Chapter 1 Introduction
Chapter 1 Introduction
DCC40132
PROJECT MANAGEMENT AND PRACTICES
1
PROJECT
2
PROJECT
3
PROJECT VS NON PROJECT
4
PROJECT FUNDAMENTAL CRITERIA
1. Completed on time
5
PROJECT CHARACTERISTICS
Specific
Objectives
Risk and
Uncertainty Unique
PROJECTS
Diverse
Temporary
disciplines
Managing
Resources
6
PROJECT MANAGEMENT CONCEPT
7
PROJECT MANAGEMENT CONCEPT
8
PROJECT MANAGEMENT CONCEPT
9
MANAGEMENT CHARACTERISTICS
10
CONSTRUCTION MANAGEMENT
11
CONSTRUCTION MANAGEMENT DEFINITION
Charles Patrick:
Construction Project Planning and Scheduling.
12
CONSTRUCTION MANAGEMENT CHARACTERISTICS
Different
Unique design
location
Huge cost
13
UNIQUE DESIGN
• Building function
• Financial allocation
• Construction duration
• Legal requirements
• Local culture.
14
DIFFERENT LOCATION
15
HUGE COST
16
THE BENEFIT / IMPORTANCE OF PROJECT
MANAGEMENT
18
OWNER / CLIENT
19
OWNER / CLIENT FUNCTION
20
PROJECT MANAGER
21
PROJECT MANAGER ROLE
23
PROJECT MANAGER ROLE
Contractor can be :
i. Main contractor
ii. Sub-contractor
Domestic Sub-contractor
Nominated Sub-contractor
26
ARCHITECT
27
OTHERS
Land surveyor
Quantity surveyor
Engineer.
Site Supervisor
28
RELEVANT AUTHORITIES
Local council
Telecommunication
Electricity
Fire Department
Department of Environment
29
IMPLEMENTATION OF
CONSTRUCTION MANAGEMENT
3. Turnkey method
30
TRADITIONAL METHOD
31
TRADITIONAL METHOD
32
TRADITIONAL METHOD
CLIENT
DESIGN
CONTRACTOR
TEAM
SUBCONTRACTOR 1 SUBCONTRACTOR 2
33
TRADITIONAL METHOD CHARACTERISTICS
RESPONSIBILITY
34
TURNKEY AND DESIGN & BUILT METHOD
35
TURNKEY AND DESIGN & BUILT METHOD
CLIENT
CLIENT
CONSULTANT
36
DESIGN & BUILT METHOD
37
DESIGN & BUILT METHOD
38
TURNKEY METHOD
• An organization is responsible for design, construct and fund
the cost of project.
• Client will make the payment after the project is finish. (when
contractor “turn the key” to client)
• The client has less say over the design of the project and
the contractor takes more risk.
39
TURNKEY METHOD
40
41