MINISTRY OF RAILWAYS
(RAILWAY BOARD)
SCHEDULE OF TECHNICAL
(AUGUST 2022)
DETAILED INFORMATION
S No Item Remarks
4.0.1 QAP Approved by RDSO (Yes / No)
Managing Director
Lab. Assistant
(Two)
1. Overall Quality Control In-charge: At least One Graduate Engineer with Civil Engineering degree.
(a) Minimum one supervisors with diploma in civil engineering for each shift per each casting
shed.
(b) Minimum one diploma engineer of mechanical/ electrical / electronic / IT /civil for
maintenance of equipments.
3. Quality Control Supervisor for Laboratory and testing: Minimum one supervisor with Diploma
in Civil Engg./ BSc .
4. Supervisors & Mixture Machine In-charge should be suitably qualified and their competency
shall be certified by the overall Quality Control In-charge of the plant.
3
7.0.1 Concrete mixer along with Automatic Batching Plant using Microprocessor 1 no.
based Weigh Batcher, Pneumatically operated Aggregate Bins, Water meter
and automatic Cement feeding, Capacity of Concrete 5m3/hr. It should be
capable of keeping digital record of ingredients used batch wise & data
storage capability for one year production and should be capable of
providing output in hard copy also.
7.0.2 Standard weights of 50 Kg or highest permissible denomination totaling 50kg 1000 Kg
& Small denominations capable of measurement to the least count of 1 kg
for calibration of weigh batcher
7.0.3 Water measuring cans or automatic water meter for calibration of water meter 1,2,5,10&20
liters
7.0.4 Concrete sleeper Mould should be made with plate thickness 6/8mm with 240 nos.*
suitable stiffening arrangement to avoid in service distortion of moulds. Rail
seat area & end plates are to be made with 10 mm thick Steel plate. Rail
seat area should also be made with adequate measures to ensure proper
rail seat slope and surface finish.
7.0.5.1 Steel Stress Benches made of channel and with Jack Anchoring Pockets, for 60 nos.*
holding 4 sleeper moulds. Design of stress bench should be such so as to
have minimum distortion on account of service stresses.
7.0.5.2 Hydraulically operated Pre-Stress Equipment with motorized unit, for 500KN 2 Sets
jacks along with Pressure Gauges / pressure transducer with digital display
and auto cut arrangement. The data should be displayed on monitor and
should be stored for future analysis of past six months data.
7.0.5.5 Steam curing chamber of adequate size and capacity to hold not more than
eight benches containing four mould each. The steam curing should be with
6
servo controlled valve with steam regulation with auto cut off arrangement
following the steam curing cycle. The thermometers should be provided at
both ends of steam chamber with digital display. The data of time vs
temperature in each chamber should be digitally displayed and stored and
system should have sufficient memory to store at least on year’s data with
facility to take out print shift wise.
7.0.6 For Production by long line method
7.0.6.1 End support embedded in ground with device permitting transfer of As per
pre stress design
7.0.6.2 Tensioning gun with digital pressure gauge, automatic cut off device and 02 nos
automatic elongation & force recording arrangement along with digital
display and logging of data on computer with data storage & retrieval for at
least six month.
7.0.6.3 Casting bed with moulds. No of moulds should be 10 % more than required As per
for daily production capacity. design
7.0.6.4 Tarpaulin hoods for covering casting beds for steam curing. With proper For each
drainage arrangement. casting
line
7.0.6.5 The steam curing should be regulated through servo controlled valve with For each
auto cut off arrangement and regulation of steam to maintain the casting
temperature as per steam curing cycle. The data of time vs temperature line
covering complete casting line should be digitally displayed and stored. The
system should have sufficient memory to store at least on year’s data with
facility to take out print shift wise.
7.0.7 Steam Boiler, Coal /oil fired/electrically operated capacity of 1000 kg/hr, 1 no.
complete with Valves, mountings and Chimney. The key parameters of
boiler such as steam pressure should be displayed. The boiler & its
operators certification from statutory authority should be ensured.
7.0.9 Concrete Bucket for carrying and pouring concrete in moulds by bottom 1 no.
controlled discharge on Monorail Hoist, Movement should be motorized and
operator controlled.
7.0.10 High Frequency 9000 RPM (+/-4%) Vibrator bottom fixing type. For PSC 16 nos.
line sleepers and Turnout sleepers, vibrators of min 2.0KW capacity are to
be used. The vibrator should have recording facility for recording date and
time of each operation. RPM should be digitally displayed during operation.
7.0.13 Vibrating Table for Cubes 15X 15 X 15, table 1mX 1m 1 no.
7.0.14 Electric Welding Arc Cutting M/c for HTS cutting at de-molding/ Abrasive 2 nos.
disc cutter.
7
7.0.16 Overhead Wire Rope Hoist 2 T capacity, Electrically driven, traveling 2 nos.
on I Beam Section, One each for demoulding and curing tank
7.0.17 Overhead Wire Rope Hoist for Steam Curing Chambers 3 T capacity, 2 nos.
traveling on I Beam Section (Excluding the structure)
7.0.18 MS Gantry Crane electrically driven with Overhead Wire Rope Hoist 4/5 T 2 nos.
capacity for Loading of sleepers and for putting sleepers in water curing
tanks.
7.0.19 Diesel Generating Set for 125KVA 1 no.
S. No Equipment Quantity
8.0.1 Compression Testing Machine, 2000KN capacity, motorized with 2 nos. of 1 no.
pressure gauges (2000KN & 500KN) with digital interface for real time
recording of testing results. The system should have sufficient memory to
store data of one year production with reporting facility in hard copy as per
format mutually agreed.
8.0.2 Flexural Beam (Tension) Testing Machine with loading Jacks, 30 KN 1 no.
capacity. The machine should be capable of digital display and recording of
data during testing with auto logging off time & date of testing. Data storage
& retrieval capability should be for one year production.
8.0.3 Motorized pumping unit with 1000KN capacity jacks, pressure gauge, 1 no.
rubber tubes and test frame complete for sleeper testing. The digital display
of the load applied should be visible to observer simultaneously along with
observation of crack. The data shall be recorded in computer with automatic
date and time record with Batch no. and other details for traceability of
record.
8.0.4 15 cm cubes moulds confirming to IS:516 50 nos.
8.0.8 Electronic balance with 1gm least count (10 / 20 Kg. capacity ) including 1 no.
weights.
8
8.0.10 Vicat apparatus with dash pot and various needles 1 no.
8.0.14 Cement mortar cube casting machine with motor and time switch complete 1no.
8.0.16 Metallic scoop, pan type container and china tray etc 2 sets
8.0.23 Proving rings of 2000 KN,1000 KN, 500 KN, and 100 KN capacity 1 each
8.0.26 Miscellaneous measuring gadgets like steel tape, Vernier, filler gauge etc. 2 sets
8.0.27 Inspection gauges for dimension checking of sleepers with digital display of 2 sets
parameters as approved by RDSO. (Optional)
A STORAGE OF RAW
MATERIALS
1 Cement Godown 2 - -
2 HTS Storage Area 1 - Only 1 camera can be provided if
HTS storage & Insert storage
area are at same location and can
3 Insert Storage Area 1 - be covered by one camera
properly.
4 Coarse Aggregate 1 - Only 1 camera can be provided if
Storage Area CA & FA storage area are at
same location and can be
5 Fine Aggregate Storage Area 1 - covered by one camera properly.
6 Admixture Storage Area 1 -
C SLEEPER PRODUCTION
1 Production line for concreting 4 1 It should adequately cover the
Sleeper casting, Mould
preparation and HTS wire
threading activities.
One sensor for bench counting
2 Extension of HTS wires 1 1 One sensor for measuring
extension of HTS wires
3 Application of Load for 1 - -
stressing of HTS Strands
4 Compaction of concrete / 1 One sensor per vibrator to
Vibration measure RPM of vibrator and
time of vibration.
5 Casting of concrete cubes / 1 1 -
vibrating table
D CURING
1 Steam Curing Chamber 2 1 Minimum 2 cameras for covering
entire steam curing area. One
Sensor per Chamber to be
provided. Temperature of steam
curing and steam characteristics
to be measured and to be
captured in the overall system
10
being used at the centralized
location.
2 Water Curing 4 - Minimum 4 cameras for covering
entire water curing area.
3 De-tensioning and de- 2 - Only 1 camera can be provided if
moulding area both operations are at same
location and can be covered by
one camera properly.
E TESTING LABORATORY
1 Concrete Cube Testing 1 1 Only 1 camera can be provided if
2 Beam Testing 1 1 Concrete Cube Testing and Beam
Testing are done at same location
and can be covered by one
camera properly.
3 Static Bending Test 1 1 -
4 Testing of various ingredients 1 - Should cover entire lab activities.
of concrete viz. Fine
Aggregate, Coarse Aggregate,
Cement Water, Admixture etc.
CERTIFICATE
2. Testing of raw material shall be carried out as per relevant specifications, the details of raw
material used is as given in as Annexure-I.
SIGNATURE OF PROPRIETOR
Annexure-I
2.1 Coarse Aggregate (as per test report submitted at the time of approval of mix design)
2.2 Fine Aggregate (as per test report submitted at the time of approval of mix design)
2.4 Water
2.4.2 pH value =
2.7 Admixture
2.7.2 Properties
14
Annexure-II
1.1 Aggregates:
Details of Receipt, Source, Date of receipt, Truck Nos., Quantity, Balance, Remarks about quality
and signature.
Date of Receipt, Truck No., Quantity, Source (Name of manufacturer), Consumption, Balance etc
shall be recorded. Each lot shall bear a lot number and it should be mentioned in the production
register to correlate which insert used in which sleeper.
Date of receipt, Source & conformance to IS codes, quantity, Shift-wise consumption, balance,
whether Test Certificate received shall be recorded. Each lot shall bear a lot number and it
should be mentioned in the production register to correlate with production of PSC sleepers.
2.1 Production Register: Batch Nos., Nos. Cast in each shift, cumulative production, Bench Nos.,
Cubes and sleeper testing details, Summary of Rejected and Usable sleepers shall be recorded
in the printed register Daily production register shall be maintained for each design of sleepers
separately (As per format no. XIV).
a) Sieve analysis with combined granulometric analysis of aggregates. (As per format no. VI).
b) Combined Flakiness and Elongation indices test. (As per format no. VII).
c) Moisture content and modified (adjusted) quantities. (As per format no. V).
d) Records of Moulds and Benches and repairs.
15
Similar analysis shall be carried out for each month and a consolidated report shall be submitted
for a given financial year.
The record shall be maintained as per Format-IX, X & XI for calibration of weigh batcher, Water
meter, SBT machine, Concrete cube test machine, cement mortar cube testing machine, Beam
testing machine and tensioning jacks. The schedule is given in Para 6.0 below.
Calibration of all the pressure gauges shall be done in the plant itself. Calibration of proving ring should
be got done from a Govt. approved test house or a National Test House. The frequencies of all the
pressure gauges and equipments are as follows:-
---------------------------------------------------------------------------------------------------------------------------------------------------------------------
Note :-
1) The items referred at S. Nos. 1 to 7 above should be calibrated by proving ring the sleeper plant
itself.
2) The items referred at S. Nos. 8 & 9 should be calibrated by the dead weights and item at S. No. 9
10 by measuring cans that should be available in the plant.
3) The proving ring should be calibrated from a reputed organization like the IITs, NCCBM or NPL
etc.
4) The record of calibration of the all the above equipments should be maintained in a manner that
previous record can be easily connected.
5) The calibration can be done more frequently at the discretion of the inspecting Official.
This is to certify that the information given as above is correct and If the information is found to be
false then the firm will accept the action taken by Railway.
SIGNATURE OF PROPRIETER
NAME
SEAL
17
Annexure III
FORMATS
Format -I
Consignment of Cement =
Room Temperature = 0C
1.
2.
3.
Ts
= cm2/gm
Format -II
NORMAL CONSISTENCY OF
SPECIAL CEMENT FOR INITIAL AND FINAL SETTING TIME
[ IS: 4031( Part-III & Part-IV ) -1988 ]
Date:
Consignment of Cement :
Room Temperature : oC
1.
Needle reading
2.
between 5 to 7 mm from
bottom of the mould
3. indicates Normal
Consistency.
4.
Normal Consistency = %
Quantity of water to be added for making paste of special cement for determination of initial and final
setting time is 85 % of the normal consistency.
Format -III
Date:
Consignment of Cement =
Room Temperature = oC
Normal consistency = %
2.
3. is minutes.
4.
5. > 60 minutes OK
6.
8.
21
9.
11
12 is minutes.
13
15
17
18
19
20
Format -IV
&
Consignment of Cement:
Room Temperature : oC
ii.
Normal Consistency (P) : % (See Normal Consistency test)
= ( P + 3) x 800
= ml
23
B: Soundness of cement
FORMAT -V
Date Shift
S.
Description Units CA1 CA2 FA Remarks
No.
Wt. of wet
A. Gms.
Sample
Wt. of dried
B. Gms.
Sample
Wt. of Moisture
C. %
Sample (A - B)
Moisture
D. %
= C x 100/B
E. Absorption %
Free Moisture
F. %
= (D - E)
Free Moisture
H. Kgs.
= G x F/100
Adjusted wt.
Kgs.
= (G + H)
W/C Ratio =
A/C Ratio =
If aggregates are wet, moisture content in coarse and fine aggregate is to be accounted for, so as to have
total water as per approved mix design.
FORMAT -VI
COMBINED GRANULOMETRIC CURVE (M55/M60) [IS: 383-2016]
Date Time Next Due on
Wt. of CA1 (20 mm) = Wt. of CA2 (10 mm) = Wt. of FA (Sand) =
Combined Passing Combined Grading
gms. gms. gms.
Passing % Range
Wt. Cum.
Sieve Cum. % % Wt. Cum. Wt. Cum. % % Wt. Cum. Wt. Cum. % % CA1 CA2 FA
Retained Wt.
Size retained Passing Retained Retained retained Passing Retained Retained retained Passing % % %
grams Retained
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
20 mm
10 mm
4.75
mm
2.36
mm
1.18
mm
600 µ
300 µ
150 µ
Format –VII
As per IRS-T-39 the above result of combined flakiness and elongation Index is less than 40 %.
Format –VIII
A: DETERMINATION OF CRUSHING VALUE [ IS :2386 (Part –IV) – 1963]
A= Weight of surface dry sample, when carried out as per provision of para :
2.4 IS 2386 (pt.IV)
Note: 1. For aggregates passing through 20mm sieve, 3.35mm sieve size for separating
finer to be used.
2. For aggregates passing through 10mm sieve, 1.70mm sieve size for separating
finer to be used.
A= Weight of oven dry sample, when carried out as per provision of para: 4.4
IS:2386(Pt. IV)
A= Weight of oven dry sample, when carried out as per provision of para: 5.2 of
IS:2386(Pt. IV)
FORMAT - IX
Calibration – I
Calibration of Weigh batcher by Standard Dead Weight
1 50
2 100
3 150
4 200
5 250
6 300
7 350
8 400
9 450
10 500
FORMAT - X
Calibration – II
10
Signature of AEN/XEN/CSP
Name
Designation
30
FORMAT - XI
10
Signature of AEN/XEN/CSP
Name
Designation
31
*P=E{(B-A)*a}/L,
where P(KN), = pre stressing force (from 50KN to final pre stressing value),
(B-A)(mm),=measured elongation
a(mm2), = total cross sectional area of HTW wires
L (mm) = effective wire length (from wedge to wedge clear length),
E(KN/mm2)= Young’s modulus (lot wise/IC wise)
Note: 1. Breakage or slippage of HTS wire, if any shall be recorded.
2. Values of ‘A’ & ‘B’ shall be based on the respective sleeper drawings
Shift : 1 Date:
Shift : 2
Chamber No. 1 2 3 4 5 6 7 8 9 10 11 12
No. of Bench
Cube No.
Time Temperature Temperature Temperature Temperature Temperature Temperature Temperature Temperature Temperature Temperature Temperature Temperature
07.00
07.30
08.00
08.30
09.00
09.30
10.00
34
10.30
11.00
11.30
12.00
12.30
13.00
13.30
14.00
14.30
15.00
15.30
16.00
16.30
Format-XIV
PRODUCTION REGISTER
On Date
Monthly Production
Cumulative
Steam
Chamber {1} {2} {3} {4} {5} {6} {7} {8} {9} {10}
No.
Bench No.
Time of
L.B.C
RELEASE CUBE STRENGTH (STEAM CURED) to be tested by Lab in charge and Railway Supervisor.
Date Weight
Time Age Load
of
Cube No. (in (in N/mm2 Remarks
Testi
Hrs.) (in Hrs.) (in KN)
ng Kgs)
FLEXURAL STRENGTH
Beam No. Date of Testing Age ( in days ) Load ( in KN ) Strength ( in N/mm2 ) Remarks
36
Total Rejected
Format -XV
DIMENSION REGISTER
1A
1B
1C
1D
2A
2B
2C
2D
3A
3B
3C
Note: 1. It should be ensured that the rejected (Red Marked) and MF tested (Yellow Marked) sleepers should not be
dispatched.
Format -XVI
SGCI Insert : DIMENSIONAL & WEIGHT CHECK LIST
Description: SGCI insert to RDSO/T-381 Alt.9 (or latest alteration) & specification IRS/T-46
(latest version)
SGCI Supplier:
S. Heat Patt Jig Length Thickness Hole Width of Top Gating Square Wt in Soundness
No. No. ern of of stem dia head radius position gauge Kg. through
No. G G1 G2 head 1.55-3% hammer
20/25+2/ 22+1/-0 67+1/-0.5 test
75±1 -1
Note:
2. AEN/XEN will check at least 20 inserts, once in 2 weeks on random basis. He will also ensure that
tests prescribed for Rly Inspectors are being conducted.
3. Other Instructions contained in Board’s letter no. 98/TK-II/22/11/17/Pt. Policy, dtd. 11.08.2003 are to
be adhered to.
Signature of AEN/XEN/CSP
Name
Designation
39
Format –XVI A
Description: SGCI insert to RDSO/T-6901 Alt.5 (or latest alteration) & specification IRS/T-46 (1996) (latest version)
SGCI Supplier:
Gauge Employed: Gauge and fixtures conforming to RDSO/T-6943 Alt.3 IC no. and date (As issued by
purchaser/Inspecting authority)
S. Heat Patt Jig Length Thickness Hole Width of Top Gating Square Wt in Soundness
No. No. ern of of stem dia head radius position gauge Kg. through
No. G G1 G2 head 1.484-3% hammer
25/35 +2/ 23+0.5/ 71+1/-0.5 test
76 +1/- -1 -0
0.5
Note:
2. AEN/XEN will check at least 20 inserts, once in 2 weeks on random basis. He will also ensure that
tests prescribed for Rly Inspectors are being conducted.
3. Other Instructions contained in Board’s letter no. 98/TK-II/22/11/17/Pt. Policy, dtd. 11.08.2003 are to
be adhered to.
Signature of AEN/XEN/CSP
Name
Designation
40
Format -XVII
STATISTICAL ANALYSIS OF CONCRETE STRENGTH AND STATIC BENDING STRENGTH TEST ON PSC SLEEPERS
ii) TYPE OF SLEEPERS (MBC, TURNOUT & OTHER) TO DRG. NO RDSO/T – 2496 OR Drg. No.
A. CUBE STRENGTH :
Batch No. No. of Rang Me Standard Characterist Coefficien No. of No. of batches Remarks
From Cube s e an Deviation ic value t of observations
N/m Val (N/mm2) variation below the
m2 ue SD CV (%) minimum
To M Min (N/mm2) specified values Double More than
a N/mm2 i.e. 55/ 60 Testing double
x (N/mm2) testing
Steam
cube
(Release
strength)
Water
cube (15
days
strength)
S. No. Batch No. Load (P) (KN) Flexural strength (N/ mm2 )
41
Description Batch No. of Range Mean Standard Characteristic Coefficient No. of No. of sleepers & Up to date No. of
No. sleepers (KN) value Deviation Strength (KN) of observations No. of batches sleepers
tested (KN) (KN) variation below the min.
% specified values
Center top
Rail Seat
Bottom
(A) A/C Ratio (B) W/C ratio (C) Mix Proportion CA-I: % CA-II %, FA %
Note: 1. Separate analysis shall be submitted for MBC, Turnout and other sleepers.
3. Indicate change of source of raw materials, water etc, if any furnish a photocopy of their test report (s)
Format -XVIII
April
May
June
July
Aug
Sep
Oct
Nov
Dec
Jan
Feb
Mar
Format -XIX
Sl. Description
No.
1 Lay length
2 Weight/meter
3 Breaking load
4 % elongation
7 Coil dia
8 Packing condition
9 Sealing of coils
Note
1. Item 1-5 are to be recorded from the Tests conducted at HTS factory and recorded in Original IC.
Signature of AEN/XEN/CSP
Name
Designation
44
Format -XX
Details of Mix Design
1 M-55 M-60
Mix Design
Date of approval
Kg Kg
Cement
Kg Kg
Coarse aggregates, CA1
Kg Kg
Coarse aggregates, CA2
Kg Kg
Fine aggregates
kg kg
Admixture
Liters Liters
Water
A/C Ratio
W/C Ratio
20 mm …. - ….. …..
10 mm …. - ….. …..
90.00
80.00
70M.0U0LATIVE % PASSING
CUM
60.00
50.00
40.00
30.00
20.00
10.00
0.00
0.1 1 10 100
SIEVE SIZE IN MM
12.0 Steam Curing Cycle: The steam curing cycle for winter season and summer seasons, if varies may be given
separately.
The following cycle is approved as follows:
14.0 Statistical Analysis of Steam cured and water cured cubes: following details shall be submitted -
S.
R M SD CS CV Remarks
No.
1 Steam cured cubes
Formulae are given below to calculate the mean value, standard deviation & coefficient of variation.
14 5) Coefficient of Variation,
15 Cv = (SD x 100) / Xmean
16
19
20
21
47
22
23
24
25
..
..
Signature of AEN/XEN/CSP
Name
Designation