Electrical Schedule - MRPL Project-Rev-01
Electrical Schedule - MRPL Project-Rev-01
Electrical Schedule - MRPL Project-Rev-01
'23 14 Aug '23 04 Sep '23 25 Sep '23 16 Oct '23 06 Nov '23 27 Nov '23
Duration S S M T W T F S S M T W T F S S M T W
1 Commencement Work Mon 17-07-23 Thu 27-07-23 10 days
2 Laying of cables of different voltage grade Tue 18-07-23 Thu 31-08-23 39 days
3 Supply of nickel-plated, flame proof IIA/IIB Mon 07-08-23 Mon 21-08-23 13 days
double compression type brass cable glands
4 Supply of nickel plated brass single Mon 07-08-23 Mon 21-08-23 13 days
compression cable glands
5 Termination of XLPE insulated armoured Fri 01-09-23 Wed 20-09-23 17 days
power cables
6 Installation of prefabricated hot dip Tue 26-09-23 Wed 25-10-23 26 days
galvanised steel cable trays
7 Installation, connection, testing and Tue 17-10-23 Tue 31-10-23 13 days
commissioning of flame proof weather proof
lighting/power panels
8 Installation of Junction Box Tue 17-10-23 Mon 23-10-23 6 days
9 Installation of Platform Lighting pole Thu 26-10-23 Sat 11-11-23 15 days
10 Installation, connection, testing and Mon 30-10-23 Mon 13-11-23 13 days
commissioning of flame proof/Div.2 lighting
fixtures
11 Supply, installation and connection of lightning Tue 17-10-23 Sat 21-10-23 5 days
arrestors
12 Installation and connection of GI earthing strip Mon 16-10-23 Tue 31-10-23 14 days
13 Connecting individual equipment to the earth Mon 23-10-23 Sat 04-11-23 12 days
strip
14 Site Handover Mon 13-11-23 Mon 20-11-23 7 days
Page 1