURE I (CENG3161)
If hourly inflows for a typical day are known, one can calculate the average hourly requirement and determine
the total maximum cumulative departures from the average over a 24 hour period. This will then be the
pondage needed to equalize the daily flow fluctuations.
4.4 Intakes and Head Race
Water Intake, Inlet Structures
The intake is a structure constructed at the entrance of a power canal or tunnel or pipe through which the
flow is diverted from the source such as a river or reservoir. It is an essential component of hydropower
schemes and provided as an integral part or in isolation from the diversion, weir or dam.
Functions of Intakes
The main functions are:
i) To control flow of water in to the conveyance system. The control is achieved by a gate or a valve.
ii) To provide smooth, easy and vortex or turbulence free entry of water in the conveyance system this
is to minimize head loss. This can be achieved through providing bell-mouth shaped entrance.
iii) To prevent entry of coarse river born trash matter such as boulders, logs, tree branches etc. Provision of
trash racks at the entrance achieves this function.
iv) To exclude heavy sediment load of the river from interring the conveyance system. Special devices
such as silt traps and silt excluders are used to control & trap the silt.
Types of Intakes
Intakes are conveniently classified in to the following types depending on the power plant type and its layout.
i) Run - of - river intakes
ii) Canal intakes
iii) Dam intakes
iv) Tower intakes
v) Shaft intakes
Intakes of special type
Settling Basins
The water drawn from a river for power generation may carry suspended sediment particles. This silt load
may be composed of hard abrasive materials such as quartz and will cause damage or wear to the hydro-
mechanical elements like turbine runners, valves, and penstocks. To remove this material a structure called
settling basin should be constructed, where the velocity of the flow will be reduced resulting in settling out
of the material, which has to be periodically or continuously flushed out.
In order to satisfy the requirement for a good hydraulic performance the basin is divided into three main
zones: inlet zone, settling zone, and outlet zone.
Inlet Zone:
The main function of the inlet is to gradually decrease the turbulence and avoid all secondary currents in the
basin. This is achieved by decreasing the flow velocity through gradually increasing the flow cross-section,
i.e., by providing gradual expansion of the width and depth (see figure 4.9).
KIOT 11
HYDRAULIC STRUCTURE I (CENG3161)
To achieve optimum hydraulic efficiency and effective use of the settling zone, the inlet needs to distribute
the flow uniformly over the cross-section of the basin. To achieve uniform flow distribution, the following
techniques, in addition to the provision of gradual expansion, may be adopted at the inlet zone:
Flushing flume
A A
Power canal
W
Flushing sluice
Power canal
Flushing flume
Section A-A
W W
Collection tank
Flushing flume
a) For continuous flushing b) For intermittent flushing
SectionB-B
Figure4.9 Settling basin
Settling Zone:
This is the main part of the basin where settling of the suspended sediment is supposed to take place. The
dimensions of this zone can be determined through calculations.
Outlet Zone:
This is a kind of transition provided following the settling zone to facilitate getting back the flow into the
conveyance system with the design velocity by gradually narrowing the width and depth. The outlet
transition may be more abrupt than the inlet transition.
Note: The cross-section of a settling basin is usually tapered at the bottom forming a sediment-collecting
flume, built with a gradient in the direction of flow.
KIOT 12
HYDRAULIC STRUCTURE I (CENG3161)
Head Race
Head race may be a power canal, a pressure tunnel, or a pipe, which in most cases conveying water from
intake structure to surge tank, forebay or pressure shaft, depending on the arrangement of the scheme.
4.5 Tunnels
General
Tunnels are underground conveyance structures constructed by special tunneling methods without
disturbing the natural surface of the ground. In many modern high head plants, tunnels form an important
engineering feature.
In the headrace of water conveyance system, tunneling is popular because of the following reasons:
i) It provides a direct and short route for the water passage thus resulting in considerable saving in cost
ii) Tunneling work can be started simultaneously at many points thus leading to quicker completion
iii) Natural land scape is not disturbed
iv) Tunneling work has become easier with development techniques of drilling and blasting and new
mechanical equipment
v) Development of rock mechanics and experimental stress analysis has given greater confidence to
engineers regarding stability of tunnels.
Tunnels of hydropower projects fall into two categories: water carrying tunnels and service tunnels.
a) Water carrying tunnels: These include head race or power tunnels, tail race tunnels or diversion
tunnels. Flows in water tunnels are usually under pressure (pipe flow), but sometimes free-flow (open
channel flow) can be experienced, especially, in tailrace tunnels. The design of free-flow tunnels
follows the same principles as used in the design of open canals.
- Head race tunnels: are tunnels that convey water to the surge tank. These are pressure tunnels
- Tail race tunnels: could be free flowing or pressure tunnels depending on the relative position of turbine
setting and tail water level.
- Diversion tunnels: are constructed for the purpose of diverting the stream flow during construction
period. Normally they are not of high pressure but should have sufficient flood carrying capacity. Such
tunnels either plugged with concrete or converted in to some use such as spillway tunnel at the
completion of the project.
Classification of Tunnels
In addition to the above classification tunnels may be classified on the basis of shape, alignment and design
aspects.
KIOT 13
HYDRAULIC STRUCTURE I (CENG3161)
Alignment: A name tunnel indicates a very small bottom slopes, i.e. tunnels are aligned nearly horizontal.
Shaft is a tunnel with vertical alignment or inclined shaft when it is steeply inclined to the horizontal. It is
very crucial to investigate in detail the geology of the strata through which a tunnel would be passing.
Sound, homogenous, isotropic, and solid rock formations are the most ideal ones for tunneling work.
However, such ideal conditions are rarely present, and rather the rock mass exhibits various peculiarities.
There may be folds, faults, joint planes dipping in a particular direction, weak strata alternating with good
strata, etc. Thus, the alignment of a tunnel should be fixed keeping in view these phenomena. The
alignment, for instance, should as far as possible avoid major fracture planes.
Design Aspects: Aspects of lining, pressure condition, etc., can be considered to identify different types of
tunnels.
Lining: Lining is a protective layer of concrete, R.C. or steel on the inner surface of the tunnel and it is an
important aspect in classification of tunnels. Thus tunnels may be lined, unlined or partially lined. Tunnels
in good, sound rock may left unlined.
KIOT 14
HYDRAULIC STRUCTURE I (CENG3161)
Pressure tunnels: are classified according to pressure head above the soffit of the tunnel. Accordingly:
In the case of low-pressure tunnels the tunnel surface may frequently be left unlined except for visible
fissures. A watertight lining is usually required for tunnels operating under medium and high heads.
Seepage is more likely to occur as the head increases, water may leak through the smallest fissures and
cracks. Moreover, under high-pressure it may penetrate the otherwise watertight rock and render it
permeable.
Low Head Tunnels
The trimmed rock surface may be sufficient by only sealing visible fissure with concrete or cement
mortar or granite layer
Full lining my be warranted only if external rock load or aggressively or water head loss reduction
justify it .
Medium head Tunnels
A water tight lining concrete is almost always needed since seepage is more likely to occur under
increasing head.
If the lining is only for water sealing purposes, and no load is carried by it, the permissible internal water
pressure head is determined by the depth of overburden and the quality of the rock.
KIOT 15
HYDRAULIC STRUCTURE I (CENG3161)
To reduce construction costs, relatively high velocities (higher than in open channels) are permitted in
tunnels.
The following velocities are suggested:
Very rough rock surface-------------- 1 to 2,0 m/s
Trimmed rock surface -------------- 1.5 to 3.0 m/s
Concrete surface----------------------- 2 to 4.0 m/s
Steel lining------------------------------ 2.5 t0 7 m/s
The permissible velocity depends upon the sediment load carried by the water. The maximum values in the
above recommendation apply when the sediment is of the silt fraction. For water carrying sharp edged sand
in significant quantity, Vmax = 2 to 2.5 m/s even in lined section.
Size of tunnels cannot be reduced arbitrarily. Requirements of passability limit the maximum size.
Minimum size of Tunnel: Circular, 1.8 m
Rectangular, 2m x 1.6m.
4.6 Water Hammer, Surge Tanks and Forebays
Water Hammer
A sudden change of flow rate in a large pipe line (due to value closure) may involve a great mass of water
moving with in the pipe walls. The force resulting from changing the speed of the water mass causes a
pressure rise in the pipe with a magnitude several times greater than the normal static pressure in the pipe.
This phenomenon is commonly known as water Hammer because of the noise & vibration with which it is
sometimes accompanied. The excessive pressure only fractures the pipe water unless it is properly analyzed
& accounted for in the design of the pipe line.
The determination of Water Hammer pressure is amenable to mathematical analysis. Practical problems
may, however, be of considerable complexity owing to the many variables involved. Here, we will consider
only elementary class. In this regard the simplest procedure is to regard the water as incompressible & the
pipe as rigid (The so-called rigid Water-Column theory).The assumption is obviously not very realistic but
can lead to reasonable estimations in the certain cases. The more realistic situation is the one that takes the
elasticity of the water & the pipe in to account (The Elastic Water Column Theory).
Surge Tanks
The surge tank, also called the expansion chamber, is a structure which forms an essential part of the
pressure conduit conveyance system whenever such system is long. Surge tanks may be considered
essentially as a forebay close to a machine. Their primary purpose is protection of long pressure tunnel in
medium and high –head plants against high water hammer pressure arising from sudden rejection or
acceptance of load, The surge thank converts these high frequency, high pressure transients (water hammer)
in to low frequency low pressure, mass oscillation.
It is located between the almost horizontal or slightly inclined pressure conduit and the steeply sloping
penstock/pressure shaft. It is designed either as chambers excavated in the mountain or as a tower raising
high above the surrounding terrain (see Figure 4.10).
KIOT 16
HYDRAULIC STRUCTURE I (CENG3161)
Surge Tank
Pressure Tunnel
Power House
KIOT 17
HYDRAULIC STRUCTURE I (CENG3161)
KIOT 18
HYDRAULIC STRUCTURE I (CENG3161)
Forebays
A forebay, also called a head pond, is a basin located at the end of a power canal just before the entrance to
the penstock or pressure shaft. It acts as a transition section between the power canal and the penstock. It is
formed simply by widening the power canal at the end. Figure 4.14 shows typical forebay.
Functions of a Forebay
A forebay serves the following purposes:
It can serve as a balancing reservoir. Water is temporarily stored in the forebay in the event of a rejection of
load (turbine closure) and the stored water will be withdrawn from it when the load is increased (turbine
opening). In the case of low-head power plants, the forebay may even provide daily pondage for the plant. It
can serve as a final settling basin where any water borne debris which either passed through the intake or
was swept in to the power canal can be removed before the water passes into the turbine. In this case, the
forebay must be large enough to reduce flow velocities sufficiently for settling to occur and to
accommodate the sediment which accumulates between cleanings. It can serve to distribute evenly the
water conveyed by the power canal among the penstocks, where two or more penstocks are provided.
Components of a Forebay
The following are the main components of a forebay:
- the basin
used to store water and sediment (if any)
- the spillway
used to dispose excess water that might enter the forebay
- the bottom outlet
KIOT 19
HYDRAULIC STRUCTURE I (CENG3161)
used for flushing out of the sediment stored in the basin as well as for de-watering the forebay and the
power canal for maintenance
- the penstock inlet serves in controlling flow into the pressure conduit and in preventing floating debris
from entering the conduit. It also provides smooth transition between the basin and the conduit.
4.8 PENSTOCK
The penstock is high pressure pipeline between forebay ( surge tank or reservoirs ) and the turbine. The
design principle of penstocks is the same as that of pressure vessels & tanks but water hammer effect has to
be considered. For short length, a separate penstock for each turbine is preferable. For a moderate heads &
long distances a single penstock is used to find two or more turbines through a special branching pipe called
Manifold.
Classification of penstock.
1) Material of construction
Factors for the choice of material are: head, topography & discharge. Various materials used are steel, R.C.,
asbestos cement, PVC, wood stave pipes, banded steel, etc. The following factors have to be considered
when deciding which material to use for a particular project:
Required operating pressure Diameter and friction loss Weight and ease of installation Accessibility of
site Cost of the penstock Design life Availability Weather conditions.
2) Method of support
A penstock may be either buried or embodied underground (or inside dams) or exposed above ground
surface & supported on piers.
KIOT 20
HYDRAULIC STRUCTURE I (CENG3161)
Buried penstocks: are supported on the soil in a trench at a depth of 1 to 1.5m and back filled. The general
topography of the land should be gentle sloping and of loose material.
Advantages Disadvantages
1. Continuity of support given by the soil provides 1- Difficulty in inspection
better structural storability.
2. Pipe is protected from high temperature fluctuations 2- Possibility of sliding on step slopes
3. Conservation of natural land escape 3- Difficulty in maintenance
4. Protection from slides, storms & sabotage. 4- Expensive for loge diameter in rocky soils.
4. Number of Penstocks
The number of penstocks used at any particular installation can be single or multiple. The general trend at
older power stations was to use as many penstocks between the forebay/surge tank and the powerhouse as
the number of units installed. The recent trend is to use a single penstock, unless the size or thickness of the
penstock involves manufacturing difficulties.
When a single penstock feeds a number of turbines, special sections called manifolds are used at the lower
end of the penstock to direct flow to individual units. The design of such sections is an intricate job and has
to be analyzed carefully.
The advantages of using a single penstock over the use of multiple penstocks are:
The amount of material required to manufacture is less, making it economical.
The cost of civil engineering components such as penstock supports and anchors is less.
On the other hand, the use of a single penstock means reduced safety of operation and complete shutdown
will become necessary in case of repair. Further more, significant losses are usually experienced at the
manifolds.
KIOT 21
HYDRAULIC STRUCTURE I (CENG3161)
In general, the use of multiple penstocks is preferably employed for low-head plants with short penstocks;
whereas for high-head plants requiring long penstocks, provision of a single penstock with manifold at the
end usually proves economical.
Hydraulics
Permissible velocities.
3 to 5 m/s ( no abrasion property settled water) for properly settled water in exceptional cases up to 5m/s
may be tolerated.
Q0 D 2 Q0
Therefore: A D 1.128
v0 4 v0
Head losses
2
i) Frictional head loss => h f L v
D 2g
v2
ii) other local losses h f c k where k = local loss coefficient
2g
K
Penstock with gradual transition entrance 0.10 - 0.20
Open butterfly valve (depending on disk thickness) 0.05 - 0.25
Needle valves 0.20 - 0.25
Bends (depending on deflection angle) 0.05 - 0.15
KIOT 22
HYDRAULIC STRUCTURE I (CENG3161)
Total cost
Cos
t
Economic Construction
loss cost
Diameter
1) SARKARIA’S Formula
3) Donald’s formula
0.466
P
D 0.176
H
4) Fahlbusch (2982)
D 0.52 H 0.17 P H 0.43
KIOT 23
HYDRAULIC STRUCTURE I (CENG3161)
h 2L C vo 2 L 2vo L
hmax .
C tc g C tc g tc
The value of water hammer pressure rise as computed above may be taken at the turbine gate, reducing to
zero at intake or surge tank level. Values at intermediate location may be calculated assuming a straight line
variation
For steel used in penstocks usually a factor of safety of 3 to 3.5 is used. Thus for material with ultimate
tensile strength of 3700 kg/cm2; a 1200 kg/cm2
For protection against coating deterioration add 1 to 3mm to the above value.
For thick welded piper where D 20 , the following formula giver sufficient accuracy
t
D a 0.07H
t 1) (1 to 3)mm
2 a 0.13H
pr
The ASME gives the formula for thickness as t 0.15
a 0 .6 P
Where t in cm
p pressure in kg/cm2
r internal radius in cm
a design stress in kg/cm2
joint efficiency factor
0.15cm is allowance for corrosion
In case where the negative water column gradient falls below the penstock center line, there is danger of
collapse of the penstock due to external atmospheric pressure. The external pressure p e likely to result in
collapse may be computed from the formula by Mayer
3EI 24EI
pe kg / cm 2
r3 D3
KIOT 24
HYDRAULIC STRUCTURE I (CENG3161)
3
I =moment of inertia of x-section of the pipe ring t m3
12
E =modulus of elasticity of steel
3
Introducing a S.F. , Pe 1 t
2 n=2 for burried pipes; n=4 for exposed pipes
D
Pe
t D3
2E
Reaction turbines: In this type the water enters the turbine in a circumferential direction in to the scroll
case and moves into the runner through a series of guide vanes, called wicket gates. The available energy
partly converted to kinetic energy & substantial magnitude remains in the form of pressure energy (eg.
Francis, Kaplan, Propeller, Bulb, etc)
KIOT 25
HYDRAULIC STRUCTURE I (CENG3161)
Turbine or synchronous speed: Since turbine & generator are fixed, the rated speed of the turbine is the
same as synchronous speed of the generator. The speed N, for synchronous running is given by :
N 120 f
p
Where f = frequency cycle/sec ( 50-60 Hz c/s)
p = number of poles ( divisible by 4 for head up to 200 m )
( divisible by 2 for head above 200 m )
The speed of a turbine is an important parameter of design. The higher the speed, the smaller the diameter
of the turbine runner & the cheaper the generator coupled to the turbine. High speed, however, makes a
turbine more susceptible to cavitation.
KIOT 26
HYDRAULIC STRUCTURE I (CENG3161)
The ratio of the peripheral speed of the bucket or vanes at the nominal diameter, D, to the theoretical
velocity of water under the effective head, H, acting on the turbine is called the speed factor or peripheral
coefficient , .
v r
2 gH 2 gH
but in rad/sec; 2N r=D/2
60
Therefore, DN DN
D and H in m; N in rpm
60 2 gH 84.6 H
The following table suggests appropriate values of , which give the highest efficiencies for any turbine, the
head & specific speed ranges & the efficiencies of the three main types of turbine.
Thus in general
Pelton turbines are used for high heads & low discharges
Francis types are used for medium & high head plants (has adjustable guide vanes but the runner is a
disc with fixed passage)
Propeller & Kaplan (Kaplan has adjustable blades) types are used for lows head plants with large
discharges.
KIOT 27
HYDRAULIC STRUCTURE I (CENG3161)
If D is found to be too large, either N can be increased or more units may be adopted. For approximate
calculations of runner diameter; the following empirical formula may be used (Mosony)
1
Q 3
D in m; Q in m3/s; N in rpm
D a
N
a = 4.4 for Francis & propeller; a = 4.57 for Kaplan.
It is not uncommon to use a member of multiple jet wheels mounted on the same shaft so as to develop the
required power.
A hydraulic turbine (runner) is designed for optimum speed & maximum efficiency at design head. But in
reality, head and load conditions change during operation & it is extremely important to know the
performance of the unit at other heads. This is furnished by manufacturer’s curve.
KIOT 28
HYDRAULIC STRUCTURE I (CENG3161)
If the external load on the machine suddenly drops to zero (sudden rejection) and the governing mechanism
fails at the same time, the turbine will tend to race up to the maximum possible speed, known as runaway
speed. This limiting speed under no-load, maximum-flow must be considered for safe design.
Minimum Maximum
Impulse (Renton) 170 - 190 65 125
Fiancés 200 - 220 50 150
propeller 250 - 300 50 150
Runaway speed and acceptable head variations
A scroll case is the conduit directing the water from the intake or penstock to the runner in reaction type
turbine installation ( in case of impulse wheels a casing is usually provided only to prevent splashing of
water & lead water to the tail race). A spiral shaped scroll case of the correct geometry ensures even
distribution of water around the periphery of the runner with the minimum possible eddy formations.
KIOT 29
HYDRAULIC STRUCTURE I (CENG3161)
a) Francis turbine with steel spiral case b) Propeller turbine with partial spiral
Figure 4.21: Recommended dimensions of scroll casings (a) full spiral b) partial spiral
These kinds of spiral case will generally used in medium and high head installations where discharge
requirement is low. See Figure 6.4 a). Spiral cases with 320<<340 are also considered full.
The design of the shape of the spiral case is governed by the flow requirements. Initial investigation should
be based on the following assumptions:
a) spiral case of constant height
b) an evenly distributed flow in to the turbine
c) no friction losses
Referring to Fig 6.6 (a) the discharge in section of spiral case defined by angle is
Q where Q is the total discharge to the runner.
q
2
k gH
vt where k 30 ( from the basic Euler equation for the power absorbed by the
r N
machine)
KIOT 30
HYDRAULIC STRUCTURE I (CENG3161)
dr Q R Q
dq vt h0 dr k ho dr q r0 k ho
R
or ln
r 2 ro z k ho
This shows for given vortex strength, k, a definite relationship exist between Q & R.
The most economical design of a power station substructure and the narrowest spiral case can be obtained
by choosing a rectangular section adjoining the guide vanes (entrance ring) by step transition (symmetrical
or asymmetrical) as shown in b.
h h0 (r r0 ) h where cot 1 cot 2
Q dr dr
r01 h
r R
r1 H 0
2k r r
Replacing and integrating
Q r R
h0 r0 ln 1 H 0 h0 H 0 ln
2k r0 r1
Knowing r1 from H h0
r1 0 r0
, the value of R defining the shape of the spiral case can be determined. The
height H0 at any angle may be assumed to be linearly increasing from h0 at the nose towards the entrance.
Shape at various is determined by assuming existence of uniform velocity equal to entrance velocity,
Q i
v0 0.2 2 gH and qi
2
qi q Area of cross-section at angle i
Ai 0.18 i
v0 H
A draft tube is a conduit discharging water from the turbine runner to the tailrace. It is employed in
conjunction with reaction type turbines, and has twofold purposes:
To recover as much as possible of the velocity energy of the water leaving the runner, which otherwise
would have gone to waste as an exit loss, thus increasing the dynamic draft head.
To utilize the vertical distance between the turbine exit and the tail-water level, called the static draft
head. In other words, to allow the turbine to be set at higher elevation without losing the advantage of
elevation difference.
The most common is elbow type which minimizes the depth of substructure compared to vertical one, it
also has a desirable effect in directing the flow in the direction of the tail water.
KIOT 31
HYDRAULIC STRUCTURE I (CENG3161)
The straight conical draft tubes are the simplest in design and the most efficient type, but they are rarely
used in actual practice. This is because, for effective recovery of velocity head, the outlet section has to be
many times the inlet section of the draft tube. For smooth eddy-free flow (flow with no separation), the
angle of flare of the tube has to be limited to 4 to 8 degrees. Hence, a considerable long tube is necessary to
achieve the desired result. This increases the depth of excavation of the substructure, making it
uneconomical and unsuitable from cavitation view point.
The elbow-type draft tube is often adopted, because of the following advantages it offers over the conical
type:
KIOT 32
HYDRAULIC STRUCTURE I (CENG3161)
Cavitation result is pitting, vibration & reduction in efficiency & is certainly undesirable. Cavitation may be
avoided by suitably designing, installing, and operating the turbine in such a way that the pressures with is
the units are above the vapor pressure of water.
Refering the previous Figures, Ys is the most critical factor in the installation of reaction turbines.
KIOT 33
HYDRAULIC STRUCTURE I (CENG3161)
2
Ns
c 0.0432 for Francis
100
3
Ns
c 0.28 0.0024 For propeller
100
With an increase by 10% for Kaplan turbines.
The preliminary calculation for the elevation of the distributor above the TWL, Yt is
KIOT 34