Delays in Construction Works On General Civil Engineering Projects
Delays in Construction Works On General Civil Engineering Projects
Mapua University
October 29
DEDICATION
pursue the vocation are honored in this research article. The paper also
dedicates this to people who pursue the advancement and continual cultivation
never stop and will always have the ability to reach levels of cognition above
The researcher would like to acknowledge and extend his sincere gratitude to
Dr. Dante L. Silva, who served as his supervisor and helped make this research
feasible. I completed all of the writing stages of my project due to his direction
fun experience.
challenges. Every day, I have felt your guidance. I was able to complete my
degree, thanks to you. For my future, I'll continue to put my trust in you.
ABSTRACT
Delays in construction projects are a common problem that can have
including the causes, effects, and mitigation strategies. The study was
reports, and case studies. The research findings indicate that delays can be
include increased project costs, reduced quality of work, loss of revenue, and
I. Introduction ………………………………………………………………... 1
Terms……………………………………………………..9
VIII. Reference………………………………………………………………17
-------------------------------------Page Break------------------------------------------
CHAPTER 1: REVIEW OF RELATED LITERATURE
Introduction
The literature review focused on studies and reports related to delays in
design. Poor planning can result in insufficient time being allocated for
disputes can lead to work stoppages and delays. Weather conditions, such
as extreme temperatures, heavy rain, and high winds can all cause delays.
Related Literature
The effects of delays can include increased project costs, reduced quality
1
sponsors. Increased project costs can result from the need to extend
delayed completion. Reduced quality of work can result from the need to
revenue can result from the inability to use the completed facility or the
sponsors can result from negative publicity or the perception that the
industry
2
Many researchers have conducted surveys and study on the causes
(111) building and civil engineering projects in Hong Kong that were
concluded between 1990 and 1993 (Kumaraswamy & Chan, 1995) It was
schedule, with the average overrun time exceeding 20% (Chan and
Kumaraswamy 1995)
and within budget. The report suggested a vision for the growth and
3
the further development of our economy in the 21st century and provide a
better living environment. To solve the critical problem areas of the Hong
Theoretical Framework
should explore the legal and contractual aspects of delays, including the
mechanisms.
4
Lastly, the framework should take into account the context of general
Conceptual Framework
In this part, will serve as a roadmap that guides the entire research
theories that define the research problem, inform the research questions,
Data analysis
The relative relevance of the various delays was assessed using the
RII technique by Kometa et al. (1994) and Sambasvian and Soon (2007).
This study used the same methodology. RIIs are determined for each
5
∑ w =5 ¿
n 5+¿ 4n4 +¿ 3 ¿
AN n3+¿
2
n2+¿ 1
5N
n1
¿
¿
(ranging from 1 to 5), A is the factor with the highest weight (in this
example, 5), and N is the total number of respondents. The RII rating
ranged from 0 to 1; the greater the RII, the more significant the cause of
delays was. RII values were used to order the causes. We were able to
determine the most common delays from the ranking given to each cause
sector.
Analysis of Variance
Every sevenfold cause has been scored using these scores and the
rate of their being under the effect on the projects has been prioritized
Levene's test determines that this test's significance is greater than 0.05, at
6
Statement of the Problem
corresponding delay.
can take proactive measures to mitigate them, which can help to improve
The research will focus on identifying the most common causes of delays,
industry. Lastly, the research will not be able to take into account
8
unforeseen circumstances such as natural disasters or political instability,
Despite these limitations, the research holds great value in its potential to
including the start and end dates for each phase of the project.
9
6. Quality: the degree to which a product or service meets the desired
work on a project.
13. Change orders: written requests for changes to the original scope of
work in a construction project, which can cause delays and increase costs.
schedule.
10
16. Float: the amount of time by which an activity in a construction
date.
construction project.
construction projects.
11
24. Value engineering: a process for reducing costs and improving the
performance.
and safety.
Introduction
Delays in construction works on general civil engineering projects
have been a major concern for decades due to their impact on the overall
project timeline and budget. To address this issue, extensive research has
been conducted over the years, aimed at identifying the root causes of
context, the methodology adopted for the research plays a crucial role in
12
1. Research Design
2. Data Collection
Both primary and secondary data will be collected for this study. Primary
This section is divided into two distinct sections: the nature of process-
based techniques used to analyse delays and their compliance with SCL
was used to analyze the data that had been gathered. The respondents
seven main categories were used to classify these causes. The causes that
are related to the client (with 19 factors), the contractor (with 13 factors),
the consultant (with 9 factors), the design (with 8 factors), the material
(with 8 factors), the labour and equipment category (with 8 factors), and
questionnaires.
14
and drawbacks. The second phase, which is among the most crucial for
project. The authors followed the SCL procedure and the Association for
3. Data Analysis
4. Ethical Considerations
ensuring that the research does not cause harm to the respondents.
15
5. Limitations
The study may be limited by the availability of data, time constraints, and
16
Reference
Lo, T. Y., Fung, I. W. H., & Tung, K. C. F. (2016, December 19). Construction
delays in Hong Kong civil engineering projects. Journal of Construction
Engineering and Management.
17