Annex 1. Work Plan

The document outlines a work plan for designing and constructing a water network and home connections in Malanje, Angola. The plan involves assessing the existing situation through surveys, modeling, and reports over 392 days. It then involves 60 days each of preliminary and detailed engineering design. The plan also includes a 510-day public consultation and social awareness campaign involving inception, stakeholder consultation, and information campaigns.

Uploaded by

Njia
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
52 views3 pages

Annex 1. Work Plan

The document outlines a work plan for designing and constructing a water network and home connections in Malanje, Angola. The plan involves assessing the existing situation through surveys, modeling, and reports over 392 days. It then involves 60 days each of preliminary and detailed engineering design. The plan also includes a 510-day public consultation and social awareness campaign involving inception, stakeholder consultation, and information campaigns.

Uploaded by

Njia
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

Annex 01

WORK PLAN
Design and Construction of Network and House Connections in the City of Malanje - Design Stage
ID Task Name Duration Start Finish '19 Mar 17 '19 Jun 2 '19 Aug 18 '19 Nov 3 '20 Jan 19 '20 Apr 5 '20 Jun 21 '20 Sep
S M T W T F S S M T W T F S S M
1 Assessment of the Existing Situation 392 days Wed 19/4/10 Tue 20/5/5
2 Counting total number of home connections in 70 days Wed 19/4/10 Tue 19/6/18
the field(executed by consultant,local water
company and contractor)

3 Technical assessment 15 days Wed 19/4/10 Wed 19/4/24


4 Social and Environmental 15 days Wed 19/4/10 Wed 19/4/24
Appraisal/assessment
5 Preparation and Submittal of assessment 16 days Thu 19/4/25 Fri 19/5/10
report (1st version)
6 Consultant's review and reply on assessment 6 days Sat 19/5/11 Thu 19/5/16
report (1st version)
7 Preparation and Submittal of assessment 56 days Fri 19/5/17 Thu 19/7/11
report (2nd version)
8 Consultant's review and reply on assessment 34 days Fri 19/7/12 Wed 19/8/14
report (2nd version)
9 Preparation and Submittal of assessment 33 days Thu 19/8/15 Mon 19/9/16
report (3rd version)
10 Consultant's review and reply on assessment 51 days Tue 19/9/17 Wed 19/11/6
report (3rd version)
11 Preparation and Submittal of assessment 26 days Thu 19/11/7 Mon 19/12/2
report (4th version)
12 Consultant's review and reply on assessment 97 days Tue 19/12/3 Sun 20/3/8
report (4th version)
13 Preparation and Submittal of assessment 52 days Mon 20/3/9 Wed 20/4/29
report (5th version)
14 Consultant's review and approval of 6 days Thu 20/4/30 Tue 20/5/5
assessment report (5th version)
15 Preparation and Submittal of CoC 23 days Thu 19/9/19 Fri 19/10/11
16 Consultant's review and approval of CoC 14 days Sat 19/10/12 Fri 19/10/25
17 Preparation and Submittal of HSP, SP(1st vers55 days Thu 19/9/19 Tue 19/11/12
18 Consultant's review and reply on HSP, SP(1st 34 days Wed 19/11/13 Mon 19/12/16
version)
19 Preparation and Submittal of HSP, SP(2nd vers86 days Tue 19/12/17 Wed 20/3/11
20 Consultant's review and reply on HSP, SP(2nd 21 days Thu 20/3/12 Wed 20/4/1
version)
21 Preparation and Submittal of HSP, SP(3rd vers26 days Thu 20/4/2 Mon 20/4/27
22 Consultant's review and reply on HSP, SP(3rd 6 days Tue 20/4/28 Sun 20/5/3
version)
23 Preliminary Engineering Design 60 days Wed 20/5/6 Sat 20/7/4
24 Topographical Surveys in the field 50 days Wed 20/5/6 Wed 20/6/24
25 Producing Topographical Surveys Map 59 days Thu 20/5/7 Sat 20/7/4
26 Analysis of Hydraulic modelling for the 7 days Wed 20/5/6 Tue 20/5/12
existing network
27 Analysis of Hydraulic modelling for four 7 days Wed 20/5/13 Tue 20/5/19
expansion areas
28 Analysis of Hydraulic modelling for the 7 days Wed 20/5/20 Tue 20/5/26
existing network and four expansion areas
29 Producing preliminary design drawings 14 days Wed 20/5/27 Tue 20/6/9
30 Producing and Submittal of preliminary 1 day Wed 20/6/10 Wed 20/6/10
engineering design report

Task External Tasks Manual Task Finish-only


Jiang Su Geology & Engineering Co., Ltd Split External Milestone Duration-only Deadline
Milestone Inactive Task Manual Summary Rollup Critical
Date: Fri 20/4/24 Summary Inactive Milestone Manual Summary Critical Split
Project Summary Inactive Summary Start-only Progress

Page 1
Design and Construction of Network and House Connections in the City of Malanje - Design Stage
ID Task Name Duration Start Finish '19 Mar 17 '19 Jun 2 '19 Aug 18 '19 Nov 3 '20 Jan 19 '20 Apr 5 '20 Jun 21 '20 Sep
S M T W T F S S M T W T F S S M
31 Preparation and Submittal of ESMP 1 day Wed 20/5/6 Wed 20/5/6
32 Consultant's review and approval of 1 day Thu 20/5/7 Thu 20/5/7
preliminary engineering design report and
ESMP

33 Detailed Engineering Design 60 days Sun 20/7/5 Wed 20/9/2


34 Producing shop drawings based on preliminary 28 days Sun 20/7/5 Sat 20/8/1
design
35 Amending BOQ according to Detailed design 7 days Sun 20/8/2 Sat 20/8/8
36 Producing and Submittal of Detailed design 15 days Sun 20/8/9 Sun 20/8/23
report
37 ESMP disclosure 10 days Sun 20/7/5 Tue 20/7/14
38 Consultant's review and approval of detailed 10 days Mon 20/8/24 Wed 20/9/2
engineering design and BOQ
39 Public Consultation & Social Awareness 510 days Wed 19/4/10 Mon 20/8/31
Campaign
40 Iception 71 days Wed 19/4/10 Wed 19/6/19
41 Preparation of Public consultation and 7 days Wed 19/4/10 Tue 19/4/16
community awareness Plan
42 Preparation and Submittal of inception 24 days Wed 19/4/17 Fri 19/5/10
report(1st version)
43 Consultant's review and reply on inception 5 days Sat 19/5/11 Wed 19/5/15
report(1st version)
44 Preparation and Submittal of inception 27 days Thu 19/5/16 Tue 19/6/11
report(2nd version)
45 Consultant's review and approval of 8 days Wed 19/6/12 Wed 19/6/19
inception report(2nd version)
46 Consultation with local stakeholders 55 days Mon 20/5/4 Sat 20/6/27
47 Prepare field work (interviews and focus 5 days Mon 20/5/4 Fri 20/5/8
group)
48 Conduct interviews with key stakeholders 15 days Sat 20/5/9 Sat 20/5/23
49 Conduct focus group 15 days Sun 20/5/24 Sun 20/6/7
50 Preparation and Submittal of consultaion 10 days Mon 20/6/8 Wed 20/6/17
report
51 Consultant's review and approval of 10 days Thu 20/6/18 Sat 20/6/27
consultation report
52 Social awareness campaign 65 days Sun 20/6/28 Mon 20/8/31
53 Create IEC(information, education and 5 days Sun 20/6/28 Thu 20/7/2
communication) campaign strategy
54 Prepare field work (public clarification 5 days Fri 20/7/3 Tue 20/7/7
session and communities activities)
55 Execution of IEC campaign 35 days Wed 20/7/8 Tue 20/8/11
56 Preparation and Submittal the report with 10 days Wed 20/8/12 Fri 20/8/21
the results of social awareness campaign
57 Consultant's review and approval of 10 days Sat 20/8/22 Mon 20/8/31
campaign report

Task External Tasks Manual Task Finish-only


Jiang Su Geology & Engineering Co., Ltd Split External Milestone Duration-only Deadline
Milestone Inactive Task Manual Summary Rollup Critical
Date: Fri 20/4/24 Summary Inactive Milestone Manual Summary Critical Split
Project Summary Inactive Summary Start-only Progress

Page 2