Night Shift - Work Permit
Night Shift - Work Permit
Night Shift - Work Permit
This application must be completed and submitted by the Main Contractor/Consultant for all projects having a
proposal for night shift. Application must be made after meeting DWC -QHSSE requirements. Night shift work
permit will cover from 18:00 hrs to 06:00 hrs.
A. PROJECT DETAILS
Project Name Plot No.:
Contractor Consultant:
Client
No. of employees.
Night Shift Responsible Name: Contact No:
Person (Safety)
Night Shift Duration From (Date): Valid till:
B. LIST ACTIVITIES TO BE CARRIED OUT
1. 2. 3. 4.
5. 6. 7. 8.
C. CONTRACTOR’S COMPLIANCE STATEMENT
We hereby confirm that the following HSEQ requirements shall be complied with:
No. Statement Description Yes No NA
Organization chart available for night activities. Responsible engineer need to be available
1
on site with the authority of decision making.*
2 DWC approved night shift risk assessment is available at site. *
3 Method statements are available for night shift activities. *
4 Emergency procedures are established and implemented for night shift activities. *
5 Full time safety advisor is available with valid SARS card / NEBOSH / IOSH certifications.
6 All the stair cases & work areas are fitted with adequate light’s with back-up power. **
7 Full time first aider & fire fighters are available for night shift activities.
8 Site security and transport arrangement is available for night.
9 Adequate site supervisors are nominated for the night shift with communication facilities.
Safety induction program for night shift and evidence of its communication to workforce is
10
available on site.
11 Welfare facilities are available as per the DWC/DM requirements.
12 Lifting plan prepared and available at site.
13 Night shift toolbox meeting program is available at site. *
14 No objection letter from the client is available at site for the night shift activities. *
We undertake to carry out the night shift activities in accordance with DWC/DM and other relevant International
construction safety standards. We are aware that we are liable for financial penalties/warning letters for failing to carry out
our works in accordance to relevant regulations & standards. We are also aware that in the event of DWC issuing violation /
stop work notices we are bound to stop the work immediately in accordance with DWC Regulations & Standards.